Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FOUN/02
PAGE 1 OF 3
SECTION: DATE OF ISSUE
FOUNDATIONS September 2007
SUBJECT: BY:
QA/QC ENGINEER
EXCAVATION, EARTHWORK AND FILLING APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure provides a standardised framework for the control of


excavation, earthwork and filling to ensure compliance with
conditions of contract and contract specifications.

2. PROCEDURE

.1 All excavation, earthwork and filling will be carried out in


accordance with the specification detailed in the project contract
documentation. In any circumstances where specifications are not Project
provided or they are in any way incomplete, the matter shall be Manager
referred back to consultant for additional information.

.2 Method Statement

A method statement will be prepared and approved where deemed


necessary, and may include:

i) Site plan showing the location of spoil heaps for temporary


storage and if appropriate permanent storage area.
ii) Type of plant and equipment to be used.
iii) Means for keeping excavations free of water.
iv) Method of trench supports.
v) Method and sequence of excavation to ensure that no damage
is caused to adjoining structures and property. If there is
potential for damage to adjoining structures and property, the
type of preventative measures should be indicated.
vi) Temporary support arrangement of adjacent structures and
services passing through the site. Project
vii) Method of compacting fill and testing procedure. Manager
viii) Health and Safety requirements. Method
ix) Any other special requirements. Statement
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FOUN/02
PAGE 2 OF 3
SECTION: DATE OF ISSUE
FOUNDATIONS September 2007
SUBJECT: BY:
QA/QC ENGINEER
EXCAVATION, EARTHWORK AND FILLING APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.3 Existing Utilities

i) Liaise with all public utility companies e.g. water, electricity,


telephone sewerage and surface water etc. to ensure that all
the available information on the location of utilities and Project
underground services through and adjacent to the site of the Manager Drawing/
excavation is obtained. N.O.C.

ii) Ensure that utilities and underground services are located on


site using markings, which are clearly visible. Ensure those
plant operators and operatives involved with the activity are Project
fully aware of the location of the various utilities and Engineer
underground services and their respective depths. Markings
Project
iii) Where deemed necessary, excavate trial holes to establish the Engineer
precise location and depth of services. Trial Holes

iv) Plant operators must be aware of overhead cables. Use height


control indicators where necessary.

.4 Site Survey and Grid of Levels

Prior to commencement of any excavation work, a level survey will


be carried out to confirm the information included on the contract Site Engr./
drawings and to provide an accurate record of existing ground levels Surveyor
for the calculation of quantities. Survey

.5 Disposal of Surplus Excavated Material

Prior to any surplus excavated material being removed from the site, Project
documentary evidence of approval to tip must be obtained Manager
beforehand from the relevant government/municipal departments and Approval to
the owner of the land where the material is to be tipped. Tip

.6 Adjoining Structures and Property

Prior to the commencement of excavation work, a detailed


dilapidation survey will be undertaken to record the existing
condition of the adjoining structures and property. Where necessary
the survey may include photographic records.
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FOUN/02
PAGE 3 OF 3
SECTION: DATE OF ISSUE
FOUNDATIONS September 2007
SUBJECT: BY:
QA/QC ENGINEER
EXCAVATION, EARTHWORK AND FILLING APPROVED BY:
QEHS MANAGER
ACTION VERIFY

This survey should be carried out in co-ordination with and involving


the participation of the Consultants representative and the Const. Dilapidation
representative of the owners/occupiers of the adjacent property. Manager Survey

.7 Excavation Work

i) Excavation shall be allowed to progress to the designed


formation level less 50mm (unless specified otherwise). The
remaining 50mm shall be carried out by further careful Project
excavation to avoid disturbing the formation level. Engineer Survey

ii) After reaching the designed formation level, Consultants


representative shall be requested in writing to inspect and
approve the formation prior to the commencement of any Inspection
subsequent activities. QA/QC Request

iii) Great care shall be taken to minimise noise, vibration and Project
dust pollution, which can cause nuisance and damage, Engineer/ Method
particularly if the site is located in a built-up area. Site Safety Statement

iv) Sides of all excavations should be properly supported using Project Method
an appropriate method as detailed in the Method Statement. Engineer/ Statement
Site Safety
.8 Filling

i) Prior to commencement of filling, the Consultants


representative shall be requested in writing to inspect and Inspection
approve the fill starting level. QA/QC Request

ii) Filling shall be carried out using approved materials in


accordance with the specification which can either be
selected from the material on site or imported from selected Project Source
and approved sources. Engineer Documents

iii) Filling shall be carried out as per approved method and as per Project Method
the contract specification. Engineer Statement
Appendix FOUN/02/A
October 2005

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR EXCAVATION AND FILL TO FORMATION Sheet No.

SUBCONTRACTOR Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE
EXCAVATION TO
FORMATION 1. Record existing GLs before excavation. SE
2. Check level profiles. SU
3. Check for location of buried utilities e.g.
foundations, drains, cables, duct, telephone lines,
sewerage lines. SE
4. Check temporary support/batters to sides of
excavation. SE/SSO
5. Record soft spots, obstructions, groundwater etc.
and how dealt with. SE
6. Check suitability of formation including test
results (CBRs, PLT etc). SE

7. Check and record final levels. SU


8. Obtain consultants approval for founding level. QA/QC
9. Check approval to tip. PE

APPROVAL TO PROCEED CM
FILL TO
FORMATION 1. Record existing GLs before fill. SU
2. Check existing services located, protected or
raised as specified. SE
3. Check level profiles. SU
4. Check fill material is as specified.
Record source and approval. PE
5. Check fill material laid and compacted to
specification. Record test results. PE
6. Check final levels and record. SU
7. Obtain consultants approval. QA/QC

APPROVAL TO PROCEED CM

CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE - Project Engineer,


SE - Site Engineer, SU Surveyor, SSO Site Safety Officer
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FOUN/04
PAGE 1 OF 2
SECTION: DATE OF ISSUE
FOUNDATIONS September 2007
SUBJECT: BY:
QA/QC ENGINEER
BORED PILING APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

The scope of this procedure covers the control of installation of


Bored Cast-in-Situ Concrete piles executed by a sub-contractor.

2. PROCEDURE

.1 Method Statement:

A method statement shall be submitted by the piling Sub-


contractor for approval which shall include:

i) Construction procedure.
ii) Pile design with calculations.
iii) Testing procedure.
iv) Documentation to be maintained during the execution of
work.
v) Mix design for concrete. Project
vi) Specification for reinforcement steel and bentonite clay. Manager Method
vii) Any other information required by the specification. Statement

.2 Construction Programme:

The sub-contractor shall submit a programme for approval based


on the Contract Programme. The subcontractor shall also indicate Sub- Approved
the mobilisation time of plant, equipment, materials and work contractor Construction
force. Programme

.3 Piling Sequence: Project


Manager
Approval of piling sequence will be given prior to commencement
of piling by the Subcontractor. Approval

.4 Setting-Out: Subcon/
Al Rajhi
HEE will execute pre-piling setting out and offer for cross- Surveyor
checking by Subcontractors Surveyor and Consultants
Representative. Field Book
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FOUN/04
PAGE 2 OF 2
SECTION: DATE OF ISSUE
FOUNDATIONS OCTOBER 2005
SUBJECT: BY:
QA/QC ENGINEER
BORED PILING APPROVED BY:
QHSE MANAGER
ACTION VERIFY

.5 Source Certificates:

Reinforcement steel and Bentonite test certificates if required


shall be obtained from the Subcontractor and, submitted for Project Source
approval by the Consultant. Engineer certificate

.6 Concrete Cube Testing:

Cube results will be assessed and retained. The cube test reports Project
shall be clearly identified with the location of pour by reference to Engineer/ Test result,
the checksheet. Labtech. FOUN/04/A

.7 Testing of Piles:

The Subcontractor shall carry out a load test and integrity test as Pile testing
specified in the Contract. Subcon. record

.8 Inspection of Work/Checksheet:

The work shall be inspected using the attached checksheet as


Appendix FOUN/04/A which shall be completed as verification
and record of compliance. QA/QC Checksheet

.9 Non-Conformity:

Non-conforming workmanship shall be notified to the Non-


Subcontractor as Appendix 7/3/6/A and corrective action taken in Conformity
accordance with good working practice and Consultants approval. QA/QC Report
Appendix FOUN/04/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR BORED PILING Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE

PREPARATION 1. Subcontractors method statement approved. PE

2. Materials approved by the consultant. PE

3. Cross-check location of Pile. SU

APPROVAL TO PROCEED QA/QC


INSTALLATION 4. Check borehole to be filled with Bentonite
slurry at all times. GF

5. Check cleaning of bottom of borehole. GF

6. Check reinforcement cage. SE


7. Check minimum cover while lowering cage into
the borehole. GF

8. Check slump of concrete. Lab

9. Check cut-off level + location. SU

APPROVAL TO PROCEED WITH PILE CAP. CM

CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE - Project Engineer,


SE Site Engineer, GF General Foreman, SU - Surveyor, Lab - Laboratory Technician
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FOUN/06
PAGE 1 OF 2
SECTION: DATE OF ISSUE
FOUNDATIONS September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONTROL OF SEWERAGE AND SURFACE WATER DRAINAGE APPROVED BY:
QHSE MANAGER
ACTION VERIFY

1. SCOPE

This procedure covers controls to be carried out during construction


of underground sewerage and surface water drainage works.

2. PROCEDURE

.1 All sewerage and surface water drainage works will be carried out in
accordance with the contract specification and good practice.

Where specifications are not provided or are incomplete, the matter Project Request for
shall be referred back to the Consultant for additional information. Engineer Information

.2 Depending upon the complexity of the work, and the requirements of


the PQP, a method statement shall be prepared and approved by the
Consultant which shall include:

i) Proposed plant and equipment.


ii) Jointing technique.
iii) Trench support (in case of deep excavation).
iv) Manufacturers jointing and installation details and test
certificates (where relevant).
v) Sequence of activities.
vi) Compaction method and quality of fill material. Project Method
vii) Test plan. Engineer Statement

.3 Check delivery order and certificates against the specification and Store-
examine marks, labels and condition of material and components. keeper/Site
Engineer

.4 Unload and handle materials and components with care to minimise Store-
damage and soiling. keeper/Site
Engineer
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FOUN/06
PAGE 2 OF 2
SECTION: DATE OF ISSUE
FOUNDATIONS September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONTROL OF SEWERAGE AND SURFACE WATER DRAINAGE APPROVED BY:
QHSE MANAGER
ACTION VERIFY

.5 Before commencing excavation, fence or board the area of work so Site


as to prevent unauthorised access. Provide adequate safeguards, e.g. Engineer/
gangways, handrails, notices or direction boards and lighting at Safety
night. Officer

.6 Contact local authority departments to obtain details of existing FOUN/06/A,


underground services. Proper marking will be employed on the site Site Records/
to avoid damage to any adjacent services. Engineer Drawings
obtained
from local
departments
.7 Provide adequate trench support to retain the sides of excavations Site
and ensure the safe and proper construction of works and completion Engr/Gen.
of backfilling. Foreman FOUN/06/A

Site
.8 Spoil heaps stacked material and vehicles to be kept at a distance of Engr/Gen.
more than the trench depth from the trench. Foreman

.9 Temporary supports to excavations will be maintained in position Site


until sufficient backfill has been placed and compacted to ensure the Engr/Gen.
stability of the sides of the excavation. Foreman

.10 Employ the proper jointing method as recommended by pipe


manufacturer. Ensure that jointing faces are dry, clean and free from Gen.
soil or bedding particles. Foreman

.11 Finalise an intermediate test plan and water testing to be done to Site
check water tightness of pipeline. Engineer Test Plan

3. DOCUMENTATION

.1 Appendix FOUN/06A and Appendix FOUN/06/B, shall be used to


monitor drainage construction. Approval to proceed will be given by
the QA/QC. QA/QC Checksheets
Appendix FOUN/06/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR SEWERAGE AND SURFACE WATER DRAINAGE Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE
PIPEWORK OR
CHANNEL 1. Set line and level. SU
2. Check location of underground services before
commencement of excavation. SE

3. Check inverts levels and gradients. SU


4. Check correct diameter and material. Also check
the compatibility of pipes, fittings and accessories
for jointing e.g. ring seals, solvent cements,
lubricants. SE

5. Check position and no. of connections. SE

6. Check availability of trench support material. GF

7. Check bedding and granular surround. GF

8. Backfill to specification material/compaction. SE


9. Ensure protection of laid pipeline from damage by
construction traffic. SE
10. Pipe run rodded and tested. PE/MEP

APPROVAL TO PROCEED QA/QC


GULLEY
CONNECTION 1. Check correct gulley used. SE
2. Check position and level of gulley. SE/SU
3. Check correct surround. GF
4. Check gulley grid. GF
5. Check gulley cleaned out. GF

APPROVAL TO PROCEED QA/QC

QA/QC Quality Assurance/Quality Control, PE Project Engineer, SE Site Engineer,


SU Surveyor, MEP MEP Coordinator, GF General Foreman
Appendix FOUN/06/B
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR SEWERAGE AND SURFACE WATER MANHOLES Sheet No.

SECTION OF WORK: _______________________________________________________________


MANHOLE No: ____________________________________________________________________

Checked
STAGE ITEM by DATE

PREPARATION 1. Set position of manhole and base level. SE/SU

2. Check base concrete. GF

3. Check correct base rings (outlets). SE

4. Check rings/reducer/step irons. SE

5. Checks cover slab level and location of opening. SE

6. Check concrete surround. GF

7. Check correct cover/brick bedding/concrete haunch. GF

8. Check manhole benching. GF

9. Clean out manhole. GF

APPROVAL TO PROCEED QA/QC

QA/QC Quality Assurance/Quality Control, SE Site Engineer, SU, - Surveyor, GF General


Foreman
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/01
PAGE 1 OF 3
SECTION: DATE OF ISSUE:
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONTROL OF FORMWORK APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure applies to the installation of formwork and the


controls required during assembly, erection and final positioning of
formwork used in Structural concrete operations.

2. PROCEDURE

.1 All formwork activities will be carried out in accordance with the Project Contract
specification. Engineer Specs.

.2 After studying the structural drawings, the Project Engineer will plan
for sizes, numbers and type of formwork to be used in consultation
with the Structural Engineer, if required. Depending upon the Project Shop
programme, the number of repetitions will be decided. Engineer Drawings

External designers may be used for specific systems.

.3 Availability of formwork will be checked with the Procurement Project


Manager and decision will be taken to buy, hire or reuse formwork Director/
material. Manager/
Resources
.4 During fabrication of formwork shutters, all dimensions shall be Manager Formwork
cross-checked with a view to avoiding corrective action during Shop
erection. drawings
General
.5 Paint reference numbers on all panels to ensure their use in correct Foreman
positions.
Gen.
.6 Ensure that the props, shores, waling, bearers, clamps and tie rods are Foreman
the right size and at the correct spacings. The Formwork designer
shall check the falsework system with respect to load imposed on it
and design parameters as laid down in the specification. Gen.
Foreman/
.7 Check that the falsework is securely braced and is on a firm Designer
foundation.
Gen.
Foreman
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/01
PAGE 2 OF 3
SECTION: DATE OF ISSUE:
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONTROL OF FORMWORK APPROVED BY:
QEHS MANAGER

ACTION VERIFY

.8 Forms fastened to previously cast concrete must be tightly fixed to


prevent grout loss. Cellular foam plastic strips can be used to make a Gen.
seal. Foreman

.9 Check quality of shutter lining, tightness of bolts and wedges, built- Gen.
in items, inserts and other embedments. Foreman CONC/04/A

.10 Tie - rod holes to be made in the formwork shall be neat so that they Gen.
can be patched or plugged later on. Foreman

.12 Particular attention will be paid to the rigidity and line of stop ends Gen.
and joint formers. Foreman

.13 Remove all tie-wire clippings and nails, which may stain both the Gen.
formwork and the concrete. Foreman CONC/04/A

.14 Ensure that adequate access and working platforms are in place for Gen.
the concreting gang and that toe boards and guardrails are provided. Foreman

.15 A spreader or lifting beam shall be used to prevent distortion when Gen.
placing formwork. Foreman

.16 Adjustable steel props shall be erected in plumb and verticality of Gen.
props checked using a spirit level. Foreman

.17 A prop should not be used if it is bent, creased or, rusted or has a bent Gen.
head or base plate, damaged pin etc. Foreman

.18 Proper release of agent shall be used so that it can be removed Gen.
without damaging the surface finish of the concrete. Foreman CONC/04/A

.19 New timber and plywood forms shall be given first coat of the
appropriate release agent 36 hours in advance, then a second coat just
before they are used. Avoid excessive use of release agent as this can Gen.
cause staining or retardation of the concrete. Foreman

.20 A close watch should be kept on all wedges and fastenings. Make
sure that they do not work loose. Grout loss is an indication that Gen.
some movement has occurred. Foreman
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/01
PAGE 3 OF 3
SECTION: DATE OF ISSUE:
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONTROL OF FORMWORK APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.21 When unsleeved tie bars are being used, ease them slightly before the Gen.
concrete sets, and remove them as soon as it is safe. Foreman

.22 Striking the Formwork:

i) Always obtain approval before striking the formwork in the


form of Appendix CONC/04/A. QA/QC Checksheet

ii) Ensure adequate safety measures while striking formwork. Gen.


Foreman
iii) Cleaning the face of forms shall start as soon as they have Gen.
been struck. Foreman

iv) Good storage is essential to ensure that formwork can be used Gen.
again. Foreman

v) Paint code numbers on them so that they can be readily Gen


identified when next needed. Foreman

.23 Safety During Formwork Operations:

i) The weights of large prefabricated sections of formwork


should be marked on them so that the lifting capacity of the
crane at the working radius is not exceeded. Lifting points are Gen.
usually provided. Foreman

ii) If necessary, a spreader or lifting beam shall be used to Gen.


prevent distortion. Foreman

iii) Where lifting is done by the vertical soldiers, check that they Gen.
are adequately connected to the walings. Foreman

iv) Fire extinguishers in working order shall be in close Gen. Project


proximity to the stored formwork. Foreman/ Safety Plan
Safety
Officer
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/02
PAGE 1 OF 3
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CUTTING AND BENDING OF REINFORCEMENT APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

The scope of this procedure covers the control required for cutting
and bending of reinforcement, including scheduling and
dimensioning.

2. PROCEDURE

.1 All cutting and bending of reinforcement will be carried out in


accordance with the specification detailed in the Specific Project
Contract documentation.

In any circumstances where specifications are not provided or they


are in any way incomplete, the matter shall be referred back to the Project Request for
Consultant for additional information. Engineer Information

.2 Test Certificates:

Prior to unloading of reinforcement steel at site, the Manufacturers


Test Certificate shall be verified to ensure compliance with the
contract Specifications in regard to mechanical and chemical
properties. If specified in the contract, a sample may be sent to an
approved laboratory for testing. A copy of the test certificate thus
obtained shall be forwarded to the Consultant for information if Source/Test
specified in the contract. Lab.Tech. Certs.

.3 Bar Bending Schedule:

Prior to commencement of the cutting and bending operation, a bar


bending schedule shall be prepared by the Site Engineer and Site Bar
submitted to Consultants representative for approval. Engineer Bending
Schedule
.4 Procurement Schedule:

Procurement of steel shall be synchronised with the construction Material


programme without causing any delay in the concreting schedule. Buyer Reqt and
Tracking
Schedule
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/02
PAGE 2 OF 3
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CUTTING AND BENDING OF REINFORCEMENT APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.5 Delivery and Storage:

i) In handling and storage special care should be taken that Store-


exposure to contamination and moisture is minimised. keeper CONC/02/A

ii) All steel should be covered during transportation and storage Store-
as far as possible. keeper

iii) A proper storage area near to bar bending yard which has
good access for delivery and adequate space for offloading Const.
shall be planned. Manager Site layout

vi) Before unloading the Storekeeper shall check the diameter of


bars and number of bars in each bundle. Any discrepancy Store-
must be brought to the notice of the supplier. keeper

v) Systematic storage shall be planned for easy identification of


different deliveries, sizes and types of steel. Bars shall be
stored in racks well clear of the ground. Similar care is
needed after reinforcing bars have been cut and bent while Store-
they are awaiting fixing in formwork. keeper CONC/02/A

.6 Cutting and Bending of Reinforcement:

i) Actual dimensions of the bars and links after bending shall be


cross-checked with the approved bar bending schedule and Gen.
formwork dimensions. Foreman CONC/02/A

ii) In order to facilitate identification of bent bars, the schedule


reference and bar mark indicated on the bar bending schedule Gen.
shall be attached to reinforcement bundles where possible. Foreman CONC/02/A

iii) The tolerances as specified shall be applicable for cutting and


bending dimensions.
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/02
PAGE 3 OF 3
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CUTTING AND BENDING OF REINFORCEMENT APPROVED BY:
QEHS MANAGER
ACTION VERIFY

iv) The Site Engineer shall ensure that cutting and bending
machine operatives are trained in the skills necessary to
produce cut and bent products of consistent quality within Site
permissible size variations. Engineer

v) The General Foreman will check the bar marks and type and
sizes of scheduled bars of various sizes and lengths, prior to
the bending and eventual use of the prepared batch.
Unsatisfactory bars will be referred back and the cutting and Gen.
bending activity reviewed to correction. Foreman CONC/02/A
Appendix CONC/02/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR CONTROL OF CUTTING AND BENDING Sheet No.


REINFORCEMENT

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE

PRIOR TO CUTTING 1. Check manufacturers certificates. PE


2. Bar bending schedule approved by the
Consultant. PE

3. Check proper storage and stacking of bars. SK


4. Check specimens of bent bars with approved
bar bending schedule. SE

APPROVAL TO PROCEED QA/QC


DURING CUTTING 5. Check labelling bent bars in reference to
AND BENDING approved bar bending schedule. SE
6. Check random specimens for correctness
with respect of size, shape etc. GF

7. Check surface condition of bars. SE

APPROVAL TO PROCEED WITH USE OF


BARS. QA/QC
QA/QC Quality Assurance/Quality Control, PE Project Engineer, SE Site Engineer,
GF General Foreman, SK Storekeeper
Al Rajhi and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/03
PAGE 1 OF 2
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
FIXING OF REINFORCEMENT APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

The scope of this procedure covers the control required for fixing of
reinforcement for structural concrete.

2. PROCEDURE

.1 All fixing of reinforcement will be carried out in accordance with the


contract specification.

Where specifications are not provided or are incomplete, the matter Project Request for
shall be referred back to the Consultant for additional information. Engineer Information

Site
.2 In order to facilitate identification of bent bars refer to point 2.6 (ii) Engr/Gen. CONC/02/A
of Work Procedure CONC/02. Foreman

.3 Overlaps will be provided as specified in contract specification. Approved


However, the approved bar bending schedule and workshop Gen. Bar
drawings will be referred to in this matter. Foreman Bending
Schedule &
Drawings
.4 While fixing reinforcement extra protruding rods for kickers/starters Gen.
shall be provided wherever indicated on the drawings. Foreman

.5 Method of Fixing:

i) Ensure that fixings are firm so that the bars stay in their Site
correct position while placing the concrete and also under Engr/Gen.
foot traffic. Foreman

ii) Use soft iron binding wire at most intersection of bars in


slabs and walls, and at intersection of main bars and links or
stirrups. For strong ties use `hairpins or `crowns which will
hold two bars rigidly against each other `Slashes can be put Gen.
on intermediate joints, for example, a flat mat. Foreman
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/03
PAGE 2 OF 2
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
FIXING OF REINFORCEMENT APPROVED BY:
QEHS MANAGER
ACTION VERIFY

iii) Bend the ends of all ties down or inwards so that does not Gen.
project into the cover zone where they might cause rusting. Foreman

iv) Organise a crane for lifting reinforcement cages and a Site


temporary storage area for them. Fabrication shall be firm Engr/Gen.
enough to be lifted safely by crane. Foreman/
Safety
.6 Cover: Officer

All reinforcement must be embedded at a minimum distance from Gen.


the surface as shown in the drawings. Foreman

.7 Spacers:

i) Ensure right types and sizes of spacers.

ii) Ensure that the ends of bars have sufficient cover and that the
stirrup `tails are bent in.

iii) Small mortar blocks are normally used as cover blocks. Make
sure that any wire cast into the blocks is kept well away from
the surface of the concrete.

iv) All spacers must be strong enough to withstand foot traffic. Gen.
Foreman
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/04
PAGE 1 OF 3
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
INSPECTION AND TESTS FOR ALL INSITU REINFORCED APPROVED BY:
CONCRETE QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure covers checks and quality control aspects to be


applied while carrying out in-situ concrete operations.

2. PROCEDURE

.1 Daily concrete requirements shall be provided to the RMC supplier


including quantity, mix details, workability time, delivery rate and Project
access arrangements. Engineer Letter

.2 The QA/QC shall ensure that checks on the following activities take
place using the Checksheet appended: QA/QC CONC/04/A

.3 Formwork:

i) Procurement of material for formwork and scaffolding to be


synchronised with Contract programme. SiteEngr Requisition
ii) The Site Engineer shall ensure that formwork of required
shape and size is fabricated. Site Engr
iii) General Foreman shall ensure that no damage is caused to the Gen.
shutters while lifting. Foreman
iv) All safety precautions will be taken while lifting heavy Safety
shutters. Officer
v) The General foreman shall paint numbers on all panels in
order to use them in correct positions against the formwork Gen.
drawing. Foreman
vi) Formwork fastened to previously cast concrete must be Gen.
tightly fixed to prevent grout loss. Foreman
vii) Over-tightening of ties shall be avoided as they may fail Gen.
when fully loaded. Foreman
viii) The holes to be drilled in the formwork shall be neat so that Gen.
they can be properly patched or plugged later on. Foreman
ix) The props shall be in good condition and erected properly. It
must be ensured that a minimum number of props are Gen.
removed and are replaced, for access. Foreman
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/04
PAGE 2 OF 3
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
INSPECTION AND TESTS FOR ALL INSITU REINFORCED APPROVED BY:
CONCRETE QEHS MANAGER
ACTION VERIFY
Gen.
x) Props shall be in plumb and bearers shall not be off centre. Foreman
xi) A prop shall not be used if it has any of these defects: Gen.
Foreman
- a bend or crease in the tube
- corrosion other than light rusting on the surface
- a bent head or base plate
- an incorrect or damaged pin

.4 Reinforcement:

i) Reinforcement steel source certificates and test results as


necessary shall be obtained, identified and filed by the Site
Engineer. Site Engr Test results
ii) Ensure bar placement as per approved drawings. Gen. CONC/04/A
Foreman
.5 Placing and Compacting Concrete:

i) It is necessary to maintain proper speed depending upon total


quantum of pour and site conditions. If placing speed is too
slow, the concrete may stiffen forming cold joints and in case
of rapid delivery, the work of placing may proceed ahead of
the compacting gang making it impossible for them to do the Gen. Visual
concrete placement properly. Foreman Control
ii) Impact of concrete on the formwork shall be avoided which Gen.
could result in movement of reinforcement and lack of cover. Foreman
iii) Forming of large heaps or sloping layers shall be avoided as Gen.
these encourage segregation. Foreman
iv) Inadequate compaction can seriously affect the quality of the
concrete. Proper size of vibrator compatible with the Gen.
formwork and Reinforcement shall be used. Foreman
v) The concrete layer being compacted shall never be deeper Gen.
than the length of the poker head. Foreman
vi) Ensure that the poker does not touch the formwork.
Otherwise it will cause `poker burn and mark the surface of Gen.
the finished concrete. Foreman
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/04
PAGE 3 OF 3
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
INSPECTION AND TESTS FOR ALL INSITU REINFORCED APPROVED BY:
CONCRETE QEHS MANAGER
ACTION VERIFY

vii) The poker shall not touch the reinforcement. The vibration
will be transmitted to concrete that has already stiffened and
the bound between mix and the reinforcement could then be Gen. Visual
affected. Foreman Control

.6 Striking the Formwork:

i) Release agents as specified, are applied before concreting


starts and before reinforcement is fixed each time that the Gen.
form is used. Foreman CONC/04/A
ii) Formwork has to be struck as per the time period specified in
the contract. An earlier striking time may be authorised by the
Consultant pending interim cube results or curing methods. Consultant
iii) While striking formwork, necessary safety precautions must Gen. Safety
be adhered to. Foreman/ Procedures
Safety
Officer
iv) Use hardwood wedges to remove the shutters entrapped with
the concrete members and avoid use of nail bars to avoid
damage to both concrete and the form.
v) The General Foreman must ensure cleaning of face of forms Gen.
as soon as they have been struck. Foreman CONC/04/A
vi) Proper storage of formwork shall be ensured so that they are Gen.
not damaged and easily identified when next required. Foreman
Appendix CONC/04/A
September 2007

AL RAJHI PROJECTS AND CONSTRUCTION LLC

PROJECT: SITE NO.:

CHECK SHEET FOR INSITU REINFORCED CONCRETE Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE
FORMWORK (Before 1. Check falsework design and issue permit to
Concreting) load. PE
2. Check quality of shutter lining for required
finish. GF
3. Check formwork erected and restrained as per
approved drawings SE
4. Check dimensions, line and level. SE
5. Check preparation of forms inc. support, tie
rods, release agents, cleanliness. GF
6. Check plumbness and spacing of props. GF
7. Check tightness of bolts and wedges. GF
8. Check special built-in items, inserts,
mechanical, electrical and plumbing
embedments. PE/MEP
9. Check stop-ends, waterbar, dowels, flexcell
etc. GF
REINFORCEMENT 10. Check bar placement as per approved bar
bending schedule. SE
11. Check tie wires, spacers, cover. GF
12. Clean out loose material (tie-wires, nails etc). GF
APPROVAL TO POUR QA/QC
PLACING
CONCRETE 13. Check correct mix, slump, temp. Lab
14. Check correct placing, compaction, grout loss
control. GF
15. Take concrete test cubes and log. Lab
16. Recheck line and level. SE/SU
17. Protection against weather condition. GF
APPROVAL TO STRIKE QA/QC
STRIKING 18. Check surface for blemishes. GF
FORMWORK 19. Check cleanliness of forms after striking. GF
QA/QC Quality Assurance/Quality Control, PE Project Engineer, MEP - MEP Co-ordinator, SE
Site Engineer, SU Surveyor, GF General Foreman, Lab Laboratory Technician.
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/05
PAGE 1 OF 2
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
PLACING OF CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

The scope of this procedure covers placing of structural concrete to


achieve the required result using proper placing speed and
compaction technique.

2. PROCEDURE

.1 All concrete placing activities shall be carried out in accordance with


the contract specification and good practice.

Where specifications are not provided or are incomplete, the matter Project Request for
shall be referred back to the Consultant for clarification. Engineer Information

.2 Before commencement of the concrete pour, mix specification, Site Engr/


formwork, and reinforcement shall be checked for compliance. Gen. CONC/04/A
Foreman

.3 Planning for plant and equipment will include crane, pump, Site Engr/
vibrators, the required speed of pour etc. will be undertaken to avoid Gen.
the formation of cold joints, or interruption in delivery schedule. Foreman

.4 Placing and proper fixing of special built-in items, inserts for Site Engr/
mechanical and electrical works, plumbing and drainage Gen.
embedments shall be thoroughly checked prior to placing of Foreman/
concrete. MEP CONC/04/A
Coord./
QA/QC
.5 While pouring mass concrete, planning needs to be done for deciding
followings:

i) Number and location of pumps.


ii) Thickness of layers.
iii) Sequence in case of large area.
iv) Back-up equipment.

.6 On no account will water be added on site to concrete without the Site Site
Consultants approval. Engineer Instruction
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/05
PAGE 2 OF 2
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
PLACING OF CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.7 Ensure adequate illumination for large, deep sections, and thin walls Site Engr/
and columns. Gen.
Foreman
.8 Avoid impact and movement damage to the formwork and Gen.
reinforcement while placing concrete. Foreman

.9 Avoid segregation of concrete. Vibration will not improve the quality Gen.
of segregated concrete. Foreman

.10 Forming large heaps or sloping layers should be avoided. Gen.


Foreman
.11 The layers of concrete should not be too deep, otherwise the weight
of the material at the top makes it difficult to compact the bottom Gen.
layer. Depth of layer depends upon method of compaction. Foreman

.12 Slump tests, noting down temperature of concrete and making Site Engr/
concrete cube shall be carried out as referred in Work Procedure Gen.
CONC/13. Foreman CONC/13/A
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/06
PAGE 1 OF 2
SECTION: DATE OF ISSUE
CONCRETE September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONTROL OF READY MIXED CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure outlines the system of control to be adopted while


using Ready Mixed Concrete (RMC) on site.

2. PROCEDURE
Project
.1 Full specifications of RMC as stipulated in the Contract Specification Manager
will be communicated to the supplier. Mix Design
Project
.2 It is essential to visit the plant before placing the order in order to Manager/
assess the plant, the yard, transport arrangements, competency of QA/QC
personnel, distance to site and testing facilities. Report

.3 While setting up the supply of RMC, the purchaser confirm the


following points with the supplier(s): PD/M
Supplier
i) Back-up supply. PD/M Order
ii) Concrete mixes are clearly understood. PD/M Order
iii) Programme of deliveries. PD/M Order
iv) Rate of supply, method of placing. Supplier Order
v) Location of pour, with access points and discharge position. Order
vi) Suppliers visits to site.

.4 The delivery note must be checked thoroughly and especially before Lab. Tech. Delivery
taking samples for slump test, temperature, cubes and any test Note/
specified in the contract document. Specs.

The Storekeeper must maintain a record of all delivery notes in a file.

.5 Nearing the end of a pour, the actual concrete quantity must be


monitored to ensure that the final load will fully service the measure, Site Engr
and that no waste is encountered. As soon as the pour is completed,
confirm this to the supplier.
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/06
PAGE 2 OF 2
SECTION: DATE OF ISSUE
CONCRETE September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONTROL OF READY MIXED CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.6 Using delivery notes, marked up drawings, and filed data, a


reconciliation statement shall be prepared to compare the quantity of Reconcilia-
RMC received at site with the quantity allowed in BOQ Project QS tion

3. DOCUMENTATION

.1 The following documentation may be used as a minimum


requirement and retained at site during the contract period:

i) Concrete cube register and cube test log.


ii) Mix designs approved for use with additives.
iii) Location of each pour.
iv) Certificates of tests conducted by the supplier on the basic
constituent of concrete.
v) Delivery tickets. Project
vi) Other records will be kept as required by the PQP Manager
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/07
PAGE 1 OF 2
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONCRETE PAVINGS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

The scope of this procedure covers the control of installation of in-


situ concrete paving surfaces including finishes to ensure compliance
with the contract specifications.

2. PROCEDURE

.1 All activities connected with concrete pavings will be carried out in


accordance with the contract specifications. In any circumstances Project
where specifications are not provided or unclear, clarification will be Manager Request for
sought from the Consultants representative. Information

.2 Where necessary a method statement shall be prepared and approved


by the Project Director/Manager. It shall include:

i) The agreed tolerance on level and surface regularity.


ii) Site protection and safety. Project
iii) Mix design details for wearing surfaces. Manager Approved
iv) Method of placing, compacting and finishing concrete. Method
v) Method of curing. Project Statement
Engineer
.3 Source certificates of basic constituents of concrete to be obtained Source
from the supplier to verify compliance with the specifications. Certificates

.4 Ensure that the proposed sequence of work is commenced in


compliance with the contract programme. While framing the
construction schedule, additional allowance shall be made for the
following:

i) Laying under floor services,


ii) Curing and drying of the base concrete before the flooring is Project
laid. Manager
iii) Curing of the flooring,
iv) Period of protection of the completed floor from damage by Contract
other trades, including restriction of access. Programme
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/07
PAGE 2 OF 2
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONCRETE PAVINGS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.5 Special care while laying concrete finishes and wearing surfaces:

i) Where a structural concrete slab itself forms the flooring or


where a topping is laid monolithically or bonded to a
hardened base, the wearing surface shall be adequately
protected against damage during subsequent building Gen.
operations. Foreman CONC/07/A

ii) In hot or drying conditions, care shall be taken that the


concrete mixes do not stiffen or dry out to an extent that
prevents full compaction. After compaction and finishing, the
surface shall not be allowed to dry out quickly and this may
be achieved by protection by plastic sheeting or other suitable
means. In addition where concrete is laid in the open, its
surface shall be protected from the effects of the sun and Gen.
wind to limit the risk of cracking. Foreman CONC/07/A

iii) Compaction of concrete shall be carried out in such a way Gen.


that an excess of `laitance is not brought to the surface. Foreman CONC/07/A

For the highest abrasion resistance, the final trowelling shall


be made when considerable pressure is required to make any
impression on the surface. However excessive trowelling
should be avoided to prevent the production of a polished or
slippery finish. Water shall not be applied between trowelling Gen.
operations as this may cause surface weakness. Foreman

iv) Curing shall be done as specified. Site Engr CONC/07/A

v) When topping is laid separately and bonded, the surface of


the base shall be thoroughly prepared as specified to ensure
proper bond between the topping and the base concrete. Site Engr
Appendix CONC/07/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR CONCRETE PAVINGS Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

STAGE ITEM Checked Date


by
1. Establish datums for finished level of finished
PREPARATION surface. SE/SU

2. Check mix design details. PE


3. Check materials (cement and aggregate) to
specification. PE

4. Check surface preparation. GF

APPROVAL TO PROCEED. QA/QC

CONCRETE LAYING 5. Check compaction (no bleeding shall occur). GF


6. Check an excess of `Laitance is not brought
to the surface. GF

7. Check surface finishing GF

8. Check curing technique being followed. SE

9. Check finished levels are within tolerance. SE

10. Protect surface against damage. GF


11. Check adhesion between concrete topping and
base by tapping for hollowness. SE

APPROVAL TO PROCEED QA/QC

QA/QC Quality Assurance/Quality Control, PE - Project Engineer, SE - Site Engineer,


SU Surveyor, GF General Foreman
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/08
PAGE 1 OF 4
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CURING OF CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

The scope of this procedure covers methods of curing to achieve


specified strength and durability parameters of concrete.

2. PROCEDURE

.1 The procedure to be adopted for curing concrete on site will vary


depending on the type, exposure, location and design mix. The Project Specs/
specification must be consulted first. Engineer approval

It is advised to check the specification and obtain the approval of the


Consultant prior to the adoption of any of the following methods:-

.2 Method One:

Keeping the surface of concrete moist by:

i) Ponding:

This method is normally applied on horizontal surfaces, such


as floor slabs. Water for curing shall be of potable quality and Gen. Curing
free from undesirable levels of dissolved salts. Foreman record

ii) Spraying/Sprinkling Water:

Curing of horizontal and vertical surfaces can be done by


sprinkling water. This method can also be used for curing
inaccessible areas. Care shall be taken that temperature of
water to be used for curing shall be similar to the concrete Gen. Curing
itself. Foreman record

iii) Damp Sand or Hessian:

Materials such as wet hessian or wet sand are used but they
must be kept continually wet and not allowed to dry out.
Constant vigilance is necessary to guard against the
protective material drying out and becoming unless. Careful
supervision is required to see that the hessian is kept properly
Damp throughout the period of curing. It may also cause Gen. Curing
staining. For these reasons it is a practice best avoided. Foreman record
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/08
PAGE 2 OF 4
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CURING OF CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.3 Method Two:

Prevention loss of moisture from the concrete by:

i) Covering concrete surface with polythene sheeting,


ii) Spraying on a curing membrane, Gen. Curing
iii) Leaving the formwork in place Foreman record

i) Polythene Sheeting:

A simple way of keeping moisture in the concrete is to cover


it with polythene sheeting. The polythene sheet shall be
placed in position as soon as possible. Wait until water sheen
has evaporated but not so long that the concrete starts to dry
out. It must be in direct contact with the concrete. It is
important that the exposed edges and corners of the sheet
shall be well fixed down. Otherwise wind and draughts would
get underneath and create a wind-tunnel effect that would dry Gen. Curing
the surface of the concrete. Foreman record

ii) Spraying on a Curing Membrane:

Curing compounds are sprayed on the surface with a hand-


held hose spray. This can be used on either horizontal or
vertical surfaces. Special precautions shall be taken while
using spray-on compounds (manufacturers instructions
regarding use shall also be followed):

a. Surfaces that will not be exposed to bright daylight


shall not be treated with a curing compound if they
are to receive any additional finish viz. screeds,
rendering, paint type finishes or a further layer of
concrete.

b. The compounds shall never be applied to dry surfaces


since these will absorb the compound and staining or
discoloration may result. If the surface has dried out,
wet it down with clean water then spray while it is
still moist.
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/08
PAGE 3 OF 4
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CURING OF CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY

c. Curing compounds do not work if sprayed on top of


water.

d. Use safety precautions while handling these Gen. Curing


compounds. Follow manufacturers instructions. Foreman record

iii) Leaving the Formwork in Place:

When it is in position, formwork protects concrete against


loss of moisture and thus allows curing to proceed.

It is only after it has been struck that further curing of


columns, walls and beams may be necessary. Even where the
formwork is left in place, exposed top surfaces must be cured Gen. Curing
in the normal way. Foreman record

3. EXPOSED CONCRETE

All concrete surfaces that will be permanently exposed to the


weather needs to be cured with extra care and at least for seven days.
Well cured concrete will be more impermeable and better able to
withstand wetting and drying and will have a better long-term Gen.
appearance, since dirt will not collect so easily. Foreman

4. PAVING AND FLOOR SLABS

.1 Always start the curing soon after water sheen has disappeared. For
small paved areas, a curing membrane applied by a hand operated
hose spray is most convenient. Always use compounds, which reflect
the suns rays. Care must be taken that a uniform coat of the
membrane is applied, particularly in windy water when stream of Gen.
compound could easily be blown `off course. Foreman

.2 As a guide, requirements for general curing of in-situ concrete shall


be as shown in Appendix CONC/08/A. The curing record will be Site
documented in the format attached as Appendix CONC/08/B. Engineer QA/QC File
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. CONC/08
PAGE 4 OF 4
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CURING OF CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY

4. DOCUMENTATION

The following documents shall be retained in QA/QC files


maintained at site.

i) Curing record.
ii) Manufacturers catalogue for curing compounds. QA/QC Files
Appendix CONC/08/A
September 2007

Al Rajhi Projects and Construction LLC

GUIDELINES FOR THE CURING OF CONCRETE

SI Type of Construction Curing Material Application


1. Road and airfield pavements, Pigmented resin-based curing Immediately finishing process
open flat slabs, etc. compound with high is complete.
efficiency rating.

Polythene or other impervious Protect with shading for the


sheeting material. first few hours especially in
hot sunshine and high drying
winds
2. Tops of beams and columns. Polythene or other impervious Immediate finishing process is
sheeting material. complete.

Protect with shading for the


first few hours especially in
hot sunshine and high drying
winds
3. Concrete columns, beams, Resin-based curing compound. Immediately formwork is
walls, etc. in hot dry removed.
conditions which are not to
receive subsequent treatment Polythene or other impervious Apply in close contact with
sheeting. surface immediately formwork
is removed.

Formwork itself Leave undisturbed for at least


4 days, preferably 7 days.
4. Concrete columns, beams, Polythene or other impervious Apply in close contact with
walls, etc. in temperate sheeting material. surface immediately formwork
conditions and where is removed.
subsequent treatment is
envisaged Formwork itself Leave undisturbed for at least
4 days, preferably for 7 days.
5. Formed, permanently exposed Insulation As soon as concrete is placed
concrete sections cast in cold and maintain for at least 7
weather Delayed removal of formwork days.
6. Large concrete section with a To surface insulation Maintain for at least 7 days or
minimum thickness or depth until internal temperature
exceeding say 1 m Delayed removal of formwork gradient is minimised.
or replacement of formwork
by insulating material

Some manufacturers of resin-based curing compounds recommend the re-wetting of formed concrete
surfaces before application. To avoid thermal shock, water used for this purpose must be close to the
temperature of the surface of the concrete.
Appendix CONC/08/B
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO:

Consultant: Date of Pour:

CURING RECORD

Structural Member Identification: ____________________________________________________

DATE PERIOD REMARKS SIGNED BY


From To (General Foreman)

Note: Any observed non-conformity of curing may be recorded in the remarks column and instructions passed on to the
General Foreman for corrective action.

Certified by Site Engineer:

___________________________
Name and Signature
Date: ______________________
Al Rajhi Projects and Construction LLC
WORK PROCEDURE
PROJECT: Ref No. CONC/09
PAGE 1 OF 4
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
BATCHING OF CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

The scope of this procedure covers checks required to be carried out


prior to and during the site batching of concrete.

2. PROCEDURE

.1 Checks Prior to Commencement of Activity:

i) Basic constituents of concrete viz. cement, coarse and fine


aggregates shall comply with the contract specifications. In Source
case of large projects and where specified, a laboratory will Certificates
be set up at site for conducting tests on materials and ensured Analysis
product. Refer Work Procedure CONC/13. Report
ii) Availability of potable water and power shall be ensured. In
case of supply failure alternative arrangements shall also be
planned.
iii) Verify the type of admixture if required, to be added. If Project
required, receive approval from Consultants representative. Engineer Approval

.2 Handling and Storage of Materials:

Special care shall be taken for proper storage of basic materials in Operation
order to avoid contamination. Unless otherwise specified, the Manual,
following measures shall be taken for proper handling and storage Site Suppliers
of these materials: Engineer instructions

.3 Cement (in bulk):

i) The silos shall be weatherproof and the mechanism will be


cleaned regularly in accordance with manufacturers manual.
ii) The air filter will be cleaned after every delivery.
iii) Care shall be taken to use stored cement in the order of
delivery.
iv) Care shall be taken to minimise the contact of cement with
air.
v) The silo shall be painted white and wherever possible, shaded Plant Manufactu-
from sun. Operator rers manual

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/09
PAGE 2 OF 4
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
BATCHING OF CONCRETE APPROVED BY:
QHSE MANAGER
ACTION VERIFY

.4 Aggregates:

i) Storage of aggregates shall be on clean; permanent clean


hard-standing laid to fall for drainage.
ii) Different sizes of aggregates shall be separated from each
other in bins or compartments with rigid dividing walls
extending high enough to prevent different aggregates from
being mixed during batching.
iii) In hot climates either shading or sprinkling clean water is
required to reduce that fines and dust have not built up at the
lower levels. If this has occurred, contaminated aggregates
shall be removed and washed or replaced with clean material.
iv) If aggregates are wet stockpiles shall be frequently inspected
to make sure that fines and dust have not built up at the lower
levels. If this has occurred, contaminated aggregates shall be Plant
removed and washed or replaced with clean material. Operator

.5 Admixtures:

i) Storage of admixture shall be as per the manufacturers


recommendations.
ii) The containers shall be levelled to indicate the contents, batch Manufactu-
number, date of manufacture, shelf life and any other Store- rers recom-
requirements for storage. keeper mendation

.6 Water:

i) Water shall be stored as cool as possible, particularly if it has


been supplied by road tanker or shallow wells.
ii) Wherever possible, storage tanks shall be sited below ground.
It this is not possible, they should be at least be shaded from
the sun and painted white.
iii) Tank to be covered properly to prevent the growth of algae.
iv) For cooling of water even site cooling towers can be used Plant
which reduces the temperature up to 10OC or ice can be used. Operator

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/09
PAGE 3 OF 4
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
BATCHING OF CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.7 Plant:

i) Batching and mixing plant shall be pained white and kept


clean.
ii) If possible, mixing and batching plant shall be shaded from
the sun.
iii) Provision shall be made to prevent dust accumulating in the
plant and immediately before it is used each day (or after any
substantial interruption in concreting) it shall be flushed out Plant
with water. Operator
iv) Feed belts and weigh batchers shall be protected from the
wind so that cement cant be blown away.
v) Ensure the accuracy of all weighing and measuring
equipment falls within + 3% unless specified otherwise
calibrate plant as necessary.

.8 Batching by Volume:

i) Prepare gauge boxes or similar standard containers of a size


such that complete filling is necessary when proportioning
materials.
ii) Clear written instructions will be provided to the Plant
operator on quantities of all materials to be batched and
batching sequence for each mix required.
iii) Priming of internal drum of mixer to be done at the time of
loading the first batch of materials.
iv) Mix ingredients for sufficient time as specified to ensure
uniform distribution of materials.
v) Check the zero reading when hopper is empty.
vi) Check the speed of mixer drum once a week and adjust to
that given in the manufacturers manual.
vii) Regular maintenance of moving parts shall be done in
accordance with the manufacturers manual.
viii) Transport the concrete with minimum delay so that it is
placed before it comes hardened and difficult to place and Plant
compact. Operator

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/09
PAGE 4 OF 4
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
BATCHING OF CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY

3. DOCUMENTATION

.1 Following documents may be appropriate as a minimum Project


requirement: Engineer

i) Test certificates of cement, aggregates, water and admixtures.


ii) Mix design details.
iii) Calibration record of all equipment of batching plant.

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/10
PAGE 1 OF 1
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
POST CONCRETE INSPECTION APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

The scope of this procedure covers the inspection to be carried out


after concrete is poured in order to control curing and identify
surface defects for rectification.

2. PROCEDURE

.1 Methods and periods of curing need to be reviewed daily. Site


Engineer CONC/10/A
.2 Removal of hardened grout leak will be by careful chipping with a
piece of hardwood or a bolster. If the joint between formwork and
hardened concrete has not been sealed properly, there may be
lipping, sandy areas and honey combing. For high quality finishes,
though, it will be necessary to cut back the lip, tempering it to reduce
the scale of the defect. Patching and finishing can then be carried out.

.3 If blow holes are larger than 5mm fill with 1:1.5 cement and sand
rubbed in with wet rubber face of the float, unless specified
otherwise. Remedial work will be carried out with the approval of
the Consultant.

Honeycombed areas of a depth greater than 10mm shall be made


good. Such areas will be repaired with the approval of the
Consultants Representative. Approval

.4 Tie rod holes will be filled with 1:3 cement and sand semi-dry mortar
well rammed in and finished flush with the face of the concrete Gen.
unless specified otherwise. Foreman Approval

3. DOCUMENTATION

Checksheet for post concrete inspections will be as Appendix Project


CONC/10/A and adapted as necessary for project use. Manager Checksheet

Appendix CONC/10/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR POST CONCRETE INSPECTION Sheet No.

SUBCONTRACTOR: AlRajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE

CURING 1. Check required method of curing adopted. SE

2. Ensure proper curing period. SE

3. Randomly inspect curing process. SE


SURFACE 4. Check any major defect viz. blemishes,
CONDITION honeycombing, voids, ridges, etc and rectify. SE

5. Arrange caulking of the holes. GF


6 Inspect cracked spalled areas and plan for
repairs. SE
7. Check dimensions of members (deviation to be
within tolerance limit). SE

APPROVAL TO PROCEED QA/QC

QA/QC Quality Assurance/Quality Control, SE Site Engineer, GF General Foreman

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/11
PAGE 1 OF 5
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONSTRUCTION JOINTS IN IN-SITU CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY
1. SCOPE

The scope of this procedure outlines methods to be used for


constructing effective and durable construction joints in accordance
with the contract specifications.

2. PROCEDURE

.1 In some cases Al Rajhi shall have to prepare shop drawings Project


proposing location and type of construction joints and obtain Manager Drawing
approval from the Consultants representative before proceeding with Approval
the work.

.2 Horizontal Surfaces:

Laitance on the surface must be removed from the concrete in order Project
to ensure that a good bond will be achieved when fresh concrete will Engr/Gen.
be placed against it. Following methods may be used for removing Foreman
laitance from the top of walls and columns unless specified otherwise
in the contract:

i) Washing and Brushing:

The easiest way is to brush off the laitance while the concrete
is still fresh but has stiffened slightly. Brushing shall be
commenced between one to two hours after placing of
concrete. Site operatives shall have brushes with soft and
hard bristles so that it can be used depending upon stiffness of
concrete. Care shall be taken that the brushing shall not be
harsh which will dislodge the coarse aggregates. In case
laitance has hardened but is still green, a wire brush should be
used.

ii) Air and Water Jet:

Laitance can be removed by directing a jet of air and water


onto it. This method can be used up to six hours after placing
or possible longer but the site operative must make his own
judgement while adopting this method. This operation must
not start too soon because it might dislodge coarse aggregate
particles.
Al Rajhi Projects and Construction LLC
WORK PROCEDURE
PROJECT: Ref No. CONC/11
PAGE 2 OF 5
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONSTRUCTION JOINTS IN IN-SITU CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY

iii) Mechanical Scabbling:

If laitance is too hard to be removed by wire brushing,


mechanical scabbling can be tried using small percussion
power tools. This method can be applied after 3 days when
concrete has hardened sufficiently. Care shall be taken not to
weaken the coarse aggregates.

iv) Abrasive Blasting:

Wet or dry abrasive blasting can be used to expose the


aggregate but special safety precautions shall be taken while
using sand.

.3 The most appropriate time for treating the joints is a matter of Project
judgement, because it depends on the rate of setting and hardening Engr/Gen.
(which is itself dependent on the temperature of the concrete). Foreman

.4 Where there is likely to be even a short delay before placing the next
concrete pour, protruding reinforcement should be protected. Before Site
the next pour is placed, rust, loose mortar or other contamination Engr/Gen. Contract
should be removed from the bars. Foreman Specs.

.5 Vertical Surfaces:

i) Stop Ends/Expanded Metal Mesh:

Vertical joints in walls, beams and slabs are usually formed at


a stop end in the formwork. Stop ends shall be located where
the reinforcement is least dense. Holes for reinforcement in
stop-ends are a potential weakness because grout loss can
occur. In lightly reinforced sections and where starter bars are
acceptable, this problem is frequently avoided by bending
bars so that they run along the inner face of the stop-end.
When the stop-end is removed, the bars are cut out and
straightened. However, the cutting out and straightening can
damage the concrete and cause local loss of bond with the
bar, especially if this is carried out within 48 hours of placing
the concrete.

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/11
PAGE 3 OF 5
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONSTRUCTION JOINTS IN IN-SITU CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY

Proprietary stop-ends have been developed which overcome


this problem by encasing the bent bars in expanded plastic
foam. The foam can easily be removed and the bars
strengthened by means of a steel tube. Take particular care
not to use impact to straighten bent steel at stop-ends as this
can cause brittle fracture.

Permanent forms of expanded metal are increasingly


employed, particularly in deep slabs. The concrete surface
produced by such system is very irregular and does not
normally require any surface preparation. Where a very high
workability mix is being used (slump greater than 200mm)
with expanded metal formwork, care should be taken to avoid
over - vibration at the joint as this may cause grout loss.

ii) Formwork:

Formwork for subsequent concrete pours must be accurately


aligned and well fixed so that there is no grout leak which
results into discoloration and honey combing. Strips of foam
rubber or polyurethane unless specified otherwise can be
fixed around the edge of the hardened prepared joint.

.6 The methods explained previously i.e. washing and brushing,


mechanical scabbling and abrasive blasting can also be used in case Site
of vertical joints. However special care shall be taken not to damage Engr/Gen. Contract
the leading edges (leave a margin). Foreman Specs.

.7 Watertight Construction:

i) In watertight construction unless specified otherwise, flexible


waterbars of specified details can be used. Care shall be taken Site
while concreting so that all waterbars are securely tied to Engr/Gen. Contract
avoid its folding during concreting. Foreman Specs.

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/11
PAGE 4 OF 5
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONSTRUCTION JOINTS IN IN-SITU CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.8 Cold Joints:

i) Cold joints normally occur during the concreting operation


when a delay in placing adjacent concrete has occurred and
earlier concrete placed has stiffened.

ii) A simple test can be used to determine whether concreting


can proceed. Embed the poker vibrator into the existing
concrete to examine the condition of concrete. Where the
action of the poker has left a distinct hole, concreting Site
operations should not continue. In this case the joint face can Engr/Gen.
be prepared by one of the methods described above for Foreman/ Contract
horizontal construction joints. QA/QC Specs.

.9 Placing the Fresh Concrete:

i) Particular care as explained below shall be taken while


placing and compacting new concrete on or against the old:

ii) Any dirt or dust from the surface of the hardened concrete
shall be removed preferably with a compressed air hose. As a
safety precaution site operatives must wear safety goggles.
This cleaning shall be done before new formwork is fixed
because not only access be easier than but also dirt might
otherwise stick to the new formwork.

iii) While fixing a new formwork extra dirt is created which can Site
be cleaned after removing a stop end - which will make it Engr/Gen. Contract
easy to be swept or blown away. Foreman Specs.

.10 Joint Sealing:

i) Where the structural component containing the joint is to be


exposed to the external environment, the joint has to be
sealed to prevent ingress of water. For type and method of Site
application refer to the contract specifications and/or Engr/Gen. Contract
manufacturers instructions. Foreman Specs.

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/11
PAGE 5 OF 5
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONSTRUCTION JOINTS IN IN-SITU CONCRETE APPROVED BY:
QEHS MANAGER
ACTION VERIFY

3. DOCUMENTATION

Following documentation and forms may be maintained as a Project


minimum pending on Project Quality Plan requirements and contract Manager
specification.

i) Contract and/or approved workshop drawings.


ii) Manufacturers test certificates (in case of sealants and
waterbars).
iii) Request for Consultants consent/approval.
QEHS
The above referenced documentation where appropriate will be Manager
retained in the HEE archive for the prescribed period of time.

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/12
PAGE 1 OF 4
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
GROUND FLOOR SLABS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure applies to insitu industrial ground floor slabs with a


tolerance of + 3mm or tighter.

2. PROCEDURE

.1 Prior to Placing Subcontract Order check the specification to ensure Project Clarify any
the full extent of tolerances and surface finish is understood. Manager areas of
uncertainty
.2 Order to be placed only when all parties have agreed tolerances,
method of checking slab and acceptable remedial actions in the event
of non-compliance. Project
Manager Elemental
Note: levels of `superflat floors (tolerance less than + 3mm in 3m) Quality Plan
to be checked using a parallel plate level.

.3 Check Ready-Mix Capability:

i) Plant inspection.
ii) Assessment of mix. Project
iii) Approval of design mix. Engineer Record
iv Capability to provide quantity/quality/type of mix. File
v) Technical back-up.

.4 A method statement is to prepared and approved by the Project


Director/Manager prior to commencement of work. The method Project
statement may be submitted for approval by the Consultant. The Manager Approved
method statement will include proposed plant, labour levels, mix Method
design, jointing details, sequence of pour, full details of guaranteed Statement
tolerances, any remedial works required to achieve tolerances.

.5 Particular Attention is to be Paid to the Method of Ensuring: Project


Manager
i) full compaction Approved
ii) concrete level of reinforcement Method
iii) pour sizes and sequence Statement
iv) achievement of surface finish, within tolerances

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/12
PAGE 2 OF 4
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
GROUND FLOOR SLABS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.6 Check all Al Rajhi Materials on Site:

i) Polythene as specified
ii) Spacers
iii) Mesh and bar reinforcement
iv) Joint Formers and dowel bars Site Method
v) Flexcell Engineer Statement

Site Engr/
.7 Procedure organised for checking of loads (for specification). G.Fman
Site Engr/
.8 Procedure agreed for reject loads. G.Fman
Site Engr/
.9 Procedure agreed for checking and signatures. G.Fman
Site Engr/
.10 Joint placement agreed. G.Fman
Site Engr/
.11 Dowel bar setting agreed. G.Fman
Site Engr/
.12 Power-float approximate start/finish time agreed. G.Fman
Site Engr/
.13 Curing method. G.Fman
Site Engr/
.14 Saw cutting timing G.Fman

.15 Prior to commencing each pour check sub-base at least 1m beyond Site
pour fully compacted and to correct level. Engineer
Site
.16 Check sand blind and final roll. Engineer
Site
.17 Check polythene positioned and laps correct. Engineer
Site
.18 Position and level road forms or screed rails. Engineer

.19 Pour starts early enough to allow sufficient time for finishing trades. G.Fman

.20 Truck cycle times are acceptable. Site Engr./


G.Fman
.21 Marshalling of trucks organised. G.Fman

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/12
PAGE 3 OF 4
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
GROUND FLOOR SLABS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.22 Turning areas are available. Gen.


Foreman

.23 Preparation Check List: Site Engr/ Permit to


QA/QC Pour,
i) Sub-base agreed beyond pour. CONC/12/A
ii) Road forms or screed rail correct level.
iii) Isolation joints complete.
iv) Polythene pre-set.
v) Compressor working and fuelled up.
vi) Airlines laid out and not damaged. Pokers are working.
vii) Distribution plant ready. Pump and hoses positioned, concrete
skip cleaned out.
viii) Beam vibrators all working.
ix) Shovels/rakes and other hand tools available, including bull
float, follow-up screed.
x) Back-up plant working.
xi) Mesh pre-cut if not already placed.
xii) Mesh properly spaced and correct level.
xiii) Mesh at induced joints pre-wired to stools.
xiv) Cast in items and box-outs fitted and to correct level.
xv) Dowelbars ready. (Debonded, end caps for movement joints).
xvi) Stop ends pre-made.
xvii) Power floats and trowels ready and working.
xviii) Saw cutter organised.
xix) Cube moulds ready, oiled and covered. Thermometer ready
for noting down temperature of concrete.
xx) Cube tank available and to correct temperature.
xxi) Slump cones and associated equipment ready.
xxii) Straight edge cleaned and available.
xxiii) Curing equipment/materials ready.
xxiv) Washing out facilities available.
xxv) Joints marked on forms.
xxvi) Chalk line available for saw cuts.

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/12
PAGE 4 OF 4
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
GROUND FLOOR SLABS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.24 During and Immediately After Pour: Site Engr/ CONC/12/A


QA/QC
i) Check correct mix, slump temperature, etc.
ii) Check correct placing.
iii) Check reinforcement in correct position.
iv) Check compaction carried out.
v) Check test cubes taken and logged.
vi) Check line and level of forms and poured concrete.
vii) Check dowel bars in correct alignment.
viii) Check timing of floating off, etc.
ix) Re-check slab for correct tolerance (3m straight edge).
x) Protect and cure concrete.

.25 Day After Pour: Site Engr/ CONC/12/A


QA/QC
i) Check slab for acceptable tolerances.
ii) Action remedial works if required in consultation with the
Consultant.
iii) Strike forms and saw cut joints.
iv) Check for blemishes and grout loss, etc.

v) Re-position curing membrane for a minimum of 7 days.

vi) Protect slab against damage. Do not store anything on slab or


traffic for 7 days minimum.

Appendix CONC/12/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR CONCRETE GROUND FLOOR SLAB Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE
PREPARATION 1. Check base preparation inc. blinding and dpm. GF
2. Check quality of forms required finish and
straightness. GF
3. Check dimensions, line and level.
(Note: check level at 1m crs. max) SE/SU
4. Check preparation of forms inc. support,
release agent, etc. GF
5. Check stop-ends, dowels, crack inducers, Flexcell,
etc. GF
6. Check special built-in items. Inserts, ducts,
drainage, box-outs etc. PE/MEP
7. Check size, orientation, placing of reinforcement.
Tie wires, spacers, laps, cover. SE
8. Clean out loose material. tie wire, nails etc GF

APPROVAL TO POUR QA/QC


PLACING 9. Check correct mix, slump and temperature. Take
CONCRETE cubes regularly throughout concrete deliveries. SE/Lab
10. Check placing, compaction, correct use of
vibrating tamp, dowel bar alignment. SE
11. Recheck line and level of forms, adjust as
necessary. SE
12. Check correct timing and use of power floats and
trowels. GF
13. Check tolerance of slab with 3m straightedge
after each pass of float/trowel. GF
14. Protection against weather conditions. SE
DAY AFTER
POURING 15. Recheck slab for tolerance and finish. SE
16. Check saw cutting of induced joints. GF

APPROVAL TO PROCEED QA/QC


17. Minor items attended to PE
QA/QC Quality Assurance/Quality Control, PE - Project Engineer, SE - Site Engineer,
MEP MEP Coordinator, SU Surveyor, GF General Foreman, Lab Laboratory Technician
Al Rajhi Projects and Construction LLC
WORK PROCEDURE
PROJECT: Ref No. CONC/13
PAGE 1 OF 5
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
SLUMP TEST AND TAKING TEST CUBES APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure applies to slump testing and concrete test cubes made
and cured at site to check the workability and strength of concrete
respectively.

2. REFERENCE

.1 For full details of tests and equipment refer to following British


Standard unless specified otherwise:

i) BS EN 12350: Part 1: 2000 Testing Fresh Concrete


Sampling
ii) BS EN 12350: Part 2: 2000 Testing Fresh Concrete
Slump Test
iii) BS 1881: Part 108: 1983 - Method for Making Test Cubes
from Fresh Concrete
iv) BS 1881: Part 111, 1983 - Method of Normal Curing of Test
Specimens (20C method) Lab. Tech.

3. PROCEDURE

.1 Obtain 4 Representative Samples from Mixer:

Equipment : A scoop to hold 5kg


A bucket to hold 20kg

Personnel : This procedure will be operated by the


laboratory technician.

Method : i) Ideally obtain sample in at least four


separate increments
iii) One after first one fifth of load has
been discharged, then one from each
remaining fifth of the load.
iii) Obtain sample by passing the scoop
through and across the stream of
concrete. Lab Tech.

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/13
PAGE 2 OF 5
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
SLUMP TEST AND TAKING TEST CUBES APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.2 Obtain a Uniform Sample:

Mix sample thoroughly using a square mouthed shovel on a mix tray.

.3 Make a Test Cube:

Unless otherwise specified 4 No. cubes should be made for each


sample to be tested.

i) 2 to be tested at 7 days.
ii) 2 to be tested at 28 days.

Equipment : Spanner to fit nuts on mould, trowel, standard


tamping bar, small scoop, mould oil and small
paint brush.

Method : Using a uniform representative sample of


concrete.

i) Make sure that the cube mould is correctly assembled, clean,


lightly coated on the material face and joints with a
proprietary mould oil and all nuts are secure.
ii) Stand mould on a firm base and fill with concrete to a depth
of approximately 50mm.
iii) Thoroughly compact the layer of concrete by tamping the
whole surface of the concrete with the standard tamping bar.

Note:- The number of tamps required to achieve full compaction will


vary depending on workability of the concrete but in no case should
the number of blows be less than: Lab. Tech.

150mm moulds - 35 tamps/layer


100mm moulds - 25 tamps/layer

iv) Repeat the process described in step (iii) until the mould is
filled.

150mm moulds - 3 layers


100mm moulds - 2 layers

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/13
PAGE 3 OF 5
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
SLUMP TEST AND TAKING TEST CUBES APPROVED BY:
QEHS MANAGER
ACTION VERIFY

v) Trowel the top surface level.


vi) Cover the surface of the concrete with a piece of damp
sacking or similar material.
vii) Cover the damp sacking with a waterproof membrane such as
polythene.
viii) Ensure cubes are kept in a place free from ventilation and at
temperature of 20C for 16-24 hours.

Note:
Do not forget to clean equipment.
The Laboratory Technician must be aware of the cost of
making cubes wrongly. Lab. Tech.

.4 Referencing and Curing Concrete Test Cubes:

Equipment : Thermostatically controlled curing tank 20C+


2C, paint scraper, spanner to fit nuts on cube
moulds, small hammer, crayon or waterproof
black felt marker.

Method : i) Clean off top of cube mould with paint


scraper, clean with wire brush.
ii) Slacken nuts on side of cube moulds.
iii) Slacken nuts on cube mould base plate
and withdraw locking lugs.
iv) Generally tap the bolt lugs on side of
cube mould to part the two halves of
the mould.
v) Lift the mould carefully off the
concrete cube.
vi) Using crayon write reference number
on topside of the concrete cube.
vii) Immediately place cube in clean water
at temperature of 20C + 2C until
required for testing.
Temp.
viii) Take daily reading of water
Records
temperature and record.
ix) Change the water in the tank at least
once a month.
Al Rajhi Projects and Construction LLC
WORK PROCEDURE
PROJECT: Ref No. CONC/13
PAGE 4 OF 5
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
SLUMP TEST AND TAKING TEST CUBES APPROVED BY:
QEHS MANAGER
ACTION VERIFY

x) Cubes will be sent to an approved


testing Laboratory or testing. After the
test results are received, they shall be
entered in the Concrete Test Cube and
Slump Test Record as Appendix
CONC/13/A. A copy of test results will
be forwarded to the Consultant for
information. Test Record

.5 Making a Slump Test:

A slump test shall be taken for every truck mixer prior to allowing
the concrete to be unloaded. Lab. Tech. Field book

Equipment : Slump cone, slump rod, rigid flat base rule

Method : i) Obtain a uniform sample as in section


3.2. For a slump test, the sample may
be obtained by taking six scoopfuls
after the first one third cubic meter has
been discharged.
ii) Check the slump cone is clean, damp
and placed on the foot pieces.
iii) Fill the cone in 3 equal layers, rodding
each layer 25 times. Make sure the rod
penetrates the layer below. The 3rd
layer shall be heaped above the top of
the cone
iv) With the rod strike off the concrete
level with the top of cone.
v) Clean away spillage from base then
carefully lift the cone clear of the
concrete.
vi) Invert the cone and place alongside the
slumped concrete. Place the rod across
the top and measure the vertical
distance from the underside of the rod
to the highest point of the slumped
concrete.

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/13
PAGE 5 OF 5
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
SLUMP TEST AND TAKING TEST CUBES APPROVED BY:
QEHS MANAGER
ACTION VERIFY

vii) There are three types of slump:

True
Collapse
Shear

4. DOCUMENTATION

.1 Record the results of tests in the format as Appendix CONC/13/A to


the nearest 5mm.
Compression
.2 Appendix CONC/13/B may be used to record external test cube Site Engr/
Lab. Tech. Test Records
preparation, reference and submission to laboratory test.

.3 For internal testing requirements, Appendix CONC/13/C shall be


used for cube compression test order. Test results will be reported as CONC/13/C,
Appendix CONC/13/D and certified by the Company Material CONC/13/D
Engineer. Lab. Tech.

.4 A record will be maintained of standard deviations of 28-day cube


results on an ongoing basis. Copies of such records will be
forwarded to the Material Engineer and QEHS Department on a Laboratory Standard
monthly basis. Technician Deviations
Appendix CONC/13/A
September 2007
Al Rajhi Projects and Construction LLC

CONCRETE TEST CUBE AND SLUMP TEST RECORD

TRACEABILITY STRENGTH RESULTS

NO. LOCATION STRUCTURAL MEMBER CUBE REF. CONC. DATE SLUMP 3 DAYS 7 DAYS 28 DAYS COMMENTS
IDENTIFICATION NO. GRADE CAST IN (M.M)

SIGNATURE OF SITE ENGINEER:______________________________ SIGNATURE OF LAB TECHNICIAN:_________________________________


Appendix CONC/13/B
September 2007

Al Rajhi Projects and Construction LLC


SITE ORDER

FOR COMPRESSION TESTS ON CONCRETE CUBES

NO. _____________ DATE: _______________

TO: ______________________________________________________________________________

FROM (SITE NO.): ___________________ TEL NO. _______________ FAX NO. _____________

P.O. BOX: ________________________________________________________________________

CONCRETE MIX DETAILS

SPECIFIED STRENGTH @ 7 DAYS ___________________ @ 28 DAYS ___________________

ELEMENT CONCRETED ___________________________________________________________

CUBE DETAILS

DATE CAST ______________ TIME OF CASTING _____________ SLUMP ______________MM

SITE REMARKS: ___________________________________________________________________


__________________________________________________________________________________

CUBE NO.

DATE OF

AGE AT TEST

REMARKS

_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________

AUTHORISED BY ____________________________________ STATUS __________________

NAME ______________________________________________ DATE ____________________


Appendix CONC/13/C
September 2007

Al Rajhi Projects and Construction LLC

Al Rajhi CONCRETE CUBE COMPRESSION TEST ORDER

Client :

Contractor :

Consultant :

Project No. :

Project Name :

Structural Ref. :

Source of Material : No. of Cubes :


Place Sampling/Casting : Nominal size (mm) :
Method of
Date Sampling : Compaction: : Manual (Hand)
Equipment of
Sampling Method : BS EN 12350-1: 2000 Compaction :
Curing/Storage (site) : Sampled by :
Cube Prepared by : Test Method :
Client Rep. Signature : Concrete Grade :

Client Cube No.


Date Cast
Required Test Age
Lab. Id. No.
Checked Nom Dim Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No
L

Dimensions W
(mm)
H

Mass (kg)
Density (kg/m)
Max.Ld. at F. (kN)
Fracture Type
Cube Strength

FOR Al Rajhi USE


ONLY :

DATE OF TEST ____________________ AGE (DAYS) ___________________REPORT NO. : ___________________

TESTED BY : __________________________________ CHECKED BY : ____________________________________


Appendix CONC/13/D
September 2007

Al Rajhi Projects and Construction LLC

Al Rajhi CONCRETE TESTING LABORATORY

REPORT ON COMPRESSIVE STRENGTH OF CONCRETE CUBES

Client : Report :

Contractor : Date Reported :

Consultant : Request No. :

Project No. :

Project Name :

Structure Reference :

Source of Material : No. of Cubes :

Place Sampling / Cast : Time: Nominal Size (mm) :


Method of
Date of Sampling : Compaction :

Sampling Method : BS EN 12350-1: 2000 Concrete Grade :

BS 1881: P 116 : 1983 (Amd


Test Method : 6720/91)

Date Test :

Actual Test Age :

Requested Test Age :

Tested By :

Specimen Client Mass As Density Max Load at Comp. Type of Fracture


No. Cube Ref Dimensions Received As Fail. Kn Strn.
(mm) Kg Received N/Mm
Kg/m
L W H
1

Certified by the Material Engineer:

___________________________
Name and Signature

Date: ______________________
Al Rajhi Projects and Construction LLC
WORK PROCEDURE
PROJECT: Ref No. CONC/14
PAGE 1 OF 2
SECTION: DATE OF ISSUE
CONCRETING September 2007
SUBJECT: BY:
QA/QC ENGINEER
FLEXIBLE SHEET TANKING AND DAMP-PROOF MEMBRANES APPROVED BY:
FOR UNDERGROUND SUBSTRUCTURES QEHS MANAGER
ACTION VERIFY

1. SCOPE

The scope of this procedure covers the installation of waterproof


protection to horizontal and vertical surfaces of concrete and
blockwork substructures.

2. PROCEDURE

.1 Refer to Project Quality Plan, drawings and manufacturers


instructions prior to commencement or application. Primers, PQP,
membranes and boards need to be hot climate grade and uniformly Project Drawings,
installed. Engineer Instructions

.2 Concrete must be fully cured prior to application. Site CONC/14/A


Engineer
.3 All surfaces to be protected will be inspected and all arises and
non-conformities will be removed or made good prior to priming,
painting, or covering. Application will take place on clean, dry, Site
smooth surfaces only. Engineer CONC/14/A

.4 Care will be taken to ensure that liquid - applied membranes are Site
applied uniformly and consistently, according to manufacturers Engr/Gen.
instructions. Foreman CONC/14/A

.5 Bonding to the substructure may be achieved by using a cold-


applied membrane with a bonding primer, or a torch on system,
depending on the specification.
Site Specs./
.6 Hot-applied systems will require safety precautions. Engr/Safety Project
Officer Safety Plan
.7 Protection of horizontal and vertical surfaces against damage to the
applied membrane may be achieved by boarding as specified. Site
Alternatively a sand/cement screed may be acceptable. Engineer Specs./PQP

.8 Care must be taken in applications to angled features. Fillet pieces


will be used with bonded systems with reinforcing where such Site
angles occur. Engineer Specs.

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. CONC/14
PAGE 2 OF 2
SECTION: DATE OF ISSUE
CONCRETING OCTOBER 2005
SUBJECT: BY:
QA/QC ENGINEER
FLEXIBLE SHEET TANKING AND DAMP-PROOF MEMBRANES APPROVED BY:
FOR UNDERGROUND SUBSTRUCTURES QEHS MANAGER
ACTION VERIFY

.9 Junctions with Damp-Proof Membranes and Courses will be made Site Engr/
in accordance with specified requirements. Cleaning, lapping and Gen
bonding will be completed and inspected on completion. Foreman CONC/14/A

.10 Where cables, pipes or ducts pass through the membrane, the
junctions will be made watertight using proprietary collars used in Site
accordance with manufacturers instructions. Engineer Specs.

.11 Following installation inspections will take place. Non-conforming Non-


workmanship will be corrected prior to backfilling and verified on conformity
the Appendix CONC14/A. QA/QC Report

Appendix CONC/14/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR CONTROL OF TANKING AND Sheet No.


WATERPROOFING BELOW GROUND

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE
1. Manufacturers instructions and specifications
PRELIMINARY consulted. PE

2. Concrete fully cured, where applicable. SE

3. Area of application prepared and accessible. SE


4. Services entries prepared as required for system
of waterproofing. PE/MEP

APPROVAL TO PROCEED QA/QC

APPLICATION 5. Primer applied and dried completely. GF


6. Liquid (Paint - applied)
Membrane (Hot - applied)
Membrane (Cold - applied)
used in accordance with specified requirements. SE

7. Internal angles filleted (bonded sheet systems only) GF

8. Junctions with Damp-Proof Coarse made good. GF

9. Junctions with service openings made good. GF


POST
APPLICATION 10. Protection board, screed installed. GF
APPROVAL TO PROCEED WITH
BACKFILLING CM

CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE - Project Engineer,


SE - Site Engineer, MEP MEP Coordinator, GF General Foreman
Al Rajhi Projects and Construction LLC
WORK PROCEDURE
PROJECT: Ref No. FINI/01
PAGE 1 OF 3
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONTROL OF BLOCKWORK APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure provides a method of control for construction of


block masonry work in order to achieve compliance with the contract
specifications and drawings.

2. PROCEDURE

.1 All precast concrete masonry blockwork will be carried out in


accordance with the specification and Project Quality Plan.

In any circumstances where specifications are not provided or they Project


are in any way incomplete, the matter shall be referred back to Manager Request For
Consultants representative for additional information. Information

.2 Checks Prior to Start of blockwork:

i) Ensure that the area to receive the blockwork is as per the


contract drawings and approved finishing schedule.
ii) Check if preceding activities have been inspected and
approved.
iii) Ensure that blocks are procured from approved manufacturer
(s). Except where otherwise approved in writing each
material shall be obtained from a single source. FINI/01/A,
iv) Source certificates shall be obtained for all raw materials e.g. Project Source
sand, cement and blocks to show compliance with the Engineer docs,
contract specification. approvals

.3 Handling and Storage of Materials:

i) Blocks shall be delivered to site palletised, off loaded as near Store-


to the point of use as practicable on a clean hard surface free keeper
from contamination by mud or surface water. Store-
ii) Cement shall be stored off the ground, kept dry and used in keeper
order of delivery. Store-
iii) Store metal ties and straps under cover and protect them from keeper
damage and distortion.

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. FINI/01
PAGE 2 OF 3
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONTROL OF BLOCKWORK APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.4 Preparation of Work, Materials and Components:

i) When the materials and components are distributed to the Site


work area, ensure that the structure is not overloaded. Engineer
ii) Plan for scaffolding material required for block work at
heights. Plan for additional manpower for lifting blocks at Site
heights. Engineer
iii) Set out anticipating the position of openings etc. in the work
above to avoid unnecessary cutting and adjustment of Gen.
masonry units leading to incorrect or uneven bonding. Foreman

.5 Preparation of Mortar Mixes:

i) Mortar shall be mixed by machine except for small quantities


only (not containing plasticiser). Hand mixing (if permitted) Gen.
may be done on a watertight platform. Foreman
ii) When mixed at site, batch boxes shall be used to ensure Gen.
correct and consistent mix proportions. Foreman
iii) Use mortars (other than retarded mortars) within 2 hours of Gen.
mixing or as specified. Foreman

.6 Building Blocks Walls:

i) Build block work within permissible deviations as specified. Site Engr


ii) Unless otherwise specified/permitted, lay blocks on a full bed
of mortar and fill all joints. Keep courses levelled and
perpend vertically aligned. Plumb quoins and all faces as the
work proceeds. It is preferable to Align vertically every fifth
or sixth perpend and `even out the size of Intermediate joints. Gen.
Try to keep horizontal joints of uniform thickness. Foreman FINI/01/A
iii) Do not carry one course more than the height specified in the Gen.
contract specifications. Foreman
iv) Rake out joints as work proceeds, on all faces to be plastered Gen.
or rendered. This will provide a good key for the coating. Foreman
v) If pointing is specified, the mortar used for the pointing
should not be stronger than that used when constructing the Gen.
wall unless specified otherwise. Foreman

Al Rajhi Projects and Construction LLC


WORK PROCEDURE
PROJECT: Ref No. FINI/01
PAGE 3 OF 3
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONTROL OF BLOCKWORK APPROVED BY:
QEHS MANAGER
ACTION VERIFY

vi) All blockwork shall be bonded to adjacent reinforced


concrete structures by means of galvanised mild steel cramps Gen.
at specified spacing unless specified otherwise. Foreman
vii) Partitions shall be bonded to main walls by toothing as Gen.
specified in the contract. Foreman

.7 Chases and Holes:

Cut chases and holes neatly and without damaging the walls as per Gen.
the following unless specified otherwise: Foreman

i) Chases in blockwork to be less than 75mm.


ii) For hollow units maintain a minimum of 15mm thickness
between bottom of chase and void.
iii) Do not cut horizontal or raking chases to a depth exceeding
one-third the thickness of the single leaf in walls or leaves
contracted of solid units.
iv) Holes shall not exceed 300mm x 300mm unless specified
otherwise.
v) Do not cut chases back-to-back exceeding the dimensional
restrictions in (i),(ii) and (iii). Offset such chases in line by a
distance at least equal to the wall thickness.
vi) It is preferable to use mechanical rotary cutters, particularly
when it is necessary to avoid heavy impact and vibration. The
number and position of chases shall be strictly in accordance
with the specification since unauthorised chasing might
adversely affect one or more of the functional requirements of
the walls e.g. its loadbearing capacity.

.8 Appendix FINI/01/B shall be used to record deliveries of blocks if Site Blocks Site
required by the specification. Engineer Register

Appendix FINI/01/A
September 2007
Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR CONTROL OF BLOCKWORK Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE
PRIOR TO BLOCK-
WORK 1. Setting out (openings etc.) SE/SU
2. Check source certificates of blocks, sand and
cement. PE

3. Check mix proportion of mortar. GF


CHECKS DURING
BLOCKWORK 4. Check alignment/width of perpends. GF

5. Check line and level of courses. GF

6. Check metal ties. GF

7. Check raked out joints. GF


8. Check toothing at joint of main wall with
partitions. GF

9. Check compliance of chases with specifications. GF

APPROVAL TO PROCEED WITH THE NEXT


TRADE QA/QC
QA/QC Quality Assurance/Quality Control, PE Project Engineer, SE Site Engineer,
SU Surveyor, GF General Foreman
Appendix FINI/01/B
September 2007
Al Rajhi Projects and Construction LLC

SITE REGISTER (BLOCK)

PROJECT NAME: ______________________________________ BUILDING PERMIT NO. ___________________________________

AREA: ____________ PLOT NO.: _______________________

BLOCK REQUIRED: _______________ SIZE: ______________ CONTRACTOR: __________________________________________

CONSULTANT: __________________________________________

DATE OF INVOICE CONSULTANT'S INSPECTOR'S


NO. LOT SIZE FACTORY NAME LOT NO. C.O.C. NO. REMARKS
PRODUCTION NO. SIGNATURE SIGNATURE
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/03
PAGE 1 OF 1
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
PLASTERING AND RENDERING APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

The procedure applies to the plastering and rendering of solid


background walls suitable to receive tiles or decoration.

2. PROCEDURE

.1 Plastering will be carried out in accordance with Contract


specification and Project Quality Plan. In any circumstances where
specifications are not provided or they are in any way incomplete, Project Request For
the matter shall be referred back to the Consultant for additional Manager Information
information.

.2 A Method Statement shall be prepared stating:

i) The agreed levels of accuracy as specified in the contract.


ii) The requirements for preparation of the background, e.g.
raking-out, keying fixing expanded metal, priming etc.
iii) Detail at junctions between different background materials,
e.g. blockwork abutting concrete surfaces, lintels etc.
iv) Mix proportions (for render). Project
v) Method of protecting existing works. Manager Method
vi) Safety aspects during execution of work. Statement
vii) Any other special requirements. Project
Engineer
.3 Certificates of basic constituents shall be provided by the supplier of Source
materials to verify compliance with the specifications. Certificats
Site
.4 Before applying plaster and/or render coat. It shall be confirmed Engr/MEP
from the Mechanical, Electrical and Plumbing Subcontractors that all Coord.
activity connected with backgrounds have been completed by them
and any defects have been made good and approved by Consultants
representative. FINI/03/A
QA/QC
.5 The work shall be inspected using the attached Checksheet, which FINI/03/A
shall be completed as verification and record.
QA/QC Non-
.6 Non-conforming workmanship shall be communicated to the conformity
personnel involved and immediate corrective action will be initiated. Report
Appendix FINI/03/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

PLASTERING AND RENDERING CHECK SHEET Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE

PREPARATION 1. 1st fix buried services complete. Check cover. MEP

2. Background checked for line and plumb. SE

3. Any dubbing-out or scabbling agreed and record SE


4. Background prepared to receive plaster.
(keyed, expamet, bonding, raked-out). GF
5. Grounds fixed top and bottom to line and
plumb. Check for min. thickness of plaster. SE
APPROVAL TO PROCEED WITH PLASTER/
RENDER QA/QC
PLASTERING/ 6. Check correct materials, mix proportions being
RENDERING used. SE
7. Check corner beads, stop beads, expansion
joints fixed to detail, square and plumb. GF
8. Check finished surface regularity. Gap less than
3mm under a 1.8m straightedge. GF
9. Check surface for local ripples, air holes,
blemishes etc. GF
10. Clean away plaster spillage from floor, chills,
etc. ready for next trade. GF

11. Inspected by Consultants Representative. CR


APPROVAL TO PROCEED WITH NEXT
TRADE CM
MINOR ITEMS
REQUIRING 12. Minor items attended to. PE
ATTENTION

CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE Project Engineer,


CR Consultants Representative, MEP MEP Co-ordinator, SE Site Engineer, GF General
Foreman
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/04
PAGE 1 OF 1
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
FLOOR SCREEDS AND CONCRETE TOPPINGS APPROVED BY:
QEHS MANAGER
ACTION VERIFY
1. SCOPE

The scope of this procedure covers the control and inspection


required for laying floor screeds and concrete toppings.

2. PROCEDURE

.1 The procedure requires that all activities connected with screeding


and topping will be carried out in accordance with the contract
specifications and Project Quality Plan. In any circumstance, where Project
specifications are not provided or unclear, clarification will be sought Manager Request For
from the Consultants representative. Information

.2 A Method Statement shall be prepared and approved by the


Project Manager. It shall include:

i) Surface preparation of concrete base.


ii) Bay sizes.
iii) Method of compaction.
iv) Method of finishing. Project
v) Surface treatment (if specified). Director/
vi) Accuracy level. Manager Method
vii) Protection of finished work. Statement

.3 Checks Prior to Commencement of the Activity:

i) A programme and sequence for completion of this activity Programme/


will be finalised in order to meet the overall contract Short term
programme. programme
ii) Check if the preceding activity has been inspected and
approved by the Consultant. Project
iii) Certificates of cement steel and aggregate (fine & coarse) will Engineer Source
be obtained and approved by the Consultants representative. certificates
iv) Check the preparation of substrate. FINI/04/A

.4 Material Handling and Storage: Store-


i) Store cement in dry, weterproof conditions. keeper
ii) Keep different types of aggregates in separate stockpiles.
Proj.Engr/
.5 Inspection and testing of screeds and concrete topping shall be QA/QC
carried out using Appendix FINI/04/A. Checksheet
Appendix FINI/04/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR FLOOR SCREEDS AND CONCRETE TOPPINGS Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE
1. Check built-in items complete e.g. services
PREPARATION trunking. PE/MEP
2. Check storage of material. SK
3. Establish datums for finished level of screed. SE
4. Check source certificates. PE
5. Check surface preparation eg. scabbling,
removal of loose material, dirt, oil etc. GF
6. Check application of bonding agent, separating
membrane if required. GF

APPROVAL TO PROCEED QA/QC


SCREED TOPPING 7. Check correct mix proportions. SE
LAYING 8. Check stop-ends to agreed bay sizes. SE
9. Check reinforcing mesh, if required. GF
10. Check compaction. GF
11. Check surface finishing e.g. trowelling,
application of carborandum dust, etc. GF
12. Check curing technique being followed. SE
INSPECTION AND 13. Check surface visually for blemishes. GF
TESTING 14. Check finished levels are within tolerance. SE/SU
a) When screed 15. Protect surface against damage. GF
sufficiently hardened
for foot traffic

b) after 14 days 16. Check for adhesion by tapping for hollowness. PE

APPROVAL TO PROCEED CM

CM Construction Manager, QA/QC - Quality Assurance/Quality Control, PE Project Engineer,


SE Site Engineer, SU Surveyor, GF General Foreman, SK Storekeeper
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/05
PAGE 1 OF 3
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CERAMIC TILES, TERRAZZO TILES AND MOSAICS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure outlines the system of control and inspections to be


adopted for the fixing on site of tiles and mosaics.

2. PROCEDURE

.1 A method statement shall be prepared and approved. It shall


include:

i) Acceptance conditions for laying e.g. maximum moisture


content of substrate, levelness, soundness, cleanliness,
environment.
ii) Surface preparation and bonding e.g. bonding agent, bed mix
proportions, adhesives.
iii) Specific requirements with regard to setting out, alignment of
joints and cutting. Project
iv) Method of protecting finished work. Manager Method
v) Source documents for tiles, adhesive Statement

.2 A sample of tiles shall be prepared on the wall in accordance with the Project
specifications laid down in the contract and approved by the Engineer Sample
Consultant. approval

.3 Storage of tiles:

i) Tiles shall be delivered to site palletised, on a clean hard


surface free from contamination by mud or surface water. Store-
ii) Ensure that manufacturers instructions in respect of storage keeper
conditions of adhesives are strictly followed. Instructions
Project
.4 The Project Director/Manager or his designate will confirm that Manager
materials are in compliance with contract specification requirements. FINI/05/A

.5 In the case of internal wall tiling, work will not proceed until all
concealed conduits, pipes, electrical cables and boxes etc. that Project
penetrate the tiling have been fixed securely in position and making Engineer
good is complete. Obtain written clearance from MEP Co-ordinator
that all their works in that area is clear for taking up the tiling work. FINI/05/A
AL Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/05
PAGE 2 OF 3
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CERAMIC TILES, TERRAZZO TILES AND MOSAICS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.6 Site operatives must observe the following while fixing tiles in Gen.
addition to the specifications laid down in the contract document. Foreman FINI/05/A

i) In the case of internal wall tiles, the setting out course or


layout course is established.
ii) The level and events of the wall surface should not exceed the
allowable tolerance as specified in the contract. Any such
defect should be rectified before proceeding further.
iii) While setting out for floor tiling, establish a datum level for
the finished floor and control the overall level of the finished
floor by means of series of spot levels. The Site Engineer will
involve Consultants representative while fixing levels.
iv) Avoid cutting tiles as far as possible. If cutting cannot be
avoided locate cut tiles where they will be least noticeable, if
in doubt refer to specification.
v) The sequence of fixing tiles shall be as follows unless
specified otherwise in the contract:

Floor tiles - from the centre of room


Internal walls - Upward from the setting out course up to
the specified height (in case of false ceiling) otherwise
from top and downwards up to starting level.
External walls - always from top to bottom covering one
horizontal strip after another but preferably to be done in
bays.
vi) The mortar or adhesive is spread on the surface using a trowel
or blade in thin layers as specified.
vii) Before placing the next tile take care to allow correct joint
width by placing the correct spacers in all corner joints.
viii) Do not start joint grouting work till tiles are properly fixed to
the surface. Normally the time period varies between 24 hrs Gen.
to 48 hrs. Foreman FINI/05/A

.7 Protection and Cleaning:

i) Protect external tiling and mosaics from rain and sun until the
bed and joints have set. Continue the protection for the period
specified.
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/05
PAGE 3 OF 3
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CERAMIC TILES, TERRAZZO TILES AND MOSAICS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

ii) Do not allow tiling and mosaics to be wetted in shower bath


areas for the period as specified, until the bedding and joints
have set and hardened.
iii) Do not permit any traffic at all on the flooring till the tiles are
set afterwards permit light foot traffic only.
iv) For general protection spread white no-staining saw dust over
the floor but not earlier than the period during which grout is
hardened.
Appendix FINI/05/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CERAMIC TILES, TERRAZZO TILES AND MOSAICS Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK ________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE

PREPARATION 1. Method statement approved. PE


2. Materials to specification (including suitability
of adhesive). SE

3. Check storage condition of materials. SK

4. Establish line and level. SU

5. Check moisture content of substrate. GF


6. Liaise with MEP section for completion of their
works. PE/MEP

7. Acceptance of substrate GF

8. Sample area acceptable. PE

APPROVAL TO PROCEED WITH LAYING QA/QC

INSTALLATION 9. Check setting-out SU

10. Check line and level. SU

11. Check mixing, colour and application of grout. GF

12. Check sequence of fixing tiles. SE

APPROVAL TO PROCEED QA/QC


POST 13. Check initial cleaning of work. GF
INSTALLATION 14. Check protection applied correctly. GF

APPROVAL TO PROCEED CM
CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE Project Engineer,
SE Site Engineer, SU - Surveyor, GF General Foreman, SK Storekeeper
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/06
PAGE 1 OF 2
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
NATURAL STONE TILES - WALL CLADDING AND FLOORING APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

The scope of this procedure covers the control and inspection of


fixing Natural Stone Tiles such as granite, marble, travertine, slate,
quartzite and limestone.

2. PROCEDURE

.1 A method statement shall be prepared and approved. It shall


include:

i) Access and loading out plan.


ii) Surface accuracy, preparation and bonding e.g. bonding
agent, bed mix proportions, adhesives.
iii) Specific requirements with regard to setting-out, pattern of Project
joints, pointing fixings etc. Manager Method
iv) Method of protecting finished work. Statement
v) Source certificates for tiles, adhesive.

.2 All activities connected with tiling and cladding will be carried out
accordance with the contract specifications and Project Quality Plan.
Project
In any circumstances where specifications are not provided or Manager
unclear, clarification, will be sought from the Consultants Request For
representative. Information

.3 Ensure that the proposed sequence of work is in compliance with the Project
contract master programme or any other relevant short-term Engineer
programme. Approved shop drawings shall be available before Drawings/
starting the activity. Project Programme
Engineer
.4 A sample area will be prepared for the approval of the Consultant. Sample
Approval
.5 Storage and handling of materials:
Store-
a) Tiles shall be delivered at site palletised, off loaded as near to keeper
the point of use as practical on a clean hand surface free from
contamination by mud or surface water.
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/06
PAGE 2 OF 2
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
NATURAL STONE TILES - WALL CLADDING AND FLOORING APPROVED BY:
QEHS MANAGER
ACTION VERIFY

ii) Prior to accepting delivery of the material the storekeeper will


verify the quantity and color/pattern of selected tiles with that Store-
of the approved sample. keeper
iii) Ensure that manufacturers instructions for storage conditions
of adhesives are strictly followed.
iv) Where a large number of tiles of different types are to be used
confirm from drawings and specifications the correct type of
tiles to be used in a particular area before loading out.

.6 Prior to commencement of fixing Natural Stone Tiles, a careful Gen.


selection of the material shall be conducted in order to: Foreman

i) Select a uniform pattern in shading, lining and veins.


ii) Select tiles of obvious nuts and marks if used in flooring.

.7 Where work is to be carried out in artificial light, ensure the lighting


is adequate and where practicable, the direction and intensity of Gen.
temporary lighting is similar to that of permanent one. Foreman

.8 Before fixing tiles check whether the surface level is within


allowable tolerance as specified, carry out remedial work if Site
necessary. Engineer Survey

.9 In case of wall tiling, obtain clearance from MEP Co-ordinator for Project
the completion and testing of embedded items. Engineer
Appendix FINI/06/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR NATURAL STONE TILES Sheet No.


(WALL CLADDING AND FLOORING).

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM By DATE
PREPARATION 1. Method statement approved. PE
2. Material to specification. PE
3. Check proper storage arrangements. SK
4. Obtain clearance from Mechanical, Electrical
and Plumbing Co-ordinator in respect of
completion of concealed work. PE
5. Check acceptance of substrate. SE
6. Establish line and level. SU
7. Check access requirements. SE
8. Check adequate lighting. GF
APPROVAL TO PROCEED WITH THE
INSTALLATION. QA/QC
INSTALLATION 9. Check correct tiles at work face. GF
10. Check line/level, verticality. SE/SU
11. Ensure metal clamps are securely fixed. GF
12. Check sealing between tiles and mortars to
Ensure good bonding. GF
13. Check mortar mix proportion and mixing
method. GF
14. Check protection of tiles against damage. GF
15. Cleaning completed. GF

APPROVAL TO PROCEED. CM
CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE Project Engineer,
SE Site Engineer, SU Surveyor, GF General Foreman, SK - Storekeeper
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/07
PAGE 1 OF 2
SECTION: DATE OF ISSUE
FINISHES September 2007
SUBJECT: BY:
QA/QC ENGINEER
ROOF WATERPROOFING APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

The scope of this procedure comprises the control of waterproof


membranes on flat and inclined substrates.

2. PROCEDURE

.1 It is advised that a meeting be held with the specialist subcontractor Project Meeting
to discuss the sequence, scope of works and inspection arrangements Manager Minutes/
for the system specified. PQP
Project
.2 The condition and moisture content of the substrate will be inspected Engr/ Sub-
and accepted by the subcontractor before commencement on site. contractor Letter

.3 All surfaces will be dry and free from dust and loose material prior to Site
application of the membrane by the use of compressed air or Engineer
vacuuming. FINI/07/A

.4 Any foreign matter such as oil, grease etc. or protrusions such as Gen.
nails, concrete fins etc will be removed to ensure a good bond and Foreman
watertightness. FINI/07/A

.5 Primers, liquid membranes, bonded and unbonded sheets will be laid Site
strictly in accordance with the manufacturers instructions, using Engineer
laps, fillets and flashings as specified. FINI/07/A
Gen.
.6 Work areas will be subject to controlled access to ensure availability Foreman
of roof and to prevent damage to membrane. FINI/07/A

.7 Following installation of the membrane suitable temporary protection


board or permanent installation will be laid as required by the Site
specification, and good practice to provide protection against damage Engineer
to the membrane while the following trades operate. FINI/07/A
Al Rajhi Projects and Constructin LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/07
PAGE 2 OF 2
SECTION: DATE OF ISSUE
FINISHES September 2007
SUBJECT: BY:
QA/QC ENGINEER
ROOF WATERPROOFING APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.8 Materials will be stored in accordance with the recommendations of Site Engr/ Manufactu-
the manufacturer especially volatile and limited - life liquids. Sub- rers
contractor Instruction

.9 The subcontractor will submit a requisite guarantee for the system Project
against leaks. The guarantee shall be in the name of the Client and Manager
shall commence from the hand over date of the building. Guarantee

.10 A flood test will be applied, if specified. Repairs will be carried out QA/QC
until a waterproof condition is accepted. FINI/07/A

Const.
.11 Inspections of installation and material will occur as Appendix Manager/
FINI/07/A. The installed membrane will not be overlaid with QA/QC FINI/07/A,
permanent covering until it conforms to the specified requirements. Specs.
Appendix FINI/07/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR ROOF WATERPROOOFING Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE
1. Condition of roof and moisture conditions
PRELIMINARY accepted by subcontractor. PE
2. Roof area cleared of loose material, projections
and oil etc. SE

3. Roof area isolated for membrane installation. SE

APPROVAL TO PROCEED QA/QC

INSTALLATION 4. Primer laid in accordance with instructions. GF


5. Liquid membrane sheeting laid in accordance with
manufacturers instructions (including bonding
where specified). SE

6. Spot checks on laps, fillets and flashings. GF

APPROVAL TO PROCEED QA/QC


POST -
APPLICATION 7. Flood test carried out? QA/QC
8. Final inspection before boarding or screeding
(including separation sheet) SE

9. Check guarantee in place. PE


APPROVAL TO PROCEED WITH
PROTECTIVE COVER CM

CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE - Project Engineer,


SE - Site Engineer, GF General Foreman
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/08
PAGE 1 OF 1
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
PLASTERBOARD PARTITIONS AND DRY LININGS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure applies to the installation of plasterboard partitions


and dry linings including co-ordination of associated MEP works.

2. PROCEDURE
Project
.1 Where necessary, a programme shall be prepared showing all inter- Planner/
related activities, sequence of work. It shall be approved by the Manager
Project Director/Manager. Programme
Project
Manager
.2 Samples of materials or named product shall be submitted for Material
approval by the Consultant. Project Submittal
Manager/
Project
.3 Co-ordinated drawings or method statement shall be prepared Engineer Shop
detailing the setting-out, provision of MEP services required for Drawing/
erection, sequence of fixing, openings, jointing, finishing and Method
repairing details. Statement
QA/QC
/Storekee-
.4 A check shall be made to verify delivery notes and source certificates per
against specifications/LPO. In particular check that materials and
components are clean, undamaged and dry, the plasterboard sheets Storekee-
are the correct types and have the required dimensions and edge per Delivery
profiles. Note/ SMR
For proper handling and storage refer to manufacturers instructions.
Unacceptable material shall be notified to the supplier using QA/QC
Procedure 7/3/6.

.5 Appendix FINI/08/A shall be completed for each area defined in the QA/QC
Project Quality Plan. Checksheet

.6 Unacceptable or damaged work shall be notified to the subcontractor Non-


on a Non-Conformity Report as Appendix 7/3/6/A for rectification. conformity
Report
Appendix FINI/08/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR PLASTERBOARD PARTITIONS & DRY LININGS Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE

PREPARATION 1. Drawings and MEP interface. PE/MEP

2. Check proper storage of materials and approval. SK

3. Establish layout and principal setting out points. SE


4. Check void ready e.g. fire protection, painting
of frame if required. GF
APPROVAL TO PROCEED WITH STUD
FIXING AND INTERNAL BOARDING QA/QC
STUD FIXING AND
INTERNAL 5. Check setting out of services. MEP
BOARDING
6. Check 1st fix service installation. MEP

7. Check line and plumb. SE

8. Check insulation. SE

9. Check noggings. SE
APPROVAL TO PROCEED WITH
EXTERNAL BOARDING QA/QC
EXTERNAL 10. Check verticality to within specified tolerance
BOARDING limits. SE/SU

11. Check positions of service outlets and openings. MEP


APPROVAL TO PROCEED WITH JOINT
FILLING AND FINISHES CM

CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE Project Engineer,


MEP - MEP Co-ordinator, SE Site Engineer, GF General Foreman, SK Storekeeper
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/09
PAGE 1 OF 4
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
PRECAST CONCRETE PAVINGS AND PAVING BLOCKS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

The scope of this procedure covers both the laying of precast


concrete paving blocks in new construction, and repairing and
reinstating precast concrete paving blocks.

2. PROCEDURE

.1 All precast concrete pavings works will be carried out in accordance


with the specifications detailed out in the Contract documentation
and Project Quality Plan. In any circumstances where specifications Project
are not provided or they are in any way incomplete, the matter shall Manager Request For
be referred back to Consultant for additional information. Information

.2 Prepare the subgrade and sub-base (and roadbase where necessary)


so that :

i) The surface levels are within the specified tolerances.


ii) The longitudinal falls and crossfalls are such that no
depressions hold water. Project
iii) The extent of the site prepared for block laying shall include Engineer/ Pre-install-
enough room to provide adequate foundations and backing Surveyor ation
for any edge restraint. Survey

.3 Form edge restraints as indicated on the contract drawings before


compacting adjacent blocks. Do not vibrate the surface course until Gen.
the edge restraint, together with any concrete haunching has gained Foreman
sufficient strength. FINI/09/A

.4 Joint Filling:

i) After compaction of the surface course, spread the specified


sand or crushed rock fines over the surface of blocks and Gen.
brush it into the joints. Ensure that materials are dry and of Foreman
specified grading. FINI/09/A
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/09
PAGE 2 OF 4
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
PRECAST CONCRETE PAVINGS AND PAVING BLOCKS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

ii) Vibrate the block paving to ensure complete filling of the


block-to-block joint by the surface-applied sand. Where
necessary, add further sand and revibrate the paving.
iii) Inspect the surface after an early period of traffic use and Site
brush in additional sand filling where necessary. Engineer

3. PROCEDURE FOR REPAIRS AND REINSTATEMENT OF


PRECAST PAVING BLOCKS
Gen.
.1 Removal of Blocks: Foreman FINI/09/A

Remove the sand from the joints around the first block and lever it
out. Remove and stack further blocks until the working area is
exposed.

.2 If the area has been heavily trafficked it may be necessary to break


the first blocks to get them out.

.3 Excavate as necessary to carry out specified work and store


excavated materials suitable for re-use. Using suitable excavated or
new materials, backfill the excavation and compact sufficiently to
avoid subsequent settlement.

.4 Use naturally occurring sand or crushed rock fines graded as


specified. Any material that is stockpiled should be properly covered
to ensure uniformity of moisture content.

The moisture content of the laying course should be as uniform as


possible and the material should be moist without being saturated.

Construct the laying course as specified in the contract. In no case


should the material be less than 25mm thick at any point unless
specified otherwise in the contract. Compact the screed material as
specified in the contract.
If any disturbance of the prepared laying course sand by pedestrian
or wheeled traffic occurs, prior to placing paving blocks, re-screed Gen.
areas of laying course material. Foreman FINI/09/A
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/09
PAGE 3 OF 4
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
PRECAST CONCRETE PAVINGS AND PAVING BLOCKS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.5 Surface Course:

i) Paving blocks are to be laid so that surface levels are within


the specified tolerance. Minor adjustments can be made to
maintain the bond pattern and ensure that the joints remain Gen
wide enough for sand filling. Foreman FINI/09/A
ii) Trim paving blocks to shape and size to form boundaries. Do
not insert pieces of a size less than one-third of a full block.
iii) Fully compact the surface block using a plate compactor with
a plate area transmitting an effective for of not less than 75
KN/M2 of plate at a frequency of vibration in the range 75
Hz to 100Hz, unless specified otherwise.

.6 Carry out compaction as soon as possible after laying but not within
1m of any laying face. Apart from this edge strip, do not leave any
area of paving uncomplicated at the completion of the days work.

.7 Remove a few further blocks from around the area to ease


replacement, taking care to include any blocks that have moved
during previous operations.

Place laying course material over the backfilled excavation and


screed to the level of the material exposed and ensure compaction (as Gen.
done in case of new work). Foreman FINI/09/A

.8 Where a pavement which has had considerable trafficking is to be


reinstated, the sub-surface will have become fully compacted. There
may still be further compaction of the excavated area but a final
surface slightly higher (typically 2mm to 3mm) than the surrounding
area will help to ensure that final levels after trafficking area are
correct.

.9 Before the original blocks are re-laid, clean off all loose and
extraneous material. Re-lay the blocks and bond them into the
existing pavement as specified.
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/09
PAGE 4 OF 4
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
PRECAST CONCRETE PAVINGS AND PAVING BLOCKS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

Compact the blocks using the method as previously described until


no further compaction of the blocks can be achieved. Spread jointing Gen.
sand and apply the final vibration. Foreman FINI/09/A

4. DOCUMENTATION

.1 The documentation used for this activity will be referenced in the Project
Project Quality Plan. It is suggested that the following may be Manager
appropriate as a minimum requirement:

i) Site survey/grid of levels


ii) Source certificates for paving blocks, concrete and base
materials etc.
iii) Layout of workshop drawings.
Appendix FINI/09/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR PRECAST CONCRETE PAVINGS & PAVING Sheet No.
BLOCKS

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE
1. Check surface levels, longitudinal falls and
SUB-GRADE crossfalls. PE/SU

2. Check compactness of sub-grade. SE

3. Check provision of drainage. PE/MEP

APPROVAL TO PROCEED QA/QC


SUB-BASE AND 4. Check surface levels, longitudinal falls and
ROAD BASE Cross falls. SU
5. Check gradation of fill material (sand or rushed
LAYING COURSE rock fines). SE

6. Check thickness of laying course layer. GF

APPROVAL TO PROCEED QA/QC

SURFACE COURSE 7. Check surface levels. SE/SU

8. Check dimensions of blocks (random checking). GF


9. Check manufacturers certificates for
compliance to specifications. SE

10. Check joint width. GF

11. Check the characteristics of plate compactor. SE

12. Check grading of sand for joint filling. SE


13. Check laying to specification. GF

APPROVAL TO PROCEED CM
CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE Project Engineer,
SE Site Engineer, MEP MEP Coordinator, SU - Surveyor, GF General Foreman
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/10
PAGE 1 OF 1
SECTION: DATE OF ISSUE
EXTERNAL ENVELOPE September 2007
SUBJECT: BY:
QA/QC ENGINEER
SUPPLY AND FIX CURTAIN WALLING APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure applies to the installation of proprietary curtain


walling.

2. PROCEDURE
Project
.1 A programme shall be prepared showing all inter-related activities, Director/
order of work, phased area of access and dates, etc. It shall be Manager/
approved by the Project Director/Manager. Project Programme
Planner
.2 A Method Statement is to be prepared and submitted for approval by
the subcontractor detailing sequence and method of erection, plant to
be used, safety procedure, and submittal and checking of design Sub- Method
drawings. contractor. Statement

.3 The subcontractor is to nominate a person responsible for their site Sub-


activities. contractor Letter

.4 Documents/test certificates shall be provided by the subcontractor to


verify compliance with the specification and thermal stress of glass Sub- Source
as appropriate. contractor Certificates

.5 The work shall be inspected using the attached check sheets, which FINI/10/A,
will be completed as verification record and retained in a file on site. QA/QC FINI/10/B

6. Unacceptable work shall be notified to the subcontractor on a Non- QA/QC Appendix


conformity report and corrective action taken. 7/3/6/A

.7 Specific subcontractor responsibilities and methods for cleaning


away debris and final clean, protection of the finished installation Project
shall be agreed and confirmed in writing to the subcontractor before Manager
placing order. Letter
Appendix FINI/10/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR CURTAIN WALLING SYSTEM Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE
BEFORE
MANUFACTURE 1. Review of design detailing. PE
2. Approval of subcontractors specification and
drawings by Consultant. CR
3. Approval of components and finishes samples
by Consultant PE/CR
4. Trial assembly of proposals approved by
Consultant (Control sample). PE/CR
5. Off site testing results approved.
(Project specific and/or system tests) PD/M/CR
APPROVAL TO PROCEED WITH
MANUFACTURE PD/M/CR
BEFORE ERECTION 6. Check fixings, H.D. bolts to specification. QA/QC
7. Building frame preparation complete. SE
8. Building frame checked for alignment and
Offered to subcontractor. SE/SU
9. Building frame accepted by Subcontractor. Subcon.
APPROVAL TO PROCEED WITH
ERECTION CM
ERECTION POST 10. All erection checksheets completed. (see also
ERECTION Appendix FINI/10/B) QA/QC
11. All corrective actions sheets signed-off. QA/QC
12. Insitu water/air testing results satisfactory. QA/QC
13. Protection to finished installation satisfactory. PE
14. Low tack protective tape renewed at 6 monthly
intervals, if applied. GF
15. All surplus material and debris cleared off site. GF
16. Tape removed and system cleaned down prior
to handover. SE

APPROVAL TO PROCEED PD/M


CR Consultants Representative, PD/M Project Director/Manager, PE Project Engineer,
CM Construction Manager, QA/QC Quality Assurance/Quality Control, SU Surveyor,
SE Site Engineer, GF General Foreman, Subcon. - Subcontractor
Appendix FINI/10/B
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR CURTAIN WALLING ERECTION Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM By DATE

1. Approval to proceed with erection. QA/QC

2. Alignment of mullions and transoms checked. SE/SU

3. Movement joints to specification. PE

4. Drainage channels clear. GF

5. Fixings complete and tightened. GF

6. Pressure plates fitted correctly. GF

7. Weather seals as specified GF


8. Glass and glazing to specification. (Setting
Blocks, orientation, gaskets). SE
9. Infill panels, insulation and lining to
specification. SE

10. Check for surface damage. QA/QC


11. Other points to specifically check.

a)

b)

c)

d)

12. Protective tape applied, if required. GF

APPROVAL TO PROCEED CM
CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE Project Engineer,
SE Site Engineer, SU Surveyor GF General Foreman
Al Rajhi Construction and Projects LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/11
PAGE 1 OF 2
SECTION: DATE OF ISSUE
FINISHES September 2007
SUBJECT: BY:
QA/QC ENGINEER
INSTALLATION OF RAISED ACCESS FLOORS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure applies to the installation of proprietary raised access


flooring including the sub-base preparation and co-ordination of
engineering services.

2. PROCEDURE
Project
.1 A programme shall be prepared showing all inter-related activities, Planner/
order of work, phased areas of access and dates, etc. It shall be Manager/
approved by the Project Director/Manager. Subcon. Programme

.2 Samples of materials or named products shall be submitted for Material


approval by the Consultant. approval,
Compliance
e.g. Floor Sealer certs.,
Raised Flooring System Project Manufac-
Pedestal Fixing Method Manager/ turers
Cable Trays technical
Floor Outlet Boxes literature
Floor Finishes Project
Manager
.3 Co-ordinated drawings shall be obtained from the Consultant
detailing the floor setting-out, including required floor loading, Project
service, runs, positions of floor boxes, cavity stopping for fire Manager Request For
protection, floor grilles, etc. Information
Project
4. Specified subcontractor responsibilities and methods for cleaning Engineer/
away debris and protection of finished installation shall be agreed MEP
and confirmed in writing to the subcontractors. Coord. Letters

.5 A check shall be made to ensure that positions of pedestals and depth


of void are able to accommodate the services, particularly at cross- QA/QC
over points. Any difficulties are to be referred to the Consultant for Request For
instruction. Information

.6 Appendix FINI/11/A shall be completed for each area defined on the


programme and in the Project Quality Plan. Checksheet
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/11
PAGE 2 OF 2
SECTION: DATE OF ISSUE
FINISHES September 2007
SUBJECT: BY:
QA/QC ENGINEER
INSTALLATION OF RAISED ACCESS FLOORS APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.7 Completed checksheets shall be retained in a file as quality records. QA/QC QA/QC File

.8 Unacceptable or damaged work shall be notified to the


subcontractor on a Non-Conformity report and corrective action Non-
taken. QA/QC Conformity
Report
3. PEDESTAL FIXING TEST

A dynamic impact test may be required to be carried out on site by Project


the fixing contractor and witnessed by Al Rajhi, on a random Engineer/
sample of installed free standing pedestals as specified in the QA/QC Test record
contract.
Appendix FINI/11/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR RAISED ACCESS FLOORS Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE
PREPARATION OF
SUB-FLOOR 1. Check sub-floor prepared and cleaned. SE

2. Apply 1st coat sub-floor sealer. GF


3. Check setting-out of pedestal positions and
levels. SE/SU
APPROVAL TO PROCEED WITH SERVICES
QA/QC

1st FIX SERVICES 4. Check setting-out of services. PE/MEP

5. Check 1st fix service installation. MEP

6. Clean and apply 2nd coat sealer. GF


APPROVAL TO PROCEED WITH RAISED
FLOOR QA/QC

RAISED FLOOR 7. Check pedestal fixings as Specification. PE

8. Check line and level of installed floor. SE/SU

9. Check positions of service outlets. PE/MEP

10. Check finished surface (carpet tiles etc.). SE


11. Install protection to surface. GF
APPROVAL TO PROCEED WITH SERVICES
QA/QC
2nd FIX SERVICES 12. Complete service installation. MEP
13. Commission services. MEP
14. Final clean and reinstate tiles. GF
APPROVAL TO PROCEED CM
CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE Project Engineer,
SE Site Engineer, SU Surveyor, MEP MEP Co-ordinator, GF General Foreman
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/12
PAGE 1 OF 2
SECTION: DATE OF ISSUE
FINISHING OCTOBER 2005
SUBJECT: BY:
QA/QC ENGINEER
INSTALLATION OF SUSPENDED CEILINGS APPROVED BY:
QHSE MANAGER
ACTION VERIFY

1. SCOPE

This procedure applies to the installation of proprietary suspended


ceiling systems including the co-ordination of engineering services.

2. PROCEDURE
Project
.1 A programme shall be prepared showing all inter-related activities, Planner/
order of work, phased areas of access and dates, etc. It shall be /Manager/
approved by the Project Director/Manager. Subcon. Programme

Project
.2 Samples of materials or named products shall be submitted for Manager Notices of
approval by the Consultant. Check inter-compatibility. Approval,
Compliance
e.g. Ceiling Tiles Certs.
Suspension System Manufactu-
Integrated Light Fittings rers
Air Grills technical
Sprinklers Project literature
Engineer/
.3 Co-ordinated drawings or method statements shall be prepared MEP
detailing the ceiling setting-out (including and superimposed loading Coord. Drawings/
from light fittings, etc.), service runs, positions of light fittings, air Method
grilles, sprinkler heads, smoke alarms, cavity stopping for fire Statement
protection, etc.
Site
.4 A check shall be made to ensure the positions of hangers and depth Engineer
of void are able to accommodate the services, particularly at cross-
over points. Any difficulties are to be referred to the Consultant for Request For
instruction. QA/QC Information

.5 Appendix FINI/12/A shall be completed for each area defined on the QA/QC
programme and in the Project Quality Plan. Checksheet

.6 Completed checksheets shall be retained in a file as quality records. File


Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/12
PAGE 2 OF 2
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
INSTALLATION OF SUSPENDED CEILINGS APPROVED BY:
QEHS MANAGER
ACTION VERIFY
Non-
.7 Unacceptable or damaged work shall be notified to the subcontractor Conformity
on a Non Conformity Report and corrective action taken. QA/QC Report

3. REFERENCE

Suspended Ceilings Association Guide No. 1 - Good Practice for the


Installation of Suspended Ceilings.
Appendix FINI/12/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR SUSPENDED CEILING Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE
1. Establish level, datum and principal setting out
PREPARATION points. SE/SU
2. Check void ready e.g. fire protection, painting of
frame completed GF
APPROVAL TO PROCEED WITH 1st FIX
SERVICES QA/QC
1st FIX
SERVICES 3. Check setting-out of services. MEP
4. Check 1st fix service installation. MEP
APPROVAL TO PROCEED WITH CEILING GRID
QA/QC
CEILING
SUPPORT GRID 5. Check hangers and fixings to specification. PE
6. Check line and level of installed grid. Level to within
specified tolerance limits. SE/SU
7. Check positions of service outlets in grid. MEP
8. Check perimeter details as specified. To line. Corners
mitred true and square. SE
APPROVAL TO PROCEED WITH 2nd FIX
SERVICES QA/QC
2nd FIX
SERVICES 9. Check service installation complete. MEP
10. Commission services. MEP
11. Check installation of cavity barriers. SE
APPROVAL TO PROCEED WITH CEILING
TILES QA/QC
12. Check tiles for alignment, clips (if spec.) and
CEILING TILES damage. Access tiles correct. SE
13. Recheck level of completed installation. PE

APPROVAL TO PROCEED CM

CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE Project Engineer,


SE Site Engineer, MEP - MEP Co-ordinator, SU Surveyor, GF General Foreman
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/13
PAGE 1 OF 1
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
PLASTERBOARD CEILING APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure applies to the installation of a suspended ceiling


system using gypsum plasterboard and galvanised steel hanging
system.

2. PROCEDURE

.1 All plasterboard ceiling work will be carried out in accordance with


the specification detailed in the contract documentation and Project
Quality Plan. In any circumstances where specifications are not Project Request For
provided or they are in any way incomplete, the matter shall be Manager Information
referred back to the Consultant for additional information.
Project
.2 Samples of materials provided by the approved manufacturer will be Manager Material
submitted for approval by the Consultant. submittal
Project
.3 Co-ordinated shop drawings shall be prepared by Al Rajhi and Manager
approved by the Consultant detailing the ceiling setting out, service Approved
runs, position of light fittings, air grills, sprinkler heads, smoke Shop
alarms, cavity stopping for fire protection etc. Site drawing
Engineer/
.4 A grid locating positions of hangers will be marked on the ceiling to Subcon.
ensure the positions of hangers and depth of void will accommodate
the services, particularly at cross-over points. Any difficulties are to Request For
be referred back to the Consultant for instruction. QA/QC Information

.5 Appendix FINI/13/A shall be completed for each work area as


required by the Project Quality Plan. Checksheet
Appendix FINI/13/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR PLASTERBOARD CEILING Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE

PREPARATION 1. Ensure approval of material. PE


2. Establish level, datum and principal setting out
points. SE/SU

3. Check setting out of services. PE/MEP

APPROVAL TO PROCEED QA/QC


CEILING
SUPPORTING 4. Check fixing of hangers, grid to specification PE
SYSTEM 5. Check line and level of supporting grid (variations
within specified tolerance limits). SE/SU
6. Check positions of service outlets in grid. (Refer
approved workshop services co-ordinated drawing). SE/MEP

7. Ensure relevant MEP works are complete. SE/MEP

APPROVAL TO PROCEED QA/QC

FIXING CEILING 8. Check fixing of plasterboard GF

9. Recheck level of completed installation. SE/SU

10. Check finishing of ceiling as specified. SE

APPROVAL TO PROCEED CM

CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE Project Engineer,


SE Site Engineer, MEP MEP Coordinator, GF General Foreman, SU Surveyor
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/14
PAGE 1 OF 2
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
ROOM / AREA INSPECTION SPREADSHEET APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

The use of a spreadsheet as a means of recording and monitoring


internal finishes inspections may be an appropriate alternative to
individual checksheets, especially where a large number of small
rooms are involved e.g. hospitals, hotels, etc.

2. PROCEDURE

.1 It is important that the checksheet list and spreadsheet are purpose-


written for each contract. The appended list and spreadsheet are Project Site
examples only and not to be used as proformas. Manager Procedure

.2 Where the requirement for a method statement is identified in the Project


Project Quality Plan, it shall be obtained and approved prior to the Manager/ Method
commencement of work. QA/QC Statement

.3 Samples approval and test requirements should also be identified in Project Approval
the Project Quality Plan and agreement confirmed prior to the Manager of sample/
commencement of work. QA/QC Test Report
Project
.4 The building shall be divided into appropriate areas e.g. floors, and Manager
each room within the area identified by reference number on a
marked-up plan. Project Key Plan
Manager
.5 A procedure shall be prepared listing the specific checks needed for QA/QC
each type of finish or trade to be included on the spreadsheet. (See Work
example, Procedure FINI/14/A) overleaf. Procedure

.6 A spreadsheet shall be prepared summarising the key checkpoints. Spread


See example. It shall identify two stages of approval for each trade: Sheet
Project
i) Approval to proceed with the following trade. Director/
ii) All check items satisfactorily cleared. Manager
QA/QC
.7 Any identified defect outstanding after an approval to proceed with
the following trade is given, shall be listed on a snag sheet for Appendix
subsequent clearance (Procedure 7/3/5). 7/3/5/A
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/14/A
PAGE 1 OF 4
SECTION: DATE OF ISSUE
INTERNAL WORKS September 2007
SUBJECT: BY:
QA/QC ENGINEER
SPREADSHEET FOR INTERNAL FINISHING APPROVED BY:
ROOM BY ROOM QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure is to be followed for the internal finishing works


following wall plastering.

It is deemed appropriate for contracts with a large number of rooms


where the finishing trades can be better controlled by a spreadsheet
approach.

It should be noted that the use of this spreadsheet system will not
reduce the site checks, but will make them more manageable. Al
Rajhi Procedures, Contract Specifications, specified standards and
the Project Quality Plan will be adhered to.

2. PROCEDURE

.1 Items shall be signed off and dated on the spreadsheet once Approved
satisfactorily completed in accordance with this procedure. (Not to Method
be signed until ALL items satisfactorily addressed for that room). Statement
available as
.2 Method statement requirements are to be identified in the Project Project required
Quality Plan and approved prior to the appropriate item on this Manager
procedure commencing. Agreed
sample/test
.3 Samples and test requirements are to be identified in the PQP. Ensure Project
these have been agreed prior to commencement of the work. Manager

3. CHECK ITEMS:-

.1 SCREED

i) Check moisture content of base acceptable. Site Engr. Checksheet


ii) Check preparation, built in items and levels are acceptable. Site Engr.
iii) Ensure compaction method acceptable and as specified. Site Engr.
iv) Check curing method applicable. Site Engr.
v) Check finished levels within tolerance and review visually. Site Engr.
vi) Check for soundness using screed tester and ensure results
recorded. Site Engr.
Al Rajhi Projects and Construction LLC

WORK
b.
PROCEDURE
Raised Floor

i) Sub-floor preparation acceptable. Subcon. Subcon.


ii) Check sub-floor sealer and 1st fix M&E installation is Checksheet
acceptable/ complete prior to proceeding with raised floor. Site Engr.
iii) Pedestal fixing/position acceptable. Site Engr.
iv) Visual check during installation. Site Engr.
v) Check finished level acceptable. Site Engr.
vi) Ensure service outlet position acceptable. Site Engr.

.2 M&E 1st FIX

i) M&E Subcontractors 1st fix check sheets/tests received,


reviewed and complied. Subcon. Subcon.
ii) Review and snag opting with sub-contractor. Site Engr. Checksheet
iii) Ensure snags completed prior to continuing. Site Engr.

.3 CEILINGS SUPPORT GRID

i) Check setting out acceptable. Subcon. Subcon.


ii) Check void preparation. Site Engr. Checksheet
iii) Check hangers, fixing ground edge trim to specification and
agreed levels. Site Engr.
iv) Check service outlets. Site Engr.
v) Check sound barriers. Site Engr.
vi) Check ceiling tile in correct position. Site Engr.
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/14/A
PAGE 3 OF 4
SECTION: DATE OF ISSUE
INTERNAL WORKS September 2007
SUBJECT: BY:
QA/QC ENGINEER
SPREADSHEET FOR INTERNAL FINISHING APPROVED BY:
ROOM BY ROOM QEHS MANAGER
ACTION VERIFY

a. Ceilings Tiles or Plaster

i) Check ceiling support, grid edge trim, and access doors. Subcon. Subcon.
ii) Ensure adequate protection elsewhere. Site Engr. Checksheet
iii) Check materials correct. Site Engr.
iv) Check finished plaster for regularity and blemishes. Site Engr.

.4 JOINERY

i) Check ceiling support, grim edge trim, and access doors. Subcon. Subcon.
ii) Check door frames for lien and level. Site Engr. Checksheet
iii) Check pellets, mitres smoke and fire seals and ironmongery
as specified. Site Engr.
iv) Check hanging of door and frame clearance. Site Engr.
v) Check surfaces clean. Site Engr.

.5 WALL AND FLOOR TILING

i) Check sub-contractor accepts the substrate to ensure it


suitability for tiling. Subcon. Subcon.
ii) Check line and level. Site Engr. Checksheet
iii) Check title placement, joints, joint widths and colour and
application of grout. Site Engr.
iv) Check tiling clean and positioning acceptable. Site Engr.

.6 WALL DECORATION

i) Check Subcontractor accepts background to ensure suitability Subcon. Subcon.


for painting. Checksheet
ii) Ensure correct paint system and correct number of coats
applied. Site Engr.
iii) Check finished paint and colour scheme. Site Engr.
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/14/A
PAGE 4 OF 4
SECTION: DATE OF ISSUE
INTERNAL WORKS September 2007
SUBJECT: BY:
QA/QC ENGINEER
SPREADSHEET FOR INTERNAL FINISHING APPROVED BY:
ROOM BY ROOM QEHS MANAGER
ACTION VERIFY

.7 M&E 2nd FIX

i) Check materials as specified. Subcon. Subcon.


ii) Materials/equipment locations correct. Site Engr. Reports and
iii) Commissioning report/Compliance Certificate and Test Certificates
Certificates and specified/as applicable. Site Engr.
iv) Check labelling installed. Site Engr.

.8 PLUMBING 2nd FIX

i) Check materials as specified. Subcon. Subcon.


ii) Ensure finished areas adequately protected. Site Engr. Reports and
iii) Check pipework and valves will be accessible for Certificates
maintenance. Site Engr.
iv) Ensure line and level checks have been completed. Site Engr.
v) Ensure specificates, flushing of system, commissioning tests
and O & M materials adequately addressed. Site Engr.

.9 SOFT FLOOR FINISHES

i) Confirm Sub-contractor accepts background. Subcon. Subcon.


ii) Confirm floor finish is applied as specified. Site Engr. Reports and
iii) Visual inspection upon completion. Site Engr. Certificates

.10 FINAL INSPECTION AND SNAG COMPLETE

i) Snag each room and agree with the Consultant on completion Proj. Engr/ Subcon.
of Works Inspection forms. Consult. Reports and
Certificates
ii) Identify snags against sub-contractors and action. Prpj. Engr/
Consult.
iii) Final clean. Proj. Engr/
Consult.
iv) Lock room and restrict access. Proj. Engr/
Consult.
Appendix FINI/14/B
September 2007

Al Rajhi Projects and Construction LLC

SPREAD SHEET

PROJECT: ____________________________________________________________________________ SITE NO : ________________________

CONSULTANT: _________________________________________________________________________________________________________

FLOOR
ROOM No.
1. SCREED OR
a. DURABELLA OR
b. RAISED FLOOR
2. M & E 1st FIX
3. CEILING SUPPORT GRID OR
a. CEILING TILES OR
b. CEILING PLASTER
4. JOINERY
5. WALL & FLOOR TILING
6. WALL DECORATION
7. M & E 2nd FIX
8. PLUMBING 2nd FIX
9. SOFT FLOOR FINISHES
10. FINAL INSPECTION AND
SNAG COMPLETE
Note:
(SIGN / INITIAL AND DATE EACH BOX UPON ACCEPTANCE OF THAT ACTIVITY FOR THAT ROOM)
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/15
PAGE 1 OF 2
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONTROL OF GLASS BLOCKWORK APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure provides a method of control for construction of glass


block walls in order to achieve compliance with the contract
specifications and drawings.

2. PROCEDURE

.1 All glass block installation work will be carried out in accordance Project
with the specification and Project Quality Plan. Manager Specs.

.2 In any circumstances where specifications are not provided or they Project


are in any way incomplete, the matter shall be referred back to Manager Request For
Consultants representative for additional information. Information

.3 Checks Prior to Start of Works:

i) Ensure that the area to receive the glass blocks is as per the
contract drawings and approved finishing schedule. QA/QC
ii) Check if preceding activities have been inspected and
approved.
iii) Ensure that blocks are procured from approved manufacturer
(s). Except where otherwise approved in writing each
material shall be obtained from a single source.
iv) Source certificates shall be obtained for all raw materials e.g. Project FINI/15/A,
sand, cement and blocks to show compliance with the Engineer Source
contract specification, where required. docs,
approvals
.4 Handling and Storage of Materials:

i) Blocks shall be delivered to site and off-loaded as near to the Store-


point of use as practicable on a clean hard surface free from keeper Delivery
contamination. Note
Store-
ii) Cement shall be stored off the ground, kept dry and used in keeper
order of delivery.
Store-
iii) Store metal ties, straps and reinforcement under cover and keeper
protect them from damage and distortion.
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/15
PAGE 2 OF 2
SECTION: DATE OF ISSUE
FINISHING September 2007
SUBJECT: BY:
QA/QC ENGINEER
CONTROL OF GLASS BLOCKWORK APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.5 Preparation of Work, Materials and Components:

i) When the materials and components are distributed to the Site


work area, ensure that the structure is not overloaded. Engineer
ii) Plan for scaffolding material required for work at heights. Site
Plan for additional manpower for lifting blocks at heights. Engineer
iii) Set out anticipating the position of openings etc. in the work
above to avoid adjustment of units leading to incorrect or Gen.
uneven bonding. Foreman FINI/15/A

.6 Preparation of Mortar Mixes:

i) Mortar shall be mixed by machine except for small quantities


only. Hand mixing (if permitted) may be done on a watertight Gen.
platform. Foreman
ii) When mixed at site, batch boxes shall be used to ensure Gen.
correct and consistent mix proportions. Foreman
iii) Use mortars (other than retarded mortars) within 2 hours of Gen.
mixing or as specified. Foreman FINI/15/A

.7 Building walls:

i) Build work within permissible deviations as specified. Site


ii) Unless otherwise specified/permitted, lay blocks on a full bed Engineer
of mortar and fill all joints. Place reinforcement as detailed in
position, use spaces as necessary to keep courses levelled and
perpend vertically aligned. Plumb quoins and all faces as the
work proceeds. It is preferable to align vertically every fifth
or sixth perpend and `even out the size of intermediate joints. Gen.
Try to keep horizontal joints of uniform thickness. Foreman
iii) Do not carry one course more than the height specified in the Gen.
contract specifications. Foreman FINI/15/A
iv) Where pointing is specified rake out joints as work proceeds.
The mortar used for the pointing should be mixed as detailed Gen.
in the specification. Foreman
v) All work shall be bonded to adjacent structures by means of
stainless steel cramps at specified spacing unless specified Gen.
otherwise. Foreman
vi) All glass blocks must be cleaned down as work proceeds.
Appendix FINI/15/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR CONTROL OF GLASS BLOCKWORK Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE
PRIOR TO WORK
COMMENCING 1. Setting out (openings etc.) SE/SU

2. Check source certificates of materials PE

3. Check mix proportion of mortar. GF


CHECKS DURING
THE WORK 4. Check alignment/width of perpends. GF

5. Check line and level of courses. GF

6. Check metal ties/reinforcement. GF

7. Check raked out joints. GF

8. Check pointing. GF

9. Check sealants. GF
APPROVAL TO PROCEED WITH THE NEXT
TRADE QA/QC

QA/QC Quality Assurance/Quality Control, SE Site Engineer, GF General Foreman


AL RAJHI PROJECTS AND CONSTRUCTION LLC

WORK PROCEDURE
PROJECT: Ref No. FINI/16
PAGE 1 OF 1
SECTION: DATE OF ISSUE
EXTERNAL CLADDING September 2007
SUBJECT: BY:
QA/QC ENGINEER
SUPPLY AND FIX METAL CLADDING APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure applies to the installation of proprietary external


metal cladding.

2. PROCEDURE

.1 A programme shall be prepared showing all activities, order of Project


work, phased area of access and dates, etc. It shall be approved by Manager
the Project Director/Manager. Project Programme
Planner/
.2 A method statement is to be prepared and submitted for approval by Subcon.
the subcontractor detailing sequence and method of correction, Method
plant to be used, safety procedure, submittal and checking of design Sub- Statement
drawings. contractor

.3 The subcontractor is to nominate a person responsible for their site Sub- Letter
activities. contractor

.4 Document/test certificates shall be provided by the subcontractor to Source


verify compliance with the specification and Client's requirements. Sub- Certificates
contractor
.5 The work shall be inspected using the attached Appendix
FINI/16/A, which will be completed as verification records and
retained in a file on site. Project FINI/16/A
Engineer
.6 Unacceptable workmanship shall be notified to the subcontractor Non-
on a Non-Conformity Report and corrective action taken. Conformity
QA/QC Report
.7 Specific subcontractor responsibilities and method for cleaning
away debris and final clean, protection of the finished installation
shall be agreed and confirmed to the subcontractor. Sub- Letter
contractor
Appendix FINI/16/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR EXTERNAL METAL CLADDING Sheet No.

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE
BEFORE
MANUFACTURE 1. Review of design detailing PE
2. Approval of subcontractor's specification and
shop drawings by Consultant. PE
3. Approval of components and finishes samples
by Consultant. PE
APPROVAL TO PROCEED WITH
MANUFACTURE PD/M

INSTALLATION 4. Check fixings, brackets to specification QA/QC

5. Building frame preparation complete. SE

6. Building frame accepted by subcontractor. Subcon.


APPROVAL TO PROCEED WITH
ERECTION CM
POST
INSTALLATION 7. All corrective action sheets signed-off. QA/QC

8. Protection to finished installation satisfactory. PE

9. All surplus material and debris cleared off-site. GF


10. Tape removed and system cleaned down prior
to hand over. GF

11. Check surface damage. SE

APPROVAL TO PROCEED CM

PD/M Project Director/Manager, CM Construction Manager PE Project Engineer,


SE Site Engineer, QA/QC Quality Assurance/Quality Control, GF General Foreman,
Subcon - Subcontractor
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. STR/01
PAGE 1 OF 2
SECTION: DATE OF ISSUE
STRUCTURAL STEELWORK September 2007
SUBJECT: BY:
QA/QC ENGINEER
FABRICATION AND ERECTION OF APPROVED BY:
STRUCTURAL STEEL QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure covers control of fabrication and erection of


Structural Steelwork carried out by a Subcontractor.

2. PROCEDURE

.1 All structural steelwork will be carried out in accordance with the


specification detailed in the Project Contract documentation. In any
circumstances where specifications are not provided or they are in Project
any way incomplete, the matter shall be referred back to the Manager Request For
Consultant for additional information. Information

.2 A method statement is to be prepared and submitted by the


subcontractor detailing the following information:

i) Welding procedure on/off site.


ii) Testing procedure for welds.
iii) Method of transporting fabricated material to site.
iv) Method of erection, plants and equipment to be used.
v) Safety procedures and drawing/erection programme
Sub- Approved
The method statement shall be approved by the Project contractor Method
Director/Manager prior to the commencement of work. Statement

.3 The subcontractor shall submit shop drawings for approval by the Project Approved
Project Director/Manager/Consultant. Manager shop
Subcon. drawing
.4 Certificates of qualified welders to be furnished by the subcontractor. Certs. of
Subcon. Compe-
tency
.5 Lifting equipment test certificates to be made available for inspection
and verified. Certificates
Project
.6 Subcontractor will submit samples and test certificate of all nuts, Manager/ Samples
bolts, washers, spacers etc. for approval by the Project Consultant and Test
Director/Manager/Consultant (if required). Certificates
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. STR/01
PAGE 2 OF 2
SECTION: DATE OF ISSUE
STRUCTURAL STEELWORK September 2007
SUBJECT: BY:
QA/QC ENGINEER
FABRICATION AND ERECTION OF APPROVED BY:
STRUCTURAL STEEL QEHS MANAGER
ACTION VERIFY

.7 The Subcontractor shall carry out tests on welds as specified in the Test
contract specification and advises Al Rajhi for witnessing purposes. Subcon. Report

.8 Upon sectional completion of the erection and in accordance with the


Project Quality Plan, the Subcontractor shall offer the work for
inspection by the QA/QC. This will be carried out in accordance with Subcon./
the attached checksheet as Appendix STR/01/A. QA/QC Checksheet

.9 Bolts shall be checked for correct torque as specified. Site STR/01/A


Engineer
.10 Final inspection will ensure that the protective paint system is clean,
intact and to the specification. QA/QC STR/01/A
Appendix STR/01/A
September 2007

AL RAJHI PROJECTS AND CONSTRUCTION LLC

PROJECT: SITE NO.:

CHECK SHEET FOR FABRICATION AND ERECTION OF Sheet No.


STRUCTURAL STEELWORK

SUBCONTRACTOR: Al Rajhi

SECTION OF WORK _________________________________ LOCATION _________________

Checked
STAGE ITEM by DATE
PRIOR TO
FABRICATION 1. Method statement approved. PD/M
2. Manufacturers test certificates for steel, welding,
electrodes, nuts, bolts, washers etc. for approval PE
3. Shop drawing approval SE
APPROVAL TO PROCEED WITH
FABRICATION PD/M
DURING
FABRICATION 4. Check welds visual inspections, not reports QA/QC
5. Check dimensions of each member and compare
the fabricated members with shop drawings. SE
6. Check shop coat of primer/surface preparation. SE
APPROVAL TO PROCEED WITH
TRANSPORTING TO SITE QA/QC
PRIOR TO
ERECTION 7. Check base lines and level. SE/SU
8. Check H.D. Bolts. SE
9. Check all members installed correctly as per the
ERECTION approved drawings. QA/QC
10. Check all bolts washers have been installed. SE
11. Check site welds have been completed. QA/QC
12. Check line, level and plumb. SE/SU
13. Check bolts tightened in accordance with the
specification. SE
14. Check NDT reports of site welds. QA/QC
15. Check protective paint system is clean, sound
and to specification. PE

APPROVAL TO GROUT BASE PLATE CM


APPROVAL TO PROCEED WITH
CLADDING/LOADING CM
PD/M Project Director/Manager, CM Construction Manager, PE Project Engineer,
SE Site Engineer, QA/QC Quality Assurance/Quality Control, SU - Surveyor
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. SERV/01
PAGE 1 OF 4
SECTION: DATE OF ISSUE
SERVICES September 2007
SUBJECT: BY:
QA/QC ENGINEER
SUPERVISION OF MEP SUBCONTRACT APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

This procedure applies to the monitoring, inspection and control of


the installation, testing/commissioning setting to work and final
hand-over of the Mechanical, Electrical and Plumbing Services being
executed by a Sub-contractor and where an MEP Co-ordinator is
deployed by HEE.

2. RESPONSIBILITY

The MEP Co-ordinator will be responsible for the effective operation Project
of the procedures listed below and for ensuring that all checksheets Director/
are signed and approvals obtained as necessary. Manager

.1 Information from the Subcontractor

Obtain from the Subcontractor the following information where


applicable:

i) Project Quality Plan and/or


ii) Method Statement and, Inspection and Test Plan.
iii) Programme of works including manpower planning, material
submittal / approval / delivery schedule, shop drawing MEP
submittal / approval schedule and cash flow etc. Subcon. PQP,
iv) Testing and Commissioning programme. & MEP MS, ITP
v) Calibration certificates for all measuring equipment. Coord. Programme

.2 Installation

.2.1 Working drawings:

i) Agree a working drawing issue schedule with the MEP Drawing


subcontractor to suit the Project Programme. Coord. Schedule
ii) Monitor and control the submission of drawings for approval. MEP
Coord.
iii) Ensure drawings are issued to the Consultant for comment MEP
and obtain status. Coord.
iv) Ensure drawings with comments appended are updated and
re-submitted immediately for approval. Subcon.
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. SERV/01
PAGE 2 OF 4
SECTION: DATE OF ISSUE
SERVICES September 2007
SUBJECT: BY:
QA/QC ENGINEER
SUPERVISION OF MEP SUBCONTRACT APPROVED BY:
QEHS MANAGER
ACTION VERIFY

v) Shop drawings issued for installation purposes must be Subcon.


stamped For Construction. & MEP
Coord.
.2.2 Builders Work Drawings:
Subcon.
i) Agree a builders work drawing issue schedule to suit the & MEP
project programme. Coord. Drawings
ii) For a single Sub-contractor, ensure drawings are prepared and Subcon.
submitted by the Sub-contractor well in advance for approval & MEP
after checking / co-ordinating for other relevant services. Coord.
iii) For separate Sub-contractors, Al Rajhi will monitor and Subcon.
control the preparation of drawings, forward to & MEP
Consultant/Client and ensure approved/commented drawings Coord.
are forwarded to relevant Subcontractor.

.2.3 Material Procurement Schedule:

i) Obtain material procurement and delivery schedule from the Subcon. Procurement
sub-contractor and monitor deliveries. Ensure that it matches & MEP /Delivery
the Main Contract Programme. Coord. Schedule
ii) Manufacturers test certificates must be obtained for all
equipment tested off site in accordance with the test plan. Subcon. Test
iii) Client/consultant to be given the opportunity to inspect any MEP certificates
equipment prior to delivery. Coord. Work
Inspection
.2.4 Installed Works: Request

i) Monitor performance against subcontractors works MEP Minutes of


programme. Chair meetings where necessary. Coord. Meeting
ii) Areas of work offered as completed must be checked by the Subcon.
sub-contractor and MEP Co-ordinator before being offered to & MEP Subcon.
Consultant for acceptance. Coord. Checksheet
iii) Ensure all snagging items are cleared during progress of MEP
works. Coord. Snag Sheet
iv) Obtain Consultants written acceptance of completed works MEP Work
(1st and 2nd fix). Coord. Inspection
v) All relevant tests are to be carried out prior to works being Request
concealed and must be witnessed and accepted by the MEP
Consultant. Coord. Test Results
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. SERV/01
PAGE 3 OF 4
SECTION: DATE OF ISSUE
SERVICES September 2007
SUBJECT: BY:
QA/QC ENGINEER
SUPERVISION OF MEP SUBCONTRACT APPROVED BY:
QEHS MANAGER
ACTION VERIFY

vi) MEP Co-ordinator must ensure that records of all testing are MEP Test
kept on site. Coord. Records
vii) The subcontractor will keep on site a full set of
installation/shop drawings. These drawings are to be
available for inspection by the Consultant. Subcon. Drawings
viii) MEP Co-ordinator to ensure that installations are in MEP Letter/NCR
accordance with the specifications and to notify the Coord./ Snagging
subcontractor in writing of any non-compliance. QA/QC sheet
ix) Ensure all design information is available as required and MEP
process sub-contractors requests for information through the Coord. Request For
Consultant. Information
x) Where necessary organise regular meetings with the MEP Minutes of
Consultant and expedite technical queries. Coord. Meeting

.2.5 Commissioning

i) Obtain a commissioning programme and method statement Subcon. Method


for commissioning & MEP Statement,
ii) Monitor commissioning performance against programme. Coord. Programme
iii) Agree witnessing/acceptance programme with the Consultant MEP Test Results
and ensure all systems are signed off. Coord.
iv) Retain records of all commissioning data and checksheets. Commng
v) Use Appendices A to S as necessary to record commissioning MEP Records/
checks, or as agreed with the subcontractor. Coord. Checksheets

.2.6 Rectification of Final Snags

i) Ensure all snags are attended to by the Subcontractors before Subcon.


final handover. & MEP Snag. Sheet
Coord.
.2.7 Setting to Work/Handover

i) Following commissioning, all systems are to be set to work


and left running for the trial period as defined in the
specification.
ii) On completion of trial run, obtain final Handover Certificate Consultant Handover
from the Consultant. Certificate
Al Rajhi Projects and Construction LLC

WORK PROCEDURE
PROJECT: Ref No. SERV/01
PAGE 4 OF 4
SECTION: DATE OF ISSUE
SERVICES September 2007
SUBJECT: BY:
QA/QC ENGINEER
SUPERVISION OF MEP SUBCONTRACT APPROVED BY:
QEHS MANAGER
ACTION VERIFY

.2.8 O&M Manuals and As-Built Drawings


Subcon.
i) Monitor the timely production of O&M manuals and As-Built & MEP
drawings which are to be issued to the Consultant. Coord.
ii) Obtain a draft format of all manuals for Consultants MEP
approval. Coord.
iii) Issue full set of draft manuals for comment by the Consultant MEP
as per the programme. Coord. O&M
iv) Issue completed manuals and `As Built drawings in required MEP Manuals
numbers prior to completion. Coord. and As-
Built
drawings
Appendix SERV/01/A
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

COMMISSIONING CHECK SHEET FOR CHILLED WATER PUMP Sheet No.

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Chilled water distribution network pressure tested and
cleared.
2 Makeup connection made.
3 Dosing pot connected.
4 Strainers are cleaned.
5 Drain connections to all equipment provided.
6 Pressure gauges and flow switches are installed.
7 Tightness of electrical connections.
8 Supply voltage and motor rating.
9 Free rotation of impeller.
10 MCC is clean.
11 Pump and motor are clean.
12 Overload setting and fuse rating.
13 Pump and motor alignment.
14 Pumps are interfaced with BMS.
15 Pumps are in manual made.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/B
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

COMMISSIONING CHECK SHEET FOR AIR HANDLING UNIT Sheet No.

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Areas being fed by AHU are clean.
2 Filters are clean.
3 Condense drain tray is clean and connected to waste
line.
4 Duct temperatures sensors and differential pressure
switches are installed.
5 All VCDs and splitters are open.
6 Fan impeller rotates freely.
7 Belt tension adjusted.
8 Alignment of pulleys and check bearings.
9 Overload setting and fuse rating.
10 Electrical connections and tight.
11 BMS wiring completed.
12 Heaters and connected if applicable.
13 DRV and GV are adjusted for design flow rate.
14 Check flow of condense drain and P trap.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/C
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

COMMISSIONING CHECK SHEET FOR FAN COIL UNIT Sheet No.

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Areas being fed by FCU are clean.
2 Filter is clean.
3 Condensate drain tray is clean and connected to waste
line.
4 Three speed switch and DP switch are connected.
5 Thermostat is installed.
6 Fan impeller rotates freely.
7 DRV and GV are adjusted for design flow rate.
8 Check fan bearings.
9 Check flow of condensate drain and P-trap.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/D
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

COMMISSIONING CHECK SHEET FOR EXTRACT FANS Sheet No.

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Check cleanliness.
2 Open all VCDs.
3 Check free impeller rotation.
4 Check pulley alignment/bearing.
5 Differential pressure switches are installed.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/E
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

COMMISSIONING CHECK SHEET FOR COLD WATER TRANSFER Sheet No.


PUMP SETS

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Roof tanks are installed.
2 Float ball valves are installed.
3 Pressure switch is fixed.
4 Filtered water tank is filled up.
5 Electrical connections are tight.
6 Supply voltage and motor rating.
7 Free rotation of pump impeller.
8 Pump and motors are clean.
9 Overload setting and fuse rating checked.
10 Pump motor alignment.
11 Pipe line pressure tested.
12 Mounting arrangement for proper floating on vibration
isolating on vibration isolating springs.
13 Control wiring is properly done.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/F
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

COMMISSIONING CHECK SHEET FOR COLD WATER BOOSTER Sheet No.


PUMP

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Cold water line pressure tested.
2 Low level cut out switch installed.
3 Pump motor alignment.
4 Mounting arrangement for proper operation on
vibration isolating springs.
5 Supply voltage and motor rating.
6 Electrical connections are tight.
7 Overload setting and fuse rating checked.
8 Free rotation of pump impeller.
9 Pressure vessel is properly charged.
10 Control wiring is properly done.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/G
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

COMMISSIONING CHECK SHEET FOR SUMP PUMP Sheet No.

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Pipe line pressure tested.
2 AVVs are installed.
3 Pressure gauges are installed.
4 Pump motor alignment.
5 Mounting arrangement for proper floating on vibration
isolating on vibration isolating springs.
6 Pump set motors are clean.
7 Supply voltage and motor rating.
8 Overload setting and fuse rating.
9 Tightness of electrical connections.
10 Free rotation of pump impeller.
11 Calorifer vent line connected.
12 Control wiring is properly done.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/H
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

COMMISSIONING CHECK SHEET FOR SPRINKLER + WET BOOSTER Sheet No.


SET

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Pipe line tested.
2 AVVs are installed.
3 Supply voltage matches with motor rating.
4 Tightness of electrical connections.
5 Control wiring is properly done.
6 Mounting arrangement for proper operation on
vibration isolating springs.
7 Pump motor alignment.
8 Pressure vessel properly charged.
9 By pass line to tank provided.
10 Raw water tank filled up.
11 Non return valve installed.
12 Overload setting and fuse rating.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/I
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

COMMISSIONING CHECK SHEET FOR AIR DISTRIBUTION SYSTEM Sheet No.

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Clean all air intake areas, air conditioned areas.
2 Clean all AHUs, FCUs and fans.
3 Open all outlets.
4 Seal all unwanted openings in air path.
5 Check for free rotation of impeller.
6 Set overload protection correctly.
7 Check for tightness of electrical connections.
8 Ensure installation of filters in all units.
9 Clean filters.
10 Check belt tension and lubrication.
11 Start fans.
12 Balance air as per design.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/J
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

COMMISSIONING CHECK SHEET FOR CHILLED WATER Sheet No.


DISTRIBUTION SYSTEM

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Avoid line air lock.
2 Provide air vents at top points.
3 Remove spades from flanges.
4 Mark distribution of flow and return on pipes.
5 Open all isolating valves after flushing with water.
6 Check for free rotation of pump impeller.
7 Check starter overload setting and electrical
connections are tight.
8 Start pumps.
9 Check current, priming of pump motor.
10 Check head developed by pump.
11 Circulate water through all equipment for four hours
and flush the system.
12 Clean strainers.
13 Repeat above until clear water is observed.
14 Check that water reaches all equipment.
15 Balance water flow through equipment and in
branches.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/K
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR TESTING AND COMMISSIONING EARTHING Sheet No.


AND EARTH BONDING

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 PHYSICAL CHECKS
a. Check the earth electrodes in earth pits for proper
installation and connection.
b. Check the protective conductors from the earth
installation and connection.
2 EARTH ELECTRODE RESISTANCE
a. Remove the conductor connection from the electrodes.
b. Measure earth electrode resistance by using an earth
meggar.
c. Repeat (1) and (2) above for all pits and tabulate
readings.
3 CONTINUITY TEST
a. Check proper earth bonding by checking continuity of
protective conductor by a D.C. ohm meter.
b. The above to be checked for all protective conductors
to various equipment.
c. Check continuity resistance between the main earth
terminal of the MDB/DB and the farthest equipment by
a DC ohm meter.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/S
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR TESTING AND COMMISSIONING OF MUSIC AND Sheet No.
PUBLIC ADDRESS SYSTEM

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 VISUAL CHECKS
a. Check installation of all the components like decks,
tuner amplifier, microphone, speakers, cassettes and
power supply units.
b. Check cable laying and connection.
2 FUNCTIONAL TEST
a. Put the system as per manufacturers recommendation.
b. Check performance of the system for its configuration.
c. Tabulate observation.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/L
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR TESTING AND COMMISSIONING OF Sheet No.


MATV SYSTEM

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 VISUAL CHECKS
a. Check the components such as antenna mast, amplifier,
splitter, power supply etc.
b. Check cable installation and connections.
2 MEASUREMENT OF SIGNAL LEVELS
a. Put the system into operation as per manufacturers
recommendations.
b. Adjust antennas and amplifier to receive the required
signal level at the amplifiers output terminal.
c. Measure signal level for the various channels specified.
d. With the signal monitor see trail pictures of different
channels at the amplifier output with amplifier gain
adjusted for clarify.
e. With a signal monitor check signal levels and picture
clarify at the points.
f. Tabulate signal levels.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/M
September 2007

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR TESTING AND COMMISSIONING OF Sheet No.


CCTV SURVEILLANCE

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 VISUAL CHECKS
a. Check installation of all cameras, switches, monitors
for proper support and connection.
b. Check all cables for proper installation.
2 FUNCTIONAL CHECKS
a. Put the system into operation as per manufacturers
recommendations.
b. Check performance of the system for its configuration.
c. Tabulate observations.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/N
September 2007
1 of 2

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR TESTING AND COMMISSIONING OF Sheet No.


FIRE ALARM SYSTEM

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 VISUAL CHECKS
a. Check installation of MICC cables for proper laying
termination, clipping, labelling, identification, etc.
b. Check cable connection to the FACP, battery, repeater
panel.
2 INSULATION RESISTANCE TEST
a. Check insulation resistance between cores with a 500V
meggar.
b. Tabulate readings.
3 FUNCTIONAL CHECKS
3(A) Fire Alarm
a. Put the system into operation as per manufacturers
recommendation.
b. Simulate fire conditions by generating smoke/heat to
activate the detectors.
c. Check display of detector number.
d. Check operation of LED on the detector.
e. Check display on mimic panel.
f. Check sounder circuits and bells.
THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY Al Rajhi : ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/N
September 2007
2 of 2

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR TESTING AND COMMISSIONING OF Sheet No.


FIRE ALARM SYSTEM

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
Contd
3(B) Fault Alarm
a. Simulate fault situations like power failure battery on,
open circuit.
b. Check visual display in the panel.
3(C) Interlock Check
a. Simulate fire conditions in each zone.
b. Check that the FAHU/AHU in that zone cuts out.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY Al Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/O
September 2007
1 of 2

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR TESTING AND COMMISSIONING OF Sheet No.


POWER AND CONTROL CABLES

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 PHYSICAL CHECKS
The cable installation has to checked for:
a. Proper laying and dressing.
b. Cable tying.
c. Cable tray supports.
d. Cable identification and labelling.
e. Termination.
f. Damage.
2 INSULATION RESISTANCE TEST
a. Measure insulation resistance between cores of all
cable with 500V meggar and tabulate readings
b. Measure insulation resistance between cores and ECC
and earth terminal with a 500V meggar and tabulate
readings

Once the valves are found to be satisfactory, the


breakers may be switched on and the following tests
may be carried out.
3 PHASE ROTATION TEST
a. Check phase rotation at all points.
b. Phase rotation at all points should be same or rectify.
THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY Al Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/O
September 2007
2 of 2

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR TESTING AND COMMISSIONING OF Sheet No.


POWER AND CONTROL CABLES

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
4 PERFORMANCE TEST
a. Switch on all isolators and run all equipment.
b. Check for any unusual temperature rise in cables,
terminals and switches.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY Al Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/P
September 2007
1 of 2

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR TESTING AND COMMISSIONING OF Sheet No.


MOTOR CONTROL CENTRE

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 PHYSICAL CHECKS
a. Check all MCCs to ensure that all components of
correct ratings have been installed against the approved
shop drawings.
b. Check that all components are wired correctly and
neatly
c. Check that all the components are labelled and
identified
d. Check that all meters and selector switches are
correctly selected.
e. Check that all nuts and bolts as well as the busbar
connections are tight.
f. Check that all components and related connections are
earthed.
2 INSULATION RESISTANCE TEST
a. Disconnect all lamps and meters, which are not
supposed to be subjected to 500V.
b. Measuring insulation resistance between phases,
neutral and earth with a 500V meggar.
c. Tabulate readings.
THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY Al Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/P
September 2007
2 of 2

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR TESTING AND COMMISSIONING OF Sheet No.


MOTOR CONTROL CENTRE

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
3 FUNCTIONAL TEST
a. Check the control circuit of each starter/system for its
correct operation in regard to switching on, thermal
over load and emergency stop-lock.
b. Check switching on and off all breakers, contractors
and relays for their desired operation.
c. Check operation all indicating lamps and meters.
d. Keep all connected equipment running for sufficient
time and check for any abnormal rise in temperature on
busbars, cables, terminals etc.
4 RCCB TEST
a. Set sensitivity currents of RCCBs at
50%
100%
150%
of the sensitivity currents.
b. Record trip times and compare with the characteristic
valves.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/Q
September 2007
1 of 2

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR TESTING AND COMMISSIONING OF


MAIN DISTRIBUTION BOARDS AND SUB MAIN DISTRIBUTION Sheet No.
BOARDS

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 PHYSICAL CHECKS
a. Check all MCCs to ensure that all components of
correct ratings have been installed against the approved
shop drawings.
b. Check that all components are wired correctly and
neatly
c. Check that all the components are labelled and
identified
d. Check that all meters and selector switches are
correctly selected.
e. Check that all nuts and bolts as well as the busbar
connections are tight.
f. Check that all components and related connections are
earthed.
2 INSULATION RESISTANCE TEST
a. Disconnect all lamps and meters, which are not
supposed to be subjected to 500V.
b. Measuring insulation resistance between phases,
neutral and earth with a 500V meggar.
c. Tabulate readings.
THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY Al Rajhi : ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/Q
September 2007
2 of 2

AL RAJHI PROJECTS AND CONSTRUCTION LLC

PROJECT: SITE NO.:


CHECK SHEET FOR TESTING AND COMMISSIONING OF
MAIN DISTRIBUTION BOARDS AND SUB MAIN DISTRIBUTION Sheet No.
BOARDS

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
3 FUNCTIONAL TEST
a. Check ON/OFF/Trip functions of all MCCBs.
b. Check operation of indication lamps and meters.
4 EARTH LEAKAGE PROTECTION
4(A) ELCB Test
a. Set sensitivity currents of RCCBs at
50%
100%
150%
of the sensitivity currents.
b. Record trip times and compare with RCCB tester and
compare with ELCB the characteristics values.
4(B) ELS Test
a. Set sensitivity currents of ELCBs at
50%
100%
150%
of the rated sensitivity current by external means
(RCCB tester may be used).
b. Record trip times and compare with EL relay
characteristics values.
THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/R
September 2007
1 of 2

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR TESTING AND COMMISSIONING OF Sheet No.


FINAL CIRCUITS AND DISTRIBUTION BOARDS

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 PHYSICAL CHECKS
a. Check all electrical components (equipment such as
conduits, wires, trunking, switches, socket, outlets etc.)
connected to final circuits for the protection and
damage
b. Check the installation of the DBs.
c. Check internal wiring for strong connection
identification, labelling etc.
d. Check that all metallic components are earthed/bonded.
2 POLARITY CHECK
a. Check that all single pole switches are installed in the
live conductor.
3 CONTINUITY OF PROTECTIVE CONDUCTORS
a. For all final circuits check continuity of the protective
conductor from the furthest point to the main earth
terminal of the DB by a DC ohm meter.
b. Repeat (3a.) above for all ring final circuit conductors.
c. Tabulate the readings.
4 INSULATION RESISTANCE TEST
a. This test is preferably carried out before the light
fittings or current using equipment are installed.
THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY Al Rajhi : ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature
Appendix SERV/01/R
September 2007
2 of 2

Al Rajhi Projects and Construction LLC

PROJECT: SITE NO.:

CHECK SHEET FOR TESTING AND COMMISSIONING OF Sheet No.


FINAL CIRCUITS AND DISTRIBUTION BOARDS

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
Contd
b. Measure insulation resistance between phase, neutral
and earth by a 500V meggar.
c. Repeat (4b.) above for all circuits and tabulate.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY AL Rajhi: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature