Roxas, Isabela
CONTRACT PAYMENT CHECKLIST
First Progress Billing
CONTRACTOR :
SMT CONSTRUCTION Payment Certificate No. First Partial Payment
Sheet No. 1 Of 1
Total Unit Price Total Total Qty Total Qty Balance
Cost of
Item Contract in Contract Approved in To This of Cost to Balance
Description Unit
No. Quantity Peso Cost Previous This Quantity Previous This Date of Cost
Date
Billing Billing Billing Billing
A. Building
900(a) R.C. for Column & PC Cu.m. 3.59 5,154.55 18,504.83 - 3.59 3.59 - - 18,504.83 18,504.83 -
404(a) R.S. for Column & PC Kgs. 482.66 50.92 24,577.05 - 482.66 482.66 - - 24,577.05 24,577.05 -
900(b) R.C. for RB & RTB Cu.m. 5.70 9,249.24 52,720.67 - 5.70 5.70 - - 52,720.67 52,720.67 -
404(b) R.S. for RB & RTB Kgs. 820.24 53.72 44,063.29 - 820.24 820.24 - - 44,063.29 44,063.29 -
403(a) Structural Steel Works Kgs. 6335.59 96.75 612,968.33 - 3,809.28 3,809.28 2,526.31 - 368,547.84 368,547.84 244,420.49
1014 Pre-Painted Long Span Metal Roofing Sq.m. 306.00 571.96 175,019.76 - - - 306.00 - - - 175,019.76
B. MISCELLANEOUS - - - - - - - -
B.7 Occupational Safety & Health Program MD 480.00 12.18 5,846.40 - 240.00 240.00 240.00 - 2,923.20 2,923.20 2,923.20
B.9 Mobilization/Demobilization LS ALL 6,792.80 6,792.80 - 50% 50% 50% - 3,396.40 3,396.40 3,396.40
******* - - - - - - - - -
- - - - - - - - -
- - - - - - - - -
- - - - - - - - -
- - - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
TOTAL 940,493.13 - ### ### ###
WE HEREBY CERTIFY that the Statement of Work Accomplished on this page is true and correct.
Submitted by: Checked by: APPROVED:
DANILO R. RAFANAN
Project Engineer
Republic of the Philippines MONTHLY CERTIFICATE OF PAYMENT
Department of Public Works & Highways Payment Cert. No. First Partial Payment
Isabela Second District Engineering Office For the Period from : February 7- 27,2017 Sheet No. 1 of 1
Roxas, Isabela Date : March 06,2017
PCMA ID No. P00140501LZ-CW1
Project ID 17BF0012
Project Name: Construction of Barangay Disusuan Community Center, 14. I HEREBY CERTIFY that the attached Statement
Disusuan, San Mariano,Isabela of Work is correct and just and does not include items
and/or portions thereat for which payment has already CHECKED & REVIEWED
CONTRACTOR: SMT CONSTRUCTION been received. In regards to this Items materials
ORIGINAL CONTRACT AMOUNT: 940,493.13 are on site and are properly protected. FELIPE A. LASAM
REVISED CONTRACT AMOUNT: - Chief, Construction Section
March 06,2017
Date
BACKGROUND:
REMARKS:
First Partial Payment
DANILO R. RAFANAN
Project Engineer
BILLING SUMMARY
March 06,2017
BALANCE 425,759.85
PAYMENT BREAKDOWN
See Attached SWA
SIGNATORIES
DANILO R. RAFANAN
Project Engineer
EXECUTIVE S U M MARY
DANILO R. RAFANAN
Project Engineer
ISABELA SECOND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE II
Roxas, Isabela
March 06,2017
Date
have been filed in this office on unpaid materials against the Contractor SMT
CONSTRUCTION.
DANILO R. RAFANAN
Project Engineer
Republic of the Philippines
DEPARTMENT OF PUBLICS WORKS AND HIGHWAYS
ISABELA SECOND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE II
Roxas, Isabela
no claims against him on Equipment lease or rental obligations filed with office, or amount
DANILO R. RAFANAN
Project Engineer
SMT CONSTRUCTION
Ilagan City, Isabela
March 06,2017
Dear Sir:
We are submitting herewith our First Partial Billing covering from the period
from February 7- 27,2017 in the amount of Php 514,733.28
We have accomplished the work satisfactorily in accordance to the terms and conditions
of the contract. We also certify that the Performance Security of Contractor's Comprehensive All Risk
Insurance (CARI) is valid and documents are hereto attached for your review and approval.
SMT CONSTRUCTION
Contractor
SMT CONSTRUCTION
Ilagan City, Isabela
March 06,2017
Dear Sir:
Disusuan, San Mariano,Isabela with Project ID: 17BF0012 ,PCMA ID: P00140501LZ-CW1
a request for the representative of your office to conduct an an inspection and/or verification thereof.
to the Budget Officer to be incorporated in the supporting documents to be attached to the voucher.
SMT CONSTRUCTION
Contractor
Republic of the Philippines Fund Cluster :
DEPARTMENT OF PUBLICS WORKS AND HIGHWAYS
ISABELA SECOND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE II
Roxas, Isabela
Date :
DV No. :
DISBURSEMENT VOUCHER
Mode of
MDS Check Commercial Check ADA Others (Please specify)
Payment
FELIPE A. LASAM
Chief, Construction Section
B. Accounting Entry:
Account Title UACS Code Debit Credit
Signature Signature
Date Date
E. Receipt of Payment JEV No.
Check/ Date : Bank Name & Account Number:
ADA No. :
Date : Printed Name: Date
Signature :
Mode of
MDS Check Commercial Check ADA Others (Please specify)
Payment
2% Tax 8,272.50
5% Vat 20,681.25
FELIPE A. LASAM
Chief, Construction Section
B. Accounting Entry:
Account Title UACS Code Debit Credit
Signature Signature
Date Date
E. Receipt of Payment JEV No.
Check/ Date : Bank Name & Account Number:
ADA No. :
Date : Printed Name: Date
Signature :
Responsibility Center
Office/Unit/Project Code:
Address ILAGAN CITY, ISABELA CONSTRUCTION SECTION 309-05-14-05
EXPLANATION AMOUNT
2% Tax 8,272.50
5% Vat 20,681.25
28,953.75
-
PMS NO: P00140501LZ-CW1
Project ID 17BF0012 NET AMOUNT DUE.. 434,306.20
Signature Signature
Printed Printed
EVANGELINE C. DUYAG REYNATO M. UBIA
Name Name
ACCOUNTING ENTRIES
RESP. ACCOUNT AMOUNT
ACCOUNTS AND EXPLANATIONS REF
CENTER CODE DEBIT CREDIT
Republic of the Philippines
Department of Public Works & Highways
OFFICE OF THE DISTRICT ENGINEER
Isabela Second District Engineering Office
Roxas, Isabela
November 22,2013
Date
Project ID :
Contractor :
Since the Contractor has satisfactorily complied with the requirements of the
Inspectorate Team, this certificate of completion is hereby issued. The warranty Period
commences from the completion.
This Certification, however, does not relieve the Contractor of his obligations and
responsibilities in undertaking repair works, in accordance with accepted standards, on any
defect or failure that may occur on any section of the Project during the one (1) year defects
liability period. During this period, the Contractor is responsible for the repair of any defects,
fair wear and tear excepted, and these should be rectified by the Contractor, at his own
expense prior to final acceptance.
EDILBERTO B. DE GUZMAN
Project Engineer
CONCURRED:
REYNATO M. UBIA
District Engineer
CERTIFICATE OF ACCEPTANCE
( By the End-User )
November 22,2013
Date
NOTED:
EDILBERTO B. DE GUZMAN
Project Engineer
ITEMIZED COST OF REVISION
(Proposed Variation Order No. 1)
Conformed:
L. C. TALON CONSTRUCTION
Contractor
0203-15-S-00070
I. EARTHWORKS
A. GRAVEL FILL:
QTY= [(34.50 X 12.00) + (10.00 X 1.00) + (10.00 +9.00)2(2.00)]0.01 = 44.30 cu.m.
QTY= [(34.50 X 12.00) + (10.00 X 1.00) + (10.00 +9.00)2 (2.00)]0.125 = 55.375 cu.m.
2. WINDOWS:
W1 = (1.96 X 1.50) + (1.97 X 1.50) + (1.98 X 1.50)2 + (1.99 X 1.50)6 + (2 X 1.50)2 + (2.01 x 1.50)
= 38.76 sq.m.
V. PLASTERING:
1. CHB WALLS:
LINE 1
QTY = {[(21.50 x 3.40) + (10.00 x 2.80) + (3.0)(3.4 +3.90)/2)] -
[(5.25 x 2.40) + (2.00 x 1.50)7 + (0.60 X 0.90)3 + (0.80 X 1.5 = 151.26
= 151.26
LINE2
QTY = {[28.10 x 2.80] - [(0.90 x 2.10)3 + (1.20 X 2.10)2 + (0.80 X 2. = 132.58
= 132.58
LINE 3
QTY = {[33 x 2.80] -[(0.90 x 2.10)6 + (1.20 X 2.10) + (0.80 X 2.10) + (0.60 X 2.10) + (2 144.8
= 144.8
LINE 4
QTY = {[(22.00 x4.05) + (7.00 x 4.65) + (5.50)(4.65 +5.20)/2)] - = 247.2
[(2.00 x 1.50)6 + (0.90 x 1.20)3 + (0.90 X 0.60)5 + (0.80 X 1.50)]} 2
= 247.2
LINE i
QTY = (2.00 x 2.80)2 = 11.2
= 11.2
LINE 2i
QTY = (2.50 X 2.80)2 = 14
= 14
LINE3i
QTY = {[13.60 x 2.80]- [(0.90 x 2.10) + (0.80 x2.10)2 + (0.60 x 2.10)= 63.14
= 63.14
LINE 4i
QTY = (1.50 X 2.80)2 = 8.4
= 8.4
Sub Total 772.58
LINE 5i
QTY= {[10.50 x 2.80] - [(1.20 x 2.10) + (0.60 x 2.10)]}2 = 51.24
= 51.24
LINE 6i
QTY = (1.20 X 2.80)2 = 6.72
= 6.72
LINE7i
QTY= [(3.00 x 2.80) - (0.60 x 2.10)]2 = 14.28
= 14.28
LINE 8i
QTY = (1.50 X 2.80)2 = 8.4
= 8.4
LINE9i
QTY = (1.50 X 2.80)2
= 8.4 = 8.4
LINE A
QTY = [(5.00 x 3.70) + (2.00 x 2.80) + (5.00 x 4.05)] -
[(1.50 x 3.00)2 + (0.90 x 2.10)]} 2 = 66.92
= 66.92
LINE B
QTY = (5.00 X 2.80)2
= 28 = 28
LINEC
QTY = (5.00 X 2.80)2
= 28 = 28
LINE D
QTY = [(7.00 X 2.80) - (0.60 x 2.10)]2
= 36.68 = 36.68
LINE E
QTY = [(10.00X 2.80) - (0.90 x 2.10)]2
= 52.22 = 52.22
LINE F
QTY = [(8.00X 2.80) - (0.80 x 2.10)]2
= 41.44 = 41.44
LINE G
QTY = (10.00 x 2.80)2
= 56 = 56
LINE H
QTY = [(10.00X 2.80) - (0.60 x 2.10)]2
= 53.48 = 53.48
LINE I
QTY = [(10.00X 2.80) - (0.60 x 2.10)]2
= 53.48 = 53.48
LINE J
QTY = {[12.00 x 3.50]-[(0.90 x 2.10) + (0.60 x 0.90)5]}2
= 74.82 = 74.82
LINE a
QTY= [(2.00 x 2.80) -(0.60 x 2.10)]2
= 8.68 = 8.68
LINE b
QTY = [(2.00 x 2.80) -(0.60 x 2.10)]2
= 8.68 = 8.68
LINE c
QTY= (5.00 x 2.80)2
= 28 = 28
LINEd
QTY = [(5.00 x 2.80) -(0.80 x 2.10)2]2
= 21.28 = 21.28
LINE e
QTY = (5.00 X 2.80)2
= 28 = 28
LINE f
QTY = [(1.75 x 2.80) -(0.60 x 2.10)2]2 = 7.28
= 7.28
LINE g
QTY = [(5.00 x 2.80) - (0.60 x 2.10)]2 = 25.48
= 25.48
LINE h
QTY = [(3.00 x 2.80) - (0.80 x 2.10)]2 = 13.44
= 13.44
Sub-Total 720.92
LINE i
QTY = [(1.00 X 2.80) - (0.60 x 2.10)]2 = 3.08
= 3.08
LINE j
QTY = [(3.00X 2.80) - (0.60 x 2.10)]2 = 14.28
= 14.28
LINE k
QTY = [(7.70X 2.80) - (0.60 x 2.10)4]2
= 33.04 = 33.04
LINE L
QTY = (1.500 x 2.80)2 = 8.4
= 8.4
WINDOWS:
QTY. = [(7.00 X 13) +- (9 X 12) + (4.20 x 2.0) + ( 4.80 X 1) + (4.60 x 2)][0.15 = 39.02
= 39.02
BEAMS
QTY. = [(34.50 X 2) +- (12.0 X 2)](0.10)( 1.50) = 13.95
= 13.95
QTY. = [(10 X 1) +- (4 X 1)2 + (11 X 1) + (1 X 9) + (4 x 3)](0.39)(2.00) = 39
= 39
COLUMNS:
QTY = [(3.4 X 6) +- (3.9 X 1) + (4.05 x 6.0) + ( 4.65 X 3) + (5.20 x 1) + (3.07 X 1) + (2.80 X 19) + (3.50 X 2 ) + (4.05 x 1) ] (1.4)(1.5)
284.97
QTY = (2.80 X 2) (1.25) (2.0) = 284.97
14
= 14
4 FASCIA BOARD
QTY= [36.50(2) + (14)(2) + (3)(2)](0.80)(1.15)
= 98.44 = 98.44
QTY= [36.50(2) + (14)(2) + (3)(2)](0.20)(2.0)
= 42.8 = 42.8
SubTotal 590.98
February 28,2014
CERTIFICATION
THIS IS TO CERTIFY that LEONARDO C.TALON , General Manager of
L. C. TALON CONSTRUCTION with business address at Cabatuan, Isabela has submitted all the
documentary requirements necessary for the processing of the First and Final Payment in the
This is to certify further that all requirements and supporting papers pursuant to
Department Order No. 55, series of 1988 have been complied with, reviewed and found to be in order.
JOCELYN P. PALEG
Assistant District Engineer
COMPUTATION OF LIQUIDATED DAMAGES
CONTRACTOR: 0
T.L.D. = One tenth(1/10) of One(1) percent of the Cost of the Unperformed portion of the
Work for every day of delay.
Approved By:
REYNATO M. UBIA
District Engineer
Republic of the Philippines
Department of Public Works and Highways
OFFICE OF THE DISTRICT ENGINEER
Isabela Second District Engineering Office
Roxas, Isabela
No.
DISBURSEMENT VOUCHER
Mode of
MDS Check Commercial Check ADA Others
Payment
TIN/Employee No. OR/BUR No.
Payee BUREAU OF INTERNAL REVENUE
Responsibility Center
Office/Unit/Project Code:
Address Naguilian, Isabela
CONSTRUCTION SECTION 309-05-14-05
EXPLANATION AMOUNT
2% Tax 9,448.09
5% Vat 23,620.21
Signature Signature
Printed Printed
EVANGELINE C. DUYAG REYNATO M. UBIA
Name Name
ACCOUNTING ENTRIES
RESP. ACCOUNT AMOUNT
ACCOUNTS AND EXPLANATIONS REF
CENTER CODE DEBIT CREDIT
#REF!