You are on page 1of 2

design economy

Structural Steel Economy:


Revisiting the
Assumptions by Jay Ruby, P.E. and John Matuska, P.E.

Clarifying what is myth and what is reality when it comes to


material and labor costs.

W While steel prices continue


to rise and fall, responding to
market factors, the basic cost equation of
structural steel design remains the same:
fabrication and erection labor exceeds
material costs. Labor remains the largest
piece of the puzzle, as illustrated in the
chart on the following page. Furthermore,
as the percentage increase in steel price is
liver the most economical designa goal
that will be even more important in todays
economic climate. There are several myths
of structural design that have a tremendous
impact on economy of design, and address-
ing them can help you make better design
choices:

Myth #1: Using less material reduces


Connectability
Trade autonomy
Trade interface
Coordination between design and
construction
Erection costs can be increased by
using less material. For instance, lighter
members (trusses and/or girders) may
require additional shoring or erection
tracked over time, the data indicates that overall costs. bracing. This adds labor costs, equip-
the percentage increase in labor costs has Design must consider material costs, ment costs, and field time to the erectors
grown in proportion to other costs. but minimizing labor (in the shop and in schedule.
Structural engineers face a myriad of the field) can improve efficiencies in the For example, during the design phase
choices as they proceed through the design construction schedule and reduce total cost of the Mercy Hospital of Willard (Ohio)
decision matrix for a project. As decisions far more than weight reduction. project for which Ruby+Associates was the
are made, careful consideration must be In general, designers can minimize la- structural EOR, our team considered using
given to use of materials, labor require- bor in the shop by: lighter members in several girders, which
ments, and schedule implications to de- Discussing fabrication/connection would have saved thousands of dollars in
preferences with the fabricator steel costs. However, when we looked at the
(welding vs. bolting) big picture, these lighter members would
Avoiding excess welding have required shoring prior to placing the
Allowing use of one-sided concrete, and the construction manager
simple shear connections and erector determined it was not worth
Reviewing member sizes as it due to additional scheduling complexity.
they relate to connection de- In this case, the field costs outweighed the
sign. For instance, using the material savings.
lightest member may require a Piece count also impacts fabrication
web doubler plate or stiffener and erection costs. Sometimes, in an ef-
to carry the connection forces. fort to minimize materials, designers can
Heavier columns and beams increase the number pieces required in a
minimize reinforcing. structure. Each additional piece requires
Designers can minimize la- labor to fabricate, ship, and install, as
bor in the field by providing: well as connections at each end to attach
Jay Ruby is president and CEO Ruby+Associates in Farm- Simple load paths it. Reducing piece count, even if material
ington Hills, Mich.; John Matuska is a senior project man- Systems that have inherent weight increases, can reduce overall costs
ager with the firm. stability during construction by reducing labor and simplifying design.

MODERN STEEL CONSTRUCTION january 2009


45
Doubler plates
40
40 Stiffener plates
Skewed connections
35
35
33 33 33 33 33
Full moment connections
Full-capacity column splices
Percenntage of total cost

30 30
30 29
Large beams framing into small beams
27 27 27
25
26
material During design, consider:
25
22
shop labor Site constraints, access, and lay-down
erection labor
20 19
20 areas
all other costs
Temporary bracing shoring
15
15
13
14
13
requirements
12
11 Approaches to minimize field welds
10
If possible, talk to the fabricator, connec-
tion designer, and erector to get feedback
5
on your design approach. Factoring coor-
0 dination of the other structural parties into
1983 1988 1993 1998 2003 2008
the design matrix can significantly shorten a
Year
Source: AISC
construction schedulesometimes by bring-
ing significant changes to the design. Work-
For example, a structural design with costs significantly. ing with a fabricator/erector during design
beams spaced at 7 ft, 6 in. on center equates With todays analysis and design tools, and construction of a multi-story facility, we
to three beams per 30-ft bay. Thats three it is easier than ever to provide beam end recently suggested a design modification to
pieces and six end connections for each reactions and member forces on the design use a steel core instead of a concrete core. A
bay. By redesigning the beam spacing to documents. This information is invaluable concrete core would have taken significantly
10 ft on center, the count is reduced to two to the steel construction team during the more time to construct in the field, extend-
pieces and four end connections. This is a bidding and delivering of projects. ing the schedule. A steel core was mostly shop
relatively small savings for a single bay, but fabricated and required less field time.
buildings typically include multiple bays Myth #3: Increase design complexity In addition, when steel members are
and multiple floors, causing this small sav- to reduce material costs. framed into, or supported by, masonry or
ings to grow proportionally. Increasing design complexity to reduce concrete, then (depending on how they in-
Design economy also can be achieved material costs may actually end up increas- terface) one trade may be waiting on another
by grouping member size. This reduces ing total project costs. Schedule is part of trade in the field, oreven worseinterfer-
fabrication costs, simplifies erection, im- cost; simpler buildings go up faster, reduc- ing with their progress. So coordination with
proves quality, and shortens the schedule. ing labor costs. Design complexities can be non-structural trades is a good practice to
This was the case in another medical proj- reduced by incorporating: follow as well.
ect with which we were involved. Our orig- Simple load paths
inal design for St. Vincent Mercy Medical Simple connections Balancing Costs
Center Heart Pavilion optimized structural Simple fabrication When designing a structure, the design
steel weight by using a mix of W18x35s Simple erection matrix must balance material costs, labor
with W21x44s. Our fabricator said it would Apply the KISS principle: Keep it costs, and schedule to deliver the most eco-
be cheaper to use all W21x44 members, simple, stupid. Increasing design com- nomical design. As the construction industry
standardizing all connections and eliminat- plexities in labor-intensive areas (such as continues to be challenged with tough eco-
ing field confusion. steel erection and fabrication) in an at- nomic conditions, this holistic approach to
tempt to reduce material costs addresses design will become a mandatory element in
Myth #2: Designing connections for the wrong side of the equation. Design moving projects forward.
a percentage of UDL is a simple and should not reduce materials at the ex-
effective approach. pense of labor. Design time should be
Design should follow analysis, not invested in identifying ways to reduce the
necessarily an arbitrary percentage of labor side of the equation to save project Ten things to remember when designing
the member capacity. As a designer, time and money. steel projects:
dont rely solely on the use of 50% of Least weight isnt always least cost;
uniform distributed load (UDL) for Myth #4: Construction methods are least labor is least cost.
connections. Put reactions on design not a design concern. Keep it simple!
drawings and give fabricators a choice of With labor costs accounting for more of Heavier columns minimize reinforcing.
how to design the connection. the structural construction costs, it is very Heavier beams minimize reinforcing.
As connection designers, we have seen important for a designer to understand how Design connections for actual reactions.
some very short beams (which, with 50% their building will be built. This under- Allow one-sided connections.
UDL rule, equate to a very large connec- standing and knowledge is a valuable tool Dont over-weld!
tion force) require full-depth bolting and to help in making good design decisions. Specify the correct bolt for the job.
web doubler plates at the connections. We Construction methods directly impact la- Integrate your design.
suggested designing for the actual mem- bor costs and schedule. Understand how your building will
ber end reaction and were able to elimi- As a designer, eliminate and minimize: be built.
nate all of the doubler plates, reducing Beam copes

 january 2009 MODERN STEEL CONSTRUCTION

You might also like