Professional Documents
Culture Documents
1 of 2
(www.HaywardBaker.com)
Project Summary
Anchored Reaction Block Slope Stabilization
American Freightways Trucking Facility
Montgomery, New York
onstruction of a trucking facility
Design Solution
Initially, an anchored sheet pile wall was
designed to permanently stabilize the slope. Hayward
Baker was asked for a Value Engineering alternative to the
costly wall. Hayward Bakers economical design utilized
43 anchored reaction blocks at 3 elevations.
Installation
A temporary access bench was initially cut to provide
access for installation of the upper row of anchors.
Hayward Baker then began anchor installation by drilling
a full-length cased hole at each anchor location. High-
strength threadbars were then inserted into each cased hole
and the bond zone was pressure grouted using 4,000 psi
Owner
American Freightways, Montgomery, NY
Above: The completed anchored reaction block wall/slope stabilization
Engineer/Geotech
DAppolonia Engineers, Monroeville, PA system provides cost-effective, permanent earth retention.
General Contractor Top: The three rows of anchored reaction blocks were installed as
Leeward Construction, Inc., Honesdale, PA the existing slope was excavated to provide equipment access.
2007 Hayward Baker Inc. 2 of 2
(www.HaywardBaker.com)
Project Summary
American Freightways Trucking Facility, continued...
QA/QC
Grout quality, quantity and pressure were monitored
during installation to ensure consistency. Being perma-
nent anchors, the high strength threadbars received dou-
ble corrosion protection consisting of epoxy coating,
grout encapsulation, and grease-filled caps. All anchors
were installed and proof tested to 133 percent of design
load in accordance with PTI standards.
Conclusion
The anchored reaction block wall provided permanent
stabilization of the cut slope at a substantial cost savings
over the sheet pile wall option.