Professional Documents
Culture Documents
Dearest IBUILD, the recent 1st WB Mission revealed that a lot improvement
is needed in our team to cope up with the demands of quality monitoring
and supervision when we will be doing field work. The all concreting
policy of the department under the current administration exposed us to
the concrete technology in road construction, a 100% turnaround from
what we are used to do all weather gravel road hence concrete is a
priority topic. Starting this 7th IBUILD Coordination Meeting and onwards, a
technical session will be included as a venue for growth especially to
those supervision teams at the regional level. The following questions
relate to concrete technology, please answer humbly and later you can
convert this as a checklist for our supervision team to utilize in the field.
(good for 1 hour).
4. What depth of weakened joint should at all times not be less than
a. 50mm answer
b. 60mm
c. 70mm
d. 75mm
7. If the strength of Item 311 control specimens does not meet the
requirements by not more than 25% and it is not feasible to obtain cores
from the structure due to structural consideration. What to do?
a. The strength of in-plane concrete will be determined by rebound
hammer test.
b. Payment of concrete will be made at an adjusted price answer
c. No payment will be made on the concrete represented by failed
specimens
d. The contractor will be required to remove and replace the concrete
represented by the
failed specimens at his own expense.
9. The number of beam test specimens that should be taken from a 200
sq.m of concrete
pavement, 0.23cm thick poured on a single day should be:
a. 2
b. 3 answer (330 sqm in the specs when converted to volume, at every 75 cum or
each day of pouring)
c. 6
d. 9
10. Three cores taken from a pavement section poured on a single day
were tested to have strength as follows:
Core Strength
1 3,650
2 3,000- 86% of 3500 psi
3 2,450- 70% of 3500 psi
Average 3,033- 87% of 3500 psi (accepted if ave fc is at least 85% and no single
test less than 75%)
If the required strength is 3,500 psi, the concrete represented by the
cores
a. Maybe accepted, subject to price adjustment
b. Is considered adequate
c. Is considered inadequate answer
d. Maybe recorded at the initiative of the implementing office
11. Forms for concrete pavement shall remain in place undisturbed for not
less than
a. 24 hours after concrete pouring answer
b. The curing period
c. The period required to attain the design strength
d. 72 hours after concrete pouring
12. The pH value of water that is acceptable for use in concrete mix is
a. 2.0 to 3.1
b. 3.2 to 4.4
c. 4.5 to 8.5 answer (or no test if source of water is potable or drinking water).
d. 8.6 to 10.0
14. What is the single factor that determines the strength of concrete?
a. Slump
b. Water-cement ratio answer
c. Cement factor
d. Gradation of aggregates
17. In a design mix, the specific gravity of Portland cement must be.
a. 3.05
b. 3.10
c. 3.15 answer
d. 6.10
18. If sea water is used in concrete mix, what will be the effect on the
hardened concrete
pavement?
a. Strength is affected answer
b. Scaling at surface
c. Cracks at the side
d. Steel bars will rust
21. The sample of reinforcing steel bars for every 10,000kgs shall be
a. 1 meter long answer
b. 2 meters long
c. 4 meters long
d. 6 meters long
23. Which of the following is not the job for a materials engineer?
a. Submits samples for testing
b. Prepares design mix
c. Checks job mix formula
d. Surveys and measures line and grade at site. answer
27. When the mixed concrete is hauled in non-agitating trucks, the time
elapsed from the time water is added to the mix until the concrete is
deposited in place at the site shall not exceed.
a. 90 minutes
b. 45minutes answer
c. 60 minutes
d. 80 minutes
28. When the mixed concrete is hauled in truck mixers or truck agitators,
the time elapsed from the time water is added to the mix until the
concrete is deposited at the site shall not exceed.
a. 60 minutes
b. 90 minutes answer
c. 45 minutes
d. 72 minutes
36. Concrete admixtures used when the normal setting time is shortened
by the higher
temperature, preventing the formation of cold joints, reduce incidence of
thermal cracking
and to maintain concrete workability during large pours or long ready-mix
hauls. .
a. accelerators
b. retarders answer
c. super plasticizers
d. Air entraining admixtures
37. Angular coarse aggregate use for concrete mix will provide more:
a. Water content answer
b. Cement and water
c. Cement and fine aggregates
d. All of the above
41. The design thickness for pccp is 200 mm. The average thickness
determination was taken and the result is 170 mm. If you are a
government materials engineer, what percent of the contract price
adjustment will you recommend.
a. 70%
b. No payment answer
c. 80%
d. 85 %
44. Cement which for any reason, has become partially set or which
contains lumps of caked cement will be rejected. Cement salvaged from
discarded or used bags shall not be used.
a. true answer
b. false
45. Fine aggregate from different sources of supply shall not be mixed or
stored in the same pile nor used alternately in the same class of concrete
without the approval of the Engineer
a. true answer
b. false
48. A change in the source of materials during the progress of work may
not necessitate a new design mix.
a. true
b. false answer
49. The person performing the batching or mixing operation shall be
capable of accurately conducting aggregate surface moisture
determination and establishing correct scale weights for concrete
materials.
a. The Concrete Batcher answer
b. The Concrete Technician
c. The Materials Engineer
d. The Project Engineer
51. Dowel bars shall be deformed bars. Tie bars shall be plain round bars.
a. True
b. False answer
52. Before delivery to the site of work, one-half of the length of each
dowel shall be painted with one coat of approved lead or tar paint. The
sleeves for dowel bars shall be metal of approved design to cover 50 mm (
2 inches), plus or minus 5 mm (1/4 inch) of the dowel, with a closed end,
and with a suitable stop to hold the end of the sleeve at least 25 mm (1
inch) from the end of the dowel. Sleeves shall be of such design that they
do not collapse during construction.
a. True answer
b. False
53. Concrete beam test will provide the compressive strength of concrete
while cylinder test will provide the flexural strength of concrete.
a. True
b. False answer
55. The forms shall not deviate from true line by more than one (1) cm at
any point.
a. True answer
b. False
56. Which of the following statements is not valid when conditioning the
subgrade or base course prior to concrete pouring.
a. ensure that the subgrade or base course shall be uniformly moist when
the concrete is placed.
b. If the subgrade or base course becomes too dry, it shall be sprinkled,
but the method of sprinkling shall not be such as to form mud or pools of
water.
c. do not allow sprinkling of water even when the subgrade or base course
is too dry as it disturbs the insitu condition of the base. answer
d. High areas shall be trimmed to proper elevation. Low areas shall be
filled and compacted to a condition similar to that of surrounding grade.
57. Stockpiles shall be built up in layers of not more than ____ meter in
thickness. Each layer shall be completely in place before beginning the
next which shall not be allowed to cone down over the next lower layer
a. 2 meters
b. 1 meter answer
c. 3 meters
d. 1.5 meters
58. Aggregates from different sources and of different grading shall not
be stockpiled together.
a. True answer
b. False
60. Concrete mixing - When mixed at the site or in a central mixing plant,
the mixing time shall not be less than ____ seconds nor more than _____
seconds, unless mixer performance tests prove adequate mixing of the
concrete in a shorter time period. Any concrete mixed less than the
specified time shall be discarded and disposed off by the Contractor at his
expense.
a. 60 seconds to 90 seconds
b. 45 seconds to 120 seconds
c.30 seconds to 60 seconds
d. 50 seconds, 90 seconds answer
61. Concrete mixing - The flow of water shall be uniform and all water
shall be in the drum by the end of the ______ seconds of the mixing period.
a. 5 seconds
b 10 seconds
c. 15 seconds answer
d. 20 seconds
62. The time elapsed from the time water is added to the mix until the
concrete is deposited in place at the Site shall not exceed _____minutes
when the concrete is hauled in non-agitating trucks, nor _____ minutes
when hauled in truck mixers or truck agitators, except that in hot weather
or under other conditions contributing to quick hardening of the concrete,
the maximum allowable time may be reduced by the Engineer.
a. 45 minutes; 90 minutes answer
b. 60 minutes; 120 minutes
c. 30 minutes; 60 minutes
d. none of the above
65. Concrete not in place within _______ minutes from the time the
ingredients were charged into the mixing drum or that has developed
initial set shall not be used. Retempering of concrete or mortar which
has partially hardened, that is remixing with or without additional cement,
aggregate, or water, shall not be permitted.
a. 90 minutes answer
b. 60 minutes
c. 50 minutes
d. 30 minutes
66. During hot weather, the Engineer shall require that steps be taken to
prevent the temperature of mixed concrete from exceeding a maximum
temperature of _______ degrees centigrade.
a. 270C
b. 32.220C answer
c. 370C
d. 40.50C
68. As work progresses, at least one (1) set consisting of three (3)
concrete beam test specimens, 150 mm x 150 mm x 525 mm or 900
mm shall be taken from each 330 m2 of pavement, 230 mm depth, or
fraction thereof placed each day. The above specification when applied to
a PCCP thickness of 150 mm and a single lane of 2.5 m is poured, what is
the required length to be covered that would trigger getting 1-set
concrete beam sample? Cylinder samples shall not be used as substitute
for determining the adequacy of the strength of concrete.
a. 100 meters
b. 200 meters answer
c. 300 meters
d. 400 meters
74. Sawing of the joint shall commence as soon as the concrete has
hardened sufficiently to permit sawing without excessive ravelling, usually
___ to ___ hours. All joints shall be sawed before uncontrolled shrinkage
cracking takes place. If necessary, the sawing operations shall be carried
on during the day or night, regardless of weather conditions. The sawing
of any joint shall be omitted if crack occurs at or near the joint location
prior to the time of sawing.
a. 6 to 12 hours
b. 4 to 24 hours answer
c. 24 hours to 72 hours
d. None of the above
77. The screed for the surface shall be at least _____cm longer than the
maximum width of the slab to be struck off
a. 60 cm answer
b. 30 cm
c. 20 cm
d. 10 cm
78. The hand-operated longitudinal float shall be not less than ____cm in
length and ____ cm in width, properly stiffened to prevent flexibility and
warping
a. 365 cm and 15 cm answer
b. 360 cm and 10 cm
c. 300 cm and 10 cm
d. 360 cm and 15 cm
79. The brooming operation should be so executed that the corrugations
produced in the surface shall be uniform in appearance and not more than
____ mm in depth
a. 3 mm
b. 2 mm
c. 1.5 mm answer
d. 1 mm
81. After forms for concrete shall remain in place undisturbed for not less
than ____ hours after concrete pouring.
a. 12 hours
b. 24 hours answer
c. 36 hours
d. 72 hours
82. In case portions of the concrete are spalled during removal of forms,
they shall be immediately repaired with fresh mortar mixed in the
proportion of __ part of Portland Cement and ___ parts fine aggregates.
a. 1:2 nswer
b. 1:3
c. 1:2:3
d. 1:4
84. Joints shall be sealed with asphalt sealant soon after completion of the
curing period (72 hours) and before the pavement is opened to traffic,
including the Contractors equipment.
a. True nswer
b. False
85. The strength level of the concrete will be considered satisfactory if the
averages of all sets of three (3) consecutive strength test results equal or
exceed the specified strength, fc and no individual strength test result is
deficient by more than _____of the specified strength, fc.
a. 10%
b. 15% nswer
c. 20%
d. 25%
89. When the average thickness of the pavement per lot is deficient,
payment for the lot shall be adjusted as follows:
91. What is the maximum size of aggregates for PCCP under Grading A?
a. 2 inches nswer
b. 3 inches
c. 4 inches
d. 2 inches
92. What is the maximum size of aggregates for PCCP under grading B
and C?
a. 2 inches
b. 3 inches
c. 4 inches
d. 2 inches nswer
98. The curing compound shall be of such character that the film will
harden within ___ minutes after application. Should the film be damaged
from any cause within the _____ hour curing period, the damaged portions
shall be repaired immediately with additional compound.
a. 180 minutes; 24 hours
b. 120 minutes; 72 hours
c. 60 minutes; 36 hours
d. 30 minutes; 72 hours nswer
100. After the final finish, but before the concrete has taken its initial set,
the edges of the pavement along each side of each slab, and on each side
of transverse expansion joints, formed joints, transverse construction
joints, and emergency construction joints, shall be worked with an
approved tool and rounded to the radius required by the Plans. A well
defined and continuous radius shall be produced and a smooth, dense
mortar finish obtained. The surface of the slab shall not be unduly
disturbed by tilting the tool during the use. The above specification is
under _____ in the blue book?
a. Edging at Forms and Joints answer
b. Surface Test
c. Final Finish
d. Straight-edge Testing and Surface Correction
101. Scales for weighing aggregates and cement shall be accurate within
0.5%.______.
102. The concrete samples should be stored in a moist condition at a
temperature within the range of 18 degrees to 24 degrees centigrade
___________until the time of test.
105. The penetration of concrete joint sealer, Hot Poured Elastic Type shall
not exceed 90 ____