Professional Documents
Culture Documents
OPERATION GUIDELINES
11. MISCELLANEOUS
CONTENTS
1
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
The Project Architect/Engineer must obtain approval before brand names can be
specified. In general, brand names shall be included only for components that have
visual impacts on the architectural and interior finishes, e.g. light fitting, grilles,
switched, temperature sensors and architects and/or clients agreement on the
selected brands shall be sought. A minimum of 3 brand names shall be specified
and or equivalent shall be included to allow other offer. It will be the tenderers
onus to prove that the equivalent complies with the specification. This proof will not
be required if he offers one of those named.
Tenderers are normally required to provide technical information of their offers in the
Technical Schedules section of the specification. Technical data submitted by the
tenderers are contractually binding on the successful contractor. They shall take
precedent over those in the product catalogues when there is conflict on these two
sets of data. Project Architect/Engineer shall ensure that only information that are
2
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
pertinent to the evaluation of the offer shall be included as items in the Technical
Schedule so that the tenderers will not have to waste time to provide unnecessary
information. On the other hand, tenderers shall be requested to insert markings and
highlight the relevant items that are offered by them in the catalogues and brochures
submitted by them so that the Project Architect/Engineer does not need to scan
through them to look for information. This requirement shall be included in the
specification for the compliance of tenderers
For tenders of goods falling under the ASEAN Preferential Trading Arrangement
(PTA), this shall be indicated in the Instruction to Advertise Tender. The T&C shall
give notice of the tender to the relevant missions of ASEAN countries 3 days before
its publication in the press.
For GPA covered tenders, the tender notice and a summary notice shall also be
published in the Government Gazette.
3
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
For Government projects, prior approval must be sought from the PS in person of the
client ministry or his delegated officer who should be the DS, if the tender period has
to be less than the stipulated minimum. The reduced period shall not be less than 10
days.
For larger and more complex projects, the tender period should be more than the
stipulated minimum. The QS Division's guidelines on tender periods (Appendix 32/2)
shall be complied with. The office calling the tender shall seek the approval of the
SVP if a tender period shorter than the QS Division's guidelines is to be stipulated.
2.2 Corrigenda/Addenda
4
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
Extension of the closing date can be considered under the following circumstances:-
Too few tenderers have collected tender documents. The Project Engineer
may invite other tenderers who are registered in the advertised financial
category/ work head to participate. If the response is still poor, consideration
may be given to open the tenders to contractors who are registered in a lower
financial category or in other work heads. The Project Engineer shall consult
the VP (QS Office) before he takes the latter course of action.
When a tender corrigendum which has a time impact on the tender period is
issued.
Written requests from the tenderers to extend the tender period. Extension is
allowed only if there are two or more such requests and approval must be
sought from the Client for such extension.
All queries from tenderers shall be in writing. The questions and answers shall
subsequently be issued to all tenderers as corrigendum/addendum as far in advance
of the closing date of tenders as possible. Project Engineer shall advise tenderers
courteously to write in if they call to inquire.
The criteria for evaluation should be stipulated in the tender documents and the
evaluation strictly based on the criteria set forth. The selected tender should be the
one most advantageous to the Client. The usual criteria include:-
Tender price - Everything else being equal, the lowest tenderer shall be
recommended for acceptance.
5
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
Life Cycle Costing - In M&E tenders, life cycle costing and other cost
effectiveness techniques may be used in evaluating the offers. However the
evaluation system and criteria must be clearly defined before tenders are
called.
Registration Head and Financial Grade - A tenderer who does not meet the
specified registration head and financial grade with the appropriate
Government Registration Authority shall be rejected unless it has submitted
an application for certification with the Government Registration Authority on
or before the tender closing date.
6
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
The Project Engineer shall treat all tender documents and evaluation reports
confidential and lock up all related documents in cabinets. Information relating to the
examination, evaluation and comparison of bids and the recommendation for award
shall not be disclosed to the tenderers or other persons not officially concerned with
such process. There shall be no communication with tenderers until LA is signed by
successful tenderer. When tenderers call and ask the Project Engineer, standard
answers shall be: The tender is still under evaluation and any information related to
this are confidential.
Technical clarification shall be in writing and the Project Engineer shall compile a list
of questions based on the tender submission and forwarded to the te nderers for
clarification. Adequate time be given to tenderers to respond. In general, 5-7 working
days shall be allowed depending on the extent of information to be supplied. Any
shorter period of time will require SVP approval.
The Project Engineer shall arrange a meeting (tender interview) with the lowest three
tenderers. Where necessary, the Project Architect, Project Manager and the Client's
representative shall also be invited to the tender interview meetings. All the
clarification and agreements made in the meeting with the tenderer's representative
must be followed up in written form from the tenderer himself.
Direct contact with tenderers shall be avoided. If face to face meeting other than the
tender view is unavoidable, the Project Engineer shall always be accompanied by
another staff from the Division to serve as witness on all issues discussed. A meeting
record detailing the issued discussed shall be made and forwarded to the tenderer
within 3 days.
The Project Engineer shall not indicate to tenderers in whatever form whether their
offer complies with specification. The Project Engineer shall not suggest or hint to
any tenderer that certain brand is better or can comply with the specification at any
time.
7
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
Not more than 2 rounds of clarification shall be made. Additional round of clarification
will require the approval of the SVP.
3.4 Negotiations
Pre-tender omission may be considered on condition that it is the lowest tender and
it does not disadvantage the next nearest tenderer.
If the schedules of rates are found to be unrealistically high, the Project Engineer
shall request the tenderers to review them reasonable level. This is not considered
negotiation as it is in the interest of the client. In the event that the tenderer refuses
to reduce the rate to a reasonable price for a particular item, it shall be struck off
from the schedule of rates. It will then be up to the SO to decide on the reasonable
unit price for that item when variation is required. A statement shall be included at
the beginning of the section on Schedule of Unit Rates that When there is no unit
rate for certain item, the SO will decide the reasonable unit of that item. The Project
Engineer shall describe the event of schedules of rates review by the tenderer in the
tender recommendation report.
Changes to tender price that is reflected in the form of tender are strictly prohibited.
8
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
9
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
Facilitators for
Ministry Name Division
Client Relations
Judiciary (Supreme & Subordinate
Khew Sin Khoon A&DS Peter How
Courts)
Ministry of Community Development Tan Chee Wee / Ong
A&PD Teo Pin
(Homes) Hong Kee
Ministry of Home Affairs Mok Kwong Wah / Khew A&DS Peter How
Sin Khoon
Ministry of Information and the Arts Khew Sin Khoon A&DS Chua Hua Meng
10
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
11
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
12
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
13
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
1. Introduction
1.1 Risk can be broadly defined as the risk of loss resulting from inadequate or failed
internal processes, people and systems or from external events.
1.2 We are required to identify, evaluate and properly manage risks in our business. In
general, we should minimize, avoid, transfer or assume risks identified. We should
be fully aware of our professional indemnity/liability, commercial/legal liability,
occupational health and safety liability, Public liability and liability in the employment
of staff.
1.3 Each EVP/SVP is accountable in assessing the risk in their projects and operation.
You are urged to ensure that this check list is widely used in your operation.
1.4 Risk Management is a process of inquiry. The following questions will be helpful :
14
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
1. The Client
3. Design
15
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
4. Contract Documentation
5. Construction
Have you compiled a list of risks and taking action regularly to manage the
risk?
Do you have competent supervisory staff?
Do you have adequate supervisory staff?
Have you assess the risk of construction?
Has the contractor submitted works method to address the risk?
Has the contractor complied with the risk management measures required by
authorities such as the BCA and MOM?
Have you read the CPG Crisis Management Plan?
6. DLP
16
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
(Note : in addition to this section, all other items in this checklist also apply to
D&B Contract)
9. PPP Project
17
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
4. Concluding Remark
This is a simple check list for possible risks in consultancy contract. In addition to the
items in this check list, staff should be conscious of risk at all time and take adequate
measures to minimize the risk, transfer the risk to another suitable party and ensure
that the risk is covered by the PII.
Reference
18
CIVIL & STRUCTURAL ENGINEERING DIVISION
OPERATION GUIDELINES
11. MISCELLANEOUS
Annex A
Identify Risks
Analyse Risks
Frequency x Consequence = Risk
Implement Plan
19