RISK FACTORS LEADING


TO COST OVERRUN IN
THE DELIVERY OF HIGHWAY
CONSTRUCTION PROJECTS

By: Garry D. Creedy

A thesis submitted in fulfilment of the requirement


for the degree of Doctor of Philosophy

Principal Supervisor:
Professor Martin Skitmore

Associate Supervisor:
Professor Tony Sidwell

Queensland University of Technology

Research Centre:
School of Urban Development,
Faculty of Built Environment and Engineering
2006
Risk factors leading to cost overrun in the delivery of highway construction projects.

Statement of Original Authorship

DECLARATION

The work contained in this thesis has not been previously submitted for a degree or diploma
at any other higher education institution. To the best of my knowledge and belief, the thesis
contains no material previously published or written by another person except where due
reference is made.

Signed: ______________________________

Date: ________________________

II
This research is dedicated to my wife, MT, who believed in me as she wrote .....

This is a dream that you thought you would never get the chance to experience, and
here it has been presented to you in a very short time. Maybe, so you cant think about
your decision too long!!! Grab it and know that I am here to support you and know
that I will not only be behind you but around you. I love you and you deserve this great
opportunity to fulfil l your dream (MT, 2002).

III
Risk factors leading to cost overrun in the delivery of highway construction projects.

ACKNOWLEDGMENTS

I would like to express my sincere thank you to the following people, without whose help,
this thesis would not have been possible.

Many thanks go to my principle advisor and supervisor, Professor Martin Skitmore for his
unwavering support and guidance throughout this research. Especially for his ability and
skill in maintaining a focus on client and industry needs in highway construction. I thank
Martin for re-introducing me to statistical theory and its practical applications in research. I
am truly lucky to have him as my advisor and supervisor who guided me through my
research project from the start to the end. Also, I would like to express gratitude to my
associate advisor, Professor Tony Sidwell, for his comments and discussions. As well, I
would like to thank all the staff in the school of Urban Design for their support.

I am grateful to the members of the Cooperative Research Centre for Construction


Innovation for their financial and personal support throughout the journey. I would like also
to express gratitude to my employer, the Queensland Department of Main Roads for the
support by way of a study scholarship during the first two years of this research. In particular
I wish to thank Dennis Wogan who acted as my industry supervisor and was a leading
member of the reference group who contributed to and supported my research project.

I would like to give a very special thanks to Alan McLennan, Adjunct Professor in
Engineering at the Queensland University of Technology. Allan contributed much of his
valuable personal time in guiding me in the practical directions of the research. I am
particularly thankful for his expert facilitation of the elicitation process that was so important
to my research.

To my mentor, Dr. Mel Silverman of New Jersey, I thank you for the confidence and
determination you have instilled in me during our long friendship. In particular, thank you
for the endless email support and direction you provided during this long journey you
picked just the right times throughout the journey to 'rattle my cage' and so get me refocused
once more.

Most importantly, I would like to thank my wife and best friend MT, for her love and
support. She inspired me to keep on going, even when it became physically and emotionally
tough thank you, my Linda. To my family, I thank you for all your patience, love and
support. To my three special daughters, Michelle, Suzanne and Rebecca, thank you for all
you have done for me.

IV
ABSTRACT

Accurate client budget estimates are critical to the initial decision-to-build process for the
highway construction projects. This decision-to-build point in a project's development is
seen as the international standard for measuring any subsequent cost estimate inaccuracies
involved (National Audit Office/Department of Transport, 1992; World Bank, 1994;
Nijkamp and Ubbels, 1999), with accuracy being defined as the difference between the
initial project estimate at the decision-to-build stage and the real, accounted project cost
determined at the time of project completion. Expressed as a percentage of estimated cost,
this is often termed cost escalation, cost overrun or cost growth, and occurs as a result of
many factors, some of which are related to each other, but all are associated with forms of
risks. The analysis of these risks is often a necessary step for the improvement of any given
estimating system and can be used to diagnose trouble spots and to pinpoint areas where
project estimating accuracy improvement might be obtained.

In this research, highway projects in Queensland, Australia that have suffered significant
cost overrun are analysed. The research seeks to address the gap in the knowledgebase as to
why highway projects overrun their costs. It focuses on understanding how client projects
budgets go wrong, when dealing with project risk.

The foundation for this research is drawn from the post-mortem analysis of highway
projects, each costing in excess of A$1m and whose final total expenditure exceeded budget
by 10% or greater. The research identifies client risk variables which have contributed to
significant cost overrun and then uses factor analysis and also expert elicitation, using
nominal group technique, to establish groups of importance ranked client risks. Stepwise
multivariate regression analysis is then used to investigate any correlation of these risks,
along with project attributes such as highway project type, indexed project cost, geographic
location and project delivery method to the percentage of cost overrun.

The research results indicates a correlation between the reciprocal of project budget size and
percentage cost overrun that can be useful in clients determining more realistic decision-to-
build highway budget estimates when taking into account project size in relation to economy
of scale.

Key words: Highway construction, project budgeting, cost performance, construction


management.

V
Risk factors leading to cost overrun in the delivery of highway construction projects.

CONTENTS
STATEMENT OF ORIGINAL AUTHORSHIP............................................................................. II
ACKNOWLEDGEMENTS .......................................................................................................... IV
ABSTRACT ...............................................................................................................................V
LIST OF FIGURES....................................................................................................................... XI
LIST OF TABLES ....................................................................................................................... XII
LIST APPENDICES ....................................................................................................................XV

CHAPTER 1
Introduction to research project........................................................................................................1
1.1 Background to the Research................................................................................................1
1.2 Research problem ................................................................................................................3
1.3 Research purpose.................................................................................................................7
1.4 Research objectives .............................................................................................................7
1.5 Justification for the research................................................................................................7
1.6 Methodology .......................................................................................................................8
1.7 Outline of the research thesis organisation.......................................................................9
1.8 Delimitations of scope and key assumptions.....................................................................10
1.9 Conclusion.........................................................................................................................11

CHAPTER 2
Literature review into project risks and cost overrun .....................................................................13
2.1 Preamble............................................................................................................................13
2.2 Introduction .......................................................................................................................13
2.3 Definitions .........................................................................................................................14
2.3.1 The Nature of Risk ...............................................................................................17
2.3.2 Risk and uncertainty .............................................................................................17
2.3.3 Risk management .................................................................................................18
2.3.4 Risk evaluation and acceptance............................................................................19
2.3.5 Risk assessment....................................................................................................20
2.3.6 Risk assessment models .......................................................................................20
2.3.7 Risk control processes ..........................................................................................21
2.4 Risk engineering................................................................................................................22
2.5 Qualitative risk assessment................................................................................................23
2.6 Quantitative risk assessment..............................................................................................23
2.6.1 Simulation ............................................................................................................24
2.6.2 Artificial logic applications ..................................................................................25
2.7 Assessment of probabilities and consequences .................................................................25
2.8 Elicitation of risk ...............................................................................................................27

VI
2.8.1 Expert elicitation ..................................................................................................27
2.8.2 Expert elicitation using the Delphi method..........................................................28
2.8.3 Elicitation using semi-structured interviews ........................................................28
2.8.4 Nominal group technique.....................................................................................29
2.9 Organisational risk culture ................................................................................................ 29
2.10 Project risk management ...................................................................................................30
2.11 Project site condition risks ................................................................................................33
2.12 Managing risks through procurement practices ................................................................35
2.13 Risk distribution in project procurement...........................................................................36
2.13.1 Risk allocation through standard-form contracts .................................................39
2.14 Payment methods for contract risks ..................................................................................39
2.15 Delivery processes for projects .........................................................................................40
2.16 The traditional method of project procurement................................................................42
2.17 Improving project delivery methods for risk.....................................................................44
2.17.1 Build-Operate-Turnover project delivery ............................................................45
2.17.2 Relationship/Alliance/Partnering contracting ......................................................46
2.18 Project contracting ............................................................................................................48
2.18.1 Procurement auctions...........................................................................................49
2.18.2 The competitive tendering process.......................................................................49
2.19 Pre-qualification of contractors.........................................................................................50
2.19.1 Research into client pre-qualification practices ...................................................52
2.19.2 Choosing contractors on low bids ........................................................................54
2.20 Bid evaluation ...................................................................................................................56
2.20.1 Research into bidding...........................................................................................57
2.20.2 Sub-contractor selection.......................................................................................58
2.21 Project budget estimating..................................................................................................58
2.21.1 Estimating processes ............................................................................................59
2.21.2 Early project estimates .........................................................................................60
2.21.3 Project cost overrun .............................................................................................60
2.21.4 Research into project estimating ..........................................................................61
2.21.5 Factors influencing costs......................................................................................63
2.21.6 The relation between cost accuracy and scope.....................................................63
2.21.7 Scope change........................................................................................................64
2.22 Cost forecasting models ....................................................................................................65
2.23 Project cost contingency ...................................................................................................68
2.24 Estimating methods for cost contingency .........................................................................70
2.25 Literature summary ...........................................................................................................74

VII
Risk factors leading to cost overrun in the delivery of highway construction projects.

CHAPTER 3
Research methodology ...................................................................................................................77
3.1 Introduction .......................................................................................................................77
3.2 Research strategy...............................................................................................................77
3.3 The research procedure......................................................................................................80
3.4 Research steps ...................................................................................................................81
3.5 Stage 1: Review literature .................................................................................................81
3.6 Stage 2: Establish data source of highway construction projects ......................................82
3.6.1 Indexing of historical road project prices .............................................................84
3.7 Stage 3: (a) Determine cost overrun factors from historic project data.............................85
3.8 Stage 3: (b) Factor analysis using principal component analysis and factor
rotation on cost overrun factors to consolidate data ..........................................................85
3.8.1 Factoring methods ................................................................................................85
3.8.2 Method of factor extraction ..................................................................................86
3.8.3 Sample size for factor analysis .............................................................................86
3.8.4 Type of factor rotation employed .........................................................................87
3.8.5 Number of factors in analysis...............................................................................87
3.8.6 Characteristics of samples in the factor analysis ..................................................87
3.9 Stage 4: Use nominal group technique (NGT) to elicit, review and prioritize
cost overrun risk groupings and highway project types ....................................................88
3.9.1 Focus group ..........................................................................................................88
3.9.2 Delphi technique...................................................................................................88
3.9.3 Nominal group technique .....................................................................................89
3.9.4 Selection of experts for NGT process ..................................................................90
3.9.5 Group composition ...............................................................................................91
3.9.6 Ranking process ...................................................................................................91
3.9.7 NGT workshop evaluation ...................................................................................92
3.10 Stage 5: Undertake data analysis and statistical modelling ...............................................92
3.10.1 Regression analysis basis assumptions.................................................................95
3.10.2 Correlation analysis..............................................................................................96
3.10.3 Statistical regression.............................................................................................96
3.10.4 Sample size of data...............................................................................................97
3.10.5 p-value ..................................................................................................................97
3.10.6 t-test ......................................................................................................................98
3.10.7 Other considerations.............................................................................................99
3.11 Ethical considerations........................................................................................................99
3.12 Conclusion.........................................................................................................................99

VIII
CHAPTER 4
Data collection, analysis techniques and statistics .......................................................................101
4.1 Preamble..........................................................................................................................101
4.2 Stage 2: Establish data sources of highway construction projects ..................................101
4.2.1 Project number and location ..............................................................................102
4.2.2 Description of works..........................................................................................102
4.2.3 Method of project delivery.................................................................................103
4.2.4 Programmed cost................................................................................................105
4.2.5 Actual cost..........................................................................................................105
4.2.6 Percentage (%) ...................................................................................................106
4.2.7 Indexing of project costs to 200203 out-turn prices.........................................106
4.3 Stage 3 (a): Determine cost overrun factors from historic project data .........................107
4.3.1 Exclusion of some initial historical project data ................................................109
4.4 Stage 3 (b): Use factor analysis (principal component analysis) and factor rotation on cost
overrun factors to consolidate data..................................................................................109
4.4.1 Factor analysis test parameters...........................................................................110
4.4.2 Principal component analysis.............................................................................111
4.4.3 Scree plot............................................................................................................113
4.4.4 Factor rotation ....................................................................................................114
4.5 Step 4: Use nominal group technique (NGT) to elicit, review and prioritise principal
cost overrun risk groupings and highway project types .................................................117
4.5.1 Identification and selection of experts ...............................................................117
4.5.2 Agenda Item 1: Research project background ...................................................118
4.5.3 Agenda item 2: Workshop aims/desired outcomes and explanation of
NGT for workshop .............................................................................................118
4.5.4 Agenda Item 3: Principal cost overrun grouping exercise .................................118
4.5.5. Agenda Item 4: Ranking of risk groupings ........................................................121
4.5.6. Agenda Item 5 of workshop: Development of highway project types...............125
4.5.7 NGT Workshop Agenda Item 6: Workshop feedback and assessment..............127
4.6 Application of NGT workshop findings to project data..................................................129
4.7 Step 4: Undertake data analysis and statistical modelling ..............................................131
4.7.1 Model dependent variable ...............................................................................131
4.7.2 Model prediction variables..............................................................................131
4.7.3 Geographic project type .....................................................................................132
4.7.4 Geographic data and model coding....................................................................132
4.7.5 Highway project construction type reference number .......................................135
4.7.6 Construction type data and model coding ..........................................................135
4.7.7 Project delivery types.........................................................................................136
4.7.8 Project delivery data and model coding .............................................................136
4.7.9 Indexed highway project programmed cost continuous variable.......................137
4.7.10 Project high level risks .......................................................................................138
4.7.11 Project high level risk data and model coding ...................................................138

IX
Risk factors leading to cost overrun in the delivery of highway construction projects.

4.8 Regression modelling ......................................................................................................139


4.8.1 Outlying data values...........................................................................................139
4.8.2 Multivariate regression analysis .........................................................................141
4.8.3 Forward selection mode for multivariate regression analysis ............................142
4.8.4 Backwards selection mode for multivariate regression analysis ........................145
4.8.5 Stepwise selection mode for multivariate regression analysis ...........................146
4.9 Summary of variable selection modes for multivariate linear regression analysis.........146
4.10 Sensitivity testing of project data used in regression analyses ........................................147
4.11 Testing the general assumptions of regression and residual analysis..............................150
4.11.1 Normality of error testing...................................................................................151
4.11.2 Standardised residuals testing.............................................................................152
4.11.3 Data transformation investigation ......................................................................153
4.11.4 Data transformation using reciprocal of X .........................................................153
4.11.5 Re-testing of general assumptions of residuals ..................................................154
4.12 Regression analysis using reciprocal indexed prog. cost $m ..........................................155
4.13 Sensitivity testing using discrete rural and urban data sets .............................................156
4.13.1 Rural project data regression analysis ................................................................156
4.13.2 Testing of general assumptions of residuals for rural project data.....................157
4.13.3 Urban project data regression analysis ...............................................................159
4.13.4 Testing of general assumptions of residuals for urban project data ...................160
4.14 Sensitivity testing using open tender and negotiated price data sets ...............................161
4.15 Regression analysis model summary...............................................................................162
4.15.1 Correlated model ................................................................................................162
4.15.2 Summary of regression analysis 163
4.16 Chapter summary ............................................................................................................163
CHAPTER 5
Discussion, conclusions and recommendations .......................................................................165
5.1 Discussion .......................................................................................................................165
5.2 Highway project data.......................................................................................................165
5.3 Cost overrun project risk factors .....................................................................................166
5.4 Factor analysis.................................................................................................................167
5.5 Expert elicitation findings ...............................................................................................168
5.6 High level project risks....................................................................................................168
5.7 Model development using multivariate regression analysis............................................172
5.8 Implications for highway cost management 'body of knowledge'...................................175
5.9 Implications for cost estimating practices .......................................................................176
5.10 Research limitations ........................................................................................................178
5.11 Further research ...............................................................................................................179
5.12 Conclusions .....................................................................................................................181
BIBLIOGRAPHY ....................................................................................................................181

X
List of Figures

Figure 1.1: Traditional project development phases....................................................................1


Figure 1.2: Stages of project estimates ........................................................................................4
Figure 2.1: Construction risk analysis .......................................................................................23
Figure 2.2: Risk-aversive, risk-neutral and risk-seeking ...........................................................30
Figure 2.3: Traditional project delivery model ..........................................................................36
Figure 3.1: Empirical research strategies...................................................................................78
Figure 3.2: Main research activities...........................................................................................80
Figure 4.2: Normal probability plot of regression standardised residuals ...............................151
Figure 4.3: Scatterplot of the standardised residuals versus predicted values of 220 cases ....152
Figure 4.4: Histogram of standardised residuals......................................................................153
Figure 4.4: Normal probability plot with transformed variable...............................................154
Figure 4.5: Scatterplot of standardised residuals versus predicted of transformed data ..........155
Figure 4.6: Normal probability plot of rural project data ........................................................158
Figure 4.7: Scatterplot of standardised residuals versus predicted values for rural projects ...158
Figure 4.8: Normal probability plot of urban project data .......................................................160
Figure 4.9: Scatterplot of standardised residuals versus predicted values of urban projects ...161
Figure 5: 1: Future research proposal on project risk contingencies .......................................180

XI
Risk factors leading to cost overrun in the delivery of highway construction projects.

List of Tables

Table 1.1: Highway projects over A$1m that exceeded estimate by >10%.................................5
Table 1.2: Research procedures ...................................................................................................9
Table 2.1: Methods for determining risk acceptance .................................................................19
Table 2.2: Quantitative risk assessment methods.......................................................................21
Table 2.3: Qualitative risk assessment methods.........................................................................21
Table 2.4: Sources of common project construction risks .........................................................32
Table 2.5: Target accuracy of highway design estimates...........................................................62
Table 2.6: Classes of project estimates ......................................................................................69
Table 2.7: Contingency ranges in highway estimates ................................................................70
Table 3.1: Situations for differing research strategies................................................................79
Table 3.2: Research procedures .................................................................................................81
Table 3.4: Model techniques ......................................................................................................92
Table 3.5: Interpretation of p-values ..........................................................................................98
Table 4.1: Number of projects analysed...................................................................................101
Table 4.2: Sample of data of completed highway ....................................................................102
Table 4.3: Refined listing of highway project work types .......................................................103
Table 4.4: Composition of project delivery methods ...............................................................104
Table 4.5 Project delivery code................................................................................................104
Table 4.6: Programmed costs of projects .................................................................................105
Table 4.7: Actual costs of projects ...........................................................................................106
Table 4.8: Percentage of cost overrun for analysis periods......................................................106
Table 4.9: RICI indices and factors applied to project costs....................................................107
Table 4.10: Project cost overrun factors derived from historic highway data..........................109
Table 4.11: Sample display of project and cost overrun matrix data used in analysis.............110
Table 4.12: KMO and Bartlet tests...........................................................................................110
Table 4.13: Initial and extraction communalities for cost overrun variables ...........................111
Table 4.14: Total variance explained unrotated ....................................................................112
Table 4.15: Rotated and ordered component matrix ................................................................115
Table 4.16: Principal factor groupings from rotated component matrix ..................................116
Table 4.17: Expert group composition .....................................................................................117
Table 4.18: Experience profile of expert group membership...................................................118
Table 4.19: Cost overrun risk factor grouping worksheet........................................................120

XII
Table 4.20: Agreed mapping of cost overrun factors to groupings..........................................121
Table 4.21: Ranked groupings derived from importance index...............................................122
Table 4.22: Final NGT highway project construction types....................................................125
Table 4.23: Desired workshop project construction types for future grouping .......................126
Table 4.24: Workshop evaluation for Question 1 ....................................................................127
Table 4.25: Workshop evaluation for Question 2 ....................................................................127
Table 4.26: Workshop evaluation for Question 3 ....................................................................128
Table 4.27: Workshop evaluation for Question 4 ....................................................................128
Table 4.28: Sample of low level to high level risk group mapping to projects .......................129
Table 4.29: Incidences across projects for the HL/ risk groups...............................................130
Table 4.30: Split of rural and urban geographic types.............................................................134
Table 4.31: Data coding for geographic types .........................................................................134
Table 4.32: Construction project type reference number.........................................................135
Table 4.33: Sample data coding for only project types 1 to 6 .................................................136
Table 4.34: Project delivery codes...........................................................................................136
Table 4.35: Sample data coding for project delivery codes .....................................................137
Table 4.36: Sample of indexed programmed cost $m continuous variables............................138
Table 4.37: High level risk groupings codes............................................................................139
Table 4.38 Sample of high level risk grouping codes against projects....................................139
Table 4.39: Case-wise diagnostics...........................................................................................140
Table 4.40: Project outlier details ............................................................................................140
Table 4.41: Variables entered/removed in forward selection mode ........................................142
Table 4.42: Forward selection mode summary using dependent variable of % over cost .......143
Table 4.43: Coefficients for forward selection mode ..............................................................143
Table 4.44: Excluded variables in forward selection mode .....................................................145
Table 4.45: Variables entered/removed in stepwise selection mode .......................................146
Table 4.46 Summary of multivariate linear regression for three modes..................................147
Table 4.47: Sensitivity testing of coefficients for secondary stepwise selection mode ...........148
Table 4.48: Sensitivity testing for stepwise selection mode summary ....................................149
Table 4.49: Coefficients for stepwise selection mode .............................................................149
Table 4.50: Excluded variables in stepwise selection mode using revised data ......................150
Table 4.51: Residual statistics for stepwise selection mode for revised project data ..............150
Table 4.52: Variables entered/removed in stepwise selection mode .......................................150
Table 4.53: Sample of data using reciprocal transformation ...................................................154
Table 4.54: Model summary using reciprocal indexed prog. cost $m transformed data.........155

XIII
Risk factors leading to cost overrun in the delivery of highway construction projects.

Table 4.55: Regression coefficients for transformed data model.............................................156


Table 4.56: Residual statistics for transformed project data ....................................................156
Table 4.57: Model summary using rural project data ..............................................................156
Table 4.58: Regression coefficients for rural data model ........................................................157
Table 4.59: Residual statistics for rural project data ................................................................157
Table 4.60: Model summary using urban project data.............................................................159
Table 4.61: Regression coefficients for urban data model.......................................................159
Table 4.62: Residual statistics for urban project data ..............................................................159
Table 4.63: Indicative over-and-above contingency percentages for project size ...................162
Table 5.1: Project price adjustment percentages derived from RICI .......................................166
Table 5.2: Top twelve highway risk factors causing cost overrun ...........................................167
Table 5.3: Experience profile of expert group membership.....................................................168
Table 5.4: Ranked principal highway cost overrun risk groups...............................................170
Table 5.5: Client risk sources during project ...........................................................................171
Table 5.6: Highway project construction types........................................................................172
Table 5.7: 1986 Texas Department of Transport highway project classifications ...................172
Table 5.8: Over-and-above contingency percentages for varying project sizes ......................175

XIV
List of Appendices

Appendix A: Road Input Cost Indices for the period 1995-96 to 2002-03 .......................207
Appendix B: Programmed and actual project costs indexed to year 2003 ........................211
Appendix C: Questionnaire format to establish NGT membership...................................217
Appendix D: Questionnaire containing summarisied NGT responses ..............................223
Appendix E: Client risks in highway project delivery.......................................................233

XV
Risk factors leading to cost overrun in the delivery of highway construction projects.

XVI
CHAPTER 1
Introduction to research project

CHAPTER 1

Introduction to research project

1.1 Background to the Research


Cost estimation is particularly difficult in the construction industry, often leading to
considerable cost overruns that are explained by large uncertainties and uniqueness of
projects (Baker et al., 1995). One might expect that cost overruns have that same probability
as completing the project below the cost estimate. However, observations clearly indicate an
overrepresentation of cost overruns (Emhjellen, 2003). Transport infrastructure projects are
particularly prone to cost overrun, with actual costs on average being 28% higher than
estimated (Flyvbjerg et al., 2003).

The delivery of projects is performed using mainly traditional processes that have evolved
from history and the industrial revolution, where specialisation of professional organisations
was the key trend (Pakkala, 2002). This means that architects, engineers, specialty
contractors, and the industry have adopted a segmented rather than an integrated type of
process. In developed countries, the majority of projects have used the project delivery
method of design-bid-build (DBB) (Gould, 1997), alternatively known as the tradition
method, and typically consisting of discrete feasibility/preliminary design, full design,
construction and operation phases (Fig 1.1).

Feasibility/
preliminary Design Construction Operation
design

Figure 1.1: Traditional project development phases

Highway infrastructure project delivery in Australia, Canada, England, New Zealand,


Sweden and the US predominately use Design-Bid-Build (DBB) (Pakkala, 2002) which
allows the design/engineering service to be produced first, and then another procurement
contract tendered for the actual construction that is based on the design.

The traditional procurement process has been developed to focus on clarity, separation of
phases and provide a transparent and independent bidding stage. The process can be
inefficient and take a long time and often sets up opposing stances between participants,
however the clarity of this process is particularly attractive to clients who need to
demonstrate probity (Sidwell et al., 2002).

Although lack of cost control in all of the project development phases can contribute to cost
control problems, of particular interest is the time the client makes the decision to build
(Hester et al., 1991). In the traditional method, this is often made towards the end of the
design phase. Accurate budget estimates are critical to the initial decision-to-build process

1
Risk factors leading to cost overrun in the delivery of highway construction projects.

for the construction of capital projects (Ward, 1999). These are usually based on a number of
factors such as the complexity of the project, the speed of its construction, the location of the
project and degree of unfamiliarity (Baker et al., 1999). Project cost overrun can be caused
by rising costs from inflation and inadequate analysis of information (Kayode, 1979) and by
costing methods (Akpan and Igwe, 2001).

Engineering designs have a high level of influence on project costs and sometimes
unsatisfactory design performance can lead to cost overrun (Barrie and Paulson, 1992).
There have been few instances where an engineering design is so complete that a project
could be built to the exact specifications contained in the original design documents (Chang
(2002). Many construction problems are due to design defects and can be traced back to the
design process (Bramble and Cipollini, 1998). Design and project specific factors such as
vagueness in scope, design complexity and project size affect the cost estimate of a project
(Akinci and Fischer 1998).

For capital projects, cost estimates are first prepared to enable clients to make reliable
decisions regarding economic feasibility and justification. Early project estimates are often
prepared on limited scope definition and little information regarding the specific parameters
that are needed in the completed facilities (Zeitoun and Oberlender, 1993). As well, they are
often prepared under severe time constraints (Chang (2002). Estimates, even when grossly
inaccurate, often become the basis upon which all future estimates are judged and for the
project team, their performance and overall project success are often measured by the client
by how well the final project cost compares to the initial cost estimate (Hester et al., 1991).

For the project client, accurate cost estimates are vital for business decisions on strategies for
asset development, potential project screening, and resource commitments for existing and
proposed project developments. Accurate estimates are critical to the initial decision-to-build
process for the construction of capital projects (Flyvbjerg et al., 2002).

There are generally four stages involved in developing project cost estimates (Queensland
Department of Main Roads, 2000:
1. Strategic stage: estimate of the cost of undertaking the planning functions required to
produce the options analysis and business case. Usually applies to non-routine
projects where significant cost will be incurred before the proposal is officially
recognised as a project.
2. Concept stage: This provides comparative costs of options prepared as part of the
options analysis. No project cost is produced at this stage. Concept approval gives
authority for the development of the preferred option.
3. Preliminary Design: This develops the total project cost estimate based on the final
design solution but usually before commencement of design, detailing and
documentation.
4. Detailed design (Decision-to-Build): This is prepared on completion of the detailed
design when final plans, specifications and bill of quantities are available. The
detailed design generally forms part of the scheme prototype documents needed for
approval to call tenders and forms the benchmark against which the final cost of
completion is measured.

2
CHAPTER 1
Introduction to research project

While cost estimates become more accurate over time, it is the cost estimate at the time of
making the decision-to-build the project that is of primary interest (Flyvbjerg et al., 2002).
This point in the projects development is seen as the international standard for measuring
the inaccuracy of project cost estimates (National Audit Office Department of Transport,
1992; World Bank, 1994; Nijkamp and Ubbels, 1999). Accuracy is defined as the difference
between the initial project estimate at the decision-to-build stage and the real, accounted
project cost determined at the time of project completion. Expressed as a percentage of
estimated cost, this is often termed cost-escalation, cost overrun or cost growth.

Total project cost estimates include the costs of all component activities from the initiation
of the project proposal to finalisation. These include the cost of developing the concept,
investigations, developing the design, acquiring land, altering public utility plant,
construction, project administration and handover (Queensland Department of Main Roads,
2000).

Estimating methods and the accuracy of project cost estimates are major reason for project
cost changes (Hester et al., 1991). When an inaccurate original estimate is prepared for a
project and is used to compare the actual cost of that project, then there can be a noticeable
difference, referred to as a cost change (Flyvbjerg et al., 2002). Clients assume that routine
changes in projects project will only affect work in the change areas, whereas, in reality, the
effects can extend well beyond specific change areas (Hester et al., 1991). Project cost
accuracy is very important to clients as it enables them to have better cost control over
projects. However, construction projects are notorious for running over budgets (Hester et
al., 1991).

1.2 Research problem


Contemporary project management practice is characterised by late delivery, exceeded
budgets, reduced functionality and questionable quality (Williams, 1999) and while risk
management is a recognised practice that helps clients deliver projects on schedule and
within cost (Project Management Institute, 2000), the risk management performed in the
construction industry has traditionally been that of gut feel or a series of rules-of-thumb (Al-
Bahar and Crandall, 1990). Consequently, project risks are often not adequately dealt with
(Thompson and Perry, 1992) and the complexities of projects, locations and types of
contracts are significant contributors to risks in construction projects (Ahmed et al. 1999).
While some industries such as the oil industry commonly respond to assessed risk, the
construction industry concentrates almost exclusively on trying to reduce financial risk and
less on managing technical risk (Baker et al., 1999).

Clients estimating policies usually focus on the preparation of unlikely to be exceeded but
not excessively conservative estimates (Flyvbjerg et al., 2002). In the case of highway client
organisations, this usually means that the estimate prepared at any stage of a project has a
90% confidence factor of not being exceeded at the cost-at-completion (Queensland
Department of Main Roads, 2000).

3
Risk factors leading to cost overrun in the delivery of highway construction projects.

Figure 1.2 shows the required estimate ranges that are normally required by clients in the
stages of project estimates.

This figure is not available online.


Please consult the hardcopy thesis
available from the QUT Library

Source: Queensland Department of Main Roads (2000).

Figure 1.2: Stages of project estimates

Transportation projects have historically experienced significant construction cost overruns


from the time the decision to build has been taken by the client (Molenaar, 2005).
Construction cost estimating on major transport infrastructure projects has not increased in
accuracy over the past 70 years. The underestimation of cost today is in the same order of
magnitude that it was then (Flyvbjerg et al., 2002).

High profile highway projects in the US, such as Bostons Central Artery/Tunnel, known as
the Big Dig and Virginias Springfield Interchange have made engineers, contractors and
public taxpayers acutely aware of the problem of cost overrun. For example, the Big Dig was
estimated at a cost of US$2.6 billion (1982 dollars) but was expected to be completed at a
cost of US$14.6 billion (2002 dollars) with completion then anticipated in 2005 (NAS,
2003).

Cost overrun of highway projects in Queensland, Australia, has been significant over a
relatively long period of time. The Queensland Governments Roads Implementation
Program 200405 (Queensland Department of Main Roads, 2005) reports on the proportion
of projects costing more than $1m that have had significant cost overrun by exceeded their
programmed estimate by more than 10%. As can be seen from Table 1.1, cost overrun in
highway projects have had a serious impact on program budgeting from the view of the
client. On average, 1 in 10 highway projects of => $1m has significantly exceeding their
decision-to-build budget (Queensland Department of Main Roads, 2005).

4
CHAPTER 1
Introduction to research project

This table is not available online.


Please consult the hardcopy thesis
available from the QUT Library

Source: Queensland Department of Main Roads (2005)

Table 1.1: Highway projects over A$1m that exceeded estimate by >10%

Planning and programming future highway construction projects are vitally important tasks
in highway organisations (Wang and Chou, 2003). A construction program outlines how
highway funds are to be spent over time and any deviation from the stated program often
brings a quick response from the public, the press and politicians. When this occurs, the
highway organisation loses creditability and time is often taken defending deviation from the
published program (Flyvbjerg et al., 2002). On the other hand, if a highway organisation can
produce realistic program estimates, especially at the decision-to-build stage that it is able to
abide by, then the agency's image can be enhanced.

To produce accurate construction programs, three conditions need to be met. Firstly, an


accurate assessment of the future funding (i.e. supply of funds) needs to be available.
Secondly, the cost of individual projects needs to be accurately estimated. Thirdly, any
potential project risks that can lead to cost increases when the facility is constructed are to be
adequately identified and managed accordingly (Wang and Chou, 2003).

Project owners, such as highway agencies, are usually engaged in specific types of
construction projects with unique features. For example, highway construction projects are
characterised by their linear complexity, with their greatest risk lying below ground level due

5
Risk factors leading to cost overrun in the delivery of highway construction projects.

to the relatively larger footprint, as compared with say building structures (Halligan et al.,
1987). Project risks can be derived by reviewing historical data and thus ensuring
consideration is given to potential cost overrun (Touran, 2003). Historical data may be used
as a guide; however estimators and project managers also use their experience and
professional judgement to weigh the competing factors to arrive at the most likely value
(Yeo, 1990).

The analysis of project risks is a necessary step for the improvement of any given estimating
system and can be used to diagnose trouble spots and to pinpoint areas where greater
improvement can be obtained (Touran, 2003). Formal and informal databases usually exist
for specific domains, such as in assessing risks or cost overruns in construction projects.
Many of these databases are deemed commercial-in-confidence, particularly in highly
competitive industries (Al-Bahar and Crandell, 1990). In-house historical databases are often
inadequate or disjointed, unavailable, or supplemented with personal knowledge. These
databases are company and/or project specific and are not usually able to be uniformly
applied across new projects (Al-Bahar and Crandell, 1990).

Models have been established showing cost influencing factors derived from past records of
construction costs (Wilmot and Cheng, 2003). Extrapolation of past trends has been used to
forecast future overall construction costs (Koppula, 1981; Hartgen et al., 1997), however
such models are usually only used for short-term forecasting because of their reliance on the
notion that past conditions and specifications are not always retained into the
future.Completed construction project data from the building industry has been used with
regression analyses to forecast the actual cost of projects (Skitmore and Ng, 2003). Models
of cost overrun across processing projects have been derived from quantitative data from
completed projects using factor analysis and multivariate regression (Trost and Oberlender,
2003).

The level of project risk contingency in estimates has a major impact on their financial
outcomes for clients. If contingency is too high it might encourage poor cost management,
cause the project to be uneconomic and aborted, or lock up funds that is not available for
other projects (Dey et al., 1996). On the other hand, if the contingency allocation is too low,
then it may be too rigid and set an unrealistic financial environment, resulting in
unsatisfactory performance outcomes (Touran, 2003). In some areas of the public sector,
there is a tendency to remove contingency provisions in budget submission, as contingencies
are often seen as fats leaving no allowance to express anticipation of any project risk
(Yeo, 1990).

The most common method of allowing for uncertainty in estimating has been the addition of
around 10% contingency to the most likely estimate of the known works (Burger, 2003).
Hartman (2000) argues that this is an unscientific approach and a reason why so many
projects finish over budget. The common method of allocating 10% contingency is regarded
as overly simplistic and heavily dependent on estimators' faith in their own experiences
(Yeo, 1990). The Department of Main Roads Queensland adopts a 10% contingency for all
detailed design estimates unless there are other reasons why they should be adjusted
(Queensland Department of Main Roads, 2000) and as shown in previous Table 1.1 could be
seen as being significantly inadequate to cover the client risks in highway construction.

1.3 Research purpose

6
CHAPTER 1
Introduction to research project

The purpose of this research is to establish the nature and extent of cost overruns of
Queensland highway projects and to develop a method for improving budget estimating
practices. The research purpose is also to develop a more definitive risk contingency
allocation regime for overall highway projects that can supersede the arbitrary models
present in most highway projects.

Two research questions are posed:


1. What client risks are present during the delivery of highway construction projects in
Queensland, Australia that lead to significant project cost overruns?

2. How does the amount of highway cost overrun in such highway projects correlate
with their project types, size, delivery processes and client project risks when
historical project data are analysed?

1.4 Research objectives


The objectives of the research are:
To undertake the analysis of historic project cost overrun factors and project
parameters to ascertain if the findings can lead to more accurate client budget
estimates in the future by estimators making more realistic allowances in estimates
for identified cost overrun factors.
Develop model relationships between the measure of the percentage of cost overrun
in highway construction projects and:
o construction risks
o types of highway construction projects
o project delivery methods
o project location
o project size.

1.5 Justification for the research


Little research appears to exist that relates the client project risks in highway construction
and their correlation to the actual completed cost of a project (Williams, 2003). Research in
this area may find relationships in construction cost data that can be usefully and simply
applied to estimating processes. There are models derived from simple linear regression, for
example, that can be used to predict the completed cost of competitively bid highway
construction projects using only the low bid as input (Williams et al., 1998). However, there
appears to be little research that identifies risk factors in specific highway project types and
their relationships to budget cost overrun (Williams, 2003). Little research exists that relates
the incidences of highway project types and client project risks to cost overrun in actual
completed projects. An understanding of the reasons for consistent cost overruns will allow
clients to focus on problem areas and implement systems into program budgeting procedures
which will lead to more realistic project budget estimates.

Numerous factors affect project construction costs and most construction cost models
developed in the past have used only a few of the many possible influential factors identified
to date.

7
Risk factors leading to cost overrun in the delivery of highway construction projects.

Research of this type has also been hampered in the past because adequate data has not been
available. However, more data sources of completed projects now appear to be becoming
available, particularly in the public sector. Once identified, post mortem analyses of these for
project risks can ultimately provide the client with more confident final project budgets that
are unlikely to be exceeded.

The interrogation of in-house historical databases is probably the best source of data to
assess risk occurrences or consequences of risk events and in many cases these databases are
inadequate or disjointed, unavailable or supplemented with personal information bias (Al-
Bahar and Crandell, 1990). These databases are company and project specific and may not
necessarily be able to be uniformly applied to new projects.

Research such as that for the Washington State Department of Transportation has identified
risk factors that have strong association with project construction costs, indicating that cost
overruns, expressed as a percentage of the original contract amount, has tended to increase
with the size of the project (Hinze and Walsh, 1997). Williams (2003), in his research into
highway contract overruns, identified the need to study further correlations between different
highway project types and constructed project cost overruns. There is little evidence in the
research to date that has identified such correlations in highway projects in Australia. As
well, many research projects to date consider only the final outcome of contracts within the
project and have not considered the clients risks associated with the full project budget.
That is, the failures that lead to cost overrun in the overall project from the time of the
client's decision-to-build is made until its completion.

Clients require different contingencies for different elements of projects (Eden et al., 2005).
The establishment of a range of contingencies can require a considerable amount of work by
estimators and so a simple contingency across the board is included in order to acknowledge
the difficulty of pinning down project uncertainty (Baccarini, 2004). This research aims at
addressing this issue by providing clients with a cost overrun model which correlates risk
contingency with highway project attributes.

1.6 Methodology
This research adopts an historical analysis as the foundation to the methodology and is an
important approach for presenting information (Kirszner and Mandell, 1992). As well, the
use of historical data assists in providing an insight into current problems relating to cost
overruns in highway project estimates through the examination of what has happened in the
past.

8
CHAPTER 1
Introduction to research project

Five stages form the basis of the research as outlined in Table 1.2 and are designed to
provide answers to the research questions.

Stage Research procedure


1 Literature research to determine research focus.

2 Establish data sources of highway construction projects.

3 a) Determine cost overrun factors from historic project data

b) Use factor analysis (principal component analysis) and factor rotation on


cost overrun factors to consolidate data.

4 Use nominal group technique (NGT) to elicit, review and prioritise principal
cost overrun risk groupings and highway project types.

5 Undertake data analysis and statistical modelling using multivariate linear


regression analysis. Establish correlations between client risks causing cost
overrun, project attributes and project programmed cost.

Table 1.2: Research procedures

1.7 Outline of the research thesis organisation


This thesis is organized into six chapters as follows:
Chapter 1 Background
Chapter 2 Literature review into project risk and cost overrun
Chapter 3 Research methodology
Chapter 4 Data analysis
Chapter 5 Discussions on findings, conclusions and recommendations

This Chapter 1 begins the background phase of the research by providing the objectives,
proposed methodology overview, scope and project organisation.

Chapter 2 is a literature review from professional journals, books, internet searches and from
interviews with highway construction delivery experts. Chapter 2 essentially provides a
review of the current state of the art in construction risk, contract delivery methods and
project cost estimating and cost control processes used in and its management and cost
estimation of risk. Brief definitions of aspects of construction risks, procurement and the
project management of projects are also contained within Chapter 2.

Chapter 3 discusses the research methodology necessary to achieve the research objectives.
The research method adopted is that of analysing historical data collected on highway
construction projects. The research techniques of factor analysis (FA) using principal

9
Risk factors leading to cost overrun in the delivery of highway construction projects.

component analysis (PCA) and rotation and then nominal group technique (NGT) are
proposed that will consolidate data on the types of construction risks and the types of
highway projects that are associated with client budget cost overruns. Multivariate regression
analysis is then used to identify potential correlations between budget cost overruns and the
various attributes and risks present in projects with excessive cost overrun.

Chapter 4 contains the various data analyses of the historical project information. Factor
analysis and then nominal group technique are used to initially break down the bulk of the
client risks identified from a post mortem of historical project data. The data analysis uses
multivariate regression analysis to investigate the statistical significance of the available data
between documented client project construction risks, highway project types, project size,
location, project delivery methods. These are then correlated against the size of completed
project budget cost overruns.

Chapter 5 discusses the findings from the data analysis carried out in Chapter 4 and develops
conclusions and recommendations that are derived from the research and how the research
objectives align with the findings. Both specific and general recommendations are provided,
as well as recommendations for future research.

1.8 Delimitations of scope and key assumptions


The traditional method of DBB is by far the most generic construction process and is
predominately used in the highway construction industry in the majority of developed
countries (Gould, 1997), however the construction of some projects are performed using
various other contract delivery methods. Only projects developed using the DBB delivery
process have been used for the purposes of this research.

Government contracts like the QDMR are typically awarded either through procurement
auctions or are negotiated price contracts with local authorities of internal workforce units.
All the highway projects chosen in this research have contractor pre-qualification so as to
ensure that all project constructors have demonstrated their ability to do similar highway
projects in the past. As well, where appropriate, contractor surety bonding has formed part of
the project delivery process.

Cost growth, cost changes and cost overrun are considered to have the same meaning for the
purpose of this research, and they can be defined as the difference between the final project
cost and the cost estimate at the time of the decision-to-build after design for a particular
project.
The total project cost estimate for the client includes the estimated costs of all component
activities from the initiation of the project proposal to finalisation. These include the cost of:
developing the concept design and business case
conducting investigations and developing the design
detailing the design
acquiring land
altering public utility plant
construction
project administration and project handover.

10
CHAPTER 1
Introduction to research project

The definition adopted for a client or project owner is an individual or organisation for
whom something is built or delivered under some form of contract agreement. The
Queensland Department of Main Roads (QDMR) is the client/owner and is the organisation
for which the highway projects are constructed. It should be noted that some historic project
data utilised in this research may be additionally influenced by long term economic
conditions and contracting climates that may vary from time to time. The variation in such
external project conditions over the seven year analysis period representing the project data
may provide some influence over any correlation of results.

Only highway construction projects are considered in the research. Other transport
infrastructure and building construction are not included. This research study uses QDMR
data for projects completed for the financial years from 1997 through to 2003. The data used
is unique due to the project variables such as project estimate and final costs, project
location, project delivery type, highway project type and reasons for project cost overruns.
All project data used came from published sources within Queensland and all relate to
projects that were initially estimated to cost A$1m or greater and whose final completed cost
substantially exceeded their initial budget (by more that 10%).

1.9 Conclusion
A focus of research effort in the area of project cost overrun will provide a more basic
understanding of the linkages of risk to highway project delivery. The purpose of the
research project is to carry out an empirical analysis in order to ascertain whether the data
support the hypothesis that there is a statistical correlation between highway project cost
overruns and project attributes.

The research concentrates effort on the study of aggregate data about highway construction
projects in order to identify common trends that occur. While the research finds a history of
underestimation of costs and the over-optimistic assumptions about performance of a
substantial number of project budget estimates, the research also specifically contributes to
the body of knowledge in project construction management and cost estimating in the
following ways. It has:
combined risk assessment and expert elicitation techniques in investigating project
management estimating and cost control issues when estimating highway projects
provided a quantitative and qualitative project assessment that will help highway
project decision makers define unforeseeable disturbances more reliably ahead of
time, so that corrective measures can be better taken into account in project design
and estimating
provided an in-depth post mortem analysis of client risks that have led to significant
project cost overrun and thus has strengthened the understanding of why highway
projects can overrun substantially above project decision-to-build budgets.
identified client risk factors that are aimed at simply providing a better understanding
of the risk parameters and management contingency requirements in project, thus
validating better risk contingency weightings in budget estimates
utilised an established expert elicitation technique in the research project in a way
that required minimal impact on the time of construction experts, but at the same
time providing an acceptable outcome to a difficult elicitation requirement
accounted for economy of scale in highway projects by proposing ranges of over and
above % contingencies for varying sizes of highway projects.

11
Risk factors leading to cost overrun in the delivery of highway construction projects.

12
CHAPTER 2
Literature review into project risks and cost overrun

CHAPTER 2

Literature review into project risks and cost overrun

2.1 Preamble
The change in project cost, or cost growth, occurs as a result of many related factors all of
which are associated with some form of risk (Flyvbjerg et al., 2003). Analysis of the reasons
for project cost overrun of construction projects is a necessary step for the improvement of
any given cost estimating system and can be used to pinpoint areas where the greatest
improvement can be obtained. As part of this process, Chapter 2 provides a literature review
of aspects of project delivery risks which often contribute to the potential for cost overrun.

It begins with some basic terms and definitions, followed by a discussion on the nature of
risk its identification and its management, particularly in the construction industry. The
review then looks at the concept of risk engineering, followed by aspects of expert elicitation
of risk probabilities. It then investigates the significance of risk assessment in tendering and
contract administration by using varying forms of project procurement used within the
construction industry. It then goes on to look at the various components that can influence
estimate cost accuracy of projects during project construction.

This literature review then focuses on the various project delivery mechanisms used in
project construction and the influence that they have on minimising and managing project
uncertainty, particularly for clients. Reviewed also are project cost estimating and
procedures that are used in minimising client risk and in reducing project cost overrun.
Project cost estimating and also project contingency, with emphasis on highway construction
projects are also considered.

2.2 Introduction
The procurement of constructed facilities is a process which involves many complex and
interrelated steps incorporating questions of value for money, probity and fitness for
purpose. Over more than three centuries, a procurement process has been developed that
focuses on clarity, separation of phases and a transparent independent bidding stage. This is
often referred to as the traditional project delivery process (Flyvbjerg et al., 2002).
Unfortunately, it has some reported serious drawbacks. For example, the process
management can be inefficient and take an extended time and so often sets up opposing
stances between the project participants which can eventually compromise the measures of
success of a project in terms of time, budget and technical performance (Sidwell et al.,
2002).

On the other hand, the main barriers to achieving project success are the changes in the
project environment (El-Choum, 1994). The problem multiplies with the size of the project
as uncertainty in project outcomes increase (El-Choum, 1994). Large-scale construction
projects are exposed to uncertain environments because of such factors as planning, design

13
Risk factors leading to cost overrun in the delivery of highway construction projects.

and construction complexity. In addition, the presence of various interest groups (such as the
project owner, consultants and contractors) as well as resources (such as materials,
equipment, project funding, climatic, economic and political environment and statutory
regulations) all add to project uncertainty. Other factors contributing to uncertainty include
the complexity of the project, the speed of its construction, the location of the project, and its
degree of unfamiliarity (Ahmed et al., 1999).

In the report, Rethinking Construction Report on Construction Industry, Egan (1998)


identifies the need for continuous improvement and establishes key performance indicators
for measuring performance in the UK construction industry.

One of the major causes of business failures is related to the client. Client-generated risk
factors can be stated as a client's financial ability to meet the cost of the work, its claims
record, changing needs, and the construction sophistication. In turn, these risks can put a
strain on the contractor's cash flow and can increase the actual cost of a project during
construction (Kometa et al., 1996).

2.3 Definitions
The Project Management Institute (Project Management Institute, 2000:21) defines a project
as:
a temporary endeavour undertaken to create a unique product or service: Temporary
meaning that every project has a definite beginning and a definite end: Unique
meaning that the product or service is different in some distinguishing way from all
similar products or services.

Much earlier, Steiner (1969:16) defines a project as:


an organisation of people dedicated to a specific purpose or objective.

Projects generally involve large, expensive, unique or high-risk undertakings that have to be
completed by a certain date, for a certain amount of money, and deliver some expected or
anticipated level of performance. These three criteria of success have become widely used. It
captures the essential task of the project manager, and the essential trade-offs that they can
make. Kohrs and Welngarten (1986:87) report seeing a sign: Good! Fast! Cheap! Pick any
two. This analogy can also be true in the project construction sense, where there is usually a
trade-off of some sort on at least one of these parameters by the project owner.

McCoy (1986) has tried to develop an integrated success criteria based on this three-fold
criterion. At its most simplistic, Avots (1984) suggests that schedule is most important early
in the project, but during the project cost becomes most important and after the project only
technical performance is remembered. Salapatas and Sawle (1986) define success to have
been achieved only when three groups perceive success: the client (based on performance,
budget and reputation), the contractor (based on profitability, reputation, client and public
satisfaction) and the customer/public (based on environment, reliability and cost). Potter
(1987) has found from experience that success and failure can in fact be very close and
Sykes (1982) supports this by pointing out that many large projects have been saved from
disaster only because of fortuitous circumstances.

14
CHAPTER 2
Literature review into project risks and cost overrun

The Project Management Institute (2000:22) defines project management as the:


application of knowledge, skills, tools, and techniques to project activities in order to
meet or exceed stakeholder needs and expectations from a project.

Project management invariably involves balancing competing demands of:


scope, time, cost and quality
stakeholders with differing needs and expectations
identified requirements (needs) and unidentified requirements (expectation)
(Project Management Institute, 2000).

In project development, the project client plays a very important role. The term client refers
to that person or organisation investing in the construction of built facilities (Mak and
Picken, 2000).

The Project Management Institute (2000) defines stakeholder as individuals and


organisations who are actively involved in the project, or whose interests may be positively
or negatively affected as a result of project execution or successful project completion.

Dake (1992) examines the concept of risk from an historical perspective. In the seventeenth
century, risk was defined as the probability of an event occurring, with a focus on either the
losses or gains that the event would represent if it occurred. The interesting aspect of this
early definition is that there was as much attention paid to benefits as to losses. This is a
perspective that has been lost in the twentieth and now twenty-first centuries. In the popular
sense, the term risk carries largely negative connotations of loss or harm that generally has
implications of negative or adverse results from an uncertain event. For example, Fishburn
(1984) calls a certain bad event 'risky' and Statman and Tyebjee (1984) see risk as being a
high probability of failure.

Jaafari (1990) on the other hand, sees risk as being the presence of potential or actual
constraints that could stand in the way of project performance by causing partial or complete
failure during construction and commissioning, or at the time of using the project.

Risk has been defined by Chapman and Ward (1997: 58) as being:
the exposure to the possibility of an economic and financial loss or gain, physical
damage or injury, or delay as a consequence of uncertainty.

By comparison, Young (1996) sees risk in the project management environment as being any
event that could prevent the project realising the expectations of the stakeholders as stated in
the agreed project brief or agreed definition.

Adameitz (2003: 43) describes various aspects of risk as follows:


Risk can be viewed as a four-letter word. There can be economic boundaries from the
addition of extra overhead activities, and political/cultural boundaries from an
unwillingness to acknowledge that a risk exists and must be mitigated. To prevent this
budget pressure, risk management and mitigation activities need to be factored into the
project plans from the very beginning of a project. Construction projects involve
numerous unpredictable and complex processes.

15
Risk factors leading to cost overrun in the delivery of highway construction projects.

Dias and Ioannou (1995) conclude that there are two types of risk:
1. Pure risk that exists when there is the possibility of financial loss but no possibility of
financial gain (e.g. physical damages)
2. Speculative risk that involves the possibility of both gains and losses (i.e. financial
and production risk).

Hillson (2002) argues that the common usage of the word risk only centres on the negative
outcomes. Ward and Chapman (2003) argue that risk is often associated with adversity,
things that may go wrong, and threats to projects.

According to the Project Management Book of Knowledge PMBOK (Project


Management Institute, 2000), risk management is seen as the processes concerned with
identifying, analysing and responding to uncertainty throughout the project's lifecycle. It
includes maximising the results of positive events and minimising the consequences of
adverse events.

The Australian/New Zealand Standard 4360:1999 sees risk management as a generic


framework for establishing the context, identification, analysis, evaluation, treatment,
monitoring and communication of risk.

Royer (2000) sees risk management as:


deciding what is an acceptable risk
how the level of the risk can be brought down to a level that is acceptable
monitoring the reduction in risk after exposure control actions have been taken.

However, Royer also points out that having such a focus of risk on adversity means project
risk management tends to focus more on processes and methods that reduce the effect of
threats.

The general conceptualisation of procurement has been expanded by McDermott (1999) into
the context of project construction. Rowlinson (1999) furthers this systems view of
procurement by including elements such as contract strategy, culture and finance.
Kumaraswamy and Dissanayaka (1998) trace and link the definition of procurement to the
action or process of acquiring or obtaining material, property or services at the operational
level. They also define building procurement as being the amalgam of activities undertaken
by a client to obtain a building.

Construction procurement, on the other hand, is defined as being the framework within
which construction is brought about, acquired or obtained (Kumaraswamy and Dissanayaka,
1998). A high degree of specialisation has evolved in the procurement of the various goods,
materials and services in the construction industry. This has led to a network of supply
chains that include multiple layers of sub-contractors and interlinked suppliers.

The next section looks at risk in both the clinical and project sense, as well as at the various
processes for identify and managing risks within projects.

16
CHAPTER 2
Literature review into project risks and cost overrun

2.3.1 The Nature of Risk

While risk is fairly well documented in the literature, the terminology is not consistently
applied across construction, project management, engineering, health and safety,
environment, business and other industries (del Cano and de la Cruz, 2002). Risk can be
classified as voluntary or involuntary, depending on whether or not the events leading to the
risk are under the control of the persons at risk or not (del Cano and de la Cruz, 2002). In the
theoretical sense, Cvethovich and Earle (1992) view risk not as an inherent quality of the
physical world but as a representation of the interaction between physical and psychosocial
characteristics with the assessment of risk involving judgements about what is valued.

Kumamoto and Henley (1996) identify five attributes of risk. These are:
1. Likelihood
2. outcome
3. significance
4. causal scenario
5. population.

Uher (1994) identifies 34 individual risks and categorises them into a single model, referring
to some as activity risks that may affect individual activities, while others were global risks
that were common to all activities. The majority of risks Uher identifies are global risks.
Rutgers and Haley (1997) developed a model that identifies four distinct phases of risks in a
project:
developmental risks technical, commercial/financial feasibility
project economics, permits/authorisation, third-party intervention and political
change
construction risks schedule, cost, performance, design changes, interest rate
escalation, consequential damage, force majeure/country risk, currency changes
operational risks market changes, statutory changes, unrest/strikes, acts of God,
third-party liability etc.

2.3.2 Risk and uncertainty

Decisions are concerned with variables which are normally classified as risks or
uncertainties. Risks are unknowns, the probability of the occurrence of which can be
assessed by statistical means (risks are usually insurable). Uncertainties are unknowns, the
probability of the occurrence of which cannot be assessed (uncertainties are uninsurable)
(Chapman and Ward, 1997). It is possible, however, for a decision-maker to assign a
subjective probability to an uncertainty. As knowledge increases in conjunction with the
amount and detail of statistical data, areas of uncertainty are progressively converted to areas
of risk (del Cano and de la Cruz, 2002). The evolution of weather data and associated
forecasting techniques is such an example (Fellows et al., 2002).

Risk links strongly with the uncertainty of the probability and consequence of a risk event.
Ayyub and McCuen (1997) point out that uncertainty has two types of origins non-
cognitive and cognitive. Non-cognitive uncertainty results from physical randomness. This
type of uncertainty is normally dealt with by employing current statistical and probabilistic

17
Risk factors leading to cost overrun in the delivery of highway construction projects.

science (Chapman and Ward, 1997). Cognitive types of uncertainty result from humans
expressing subjective judgements. Blair (1999) uses a fuzzy set theory approach for the
development of costs and schedules for complex engineering systems. Uncertainty always
exists in the modelling and project management of complex construction projects and this
uncertainty is due to the model representing real systems and is also attributed to humans
who express risk in subjective terms.

Raftery (1994) points out that risk and uncertainty characterise situations where the actual
outcome for a particular event or activity is likely to deviate from the estimate or forecast
value. As well, risks exist in projects because of their uniqueness and temporary nature and
can impact on the project contractor and sub-contractors, stakeholders and project owner in a
variety of ways. Leu et al. (2001) point out that during project implementation, many
uncertain variables dynamically affect the project duration and the costs can thus change
accordingly (del Cano and de la Cruz, 2002).

2.3.3 Risk management

Risk management is the process by which clients and their project managers make decisions
based on data generated in risk assessments. Risk management involves making educated
decisions about different configurations, construction scenarios and operational parameters.
The Australian/New Zealand Standard 4360:1999 defines risk management as a generic
framework for establishing the context, identification, analysis, evaluation, treatment,
monitoring and communication of risk. However, the standard is not prescriptive, but rather
describes the systems and processes required for risk management. Tuohey (2002) points out
that the use of this standard is an integral element of good management practice across an
enterprise and makes the Standard an ideal choice as the framework for project risk
management. It provides a uniform, structured system that can be used across an
organisation and by which clients can better understand risk issues on individual projects.

The management of risk is seen as an essential part of the management of projects. Strategies
for mitigating risks on projects include(Turner, 1999; OGC, 2002).:
reducing the uncertainty associated with the project
avoiding the risk by finding a different way of doing the project
abandoning the project
reducing the likelihood of the risk occurring or the impact on the project
transferring the risk to other parties such as contractors or insurance companies
accepting the risk and creating a contingency plan

Risk management is also dependent on numerous factors such as industry sector, the size of
the project, and the stage of the project life cycle (Baker et al., 1999). To include some of
these ideas for the management of risk, the risk register is often been seen as the starting
point (Williams, 1993a). Also, Williams (1993b) provides a discussion of how the risk
register can assist in the allocation of risk and the preparation of risk management plans. The
use of project risk registers is often seen as an important step in the reuse of historical project
information (del Cano and de la Cruz, 2002). They can be seen as repositories of personal
knowledge or organisational memories where experiences about risks and responses are
continuously recorded (Tah and Carr, 2001).

18
CHAPTER 2
Literature review into project risks and cost overrun

However, Williams et al., (1997) point out that the project risk register fails to capture the
inter-relationships between risks and the systemic structure within the risks. This makes it an
inadequate tool for the capture and representation of risks, and therefore they question the
basis for analysis and decision making.

Dey (2001) has identified the following as general benefits that can be achieved from the
application of risk management in any type of project:
issues of the project are clarified and allowed for right from the start
decisions are supported by thorough analysis of available data
structure and definition of the project are continually and objectively monitored
contingency planning allows controlled and pre-evaluated responses to risks that
materialise
clearer definitions of the specific risk associated with a project
encourages problem-solving innovative solutions to problems within a project
provides a basis for project organisation structure and appropriate responsibility
matrices
builds up a statistical profile of historical risk for modelling future projects.

2.3.4 Risk evaluation and acceptance

Evaluating risk involves combining an events probability and its corresponding


consequence. Several methods have been developed to assist in determining risk acceptance.
A summary of these methods, as adapted from Ayyub and Wilcox (2000), is shown in Table
2.1.

This table is not available online.


Please consult the hardcopy thesis
available from the QUT Library

Source: Ayyub and Wilcox (2000)


Table 2.1: Methods for determining risk acceptance

Kaplan and Garrick (1984) assert that the purpose of risk analysis and risk quantification is
always to provide input to an underlying decision model which involves not just risks but

19
Risk factors leading to cost overrun in the delivery of highway construction projects.

also other forms of costs and benefits. Risk analysis is a systematic process for evaluating a
risk at the systems level.

Once risks are determined, the next process involves the modelling and quantifying risks
under risk assessment. The following sections deal with these aspects.

2.3.5 Risk assessment

Risk assessment provides qualitative and quantitative data to decision makers for later use in
risk management and when project risk assessment is undertaken properly and implemented
correctly, and in sequence (Ayyub and Wilcox, 2000). It enables continual improvement in
project decision making and can increase the likelihood of the successful completion of
projects to cost, time and performance objectives. It is an effective tool in meeting clients
needs in project delivery (Halpin, 1998).

A strong risk management program is essential in all project delivery strategies and is the
central aspect of project management (Shepherd, 1997). On the other hand, some people do
not even consider risk assessment to be a form of science, referring to it as art or even
hocus pocus (Gregory, 1989). Jackson (1989) argues that risk assessments are as full of
unknowns and value-laden assumptions as to lend such processes to be of no real benefit.

2.3.6 Risk assessment models

A number of systematic models have been proposed for use in the risk-evaluation phase of
the risk-management process. Kangari and Riggs (1989) classify these methods into two
categories classical models (i.e. probability analysis and Monte Carlo simulation) and
conceptual models (i.e. fuzzy-set analysis). They noted that probability models suffer from
two major limitations. Firstly, some models require detailed quantitative information that is
not normally available at the time of planning. Secondly, the applicability of such models to
real project risk analysis is limited, because agencies participating in the project often have
problems with making precise decisions. Such problems are often ill defined and, thus,
require subjective evaluations that classical models cannot handle.

The risk assessment control process attempts to answer the following three questions derived
from Kaplan (1991):
1. What can go wrong?
2. What is the likelihood that it will go wrong?
3. What are the consequences if it does go wrong?

In order to perform risk assessments, several methods have been created to help answer these
questions. Each of these methods is suitable in certain stages of a projects lifecycle. The
characteristics of particular risk assessment methods are shown in tables 2.2 and 2.3.

20
CHAPTER 2
Literature review into project risks and cost overrun

This table is not available online.


Please consult the hardcopy thesis
available from the QUT Library

Source: Ayyub and Wilcox (2000)


Table 2.2: Quantitative risk assessment methods

Qualitative risk analysis uses expert opinion to evaluate the probability and consequence of
interaction within a system. Table 2.3 details some qualitative risk assessment methods used

This table is not available online.


Please consult the hardcopy thesis
available from the QUT Library

Source: Ayyub and Wilcox (2000)


Table 2.3: Qualitative risk assessment methods

2.3.7 Risk control processes

An essential function of the construction project manager is the control of projects and hence
the control of risks. Risk monitoring is required so as to respond to events that occur over the
course of a project. Risk control can be achieved through the updating of risk management

21
Risk factors leading to cost overrun in the delivery of highway construction projects.

plans with new information, identifying alternatives to unplanned risk events, and by
mitigating unplanned risks (del Cano and de la Cruz, 2002). Perry and Hayes (1985) suggest
a checklist of risks that may occur throughout the life span of any project. Bent (1988), in
introducing the concepts of control, asserts that the fundamental elements of control are the
cost element and the project schedule. However, Might (1984), in carrying out a survey on
the effectiveness of project control systems on high-risk US Department of Defence and
NASA projects, reports that such control mechanisms are unclear and hence ineffective.

Williams (1995) describes various risk identification and analysis tools used by researchers
and practitioners in project risk management that can be used in controlling risk. Tummala
and Leung (1999) developed a methodology governing risk identification, measurement,
assessment, evaluation and control and have applied it in managing costs associated with risk
for transmission-line projects.

Most risk analysis reported in the literature so far has centred around analysing the duration
of projects and many authors, such as Farnum and Stanton (1987), present the distribution of
duration of activities as classical beta distributions. For example, Berny (1989) proposes a
distribution for practical simulations. Turner (1999), on the other hand, suggests expert
judgement, plan decomposition, assumption analysis and brainstorming for effective
identification of risk factors in projects. Delphi technique is used by Dey (1999) for
identification of project risk factors.

2.4 Risk engineering


Risk, as defined previously, and in Kumamoto and Henley (1996), is generally thought of in
terms of the possibility of suffering harm, typically resulting in negative consequences.
However, in project management, the aim is to maximise the results of positive events and
minimise the consequences of adverse events (Project Management Institute, 2000). Thus, in
the project management context, risk should be thought of as being concerned with
opportunities as well as threats or negative consequences. The Association for the
Advancement of Cost Engineering sees negative risk as having consequences that adversely
affect a projects cost (AACE, 2000). Opportunistic risk is viewed as having the potential to
improve or lower the projects cost. Wang and Roush (2000) point out that risk management
helps to limit the potential for negative consequences arising from uncertainties and also
maximises the possibilities of results being better than target values.

Cooper et al. (1985) suggests a risk-engineering approach where systematic risk evaluation
could be performed by subdividing a project into its major elements and analysing the risk
and uncertainty associated with each in detail. A classic risk analysis process is shown in the
upper tiers of Figure 2.1. The dotted box of risk engineering is shown to highlight this as a
backdrop to risk assessment and risk management.

22
CHAPTER 2
Literature review into project risks and cost overrun

R
This figure is not available online.
Please consult the hardcopy thesis
available from the QUT Library

Source:(Cooper et al., 1985)


Figure 2.1: Construction risk analysis

2.5 Qualitative defined


According to the Oxford Dictionary of English (Soanes and Stevenson, 2003), the term
qualitative is described as:
Relating to, or involving quality or kind.

Patton (1986:35) offers a more technical definition in the context of program evaluation by
describing qualitative data as consisting of:
Detailed descriptions of situations, events, people, interactions, and observed
behavior; direct quotations from people about their experiences, attitudes, beliefs, and
thoughts; and excerpts or entire passages from documents, correspondence, records,
and case histories.

2.6 Quantitative risk assessment


Quantitative risk assessment relies on statistical methods and this quantitative approach is
difficult to document because it relies on quality data. As well, each project is unique and
what data exists is based on past projects that may contain significant uncertainty when
applied to current projects (del Cano and de la Cruz, 2002). Literature on quantitative risk
assessment appears to be limited for eliciting risks from experts. Charette (1989) attempts a
structured approach for software projects, describing a risk estimate of the situation and an
associated information gathering process.

The classic treatment of quantifying probability distributions from experts by direct


encoding is attributed to Merkhover (1987) who discusses the fact that experts tend to
underweight distributional information or regress towards the mean. The simplest such

23
Risk factors leading to cost overrun in the delivery of highway construction projects.

approach categorises risks into high/medium/low probability and for this purpose can be
defined arbitrarily.

Construction simulation, fault tree analysis, fuzzy stochastic applications, risk premium and
expected net present value are just a few of the many quantitative risk assessment techniques
that can be used. These are explained in detail in the following paragraphs.

2.6.1 Simulation

Ang et al. (1984) define simulation as being the process of replicating the real world on a set
of assumptions and conceived models of reality. Simulation can be applied to construction,
manufacturing, public health, transportation, business process re-engineering and a host of
other industries (Banks et al., 1996). Simulation is one method to quantitatively assess
project construction risks. It is normally used to represent large, complex projects or systems
because it is much less expensive to experiment with models than real systems. Simulation is
particularly useful for studying systems in the design stage, because it is good for predicting
performance or cost of a proposed facility to be built.

Simulation is also particularly suited to construction because it allows experiments in


construction operations to evaluate potential impacts or improvements to costs and schedules
(Halpin, 1985) and assumptions made in building a simulation model can be changed to
investigate what if questions about the real project or process. As new information
becomes available during the life of a project the model can be updated to provide a better
simulation of the final costs.

Discrete event (DE) simulation is the particular modelling of a system as it evolves over time
in which state variables change instantaneously at separate points in time (Law and Kelton,
1991). As an example, the simulation of the process of bridge concrete components being
manufactured has the discrete steps of:
an order arrives at a concrete precast yard
component moulds are manufactured
multiple step casting processes
inspections
shipping to the bridge site.

At each point in the process the variables change, that is from raw material to finished
components or structure.

A construction simulation that is built on potential construction scenarios can identify risky
elements, resource constraints and potential bottlenecks (Mak and Picken, 2000). As well, it
can define sequences, construction times, facilities, materials, transport, labour etc.
Simulation is also well suited to calculate the consequences of a potential risk event that may
result in a cost escalation. For example, the environmental concern that occurs when
building on former industrial sites through the uncovering ground contaminants. The
subsequent risks of schedule delays and cost escalations can be approximated through the
use of simulations of various rehabilitation treatments (Hegazy and Ayed, 1998).

24
CHAPTER 2
Literature review into project risks and cost overrun

2.6.2 Artificial logic applications

Artificial logic applications can be developed to consistently emulate the way humans think
and judge by following accountability rules. Fuzzy sets and logic are used to capture
qualitative domain expert opinion for developing affordable project schedules and budgets.
Although this technique cannot substitute for deterministic scheduling and costing methods,
it does complement modelling methods in cases where vague and incomplete project
information is present. Blair (1999) explains that expert opinion can be used to model
construction simulations using fuzzy stochastic techniques. Applications include:
estimating project cost (Paek et al., 1993)
developing a risk-based cost and schedule (Blair, 1999)
developing the schedule (Ayyub and Haldar, 1984)
performing risk-based decision making (Blair et al., 2000)

The use of fuzzy theory is particularly suited to construction issues where there is a severe
lack of realistic historical data (Hegazy and Ayed, 1998)

2.7 Assessment of probabilities and consequences


There has been a considerable amount of research and published material, on the meaning of
probability. Schafer (1976) defines two types of probability. Firstly, aleatoric probability,
relates to the outcome of an intrinsically uncertain situation (from the Latin alea, meaning
dice). Secondly, epistemic probability relates to a measure in belief in a proposition, or more
generally to a lack of complete knowledge. This is also referred to as the Dempster Shafer
Theory of Evidence (Shafer, 1976).

In general, epistemic risk constitutes the biggest problem in project planning and risk
prediction, where there is little historical evidence on which to base predictions (del Cano
and de la Cruz, 2002). The definitions of probability and risk have implications for how
these are perceived by project owners. Key work on the perception of uncertainty has been
carried out some time ago by Tversky and Kahnernan (1981). Around the same time,
MacCrimmon and Wehrung (1986) describe a study of managers' attitudes to taking risks
and how they choose options and risk action/outcome benefits in standardised risk situations.

Fellows et al. (2002) point out that a decision will have a range of possible outcomes
between quite well-defined extremes. They point out that it is not likely that the probability
of the occurrence of each possible outcome is equal everywhere within the range. The
probabilities may be represented as a graph of probability against possible outcomes and is
referred to as a probability density, with the normal distribution curve being the most
common example (Fellows et al., 2002).

In a perfect risk scenario, an objective assessment of probabilities and consequences can be


exactly determined (Kumamoto and Henley, 1996). Therefore, the best method of
establishing associated probabilities and consequences is through the use of representative
data. However, this is difficult in the construction industry because each project is unique in
form, function and the resources that build it.

25
Risk factors leading to cost overrun in the delivery of highway construction projects.

Elkington and Smallman (2002) make the point that, in approaching risk management,
managers have the luxury when working in the world of financial risk of vast statistical
databases to instruct probability. Whereas project managers outside of finance, who face
operational risks constantly need to decide the chances of an identified risk occurring. Some
use historical project data, and others use unwritten past experience. But in many cases, the
likelihood of a risk occurring is derived by means of an educated guess (Elkington and
Smallman, 2002).

A quantitative approach to construction risk assessment is hard to document because these


methods rely on construction data that is often difficult to obtain because each project is
unique. Data that is based on past projects may contain significant uncertainty when applied
to current problems.

Databases, either formal or informal, usually exist for specific domains, such as in assessing
risk in construction projects. Many of these are commercial-in-confidence, particularly in
highly competitive industries such as the oil industry. Two early examples of established
databases of project risks are Niwa and Okuma (1982). They describe a well-structured
database in use at Hitachi, and the value of the database for knowledge transfer of project
risk. Ashley (1987) describes a number of examples of expert systems that are based on risk
knowledge.

In-house historical databases are probably the best source of data to assess risk event
probability or consequence. However, in many cases these databases are inadequate or
disjointed, unavailable, or supplemented with personal knowledge (Al-Bahar and Crandell,
1990). These databases are company and/or project specific and are not usually able to be
uniformly applied across new projects.

While industryaverage data exists for the some construction operation variables, (say for
excavators), a firms own historic database can provide improved accuracy in forecasting
production risk and hence costs. Such databases can be developed by project owners, as well
as contactors, and can be used for future projects and comparison with industry averages.
However, many organisations do not maintain such detailed databases. For example, Iseley
and Gokhale (2003) provide an example where the equipment selected for the land clearing
and grubbing activities for a project was based on only the estimators own experience.

Production estimating is extremely effective when experienced estimators are responsible for
making the necessary productivity risk decisions. However, more detailed databases would
permit decisions to be made at a lower level by less experienced people without sacrificing
accuracy (Iseley and Gokhale 2003). This would allow the more experienced estimators to
use their time more effectively. In addition, more detailed databases provide better
information to substantiate the impact if a change in conditions should develop (Iseley and
Gokhale 2003).

When available, government-collated data is generally overly broad and may be used to
gauge or forecast overall trends. For example, the number of accidents per thousand hours of
work can be broken down by specific industry, and yet, this data is difficult to apply to
specific construction project risk probabilities as the data usually considers all types of
construction, from residential, road-building, heavy-civil, to large commercial developments.

26
CHAPTER 2
Literature review into project risks and cost overrun

Databases for construction projects may be available from in-house governmental agencies,
such as the Australian Bureau of Statistics (ABS), from industry sources or from published
academic literature.

2.8 Elicitation of risk


In risk assessment, probability theory is used to represent engineering uncertainties.
However, uncertainty is a vague concept as it refers to events that occur with periodic
frequency, such as demands on equipment and resources, as well existing but unknown
conditions, such as poor ground foundations (Mak and Picken, 2000).

By contrast, probability is a precise concept having a mathematical concept with an explicit


definition. The mathematics of probability theory is used to represent uncertainties, despite
the fact that such uncertainties take many forms. Uncertainty versus the specificity of
probability is particularly significant in the discipline of project management where
subjective methods are better suited for the assessment of risks. However, this technique
requires an application of personal knowledge or documented research and, in certain
situations, the application of standard probability distributions may represent the appropriate
risk assessment (del Cano and de la Cruz, 2002).

Deriving probability values for different cost elements of an estimate was first suggested by
Hertz (1964) as a means of reducing uncertainty. It was recommended as an integral part of
project appraisal by the World Bank, over 30 years ago (Reutlinger, 1970). With this method
it is possible to quantify the range of a particular cost estimate. Probability analysis, in the
context of cost estimating, entails assigning estimated values of each cost element and
analysing the risk associated. The individual probability distribution of each cost component
is then aggregated so as to derive the overall probability distribution of the total cost.

2.8.1 Expert elicitation

While risk assessments have a place in risk decision-making, it is increasingly difficult to


argue that this should be the sole basis. Freudenburg and Pastor (1992) have found risk
analysts guilty of evoking the tyranny of illusionary precision, by conveying an impression
of a higher level of accuracy and confidence than is actually warranted. In fact, there is a
growing body of evidence which suggests that risk experts may be subject to the same
foibles and judgemental errors that affect the general public (Freudenburg, 1988). Such
errors can include:
failure to see the way systems are interrelated
failure to predict the cumulative impact of individually minor problem
overlooking non-technical aspects of a technological system or those aspects outside
their area of expertise
insufficient attention paid to the sensitivity of assumptions and the problems of small
sample size
conscious decisions to simplify analysis by excluding low-probability events from
consideration
over-confidence in the reliability of analyses.

27
Risk factors leading to cost overrun in the delivery of highway construction projects.

Expert elicitation is a formal way of obtaining information or answers to specific questions


about certain issues where the information is highly subjective. The process is used by quite
a number of disciplines. The expert elicitation process consists of the following steps
(Ayyub, 1997):
1. selection of issues
2. selection of experts
3. issue familiarisation for expert
4. training of experts
5. elicitation of experts about the issues
6. aggregation and presentation of results
7. discussion and revision by expert
8. revision of results and reporting.

Expert elicitation is a valid method to develop risk assessments and is the formal process of
obtaining assessment probabilities and consequences when the information is subjective. The
expert elicitation process needs to be systematically structured and can use a participative
method such as Delphi or modified Delphi techniques to quantify probabilities and
consequences (del Cano and de la Cruz, 2002). Personnel with a risk-analysis background
that are familiar with the construction, design, operation, and maintenance of projects need
to define these issues in the form of specific questions.

2.8.2 Expert elicitation using the Delphi method

The Delphi technique (Linstone and Turoff, 1975) can be used to anonymously elicit the
opinions of experts concerning risks. It provides feedback to experts in the form of
distributions of their opinions and reasons. They are then asked to revise their opinions in
light of the information contained in the feedback. This sequence of questionnaire and
revision is repeated until no further significant opinion changes are expected. The technique
is designed to protect anonymity of the experts opinions and reasoning. Sackman (1972)
points out some shortcomings of the Delphi and these can be characterised as:
The information and questions provided to experts need to be carefully reviewed to
ensure objectivity
It is difficult to summarise and present to the group a common evaluation scale that is
interpreted uniformly by the experts
The benefit of experts participating in active dialogue is missed
It can be difficult and time consuming to explore disagreements between experts.

For the rapidly paced project management world, any expert elicitation method needs to be
efficient because project managers are continually confronted with not having enough time
for all the activities required of them (Laufer, 1996).

2.8.3 Elicitation using semi-structured interviews

The purpose of semi-structured interviews is to extend the scope of a study to a wider range
of exponents and to test the conclusions drawn from exploratory work. This can be achieved
by developing an outline list of questions developed for consideration by the interviewee
with key questions about the issues being researched. The technique of personal construct

28
CHAPTER 2
Literature review into project risks and cost overrun

elicitation, as described by Stewart and Stewart (1981), has been used in project
management technique assessment. Bannister and Fransella (1989) define a personal
construct as being a bipolar distinction, or scale, which is used when contrasting different
people, objects or situations.
Semi-structured interviews can provide opportunity to evaluate tacit knowledge based on the
experience of individual practitioners. Koskinen, Pihlanto and Vanharanta (2002) explain
tacit knowledge as that which expresses itself in human actions in the form of evaluations,
attitudes, points of view, commitments and motivation

2.8.4 Nominal group technique

Originally developed as an organisational planning technique by Delbecq, Van de Ven and


Gustafson in 1971, the nominal group technique is a consensus planning tool that helps
prioritise issues (Delbecq et al., 1975). In the nominal group technique, participants are
brought together for a discussion session led by a moderator. After the topic has been
presented to session participants and they have had an opportunity to ask questions or briefly
discuss the scope of the topic, they are asked to take a few minutes to think about and write
down their responses.

There are three main advantages of nominal group technique:


1. Voting is anonymous
2. There are opportunities for equal participation of group members
3. Distractions in the form of communication noise that can be inherent in other
group methods are minimised.

Some disadvantages of nominal group technique include:


1. Opinions may not converge in the voting process
2. Cross-fertilization of ideas may be constrained
3. The process may appear to be too mechanical.

2.9 Organisational risk culture

When considering risk in terms of monetary outcome, there are three general attitudes
toward risk (Kumamoto and Henley 1996). These are:
risk-aversive
risk-neutral
risk-seeking.

These attitudes are shown in Figure 2.2.

29
Risk factors leading to cost overrun in the delivery of highway construction projects.

This figure is not available online.


Please consult the hardcopy thesis
available from the QUT Library

Source: Kumamoto and Henley (1996)


Figure 2.2: Risk-aversive, risk-neutral and risk-seeking

An example of this can be seen in say an individuals investment practice. Some investors
prefer to buy stock of small companies in the high technology sector. Typically this is
considered a risk-seeking stock choice because there is a chance of losing an initial
investment but the potential monetary gain can be quite substantial. Economists agree that
those who take over or bear the risk have to be rewarded for doing so. Begg et al., (2000)
comment that many economic activities consist of:
the more-risk-averse bribing the less-risk-averse to take over their risks.

A very early study by Reutlinger (1970) reports on the results of the attitude to risk taking of
US executives in relation to corporate investment decisions. It showed that, although there
were widely different attitudes towards risk taking, even within the same corporation, there
was a tendency for most of those surveyed to be conservative when assessing risk.

In the project management context, it is generally reported that large established companies
are risk-aversive, governmental ventures are risk-neutral to risk-aversive, and smaller newer
companies are risk-seekers. Therefore, risk analyses will account for the acceptability of risk
according to an organisation's established risk attitudes (Kumamoto and Henley, 1996).

Paul and Gutierrez (2005) point out that when a contractor is risk neutral, then the risk
premium will not vary across contract type. They assert that, in general, a contractor will
tend to be risk neutral if the contract is small relative to their total volume of business. In
such cases, risk neutral decisions will maximise the contractors profit. However, if a
contractor is risk averse, then he or she will tend to factor in a higher risk premium in a fixed
price contract since more financial risk needs to be borne than in say cost-plus contracts
(Paul and Gutierrez, 2005).

2.10 Project risk management


Thompson and Perry (1992) show evidence from projects worldwide that project risks are
not being adequately dealt with. Complexities of the project, location, type of contract,
familiarity with the work and breakdown in communication are some of the significant

30
CHAPTER 2
Literature review into project risks and cost overrun

contributors to risks in construction projects (Ahmed et al. 1999). Baker et al. (1999) report
that in a survey of over 100 companies in both the oil and construction industries, companies
commonly respond to assessed risk, however the construction industry concentrates almost
exclusively on the reduction of financial risk and less on managing technical risk.

Construction is an industry associated with many risks. Sampling of the most prevalent risk
will convince any causal observer that the construction process is risky. The literature has
several case studies of construction risk management from general building construction
(Baker et al., 1995), offshore construction (Curole, 1995), or highway construction (Wang
and Chou, 2003). In the field of project management, risk management is a recognised
practice to help clients deliver projects on schedule and within cost (Project Management
Institute, 2000). However, the risk management performed in the construction industry has
traditionally been through the use of gut feel or a series of rules-of-thumb (Al-Bahar and
Crandall, 1990). This may be due to a lack of understanding of the benefits and cost, the
perceived difficulties, or cumbersome processes in developing risk management (McKim,
1992; Ward, 1999). In discussing the US construction industry, Kangari (1991:46) supports
this notion by pointing out that:
Most managers rely primarily on their judgements, rules of thumb, and expertise and
that the conventional algorithmic models developed for risk analysis are not generally
accepted by management for decision making under uncertainty.

As well, Dalchar (1993) in Williams (1999: 273) claims that:


Contemporary project management practice is characterised by late delivery,
exceeded budgets, reduced functionality and questioned quality. As the complexity and
scale of attempted projects increase, then the ability to bring these projects to a
successful completion dramatically decreases.

Since the early 1990s, a variety of risk management processes have been written about.
These include Al-Bahar and Crandall (1990), Del Cano (1992), BSI (1999), NASA
(Rosenberg et al., 1999), and the US Department of Transportation (FDOT, 2003). De Cano
and de la Cruz (2002) have described the most noteworthy, comprehensive, and sound
project risk management processes. These include:

PRAM this was the first highly comprehensive process developed by a large team,
including both practitioners and academics (Simon et al., 1997; Chapman and Ward,
1997)
RAMP this risk management process has characteristics similar to those of the
PRAM process in scope, structure, and conception but importantly has been
conceived for the construction environment. RAMP has been developed jointly by
the Institute of Actuaries and the Institution of Civil Engineers to assess all kinds of
risks and uncertainties so that they can be identified, evaluated, reduced and
controlled (ICE, 1998).

The Project Management Institute (2000) points out that both PRAM and RAMP tend to
reflect more a British European way of performing project risk management.
PUMA (Project Uncertainty Management) This is an integrated methodology
based on a hierarchically structured, flexible, and generic project risk management

31
Risk factors leading to cost overrun in the delivery of highway construction projects.

process for construction projects from the point of view of the owner for individual
projects (del Cano and de la Cruz, 2002).

Project construction risk can have physical or capability related aspects (Zack, 1997).
Physical risks are those events that prevent one from completing the project or increase the
costs and schedule such as acts of God, weather, impracticability, or other things that are
beyond the control of the project team. Capability related risks are those that interfere with
performing the work but management has a choice in minimising the risk such as poor
quality, safety and equipment selection. Project Management Institute (2000) classifies risks
as:
external (uncontrollable)
internal (controllable).

Project size can be a major cause of risk, as can other factors such as:
the complexity of the project
the speed of construction
location of the project
degree of project unfamiliarity.

Edwards (1995), Smith and Bohn (1999), and Kim and Bajaja (2000) list potential
construction risks. Table 2.4 details some of the most common risk sources in construction
projects.

Risk source Description of risk source


Cost Estimate is uncertain because it is based on past and projected costs
Schedule Schedule is uncertain because it is based on past and predicted performance
Labour Labour strength and productivity uncertainties
Project
Uncertain experience levels, team cohesiveness and composition
management
Safety Potential for accidents and consequences of injuries or higher costs
Change orders Potential increased cost, schedule delay, and poor technical performance
Unforeseen Undefined underground or hidden site conditions that can cause cost and schedule
Conditions growth
Environmental Regulatory approvals and mitigation of environmental concerns may cause time
concerns delay or cost escalation
Inflation Potential for material and labour price increases
Weather Delay causing costs and technical non-performance from adverse weather
Construction
Level of difficulty increases the potential for cost and schedule growth
Complexity
Fire Probability of fire hazard from work operations, vandalism or lightning
Non-performance from vendors, sub-contractors or suppliers that can cause
Suppliers
impacts to cost and schedule
Property loss Potential for loss due to flood, fire, theft, sabotage or vandalism
Design Incomplete or lack of design elements that considers construction aspects
Quality Potential for consequence of poor quality and technical non-performance
Political Potential loss of support leading to less opportunity to acquire new projects

Table 2.4: Sources of common project construction risks

32
CHAPTER 2
Literature review into project risks and cost overrun

One of the main sources of construction risk derives from the site conditions in which
projects are planned to be constructed. The next section looks at project site conditions as
sources of risks.

2.11 Project site condition risks


A major risk in any civil engineering project is that the construction may encounter physical
obstructions or conditions on the project site which were unexpected and unforeseeable at
the time of making the decision to build the project and which may delay work or cause
increased costs. Highway construction projects, for example are characterised by their linear
complexity and they have intrinsic design parameters such as minimum pavement subgrade
strength conditions that need to be satisfied throughout the whole of their project footprints.
Ground conditions may be substantially harder or softer than anticipated and sub-surface
water may be discovered where none was foreseen. In bridge structures, sound foundations
or rock may be found only at substantially lower levels that anticipated in foundation designs
(Queensland Department of Main Roads, 2000).

Studies from around the world have consistently highlighted the recurring frequency of
claims for unforeseen ground conditions. In Canada, Revay (1992) reports that inadequate
site and/or soil investigations and unexpected ground conditions were among the six most
frequent causes of claims. A study in Hong Kong by Kumaraswamy (1997) aimed at
identifying root causes of claims for extension of time and extra payments on construction
projects, found that unforeseen ground conditions was ranked fourth in the top 10 common
categories of construction claims. In the US, studies by Halligan et al. (1987) on Federal
Highway Administration funded state highway construction projects indicate that claims for
ground conditions accounted for approximately 35% of the total dollar amount paid to
contractors for claims.

The traditional position on site information has been that there is no obligation on the owner
to provide the contractor with any information on the nature of the site and sub-soil
conditions (Mak and Picken, 2000). It is therefore the responsibility of the contractor to
investigate these matters and to be satisfied with the feasibility of constructing the works on
the designated site. Even if there is relevant information in the owners possession, there is
no obligation in English law to disclose it to a contractor. There are a number of civil law
judgements which establish precedence in this area:
1. Thorn v. London Corporation (1876) 1 App Case 120
2. Dillingham Construction v. Downs (1972) NSWLR 49
3. Morrison-Knudsen International v. The Commonwealth of Australia (1972)
13 BLR 114.

On the other hand, some jurisdictions impose such an obligation only in special
circumstances. For example, US public project owners have an obligation to supply site
information to the contractor where the circumstances are such that the contractor cannot
otherwise obtain it (Glower, 1990; Smith, 1995). If the owner decides to provide such
information and the information is incorrect, then the contractor may have remedies against
the owner for breach of warranty, misrepresentation or negligent misstatement.

33
Risk factors leading to cost overrun in the delivery of highway construction projects.

In Great Britain, legislation gives the contractor some protection against exclusion of
liability for inaccurate information even if it was not provided fraudulently such as that of
Section 3 of the Misrepresentations Act 1967 (as amended by Section 3 of the Unfair
Contract Terms Act 1977). However, because of the uncertainties of geotechnical
engineering it has been suggested that such riders would be effective in excluding the normal
consequences of misrepresentation, provided that the owner has not been careless or
fraudulent (Wallace, 1995).

In judging the physical site conditions, the contractor is assumed to have taken into account:
the site information
publicly available information referred to in the site information
information obtainable from a visual inspection of the site
other information which an experienced contractor could reasonably be expected to
have or to obtain.

Ndekugri and McDonnell (1999) point out that it is commercially impracticable for tenderers
to carry out full geotechnical investigations even if there are no time constraints in the
particular bid. In general, a contractors entitlement operates on the basis of the test of
foresee ability. If the physical conditions or obstructions are not foreseeable by an
experienced contractor then the contractor may claim. Jones (1996) notes that there has been
no widespread acceptance of foresee-ability as a general philosophy of risk allocation, but
there has been a strong international acceptance of alternative philosophies such as those put
forward by Abrahamson (1984). By contrast, Eggleston (1996) suggests that a contractor can
be compensated for time and money if the physical conditions are such that an experienced
contractor would have decided at the time of entering into the contract that they had such a
small chance of occurring that it would have been unreasonable to allow for them. Shadbolt
(1990) believes that this is as it should be because it is reasonable for an owner to expect a
contractor to exercise their skills and judgement and for the owner to rely on them in that
respect.

ASCE (1989), Smith (1995) and OReilly (1995) all propose that risk allocation should be
motivational and risks should be allocated to the party with the greatest opportunity to
influence the magnitude of the risk. With regard to ground condition, this is with the project
owner. It is their site and they can commission a thorough site investigation that will, within
limits, sensibly define the ground conditions and safeguard against the risks.

Attempts have been made in contracts to limit the contractors entitlements to make claims
on account of climatic/weather conditions. Climatic conditions on site have been removed
from some prominent contract provisions because it has always been difficult to assess
whether such conditions could or could not have been foreseen by an experienced contractor
(Seppalla, 1991). However, while the contractor may not claim for costs in such cases, a
claim for an extension of time for exceptionally adverse climatic conditions may be made
under the appropriate clause. In some standard contracts like the NEC, a contractor can claim
for weather conditions that occur, on average, less frequently than once in 10 years, but their
entitlement includes both costs and time.

34
CHAPTER 2
Literature review into project risks and cost overrun

2.12 Managing risks through procurement practices


All construction projects are, by their very nature, economically risky undertakings and so
projects let on the basis of competitive tenders can add to such risks. Smith (1995) talks
about a quantity surveyor writing over a century ago when Blake (1900) reported:
Responsibilities are sometimes thrown on the builder when estimating, by leaving to
his discretion some matters of doubtful yet ascertainable value; a matter which little
investigation on the part of those arranging the contract would free from any doubt or
uncertainty whatever, and thus enable the competing builders to price it at fair value
instead of allowing a good margin to cover such contingency. Every point on which
there is any doubt, and every matter as to which there may be the slightest
misunderstanding during the execution of the contract should, in justice to all parties,
be thoroughly threshed out before the contract is signed.

Construction industry studies, such as by Latham (1994) and Egan (1998), echo an
underlying lament that can be traced back many decades to the Simon Report in 1944, the
Emerson Report in 1962, the Banwell Report in 1964 and the Tavistock Report in 1966.
These all point out many problems arising from poorly structured project procurement
systems.

The procurement of constructed facilities is a process which involves many complex and
interrelated steps. Along the way there are questions of value for money, probity and fitness
for purpose. Over more than three centuries, the traditional procurement process has been
developed that focuses on clarity, separation of phases and a transparent independent bidding
stage. Unfortunately, there are some serious drawbacks. For example, the process can be
inefficient and take a long time and often sets up opposing stances between participants
(Sidwell et al., 2002). However, the traditional process does have some notable
characteristics which continue to hold relevance in todays climate. These characteristics are
illustrated in the RIBA Plan for Work (RIBA, 1984) which emphasises the step by step
functional contribution and progressive definition, the output from each stage being the input
into the subsequent stage. The clarity of this process is particularly attractive to clients who
need to demonstrate probity.

Project procurement processes in the Australian construction industry are largely derived
from the United Kingdom where the traditional process which separates design and
construction, and awards the construction to the lowest bidder, has been developed over the
centuries, particularly since the industrial revolution. The traditional approach to project
management is shown in Figure 2.3 below.

35
Risk factors leading to cost overrun in the delivery of highway construction projects.

This figure is not available online.


Please consult the hardcopy thesis
available from the QUT Library

Source: Queensland Department of Main Roads (2000).

Figure 2.3: Traditional project delivery model

2.13 Risk distribution in project procurement


A most important aspect of risk for either client or a contractor is: Who is liable for the risk,
and who, thus, has the motivation to avoid or vitiate the risk? (Curtis et al., 1991).
Therefore, the contract is at the heart of any analysis of risk. A prime function of any
contract is to identify, assess and allocate risk (NEDO, 1982). Ownership of a risk implies
responsibility for the management of that risk as well as responsibility for bearing its
consequences. Chapman and Ward (1997), however, point out that in certain circumstances
it may be important to distinguish between responsibility for managing a risk and
responsibility for bearing the consequences of the risk. In particular, they assert that it may
be desirable to allocate these responsibilities to different parties, recognising which party is
best able to bear the consequences of that risk. Thus, while one party, perhaps a contractor,
may be best placed to manage a source of risk, it may not be appropriate or desirable for that
party to bear all the associated financial risk (Chapman and Ward, 1997).

Wang and Chou (2003) assert that risk management needs to be made more efficient and
effective so all parties can understand:
their respective responsibilities
risk event conditions
risk preferences
risk management capabilities.

They also point out that if a project contractor has different perceptions of risk allocation to
those of the client or even a lack of clear understanding of risk management, then the
contractor will inappropriately manage the risks in construction projects by assuming that the
risk events or consequences are not the contractors responsibilities.

On the other hand, Carmichael (2000) argues that there may be an overall saving to the
project client by accepting some risk. Generally client expect that contractors bear some risk,

36
CHAPTER 2
Literature review into project risks and cost overrun

though some take this to an extreme and, through contract condition mechanisms, require
contractors to bear essentially all risks.

Contracts can be considered as having three main functions (Barnes, 1981):


1. Work transfer defines the work which one party will do for the other
2. Risk transfer defines how the risks inherent in doing the work will be allocated
between the two parties
3. Motive transfer implants motives in the contractor party, which, ideally, should
match those of the client party.

There is a basic conflict between the risk and motive provisions in most contracts. If a risk is
placed on the contractor, they have a strong motive to minimise that risk, whereas the client
has no such motive.

Many standard forms of contract hardly mention risk and frequently contracts are not clear
on who bears the risk. Robinson (1987) claims this as the strength of design-and-build
contracts
A survey by the Victorian Government, Australia (Victorian Government, 1999) provides
some interesting insights into the strategic decision making by various parties in the
allocation of risk in public projects. A factor that tends to defeat the efficient allocation of
risk in construction contracts is that project owners may have significantly more power at the
contract formation stage than does the contractor. This power can be derived from a number
of sources, such as:
the competitive bidding process, with unreasonable time pressures and often
involving a large number of bidders
in-house risk management and legal expertise which greatly exceeds that of the
contractor
a general reluctance by some contractors to price adequately for the risks that they
are being required to accept.

The joint use of formalised risk management processes can provide all parties with a way out
of this bind by providing a revised contract form of potentially greater benefit to both the
contractor and owner. However, Tuohey (2002) points out that most contracts are drafted
unilaterally by the owner and risks are allocated without the benefit of a risk management
process. Tuohey (2002) also reports that, in some Australian Government Agencies, it is now
a common requirement for the tenderer to include draft risk management plans for the entire
project. He adds that it is easy to believe that in the near future, risk management will
become a necessary and formal process in the execution of all projects. More projects will be
likely to succeed as a result.

Construction contracts are the written agreements signed by the contracting parties which
bind them and also define relationships and obligations. In any particular contract, the
project owners goals can best be achieved by selecting the contract type that will most
effectively motivate the contractor to the desired end and is also dependent on completeness
of information for the bidder(s) at tender time and the extent the owner wishes to take
specific risk (Zaghloul and Hartman, 2003). Given the opportunity, an owner should favour

37
Risk factors leading to cost overrun in the delivery of highway construction projects.

efficient allocation of risk between parties to a project that simultaneously reduces risk and
improves performance.

The contract terms define how such risk is distributed between the owner and the contractor.
In establishing the context of a contract which is composed of specifications and clauses,
both owners and contractors strive to understand each others goals and capabilities, and
risks should be allocated accordingly (Akinci and Fischer, 1998). However, a comprehensive
empirical study about the allocation of risk in contract clauses conducted by Ibbs and Ashley
(1987) concluded that on an aggregate basis, owners are at risk 11% of the time, contractors
are at risk 46% of the time, and both parties are at risk 43% of the time. These results
confirm that owners use contracts to minimise their risk exposure.

Liabilities and responsibilities of each contracting party are allocated through the conditions
of contract. It has been postulated that inappropriate and unclear risk allocation among the
contracting parties generates avoidable construction claims and disputes (McGowan, 1992;
Fisk, 1997; Kumaraswamy, 1997). One of the main areas where risk management can be
applied is in developing clearer and more appropriate conditions of contract that provides
clearer definition of the risks and hence lead to their proper allocation and management
during the construction process. However, contract language alone is not sufficient to clearly
specify risk apportionment between the contracting parties as contract clauses can be
interpreted in different ways by different parties (Hartman et al., 1997).

Zaghloul and Hartman (2003) report that appropriate risk allocation is a significant
contributor to low transaction costs in specific projects and is a vital issue in the success of
the contracting process. On the other hand, Gransberg and Ellicot (1997) point out that, in an
ownercontractor relationship at least, a common aim of owners appears to be to avoid risk
as far as possible by allocating as many risks as it can to the contractor. Carmichael (2000)
notes that a general belief is that the owner should, wherever possible, define the work as
carefully as possible beforehand, irrespective of the type of contract used so as to reduce the
risks to all parties.

The appropriate contracting method and the contract documents for any construction project
depend on the nature of the project, but an appropriate contracting method coupled with
clear and equitable contract documents do not by themselves ensure project success. This is
especially the case where parties work together in the face of uncertainty and complexity,
whilst having diverse interests and conflicting agendas. The attitudes of the contracting
parties and the co-operative relationships among the project participants are important for
successful project delivery.

The theme of risk allocation in procurement methods is seen as a critical issue in the
selection of construction contracts. Latham (1994) points out that clients often prematurely
select procurement methods without consideration of the appropriate division of risks. The
risk involved could be physical in nature but is more likely to be mercantile (Langford et al.,
2003). This supports Taylors (1993) argument that consideration of risks at the procurement
stage could save money and time and also improve quality. As well, Smith (1995a) has
confirmed that inappropriate risk management can also lead to higher costs for the client.
According to Hibbert et al. (1990), procurement choice advice is often made to clients even
without hard factual evidence of judging the successes of previous procurement decisions.

38
CHAPTER 2
Literature review into project risks and cost overrun

2.13.1 Risk allocation through standard-form contracts

Any construction project involves risk and there is no possibility of eliminating that risk. All
that can be done is to regulate the risk allocated and then to properly manage the risk. This is
usually done through the language of the construction contract.

Not only are procurement issues a factor influencing risk, but, as Uff and Odams (1995)
noted, contractual risks are seldom analysed and quantified. Hence it is important that clients
select appropriate procurement routes and contract strategies which fit the clients ambitions
for a project. Invariably, this will include factors which will deliver value for money
(Langford et al., 2003).

Kozek and Hebberd (1998) point out that decisions regarding risk sharing or risk shifting are
made within the context of a project owners contracting policy. Hughes (1997) asserts that
the purpose behind using standard-form contracts is to allocate risks fairly between the
parties
Zaghloul and Hartman (2003) define one way in which the contracting parties can attempt to
address the right responsibilities for risk by dealing directly with the issue of legal liability
arising from certain contract clauses such as disclaimer (exculpatory) clauses. Such clauses
attempt to transfer one partys risk (which may be legal liability) to another by contractual
terms (Hartman, 2000). The use of disclaimer clauses to allocate risk has been identified by
studies and industry practice as a key reason for increasing the overall cost of a project
(Khan, 1998; Zack, 1996).

When a risk is shifted to a contractor and the contractor has no means by which to control
the occurrence or outcome of the risk, the contractor either insures against it or adds a
contingency to the bid price (Jergeas and Hartman, 1994). A study conducted by de
Neufville and King (1991) in the US found that contractors add significant premiums, in the
order of 3%, to their risks when they have a low need for work or projects that have high
risks. Zaghloul and Hartman (2003) state that recent studies of Canadian contracts indicate
that the use of disclaimer clauses can carry a premium of between 8 and 20%, depending on
whether business conditions were favourable low need for work, fair contract
administration, suitable contract type, and completeness of design works; or adverse high
need for work, high technical complexity, unfair contract administration, and incomplete
design works.

2.14 Payment methods for contract risks


Different project procurement types offer different incentives to the contractor to influence
the cost, delivery time and performance of contracts. On any given project there may be a
whole range of contract payment types between owner, contractor, consultant, sub-
contractors, suppliers etc. (Carmichael, 2000). The choice of any given procurement
approach to deliver a project should only be made after a detailed and carefully considered
risk analysis that considers the objectives, opportunities and risks involved in successfully
delivering the project.

39
Risk factors leading to cost overrun in the delivery of highway construction projects.

A number of possible payment schemes can be used within a contract to manage risk. A
good overall summary of the main types of payment scheme is given in In't Veld and Peeters
(1989). They describe cost-reimbursable schemes such as:
cost plus percentage
cost plus fixed
cost plus incentive
schemes that contain both fixed price and fixed price with incentive provisions.

Carmichael (2000) describes two contract groups that are generally classified according to
the form the consideration from the project owner takes:
1. Where the consideration is either a stipulated sum of money covering all the work or
is a set of monetary rates covering the components of the work, the contracts are
referred to as fixed-price contracts
2. Where the contractor is paid the cost of the work together with an additional amount
for the use of the contractors services, the contracts are referred to as prime-cost
contracts.

It is also common to have contracts with a combination of fixed-price and prime-cost


components.

2.15 Delivery processes for projects


Delivery methods for capital construction projects are mainly traditional processes that have
evolved from history and the industrial revolution, where specialisation of professional
organisations was the key trend (Pakkala, 2002). This means that architects, engineers,
specialty contractors, and the industry have adopted a segmented rather than an integrated
type of process. Subsequently, laws have sometimes been changed and adapted to reflect this
movement.

The polarisation of construction from design in the construction industry may have arisen
from expected efficiencies in specialisation and the perceived need for independent design
and oversight. But the resulting fragmentation and adversarial contractual cultures have now
been seen by many to be an unfortunate departure from the single-point procurement
solutions provided by master builders in previous centuries.

Attempts to redress these imbalances have led to experimentation with a proliferation of


procurement options. These include various approaches to:
the division of a big construction project into work packages
the allocation of design, construction, supervision and management functions
the distribution of risks as reflected in various conditions of contract
the methods of payment
the selection of project teams/sub-teams.

Research into procurement best practice has identified a need for wider consideration of
what constitutes project deliverables (Rowlinson and McDermott, 1999; Walker and
Hampson, 2002). The construction industry is usually characterised by its complexities,

40
CHAPTER 2
Literature review into project risks and cost overrun

reluctance to change and resistance to innovations. The increasingly demanding present-day


scenarios such as scarcity of resources, growing competition and costbenefit/value-for-
money issues require a clear understanding of what works best and how it can be applied to
implement a philosophy of continuous change and improvement in organisations
(Palaneeswaran and Kumarasamy, 2000).

Not until more recent years has there been interest in seeking alternative methods, even
though these so-called alternative methods were used in the past procurements of a number
of public sector projects. Below are terms applied to procurement types from Pakkala
(2002).

Design-Bid-Build (DBB Traditional Method): This system was developed during the
industrial revolution and resulted in the creation of specialised professional movements of
architects, contractors and engineers. This approach has been the standard choice of project
delivery systems for many years. In this model, the owner/client procures the services of a
design consultant to develop the scope of the project and complete design documents which
are then considered as legal documents for use in selecting a contractor who builds in
accordance to the specifications developed by the design team. The owner maintains most of
the risks. Typically in a public organisation, the proposal is in an open competition for a low
price. The contractor that wins the award is legally bound to produce the project at a certain
price, schedule, and minimum level of standard care. After completion of the project, the
owner is responsible for operations and maintenance of the project. The owner is also
responsible for all the financing needs.

Design-Build (DB): This systems heritage dates back to the construction of the pyramids,
when it was referred to as the master builder. Design-build is simply a project delivery
method in which the owner/client selects an organisation that will complete both the design
and construction under one agreement. Upon completion, the owner is then responsible for
all the financing aspects.

Design-Build-Operate-Maintain (DBOM): This is a project delivery mechanism in which the


owner/client selects an organisation that will complete the design, construction, maintenance
and an agreed-upon period of operational parameters under one agreement. Upon
termination of the operational period, the owner is responsible for the operations and
maintenance of the project; unless the operations are continued under a separate procurement
method.

Design-Build-Finance-Operate (DBFO): This project delivery method is similar to DBOM,


except that the contractor is also responsible for financing the project. The contractor
assumes the risks of financing until the end of the contract period. The owner is then
responsible for operations and maintenance of the asset.

Build-Own-Operate Transfer (BOOT): This project delivery method is similar to DBFO,


except that there is an actual transfer of ownership. The contractor is responsible for the
design, construction, maintenance, operation and financing of the project. The contractor
assumes the risk of financing until the end of the contract period. Subsequently, the owner is
then responsible for the operations and maintenance of the asset.

41
Risk factors leading to cost overrun in the delivery of highway construction projects.

Construction Management (CM At Fee Agency): This is the process similar to DDB, the
traditional model, in which the owner/client is responsible for the design, bidding, and
construction of the project. However, the construction management organisation takes on the
responsibility for the administration and management, the constructability issues, day-to-day
activities, and also assumes an advisory role to the owner/client. The CM organisation has no
contractual obligations to the design and construction entities. Again, the owner is
responsible for operations and maintenance of the project as well as the financing aspects.

Construction Management At Risk Advisor (CM At Risk): In this scenario the


owner/client has one agreement with the construction manager, who then manages the
contracts with the design consultant and the general contractor. CM At Risk assumes many
of the risks of the project, which differentiates this model from CM-Agency and DBB, where
the owner maintains most of the risk. Again, the owner is responsible for operations and
maintenance of the project as well as the financing aspects.

Lump Sum: This is considered as a fixed-price agreement for the total work and products of a
given project. Sometimes this is also referred to as a fixed-price contract. Any changes to the
contract should be agreed upon by both parties, and they are usually described under change
orders.

Unit Price or Schedule of Rates: This refers to price considerations for specific aspects of
construction and materials. For example, the cost per unit is for physical work or products,
such as the price base for so many metres of guardrail etc.

Program Management (sometimes referred to as Project Management of Full Delivery):


This is considered as a construction entity that provides a comprehensive list of services to
an owner/client from the planning stage throughout the entire process. This can also include
maintenance and operations. This may be considered as the best alternative when in-house
expertise is lacking, staffing reductions are needed, and outsourcing issues are current.

Pure O & M (Operations & Maintenance): This is a delivery method in which the
owner/client secures both operations and maintenance for a project under one agreement
from a single provider, usually called the contractor. The owner is also responsible for
financing aspects.

2.16 The traditional method of project procurement


Pakkala (2002) writes that, in a global perspective, delivery of infrastructure services and
products for capital projects vary in practice from country to country. He reports on highway
infrastructure project delivery in Australia, Canada, England, New Zealand, Sweden and the
US and notes that all use a common practice for the main delivery model, known as the
traditional model, or Design-Bid-Build (DBB). This means that design/engineering services
are produced first, and then another procurement contract is tendered for the actual
construction or physical works, based upon the design/engineering portion of the contract.
Also, he reports that variations and a range of combinations of the traditional process, such
as parallelprime contracting, are not common practice now.

42
CHAPTER 2
Literature review into project risks and cost overrun

Pakkala (2002) also identifies that Great Britain is one country which deviates substantially
from this practice and uses the Design-Build (DB) models and the Design-Build-Finance-
Operate (DBFO) model (sometimes referred to as Public Private Partnerships or PPP), which
integrates the philosophy of integration and external financing for these processes. He also
notes that the DB model is beginning to be used more frequently for many types of
infrastructure projects, particularly in power plants, water works, bridges, rail, road and also
in some local authority infrastructure projects.

Langford et al. (2003) investigated construction costs in 11 similar motorway project parcels
in the UK between 1990 and 1995. Five of these projects were carried out by a traditional
design, tender, construct method. Five were undertaken by a procurement system by which
the contractor bid a lump sum for the work. One project was done as a DB project. The
results of their analysis indicate that, in road works, the construction costs per kilometre was
some 11% less expensive when lump sum contracts were used. Langford et al. (2003) also
reports that their research shows that lump sum projects are much more likely to be
completed within budget and require less management by the client organisation. They also
report that lump sum also delivers a more harmonious working relationship between the
client and contractor.

In the traditional contract, the majority of cost overrun is borne by the owner, whereas in
lump sum bids, the performance risk is shifted to the contractor. Langford et al. (2003) point
out that the pattern of risk sharing due to that of just chance (aleatoric factors) is unlikely to
be changed as both types of contract arrangements permit the usual range of claims for
unforeseen events. However, sharp differences may be seen in risk situations which may be
defined as epistemic (which relates to the knowledge base of those taking the risks). For
example, a contractor who perceives a particular item of work to be particularly high (or
low) risk will price that item accordingly since the contractor sees its knowledge base and
hence their ability to manage the risk as different from that of their competitors. For
example, a contractor considering the risk of delay and additional cost due to a highway
excavation through rock would include in their assessment any special knowledge of the
geology of the area; and consequently the risk of encountering rock.

Situation-dependent factors can determine which contract payment type or combination is


most suitable in any given project. In 1975, the Aqua Group expresses a particular
preference in that they believe that:
Fixed price should be the norm and it should rest with those advising the owner to
prove that some other form of paymentwould be in the best interest of the owner.

Carmichael (2000) states that there is an increasing transfer of financial risk from the
contractor to the owner as the contract type moves from fixed-price to prime-cost contracts.
As the owner takes more and more risk, it is expected that the contract price would decrease.

De Neufville and King (1991) identify two ways of compensating for risk when developing a
bid. One is to develop a standard cost estimate not considering risk and varying the mark-up
depending on the risk. The second method is to develop a cost estimate that adjusts
productivity factors or adds contingency based on the risk of each item being estimated and
then apply a standard mark-up to this risk-compensated estimate. They report that, in
practice, most contractors used the latter method. With regard to contract type, a contractor

43
Risk factors leading to cost overrun in the delivery of highway construction projects.

experienced in undertaking contracts of a similar type would seem to require less risk
premium, because the contractor is likely to have greater confidence in being able to
complete the contract in accordance with the clients brief.

In respect of size of contract, Hillebrandt and Cannon (1990) point out that risks, including
errors by the company itself, technical risks, financial risks of the project and onerous
contract conditions, bear little relation to the size of contract and so it is difficult to put a
percentage on the mark-up for them. They also state that, in general, a company that has a
large number of smaller projects is likely to be subject to less risk overall than a company of
similar size with a few large contracts.

2.17 Improving project delivery methods for risk


A significant volume of literature discusses possible options for improving contracting
methods and better risk allocation processes. Some studies present new ways of doing
business such as partnering/alliances, risk sharing/reward systems, incentive-based contracts
and others. However, Zaghloul and Hartman (2003) point out that those new delivery
strategies between project owners and contractors are still founded largely on the self-
interest of each participant. Motivation for performance under these strategies has focused
largely on the retribution for non-performance and in most cases the relationships of the
contracting parties are still defensive, although, in some cases, adversarial. The atmosphere
created by such relationships has not been conducive to innovation or co-operation between
parties (Hartman, 2002).

Palaneeswaran and Kumaraswamy (2000) report that few public clients venture to adopt
some sort of innovative measures in their project delivery methods, other than limited trials
in pilot or experimental projects.

Current trends indicate an industry-wide acknowledgement that many existing procurement


practices lead to inefficiencies and inequities and that this can result in compromised project
outcomes. In responding to this need in Australia, government and industry are working
together to develop innovative procurement methods with a view to enhancing project
outcomes. Balanced with this, however, is the need for project delivery methods to meet the
highest standards of probity and public sector tendering requirements.

Zaghloul and Hartman (2003) surveys more than 300 respondents in the Canadian and US
construction industry. They report that, to reach a better risk allocation process, a trust
relationship between contracting parties needs to exist first, and that this can be achieved
through the following stages:
a clear understanding of the risks being borne by each party and who owns or who
can manage the risk
more time and effort in the front end of a project and sufficient expertise to manage
or mitigate the risks and administer the contract
a negotiation phase prior to the start of the contract should exist, this phase is
required to build a trust relationship between the contracting parties (this negotiation
phase can be part of the contract itself)
an adequate risk-sharing or risk-reward system should exist to share the benefits if
the risk does not occur during the project life cycle.

44
CHAPTER 2
Literature review into project risks and cost overrun

Some of the main criticisms of the traditional DBB method are the lack of innovation,
delayed completion periods and cost overrun that are sometimes encountered in projects.
Since the client bears most of the risks of both the design and construction aspects, there
desirably needs to be better practices to ensure the clients needs are being met, quicker
project completion times and cost effective solutions (Pakkala, 2002).

Highway administrators and other public organisations (rail transport, airports and others)
are seeking better practices. Some are using or evaluating alternative models such as DB,
DBOM and BOO. In Pakkala (2002, the main goals of these innovative project delivery
methods are to:
produce projects that have better quality
bring cost savings to the client
transfer risk to the organisation best able to manage the risk
complete projects faster than the traditional methods.

Pakkala (2002) also reports that there are some tools available for predicting which delivery
method might be applicable to projects that are being considered or planned and identifies
the following:
Design-Build Selector (from the University of Colorado)
Project Procurement Selection Model (PPSSM).

The rationale for better risk allocation between owners and contractors ought to be based on
meeting the above conditions as far as possible. Missing one of these criteria is very likely to
trigger an inappropriate risk allocation process for any given project and hence bring
additional cost for the contracting parties (Zaghloul and Hartman, 2003).

2.17.1 Build-Operate-Turnover project delivery

The Build-Operate-Turnover (BOT) approach to infrastructure delivery is where the private


sector has to finance, design, build, operate and maintain the facility and then transfer it to
the government after a specified concession period. This method has gained widespread
popularity over the last 10 years, especially in developing countries (Chee and Yeo, 1995).
The opportunity for profit and reward, however, does not come easily. The responsibilities
are heavy and the stakes are high (Tiong, 1995).

An essential part of the agreement between the government and the private contractor is the
allocation of risk between the parties, that is, when an event occurs that influences the cost or
quality of the contracted service, which party should pay to rectify the situation or,
alternatively, which party should gain the resulting benefits (Arndt, 1999). Compared with
conventional delivery methods, there is a higher risk exposure for the BOT sponsors because
of the following:
high front-end development costs
extensive and lengthy negotiations with the host government
multi-party involvement
long-term commitment
equity contribution from sponsors.

45
Risk factors leading to cost overrun in the delivery of highway construction projects.

BOT infrastructure projects carry higher-than-traditional levels of risk as they typically


involve high capital outlays, long lead times, and long-lived assets with little value in
alternative use. The high-risk exposure associated with BOT projects means that special
attention should be paid to analysing and managing risks (Chee and Yeo, 1995). Risk in the
delivery of construction projects cannot be eliminated, but it can be minimised or transferred
from one party to another (Kangari, 1995).

The identification, analysis, and allocation of various types of risks are important for the
validation of privately promoted infrastructure projects. Dias and Ioannou (1995) have
classified sources of BOT risk in the following 10 risk categories:
1. country (political and regulatory)
2. force majeure
3. physical
4. financial
5. revenue
6. promoting
4. procurement
5. developmental
6. construction
7. operating.

Determining the relative importance of these types of risks is essential for BOT management
decision makers. The decision makers of construction companies should evaluate and rank
BOT projects with respect to their risk (Zayed and Chang, 2002).

Zayed and Chang (2002) propose a risk index for evaluating BOT projects. The index
assesses the risk and rank of BOT projects. To do this, they identify and analyse the main
areas of BOT project risk and a model for calculating a risk index is constructed. The
accuracy and robustness of their model has been verified by the comparison with holistic
evaluations. They also advocate their newly developed approach as being more convenient
than other approaches in dealing with BOT project risk. Nevertheless, this study relies upon
a small academic study group for collecting the evaluation data and they recommend the data
collection zone be increased more widely to practicing professionals in BOT projects in
order to improve the accuracy of the developed risk model.

2.17.2 Relationship/Alliance/Partnering contracting

The construction industry has used many delivery approaches to implement major
infrastructure projects. Over time, dissatisfaction with the adversarial nature of some of the
more traditional approaches, lead to sponsoring organisations adopting various means to
work in more collaborative manners, particularly during the late 1980s and 1990s. Rahman
et al. (2001) suggest that a relational contracting (RC) approach can be mobilised as a
potential route towards improving relationships and team work. The transaction cost
economics approach provides a useful framework for analysing the inevitable differences in
interest between different contracting parties who are members of the project coalition
(Winch, 1989). On the other hand, relational contracting encourages long-term provisions

46
CHAPTER 2
Literature review into project risks and cost overrun

and mutual future planning, and introduces a degree of flexibility into the contract by
considering a contract to be a relationship among the parties (MacNeil, 1980).

Relational contracting principles embrace and underpin various approaches, such as


partnering, alliancing, joint venturing, and other collaborative working arrangements that
provide better risk sharing mechanisms (Alsagoff and McDermott, 1994; Jones, 2000). At
the core of relational contracting, the legal mechanisms offered by specific contracts are not
strictly followed, but the parties themselves govern the transaction within mutually accepted
social guidelines (Macaulay, 1963).

Partnering is a good example of relational contracting principles. Thompson and Sanders


(1998) observes that benefits from partnering increase with a migration of teamwork attitude
from competition to co-operation, through to collaboration and finally to coalescence.
Rahman et al. (2001) reinforce this by reporting that more relational and performance-
oriented contractor selection practices encourage amicable relational contracting
environments and more collaborative teamwork. Ho (2000) depicts cost savings of 11 to
38% on similar office building construction in Hong Kong when the contractor was brought
into the team at the very outset of a project.

Extending the relational contracting approaches to sub-contractors and suppliers through the
supply chain and ensuring their participation at early stages of projects can further increase
benefits (Kumaraswamy and Mathews, 2000). However, relational contracting approaches
are expected to work in almost any environment, if applied properly. This requires
transforming traditional relationships towards a shared culture that transcends organisational
boundaries (CII 1996).

In the US, the partnering model has evolved as a typically non-legal commitment to
teamwork and collaboration. In the United Kingdom, the Institution of Civil Engineers
launched the New Engineering Contract and at the same time project alliances evolved
(initially in the North Sea oil and gas industry). Since then, project alliancing has become
more established in the oil and gas industries in particular and some other major
infrastructure industries in Europe. Incentive contracts are also widely accepted practices
around the world. These differ from alliances in that, under defined incentives, there can be
the traditional scope of work contracts and allocation of risks.

In Australia, project alliances have been taken to a deeper level of sophistication and use,
particularly in major public sector infrastructure projects. A project alliance, to describe it
most simply, is a project/program delivery strategy where the clients and commercial
participants objectives are aligned to maximise performance, proactively manage risk,
reduce cost and achieve outstanding outcomes.

The first two project alliances in Australia were oil and gas industry projects the Ampolex-
Wandoo Alliance and the Western Mining Corporation East Spar Alliance. It was after
completion of these two projects in 1998 when the first three government project alliances
were created. Sydney Water became the first public sector organisation to create a project
alliance on the Northside storage tunnel project, a 26 kilometre tunnel under the northern
suburbs of Sydney with a firm schedule deadline (the Sydney Olympic Games). This was
followed by the National Museum of Australia, known as the Acton Peninsula Alliance

47
Risk factors leading to cost overrun in the delivery of highway construction projects.

(A$150m) (Walker et al., 2000), and the Western Australian Water Corporations Woodman
Point waste water treatment alliance. Since 2002, numerous project alliances have been
undertaken, with the Department of Main Roads in Queensland being the government
agency with the most alliance experience at the end of 2002 in Australia.

Not all projects are suited to an alliance approach. Project alliancing is best suited to those
projects where the traditional risk transfer strategy is not appropriate. In many projects,
outcomes can be enhanced and the project optimised by embracing risk through
collaborative and co-operative contracting against the traditional blind faith transfer or
shifting of risks to others. A fundamental design principle of a project alliance commercial
framework is that if one participant wins, all win; or if one looses, all loose.

The key tangible and intangible benefits of a project alliance delivery approach include:
cost reduction
early completion
improved quality of the asset through enhanced workmanship and finish
improved operability.

As well, benefits for commercial participants in alliancing include:


enhanced profit margin
enhanced market-place reputation
outstanding risk management.

Project alliances are not only better equipped to analyse the real risks of the project, but can
also be better equipped to deal with their consequences. On the other hand, Tuohey (2002)
points out that, in practice, there have been a number of issues in the execution of alliance
type contracts. These include:
the risk/return ratio can be such that the rewards to the contractor are low,
particularly if the contractor is required to have some key people tied up in the
alliance for extended periods
the integrated team environment can be quite stressful for people
the nature of long-term alliance contracts are that there is one winner only, with the
consequence that there is the potential for competition in the market to be reduced,
particularly in thin markets like Australia.

The next section of this literature review document focuses on the linkage of risk to project
contracting in project delivery.

2.18 Project contracting


Once the project delivery method has been selected by the owner and pre-planning processes
have been completed, there is usually some form of Request for Proposals (RFP), sometimes
referred to as Request for Tenders (RFT), which includes the type of contract and the criteria
that are being used to determine the eventual winner of the tender. This contractor selection
method can vary its criteria range between a 100% price to a 100% quality-based selection
criterion.

48
CHAPTER 2
Literature review into project risks and cost overrun

Various researchers such as Russell et al. (1992), Holt et al. (1994), Kumaraswamy (1996),
Rankine et al. (1996), Russell (1996), Hutush and Skitmore (1997a), Holt (1999),
Kumaraswamy and Walker (1999) and Palaneeswaean and Kumaraswamy (2000) have
studied and reported on various contractor selection practices. All suggest improved
methodologies, but also highlight their strengths and weaknesses in different practices.
Despite the increasing use of alternative forms of project delivery systems in the past two
decades, the methodologies and procedures for bid evaluation, selecting contractors and
awarding contracts have remained relatively unchanged (Hatush, 1998).

Hatush and Skitmore (1998) suggest there are five process elements that are common across
all contract award practices. They are:
1. project packaging
2. invitation
3. pre-qualification
4. short-listing
5. bid evaluation.

2.18.1 Procurement auctions

The background to the traditional foundation in procurement of bidding for works in the
form of auctioning goes back to ancient times but the earliest academic treatments are
relatively recent, with the contributions of Friedman (1956) from an operations research
perspective and Vickery (1961) from a game theoretic perspective. Auctions have developed
into four basic allocation methods English (first-price open-cry), first-price sealed-bid,
second-price sealed-bid and Dutch (descending). A fundamental implication of the common-
value model that stands in marked contrast with private value auction theory is that, other
things being equal, the bidder with the largest estimate will make the highest bid.

Consequently, even if all bidders make unbiased estimates, the winner will find that he had
overestimated (on average) the value of the rights he has won in the auction (Milgrom and
Weber, 1982). This is commonly known today as the winners curse, due to the winner being
said to be cursed by:
having paid more for the asset than its true value (Marks, 2000:11).

Analytical game theory assumes that rational bidders will anticipate the winners curse and
bid very conservatively to avoid it (Camerer, 2003). However, field study research by Dyer
and Kagel in 1996 in the construction industry found no evidence of winners curse. Neither
does there appear to be any anecdotal evidence of the effects of this (Dyer and Kagel, 1996).

2.18.2 The competitive tendering process

Competitive tendering, particularly for public works, has a long history in places like the
UK. The origins of the practice are reported by Powell (1980) to have come from the early
19th century and basically arose out of dissatisfaction with the then existing system of
measure and value. This was where trades were paid directly by the client for work as it
proceeded. Powell (1980), in quoting Elsam (1826), wrote that:

49
Risk factors leading to cost overrun in the delivery of highway construction projects.

Measurement of completed building work prior to payment causes enormous


difficulties and frequent disputes, with the ruinous uncertainty of common estimates by
measurers who were said to be seldom if ever right. The response of Commissioners
reporting on the Public Office of Works in 18121813 was to favour competitive
tendering as a superior alternative to measure and value.

The clients objectives in the competitive tendering process are:


1. to obtain a fair market price for work, bearing in mind the general state of the
construction market at the time
2. to enter into an agreement with a contractor who possesses the necessary technical
skill, resources and financial backing to give the project owner the best possible
chance that the works will be completed within the required time, cost and quality
standards.

To achieve these objectives, Smith (1995) suggests the involvement of the following:
selection of an appropriate procurement methodology
the preparation of appropriate tender documentation
identification and selection of an appropriate number of suitable contractors who are
willing to tender for the work
choice and acceptance of the most suitable tender.

The nature and form of the competitive arena for the contractor in construction contracting
are largely determined by the project owner or their representative. The choice of bidding
system, coupled with bidder selection practices, has a direct bearing on the degree of
competition, because it affects both the number and the identities of bidders competing for a
particular contract.

Selective tendering systems appear to be more restrictive than open tendering systems,
because the contractor can bid only upon receiving an invitation. For open tendering, the
onus is on the contractor to bid after responding to an advertisement. Private sector clients
appear to have more flexibility in contractor selection, because public sector clients, mainly
for the sake of public accountability, are forced to adopt strict procedures. The tendering
process is an important stage in project delivery. However, the activity involving contactor
selection is an important decision required by any client so as to minimise project risk
exposure.

The next section of this literature review looks closely at research aspects of contractor pre-
qualification.

2.19 Pre-qualification of contractors


Contractor failure is an extremely disruptive force to every stakeholder in a construction
project. Unfortunately, the construction industry is such that it is highly susceptible to
varying economic conditions and to increases in competition. These characteristics sharply
distinguish the construction industry from other sectors of the economy and explain why
contractors are far more at risk than their counterparts in almost all other industries (Kangari
and Riggs, 1989).

50
CHAPTER 2
Literature review into project risks and cost overrun

If signs of contractor distress can be detected early on, then it may be possible for a project
owner to either not engage a particular contractor or become more actively involved with the
project before the contractor has suffered irreversible damage which can lead to bankruptcy
and increased losses to all stakeholders. One of the most difficult and important decisions
taken by a project owner for the success of a project is the selection of the contractor. Such a
decision deserves careful attention because of the complexity and sensitivity involved
(Hatush, 1998).

The following four weaknesses are found in contractor selection practices (Holt et al., 1993;
1995):
1. lack of a universal approach
2. long-term confidence attributed to results of pre-qualification
3. reliance on tender sum in decision making
4. inherent subjectivity of the process.

Choosing a contractor based solely on the lowest bid price is seen as one of the major causes
of project delivery problems. Another disadvantage of using the lowest bid as a principal
discriminating criterion is that some contractors who are facing a shortage of work may enter
unrealistically low bid prices, simply to try and maintain cash flow. Therefore, as Hatush and
Skitmore (1998) indicated, financial and technical criteria should be considered in order to
assess the potential of contractors finishing projects on time and to assess whether
contractors have the resources necessary to complete any contract awarded to them.

Disastrous consequences from awarding contracts to the lowest bidders, without due
consideration of their competencies, have led to growing awareness of the needs to
incorporate non-price parameters into contractor selection methodologies. Such fresh
approaches have been documented, for example by Schexnayder and Ohrn (1997), Arditi
and Yasamis (1997), Kumaraswamy and Walker (1999) and Palaneeswaran et al. (1999).

While the risk of contractor default cannot be eliminated by the project owner, it can be
transferred. When the owner signs a contract with a contractor, the risk of contractor default
is normally transferred partly or totally to a surety company. The general contractor may do
the same when signing contracts with sub-contractors. While the end point may be the surety
company, there is still a cost to transfer risk in terms of premiums assessed and the cost of
dispute resolution. The project owner is the one who pays for it in the end (Al-Sobiei, et al.,
2005). For an owner, the costs of default may also include loss of profits due to the project
not being completed on schedule, administrative expenses to analyse the situation, cost to
complete the project beyond the money yet paid to the contractor, fees associated with the
resolution of conflicts, and negative publicity and loss of goodwill within the community.

Given the fact that contractor default depends on environmental, operational and strategic
factors, it is important to use the past history of situations to minimise contractor default. For
any given project, pre-qualification is a highly important decision for the project owner. The
ability to optimise the short listing from a larger number of potential contractors can be as
important as the selection of the right bidder. This is because the quality of the final bidder
can only be as good as those short-listed (Khosrowshahi, 1999).

51
Risk factors leading to cost overrun in the delivery of highway construction projects.

Pre-qualification is widely used as an important procedure to help a project owner to short-


list proper contractors and is a screening process to evaluate candidate contractors ability to
complete a contract satisfactorily before being allowed into the bidding process. The project
owner needs to assess a contactors overall capacity, including their technological ability,
financial status, management skills, organisational structure and so on. Shen et al. (2003)
suggest that, to engage in a fair pre-qualification process, the parameters used for conducting
the assessment and method for analysing the parameters should be consistent.

The pre-qualification process basically consists of evaluating the available pool of potential
tenders, identified either by advertisement or invitation, against some given set of criteria in
order to find some group of firms who are all considered competent to carry out the work
and who are expected to provide an acceptable range of prices. The current practice of pre-
qualification is normally made by exercising accumulated experience and judgement in
assessing a given set of input variables such as reputation, past performance, financial
stability, current workload, firms resource capacity, experience records and technical
expertise (Lam et al., 2002).

Different project owners operate their pre-qualification processes under different objectives
and constraints. There are certain characteristics that distinguish public clients from private
clients. Khosrowshahi (1999) asserts that private clients tend to put emphasis on best service,
lowest price, best value-for-money and competitive advantage to their own organisation,
whereas public clients aim to demonstrate accountability for public funds and even-
handedness to suppliers and contractors.

On the other hand, Lam et al. (2000) points out that the criteria for pre-qualification may
differ from each other because the characteristics of the project and contractor are distinct
and dynamic. Masterman (1994) also points out that, in spite of different clients and projects,
there are common characteristics of contractor pre-qualification such as:
reasonable cost
reasonable quality
reasonable security.

In many cases, and particularly in the case of small contracts or much specialised work, a
number of contractors might be chosen simply on the basis of work that they have done for
an owner in the past. Most firms tend to accept such invitations even if they have no
intention of submitting a bona fide tender. Drew and Skitmore (1992) point out that this
method has deficiencies and should not be used on its own except for very small projects as
it is rather unreliable and may result in the selection of bidders that are either not interested
or are unable to provide competitive bids for a particular contract.

2.19.1 Research into client pre-qualification practices

In their study, Palaneeswaran and Kumaraswamy (2001) examine pre-qualification practices


in different countries such as the US, Hong Kong and Australia. Many project owners in the
US public sector use various pre-qualification ratings providing a basis for a more structured
and dynamic approach in order to define bidding boundaries for contractors. In the US, some
departments of transport use pre-qualification ratings such as:
aggregate rating

52
CHAPTER 2
Literature review into project risks and cost overrun

current bid capacity


maximum rating
project rating
maximum capacity rating
work class rating
performance rating.

These ratings can be used to define parameters such as the maximum monetary amount of
work that can be allowed to a contractor or the maximum value of a work that a contractor
can bid for a particular project.

The Department of Public Works Bureau of Hong Kong prepare approved lists according to
relevant expertise, financial status, and technical and managerial capabilities of contractors
as well as their completion of other contracts. Only contractors on the corresponding list can
apply for contracts. Hong Kong Housing Authority maintains a comprehensive Performance
Assessment Scoring System to review the registered contractors performance levels of their
contracting works in the ongoing projects. Scores for contractors are calculated and a
comparative score league is formed. Contractors who fall in the upper section of this league
are invited for bidding in upcoming projects.

The Mass Transit Railway Corporation of Hong Kong, on the other hand, uses a set of pre-
qualification criterion for the evaluation of contractors. Members of a committee score
candidate contractors with respect to these and then use the scores for recommending
contractors pre-qualification. These criteria and sub-criteria are:

Corporate structure
o management
o relations
Experience
o performance on corporations contracts
o construction performance in similar projects
o work experience
Resources and facilities
o staffing
o labour
o construction plant
o planning/programming
o design
o manufacturing/fabrication
o sub-contractors
Workload
o current
o future
Support functions
o safety
o quality management.

53
Risk factors leading to cost overrun in the delivery of highway construction projects.

The Construction Industry Development Agency in Australia also uses pre-qualification


procedures. The Agency prescribes mandatory criteria to screen out ineligible or unsuitable
applicants. As well, additional and reserved criteria are used to further describe and/or
evaluate the applicants skills and philosophies in order to discriminate them properly.
Mandatory pre-qualification criteria include:
technical capacity
financial capacity
quality assurance
time performance
occupational health and safety
human resources management
skills formation.

Claims performance, compliance with legislative requirements, and management for


continuous improvement can be prescribed as additional criteria.

Although contractors are generally pre-qualified so as to minimise risks and failures, their
performance levels differ widely under different workloads and dissimilar environments.
Palaneeswaran and Kumaraswamy (2000) point out that many Federal states of the US have
recognised this and incorporate well-structured capacity rating assessments in their
contractor selection procedures. For example, the US Washington State Department of
Transportation looks at the total value of uncompleted prime contract work and also
maximum work class type value, such as asphalt/concrete paving, bridges etc., which a
contractor is permitted to have under contract at any one time within the pre-qualification
period.

In Australia, the Queensland Department of Main Roads specifies similar maximum capacity
ratings in their Project Delivery System Guidelines (Queensland Department of Main Roads,
2000). Once these levels are determined, this is used to determine a contractors eligibility to
bid for a new project. The pre-qualification systems of the Queensland Department of Public
Works and Housing, as well as the Queensland Department of Main Roads, use aspects of
technical capacity, management approach, people involvement, business relations and
financial capacity as the pre-qualification criteria. By evaluating applicants with respect to
these criteria, contractors are pre-qualified for two years and are placed at a pre-defined
level. The aim of the system is to ensure proper matching between the size and the
complexity of the projects and the abilities of the contractors (Topcu, 2004).

2.19.2 Choosing contractors on low bids

Hatush and Skitmore (1998) have all published research works on decision criteria used by
clients for choosing a construction contractor. Holt et al. (1994a) carried out a survey of 53
major UK construction client organisations to determine the decision criteria used for
contractor selection and the importance of these criteria in terms of influencing their choice
of contractors. Hatush and Skitmore (1998) report that all clients use a similar set of criteria
for contractor selection, but that the way clients quantify these criteria can be very different
in practice. In these works, a contractors bid amount appears to be the most dominant and
important criterion (Holt et al., 1994; Hatush and Skitmore, 1998).

54
CHAPTER 2
Literature review into project risks and cost overrun

Holt et al. (1994a) developed a method to evaluate contractor pre-qualification criteria and
provided guidelines for practitioners, highlighting areas to address when evaluating a
contractor based on a particular criterion. In Holt et al. (1996), they used cluster analysis as a
means of reducing a large number of potential bidders in order to identify only those suitable
to tender for a particular project. Ng (1996) investigated different decision support systems
(DSS) for contractor pre-qualification. Among the surveyed decision support systems were
database management systems (DBMS), expert systems (ES), fuzzy sets (FS) and case-based
reasoning (CBR).

For the project owner, it is vital to be able to select the best available contractor and
currently a standard pre-qualification model that can be used widely in the construction
industry is not readily available. Most public agencies and companies who perform pre-
qualification have their own specific pre-qualification model. Tran (2002) lists and describes
a number of international pre-qualification models found in literature. These include:
Qualifier-1, Contractor Pre-qualification Model. This employs a dimensional
weighting procedure that produces aggregate weighted ratings of candidate
contractors from questionnaires
Qualifier-2, Knowledge-based system for Contractor Pre-qualification. This is a
knowledge-based system in which the decision of pre-qualification is based on the
user using decision rules, not calculated scores, and where contractors meet the
decision criteria to proceed to the next step in the decision model
Fuzzy Set Pre-qualification Model. This uses fuzzy set theory to include the
uncertainties in the contractor evaluation process and takes into account the
uncertainty associated with the information from contractors, data reliability and the
uncertainty associated with the decision makers
Hypertext Decision Support Pre-qualification Model. This model uses pair-wise
comparison of factors and an aggregate weight for each contractor is developed
Cluster Analysis in Contractor Classification. This involves the evaluation of
candidate contractors using predetermined selection criteria. Cluster analysis is used
on raw data to divide it into a series of sub-sets by which contractors are ranked
Neural Network Pre-qualification Model. Neural networks are used to learn from
historical contractor data
Contractor Pre-qualification Process. This is based on fuzzy logic and is a three-stage
model employing a hierarchical framework
University of Toronto Contractor Pre-qualification Model. This method considers
contractors efficiency measures and calculates the efficiency score of each
contractor.

Ng (1996) developed an integrated object-oriented expert system for contractor pre-


qualification, whereas Taha et al. (1995) proposed a knowledge-based decision support
system for predicting construction contract bond claims using contractor financial data. This
decision support system employs inductive learning and neural networks to extract the
problem-solving knowledge.

Once contractor pre-qualification is carried out satisfactorily by the client, the next stage in
managing risks in the delivery of projects is that of bid evaluation. The next section looks at
this process.

55
Risk factors leading to cost overrun in the delivery of highway construction projects.

2.20 Bid evaluation


Public agencies typically acquire construction services through competitive procurement,
awarding contracts to the lowest responsive bid read out at a public bid opening. Policy-
makers have seen this lowest bid method as the most risk-averse method of awarding general
construction contracts. There are inherent risks in using competitive procurement in public
agencies. The principal risk is contracting the wrong firm and the owners dilemma, as a
corollary of the winners curse, where the low bidder is cursed because they are the one most
likely to have underestimated the project cost.

The intensity of price competition between contractors has been blamed for many industry
ills, particularly in scenarios where price considerations have been deemed paramount. The
apparent, but often misleading, economy and convenience of awarding contracts to the
lowest bidder is particularly comforting in the public sector, where high accountability
regimes require onerous justification when awarded to other than the lowest bidder.

Selecting the best contractor is one of the most important decisions a client has to make.
Conversely, it is equally important for contractors to know why their bids are rejected. In the
case of a public client, the results and reasons for awarding a contractor and/or rejecting
others should be explicit because of public accountability. If the client is a private one,
contractors may also wish to know the reasons for their failure. In either case, the feedback
of contractors weaknesses can only help improve contracting firms to the betterment of the
industry.

Palaneeswaran and Kumaraswamy (2000) point out that all necessary information should be
provided in tender documents and all project procurement procedures and practices followed
by public procurement agencies should be transparent so that contractors can be become
aware of their strengths and weaknesses. This will thus improve their performance levels to
obtain more contracting opportunities while remaining competitive.

A low tender price may seem appealing to the client at tender stage, but the project may
encounter problems if the contractor is, for example, not able to complete the work on time
or even compromises on the construction quality in an attempt to reduce the contractors cost
(Mahdi et al., 2002). Crowley and Hancher (1995) caution that the awarding of a
construction contract to the lowest bidder without considering other factors can result in
problems such as cost overrun, delays and poor performance. They point out that it is very
real that the lowest bidding contractor may tend to adopt a confrontational claims oriented
position once the project is awarded as a means of making-up any financial short fall.

Smith (1995) argues that what is really required from a public sector point of view is not
simply to obtain the lowest price, but to obtain the best value for the money spent. According
to Smith, there is considerable doubt s to whether this can be achieved by taking the lowest
price in a largely unrestricted open competition (Smith, 1995).

Pakkala (2002) points out that, although the low bid process with 100% price criteria is the
easiest and simplest method of choice because it is quantatively measured, objective,
unbiased and not contestable, his study find that this low-bid process is not conducive to the
creation of innovation and long-term savings in the longer term. He also points out that

56
CHAPTER 2
Literature review into project risks and cost overrun

especially for road projects in particular, most project owners usually desire some elements
of quality and technical criteria since road project are used by the general public and there is
demand for quality and reliability. Some of the more common quality criteria identified are:
technical skills
personal skills (resources)
management team
supply chain management
methodology
environmental criteria
relevant experience
past performance.

Some of the quality criteria can be clearly identified as relevant, and important. However,
the difficulty arises when evaluating these aspects because some of them are personal skills
and not totally objective criteria.

Some of the common forms of bid selection methods used include:


Low bid or lowest price,
Lowest price conforming tender (lowest price which meets certain pass/fail criteria)
Weighted Average WA formula (for weighting price and non-price criteria)
Quality Price Trade Off QPTO (a trade off system for providing quality)
Negotiated (where both parties negotiate until a satisfactory price is agreed upon).

Wang (2003) proposed that, before considering bids submitted by competing contractors for
a public procurement project, the owner should determine a project ceiling price or cost
estimate to use as a threshold or reference point for evaluating the bids and points out the
dilemma for the project owner is setting a ceiling price that is sufficiently low to satisfy the
owners interests in cost savings, yet sufficiently high to tender out the project. Wang (2003)
also points out that while some project owners will fix a ceiling price by an average bidding
ratio (winning bid divided by ceiling price) of past projects, most owners merely make a
decision based on gut feeling. Wang (2003) goes further in saying that, despite its popularity,
the historical average bidding ratio is inferior to more systematic evaluation methods. This is
because the major problem with it is that the ratio tends to be unrealistically low, especially
in a slow construction economy when bidders tend to propose unsustainably low bids simply
to get a contract. A further drawback is that the unique characteristics and risks of the project
are ignored.

2.20.1 Research into bidding

Research in bidding has focused either on the development of bidding models to assist
bidders in winning contracts (Dozzi et al., 1996; Fayek, 1998) or on the evaluation of
competitive bids (Crowley and Hancher, 1995; Crowley, 1997; Williams, 2003). Statistical
methodologies have been developed which allow the detection of bids which are too low and
are usually considered to be discordant bids because they are in disagreement with the other
bids (Crowley, 1993). Furthermore, Crowley asserts that there is a historical relationship
with data between discordant bids and the magnitude of cost growth experienced within the

57
Risk factors leading to cost overrun in the delivery of highway construction projects.

particular project, with the owner taking the perceived benefit of a lower bid but incurring
the financial risk of having higher project cost growth.
Williams et al. (1999) have shown that there is a systematic relationship across highway
projects between the low bid and the completed project cost for competitively bid highway
projects in New Jersey and Great Britain. They found that as the magnitude of the low bid
increased, the resulting completed project cost tendered to increase absolutely and as a
percentage of the original bid. Williams (2003) suggested that large highway projects tend to
have much higher relative cost increases than small projects. His research also suggested that
methods of minimising the size of competitively bid highway projects, such as breaking a
project into smaller components, may have been useful in minimizing cost overruns.
Williams (2003) also concluded that cost increases for different types of construction will
follow different patterns and that it was not possible to generalise that the low bid and related
project were related in the same way for all types of projects.

2.20.2 Sub-contractor selection

Currently in construction, many project activities have been sub-contracted out by the main
contractor. Although sub-contracting has many advantages, it also brings additional risks to
the main contractor and to the client. These risks are uncertainties related to a sub-
contractor's technical qualifications, timeliness, reliability and financial stability (CII,
1989a). A large proportion (up to 90%) of construction activities can be sub-contracted on a
given project and so it is important to probe deeper down the supply chain in order to ensure
that appropriate sub-contractor selection is also a vital element managing risk in construction
projects. Improvements in sub-contractor selection processes have not received the attention
that one would expect from such a significant contribution to the industry.

Price-based selection often squeezes out the more responsible sub-contractors, driving down
both prices and performance levels. A growing appreciation of such anomalies has led to
recent initiatives towards longer term main-sub-contractor relationships (Matthews, 1996).
The evaluation of sub-contractors by main contractors (and vice versa) is a complex
undertaking. An example of a neural network based approach to sub-contractor rating is
proposed by Albino and Garavelli (1998).

2.21 Project budget estimating


An estimate can be defined as the calculated prediction of the amount of money required to
undertake a specific amount of work expressed in dollar values in the year in which it was
prepared. Out-turn dollars is the cost, for the period in which the work was or is to be
performed. Estimates prepared at a particular date can be converted to out-turn dollars by
applying an appropriate inflation rate to the time-series cost of the project. It is prepared in a
systematic manner appropriate to the size and complexity of the project, and to a level of
accuracy commensurate with the available information and the intended use of the
information developed. It may include some prior expenditure in a mix of year dollar values.

The project cost estimate is primarily concerned with the cost of resources needed to
complete the project activities and include all the processes which are employed to maintain
financial control over a project. Common value auctions generally assume that a true cost
exists but it can only be estimated (Friedman 1956). Management theory, on the other hand,

58
CHAPTER 2
Literature review into project risks and cost overrun

tends to assume that the forecast or budget cost is fixed and that production activities are
sufficiently variable to be somehow manipulated to be kept within budget. In project
construction, this fixing of budget costs is often done by reference to the estimators little
black book of figures that are known from experience and thus can provide a reasonable
target cost.

The traditional approach to cost estimating is the derivation of a best estimate from the
knowledge of existing conditions based on current rates and prices in similar situations, but
with adjustments to reflect anticipated differences in say ground conditions, site accessibility
and other factors. A contingency allowance which usually varies according to type of work,
anticipated risk and project stage is added to cover unforeseen expenditure.

2.21.1 Estimating processes

Abbasi and Al-Mharmah (2000), Hutchings and Christofferson (2000) and White and
Fortune (2002) examined various management tools and techniques that are used in project
estimating as well as in cost control processes. The most popular areas are detailed as:
analogous
parametric
detailed.

Analogous estimating: This is an approximate estimating method that compares costs with
similar past projects and which often depends on expert judgement. It can be used in the
preparation of the earliest price estimates for the client. The estimator should have the
relevant experience of estimating the cost of similar projects (Ashworth, 1994). Analogous
estimating using the actual cost of a previous, similar project is the basis for estimating the
cost of a current project and is frequently used to estimate the cost when there is a limited
amount of detailed information about the project. Usually estimators retain their own
database of historical project costs from which equivalent or similar cost information may be
drawn (Loftus 1999).

Parametric estimating: Parametric estimating uses project characteristics in a mathematical


model to predict project cost. This method is considered fairly accurate when historical
information used to develop the model is accurate. Conceptual estimates based on parametric
costs are most commonly used in building and highway construction. The parametric cost
approach relates all costs of a project to just a few physical measures, or parameters that
reflect the size or scope of the project. For example, the gross floor area of a pre-stressed
concrete deck surface over water would be a typical overall parameter for a structure such as
a bridge over water. Some costs, say for concept road construction projects, can be expressed
in lane/km. With good historical records on comparable structures and associated risks,
parametric costing can give reasonable levels of accuracy for preliminary estimates (Barrie
and Paulson, 1992). Linear measure is the most widely used parameter.

Detailed estimating (Bottom-up): Unit price estimates can be compiled when quantities of
work items may not be precisely determinable but the nature of the work is well defined
(Clough, 1986). This is best suited for works which are relatively simple and repetitive in
nature such as buildings. It involves estimating the cost of individual work items and the
synthesis of cost estimates from resource estimates made at the lowest possible level of

59
Risk factors leading to cost overrun in the delivery of highway construction projects.

work-breakdown-structures (Project Management Institute, 2000). The addition of indirect


cost, plant and equipment, office overheads, profit, escalation and contingency develops the
total estimated project cost (Barrie and Paulson, 1992).

A study by Hester et al. (1991) indicates that the estimating method and the accuracy of
project cost estimates could be a major reason for having cost changes. They found that that
most project owners assume that routine changes in the project will only affect the work in
the change area, whereas. In reality, the effects can extend well beyond that specific change
area Hester et al. (1991).

2.21.2 Early project estimates

Various cost estimates are made at different stages of the process: project planning, decision
to build, tendering, contracting, and later renegotiations. Cost estimates at each successive
stage typically progress toward a smaller number of options, greater detail of designs, greater
accuracy of quantities, and better information about unit price. Thus, cost estimates become
more accurate over time, and the cost estimate at the time of making the decision to build is
far from final.

Accurate, early cost estimates for engineering and construction projects are extremely
important to the sponsoring organisation and the project team. For the sponsoring
organisation, early cost estimates are vital for business unit decisions that include strategies
for asset development, potential project screening, and resource commitment for further
project development. Inaccurate early estimates can lead to lost opportunities, wasted
development effort, and lower than expected returns.

Early estimates are typically plagued by limited scope definition (and thus high potential for
scope change) and are often prepared under tight time constraints. Furthermore, reliable cost
data are often difficult to obtain during the early stages of a project, particularly if basic
design and geographic issues remain unresolved. Early estimates, even when grossly
inaccurate, often become the basis upon which all future estimates are judged (with future
estimates sometimes being corrected to be consistent with early estimates). However, final
cost often exceeds the initial estimate.

The accuracy of early cost estimates for capital projects has been a major concern and a
subject of much scrutiny over the last 35 years. Hackney (1986) proposed the use of the
definition checklist for applying contingency to capital cost estimates and then validated the
checklist by comparing the definition ratings of 30 projects to their respective levels of cost
overrun. Hackney later revised the checklist in 1986 to specifically address process projects
and developed a separate checklist to apply the definition rating method specifically to
hazardous waste remedial projects (1986).

2.21.3 Project cost overrun

The problem of cost overrun, especially in the construction industry, is a worldwide


phenomenon, and its effects are normally a source of friction between clients (especially
government clients), project mangers and contractors on the issue of project cost variation.
In 1882 for instance, the Amazon province of Brazil, at the height of its financial might,

60
CHAPTER 2
Literature review into project risks and cost overrun

awarded a contract to the Portuguese Engineering Council of Lisbon to construct a theatre at


Manaus at the cost of 500 cruzerio. As reported by Carelli (1989), the project was completed
at a staggering cost of 20,000 cruzerio 12 years later. Akpan (1987) also reported the case of
the British National Westminster Bank Headquarters building where the cost overrun was
reported to have risen to five times more than the original estimate.

When the Suez Canal was completed in 1869, actual construction costs were 20 times higher
than the earliest estimated costs and 3 times higher than the cost estimate for the year before
construction began. The Panama Canal, which was completed in 1914, had cost escalations
in the range of 70 to 200% (Summers, 1967). More recently are examples such as Denvers
US$5 billion airport that was 200% overspent (Szyliowicz and Goetz, 1995), the 800 million
Danish Kroner Oresund rail/road bridge between Copenhagen and Malmo, Sweden that was
68% overspent, (Flyvbjerg et al., 2003). An example of cost underestimation in Australia is
the Sydney Opera House, with actual costs of approximately 15 times greater than those
projected (Hall, undated: 3).

On the other hand, Yeo (1990) points out that the entire Apollo space program cost was
about US$21 billion, which was only 5% above its initial estimated budget. But few are
aware that there was, in fact, a hefty $8 billion contingency already built into the initial
estimate (Morris and Hough, 1987).

Despite the large number of reported cases, it seems that construction ranging from the
simplest to more complex projects such as transportation systems and oil and gas platforms
have increasingly faced overrun. Raftery (1994) points out that construction projects tend to
have poor reputation for excessive time and cost overrun. Morris and Hough (1987), during a
study of records from different types of projects funded by the World Bank between 1974
and 1988, found that 63% out of 1778 projects had experienced significant cost overrun. In a
study of 204 construction contracts let between 1986 and 1990 in Italy, Tagliaventi (1991)
reported that an average cost overrun of 50%. Research carried out around 1992 by the
Transportation Research Board evaluated construction cost overruns on projects completed
for the Washington State Department of Transportation. The objective was to identify factors
that have the strongest association with construction cost overruns. Results of the analysis,
which examined information from 468 construction projects, indicated that cost overruns,
expressed as a percentage of the original contract amount, tended to increase with the size of
the project. Evidence also suggested that the cost overrun rate increased with the number of
bidders and with the increased dispersion of the various bids submitted per project
(Hinze and Walsh, 1997).

Construction cost estimating on major transport infrastructure projects has not increased in
accuracy over the past 70 years. The underestimation of cost today is in the same order of
magnitude that it was then (Flyvbjerg et al., 2002; Molenaar, 2005).

2.21.4 Research into project estimating

In the late 1970s, the US Department of Energy recognised the importance of accurate early
cost estimates and contracted with the Rand Corporation to study the capital cost estimation
problems associated with pioneer energy, process plants (Merrow, 1978). During the study,

61
Risk factors leading to cost overrun in the delivery of highway construction projects.

Merrow determined that 74% of cost growth is caused by underestimation (i.e. improper
estimation).

In 1988, the US Federal Construction Council commissioned the Building Research Board to
study construction estimating practices and to recommend techniques for improving the
accuracy of early cost estimates. The Board identified three recommendations for improving
estimating procedures (Morris, 1988):
1. developing standard terminology and formats for budgets and estimates
2. taking steps to ensure that estimators are properly qualified for conceptual estimating
3. expanding the use of parametric and probabilistic estimating techniques for
conceptual estimates.

Ogunlana (1989) carried out research into monitoring cost estimators accuracy of the last
cost forecast prior to tender for projects. Data for the research were collected from seven
County Councils Offices in the United Kingdom. The projects used in this study were all
road projects for new construction or facilities improvements such as roundabouts,
maintenance works, and expansion of existing roads or bypasses. A total of 36 projects were
analysed. The research included a survey to ascertain what level of error was acceptable in
seven design offices. Table 2.5 below shows that all the offices fell within a +/ 15% range.

This table is not available online.


Please consult the hardcopy thesis
available from the QUT Library

Source: Ogunlana (1989)


Table 2.5: Target accuracy of highway design estimates

Later Ogunlana (1991) reported on the accuracy achieved on different stages of road
estimates where the mean accuracy of statutory utility estimates was reported as 35.7% for
12 projects, with the overall value of accuracy for all elements of the projects being 12.8%
with a coefficient of variation of 11%.

Transportation projects have historically experienced significant cost overrun from budget
estimates. A recent study of 258 infrastructure projects spanning a time period of more than
70 years found that project costs are underestimated in approximately 90% of the
cases/projects, and the actual costs averaged 28% higher than estimated on this sample
(Flyvbjerg et al., 2002). Although highway projects fared better than rail and fixed-linked
projects, the sample still displays an increase in project costs of more than 20%.

High-profile highway projects in the US, such as Bostons Central Artery/Tunnel, known as
the Big Dig and Virginias Springfield Interchange have made engineers, contractors, and
the public acutely aware of the problem of cost overrun. For example, the Big Dig was
estimated at a cost of US$2.6 billion (1982 dollars) and was expected to be completed at a
cost of US$14.6 billion (2002 dollars) with completion then, anticipated for 2005 (NAS,
2003).

62
CHAPTER 2
Literature review into project risks and cost overrun

2.21.5 Factors influencing costs

The literature shows that a wide variety of factors influence construction costs. In a study
conducted in Newfoundland on highways, Hegazy and Ayed (1998) found that season,
location, type of project, contract duration and contract size had a significant impact on
individual contract costs. Herbsman (1986) determined that, in addition to input costs of
materials, labour and equipment and the total volume of contracts bid each year (so-called
bid volume) all influenced project costs.

Some factors are intrinsically related to construction organisations which are solely
responsible for managing them, whereas others are closely related to socio-cultural,
economic, technological and political environments within which most organisations
operate.

Cost overrun arises primarily because of four factors (Yeo, 1990; Minato and Ashley, 1998):
external risk due to:
o modifications in the scope of a project
o changes in the legal, economic and technologic environments
technical complexity of the project due to:
o size
o duration
o technical difficulty
inadequate project management due to:
o the control of internal resources
o poor labour relations
o low productivity
unrealistic estimates because of the uncertainties involved.

2.21.6 The relation between cost accuracy and scope

Project scope describes the work to be performed in a project and so a cost estimate heavily
depends on this scope definition. Lack of proper scope definition has been stated to be a
major source of bad estimates (Cowie, 1987). Vagueness in scope has two implications for
cost control.
1. It decreases the accuracy of cost estimates
2. It creates a potential for changes in scope during the construction stage, which
generally results in an increase in cost to both owners and contractors.

The accuracy of a cost estimate is highly dependent on the level of detail in the project scope
definition. Peurifoy and Oberlender (1989) have divided the accuracy of an estimate into
three levels depending on the preciseness of scope definition. They found that a conceptual
estimate prepared from a project scope definition that does not include design information is
usually accurate within +40 and 10% of the actual cost. A cost estimate prepared upon
completion of the preliminary design is usually accurate within +25 and 5% of the actual
cost. A detailed cost estimate prepared upon completion of the final design is expected to be
accurate within +10 and 3% of the actual cost.

63
Risk factors leading to cost overrun in the delivery of highway construction projects.

Deciding on the likely cost-variation range of a project is subjective. However, the more
experienced the estimator, the greater likelihood that the subjective decision will be based on
objective experience (Bradley et al., 1990). One inherent difficulty in having an estimator
quantify the likely variation of an estimate is that estimators will not always agree on the
magnitude of the variation. It is an established fact that individuals attitude to risk vary.
Some people are by nature risk-seeking, whereas others prefer to avoid risk. These attitudes
are not necessarily based on past experiences in related fields; rather, they reflect the
individuals basic personality. Those individuals with a risk-aversion personality tend to
assume that, regardless of the apparent reliability of the data base, events will arise that
should be covered by an adequate contingency factor added to the best estimate. By
comparison, individuals who are by nature risk-takers will tend to underestimate the
likelihood of the best estimate being too low (Bradley et al., 1990).

There is frequently a substantial contrast when comparing the importance of early estimates
with the amount of information typically available (i.e. scope definition) during the
preparation of an early estimate. Although lack of scope definition often leads to inaccurate
estimates, early estimates (accurate or not) often become cast-in-stone, and future estimates
are unrealistically expected to agree with the early estimate.

In addition to the adverse effect on the accuracy of cost estimates, lack of proper scope
definition creates a potential for change or growth in scope during construction. Cowie
(1987) observes that the majority of cost growth during the construction period derives from
scope growth. Increases in scope, without extending a project delivery date, can only be
executed by increasing the resource intensity over and above the planned level. Hetland
(1994) points out that this often leads to increased unit cost and hence increased total cost of
a project.

Design and project specific factors affect the cost estimate of a project and can include such
other factors as vagueness in scope, design complexity, and project size (Akinci and Fischer
1998). Engineering designs have a high level of influence on project costs and sometimes
unsatisfactory design performance can lead to cost overrun (Barrie and Paulson, 1992).
Anderson and Tucker (1994) reported that their survey found that about one-third of
architectural/engineering projects miss cost and schedule targets. Chang (2002) notes that, as
reported by Smith (1996), there have been few instances where an engineering design is so
complete that a project could be built to the exact specifications contained in the original
design documents. Many construction problems are due to design defects and can be traced
back to the design process (Bramble and Cipollini, 1998).

2.21.7 Scope change

In their research study to quantify the impact that project changes have on engineering and
construction project performance, Ibbs and Allen (1995) define change as any event which
results in a modification of the original scope, execution time or cost of work. Because
change may occur throughout all phases of a project, their research focuses on the
quantitative impacts that change has on the detailed design and construction phase of
projects. They found that project change has a large effect on the financial performance of a
construction project. Thomas (1985) studied highway construction programs and reported on
selected claims for project changes and cost/schedule overrun on these same projects. The

64
CHAPTER 2
Literature review into project risks and cost overrun

study concludes that project change has a direct effect on costs and schedules of construction
projects, primarily cost/schedule overrun.

Constructability in the highway industry has also gained considerable attention for adding
costs to designed projects. Early research by OConnor et al. (1991) identified that poor
specifications can cause construction rework and delays. Their findings suggest that 22% of
all constructability problems are related to ineffective communication of engineering
information, plans, and specifications, especially inadequacies in project specifications.
Anderson et al. (1999) also confirmed the issue of inadequacies in project specifications in
their research on state highways in the Unites States.

Chang (2002) reported that on four completed case study projects for environmental and
engineering design services for roadway construction projects in California carried out on a
cost-plus-fixed-fee basis, cost increases averaged 25%.

While the reason for cost overrun can be obvious, the problem still remains that an estimate
is a forecast of a cost to be incurred sometime in the future the problem is that the future
is not always predictable. Kayode (1979) reports that project cost overrun are caused by
rising costs largely due to inflation, inadequate analysis and inadequate information. Orji
(1988) is of the opinion that the causes include certain government fiscal/monetary policies,
poor costing of projects, inflation within the economy and some practices of project
participants, especially those involving government projects. A further reason advanced for
the incidence of project cost overrun is attributed to costing methods (Akpan and Igwe,
2001).

The quality of project design documentation has fallen alarmingly over the past 15 to 20
years (Tilley, et al., 2000). It has been reported that many client organisations routinely
tender major projects on sketch plans of partially completed documentation to transfer
design risk to the managing contractor (McLennan and Jorss, 2006). They also reported that
the findings of the task force set up by the Queensland Division of Engineers Australia in
2004 included the following root causes:
inadequate project briefs based on unrealistic expectations of time and cost
lack of integration along the supply chain linking parties, and between project phases
poor understanding and low skills in risk assessment and management
inadequate use of CAD/computer technology in the design process and in the
compilation of specifications.

2.22 Cost forecasting models


A considerable amount of literature advocates that forecast project cost accuracy is very
important to both the client (who can have better cost control over the project) and the
contractor (who can have a better chance to bid the job with a reasonable profit margin).
Many of the research works have concentrated on the accuracy in the construction cost
forecasting. Ashworth and Skitmore (1983) suggest that the factors influencing project cost
forecasting accuracy are:
availability of design information

65
Risk factors leading to cost overrun in the delivery of highway construction projects.

building size
market condition
number of bidders.

The development of cost forecasting models is one of the techniques for assessing project
costs, and hence, ultimately, the projects cost at completion. The development of cost
forecasting models is summarised by Raftery and Ng (1993) as:
First Generation Models: Element cost planning in the UK and by bidding models in
the US
Second Generation Models: using regression analysis
Third Generation Models: probabilistic estimates, frequently based on Monte Carlo
techniques.

Raftery (1994) also suggests that range estimating can be developed to show the form/shape
of project cost distributions. In 1996, Skitmore indicated this might be done parametrically
for tender price forecasts, by fitting one of the standard probability density functions to the
cumulative frequency of the tender price forecast/actual values (Skitmore, 1996).

Oberlender and Trost (2001) and Trost and Oberlender (2003) report on quantitative data
they collected from completed construction projects in the process industry. Their data are
analyzed using factor analysis and multivariate regression analysis. The resulting model,
known as the estimate score procedure, allows a project team to score an estimate and then
predict its accuracy based on the estimate score. They identify six main factors affecting
estimate accuracy and, in order of significance, are:
1. basic process design
2. team experience and cost information
3. time allowed to prepare the estimate
4. site requirements
5. bidding climate
6. labour climate.

Weverbergh (2002) comments that market data without background information on costs,
uncertainly and privileged knowledge only leads to very crude types of cost estimates, but is
likely to be the best that can be provided under the circumstances.

In the past, forecasting future highway construction costs has been achieved in basically
three ways. Firstly, unit rates of construction such as dollars per lane kilometre by highway
type have been used to estimate construction costs in the short term (Hartgen and Talvitie,
1995; Stevens, 1995). However, this method has generally been found to be unreliable,
because site conditions such as topography, in-situ soil, land prices, environment and traffic
loads differ sufficiently from location to location to make the use of average prices
inaccurate for individual projects (Hartgen and Talvitie, 1995).

Secondly, extrapolation of past trends, or time-series analysis, has been used to forecast
future overall construction costs (Koppula, 1981; Hartgen et al., 1997). Typically in these
analyses, construction costs are collapsed down into overall expressions of construction

66
CHAPTER 2
Literature review into project risks and cost overrun

indices. These types of models are usually only used for short-term forecasting because of
their reliance on the notion that past conditions and standards are maintained into the future.

Thirdly, models have been established that describe construction costs as a function of
factors believed to influence construction costs. The relationship between construction costs
and these factors is established from past records of construction costs. Typically, these
models are used to estimate the cost of individual contracts only. These models, with their
relational structure, are the only models expected to provide reliable long-term estimates
(Wilmot and Cheng, 2003).

Recent research has attempted to apply artificial intelligence to the prediction of completed
project costs. These efforts start with the a priori assumption that each project is considered
unique. Attempts have been made to develop extremely complex models that incorporate the
many factors and their interactions that can affect the cost of a construction project. These
efforts have yielded software that requires significant computing power, a sophisticated user,
input of subjective information, and significant required input data. Ashley (1989) describes
a general performance model for analysing individual construction projects that requires the
analysis of many factors such as labour productivity, design, quality, procurement and the
interaction between the factors.

Leu et al. (2001) point out that during project implementation many environmental variables
such as weather, space, congestion and productivity level dynamically affect activity
duration, and hence cost. Leu et al. (2001) also assert that activities need to be executed in
cost effective ways that are based on the principle of construction time/cost trade off. Several
early mathematical and heuristic models have been generated to solve construction time-cost
trade-off problems (Panagiotokopoulos, 1977). By measuring the cost of risk as an input into
a projects estimate, the success or otherwise of initial risk assessments may be seen as a
variance from the projects estimated cost at completion. It has been postulated that this can
provide a measure of the successful outcomes of projects through defined key performance
indicators. Central to any project improvement is the ability to measure aspects of the project
outcomes, including the cost of risk, for benchmarking and performance measurement
purposes.

An early study by Charles and Andrew (1990) identifies factors that influence the
construction change order rates causing cost overrun. These consist of:
size of project
difference between the low bid and the estimate
type of construction
level of competition
quality of the contract documentation
interpersonal relations within the project
policies of the contractor.

It was discovered that a cost overrun rate of 1 to 11% is more likely to occur on larger
projects than smaller ones. Contracts with an award amount less than the estimate are found
to be more likely to have cost overrun rates above 5%.

67
Risk factors leading to cost overrun in the delivery of highway construction projects.

2.23 Project cost contingency


The cost performance of construction projects is a key criterion for project owners.
Construction and development is fraught with difficulty and the basic principle of risk
analysis is that an attempt should be made to at least identify these risky project items and
attach some financial value to them. These amounts can then be added to a project budget as
items of possible expenditure. The intention of this notion is that the project budget becomes
a more realistic representation of the clients likely outlay. Some of the project uncertainties
will be eliminated or clarified as the planning of the project matures, however some
uncertainties will be carried forward to project tender stage. The use of risk premium money
is regarded as standard practice in construction. Despite the fact that most project
construction owners transfer most risks to other parties in different forms, in many
construction projects the owner adds a contingency allowance to the estimated cost in order
to avoid project overrun arising from unexpected events.

In terms of managing risk on a project, contingency can take many forms. It may be a time
allowance in the program of work for delay such as wet weather, a cost allowance in the
project cost estimate to account for the residual risk accepted by the project manager or a
contingency process in case an event happens. Cost contingency is included within a budget
to represent the total financial commitment for a project client and the quantum of such
contingency is of critical importance to projects.

There appears to be no standard definition of contingency. Patrascu (1988:115) observes


that:
Contingency is probably the most misunderstood, misinterpreted and misapplied word
in project execution. Contingency can and does mean different things to different
people.

More recently, the Association for the Advancement of Cost Engineers (AACE 2000: 28) defines
contingency as:
An amount of money or time (or other resources) added to the base estimated amount
to achieve a specific confidence level, or to allow for changes that experience shows
will likely be required.

In Project Management Institute (2000:199), it defines contingency as:


The amount of money or time needed above the estimate to reduce the risk of overrun
of project objectives to a level acceptable to the organisation.

The key attributes of the concept of project cost contingency are:


reserve cost contingency is a reserve of money (AACE, 2000)
risk the need and amount for contingency reflects the existence of risk in projects
(Thompson and Perry, 1992).

Contingency can be divided into two categories of risk known unknowns and unknown
unknowns (Project Management Institute, 2000; Hillson, 1999) and can be invoked for
events within the defined project scope that are:
unforeseen (Moselhi, 1997; Yeo, 1990)
unexpected (Mak et al., 1998)

68
CHAPTER 2
Literature review into project risks and cost overrun

unidentified (Levine, 1995)


undefined (Clark and Lorenzoni, 1985; Thompson and Perry, 1992).

Traditionally cost estimates are treated as deterministic, having point estimates for each cost
element that are based on their most likely value (i.e. a single value estimate based on the
most likely values of the cost elements) (Mak et al., 1998). These single values may or may
not accurately indicate the possible value of the estimate, and they certainly do not indicate
the possible range of values an estimate may assume (Toakley, 1995).

The cost performance of construction projects is a key success criterion for project sponsors.
Construction projects are notorious for running over budget (Hester et al., 1991; Zeitoun and
Oberlender, 1993). When cost estimates are being prepared for feasibility, planning and then
design stages, the cost of risk is reflected by the inclusion of a contingency sum. The
contingency sum, usually expressed as a percentage markup on the base estimate is used in
an attempt to allow for the unexpected.

One of the most commonly used methods for contingency allocation is the classes of
estimate method. Almost all major companies in every industry group develop their own
criteria for the classification of cost estimates. As an example, Blok (1982) defines five
classes of estimate as shown in Table 2.6.

This table is not available online.


Please consult the hardcopy thesis
available from the QUT Library

Source: Blok, 1982


Table 2.6: Classes of project estimates

Project cost estimates are prepared at different stages over the life cycle of a project. The
estimating techniques used and the associated probable error ranges depend on the
availability of project information and engineering data. For instance, classes IV and V are
basically the study estimates, whereas class III is the budget estimate prepared prior to
budget approval and the final commitment of funds for project execution. Class I and II
estimates are control estimates where the level of accuracy is high (Blok, 1982).

The Department of Main Roads Queensland expects the following contingency allowances
shown in Table 2.7 in their project estimates unless there are other reasons why they should
be adjusted (Queensland Department of Main Roads, 2000).

69
Risk factors leading to cost overrun in the delivery of highway construction projects.

This table is not available online.


Please consult the hardcopy thesis
available from the QUT Library

Source: Queensland Department of Main Roads, 2000


Table 2.7: Contingency ranges in highway estimates

2.24 Estimating methods for cost contingency


The practice of presenting project cost estimates as a deterministic figure comprising a base
estimate and the addition of a single contingency amount (usually as a percentage addition)
has been adopted in the construction industry for a long time for budgeting purposes. Usual
practice is for this amount to be a single lump sum with no attempt made to identify,
describe, and value various categories and possible areas of uncertainty and risk. Cost
contingency is included within a budget to represent the total financial commitment for the
project owner. Therefore the estimation of cost contingency and its ultimate adequacy is of
critical importance to project owners.

Baccarini (2004) details numerous estimating methods available for project cost contingency
as shown below:
traditional percentage
method of moments
Monte Carlo simulation
factor rating
individual risks expected value
range estimating
regression
artificial neural networks
fuzzy sets
controlled interval memory
influence diagrams
analytical hierarchy process.

When estimating, the most common method of allowing for uncertainty is the addition of a
percentage contingency figure to the most likely estimate of the final cost of the known
works. Although this contingency can be calculated in various ways as detailed previously,
the most common way is to consider around 10% of the estimated project cost (Burger,
2003). Hartman (2000) argues that this is an unscientific approach and thus a reason why so
many projects finish over budget.

As Yeo (1990) also points out, the most common method of contingency allocation could be
regarded as overly simplistic and heavily dependent on an estimators faith in their own
experience.

70
CHAPTER 2
Literature review into project risks and cost overrun

Quantification of contingency allowances for cost estimating items can also be achieved by
applying the risk management processes detailed in AS/NZS 4360 (Standards, 1999).
Historical events may be used as a guide; however estimators and project managers need to
use their experience and professional judgement to weigh the competing factors to arrive at
the most likely value. Where risks are significant and complex, a statistical evaluation such
as the Monte Carlo method can be used. The objective of contingency allocation is to ensure
that the estimated project cost is realistic and sufficient to contain any cost incurred by risks
and uncertainties.

This contingency is often calculated as an across-the-board percentage addition on the base


estimate, typically derived from intuition, past experience and historical data. This approach
is considered arbitrary, as Thompson and Perry (1992:121) observe:
All too often risk is either ignored or dealt with in an arbitrary way: simply adding a
10% contingency onto the estimated cost of a project is typical.

However, Thompson and Perry (1992) outline several weaknesses of using a contingency
amount as follows:
The percentage figure is most likely arbitrarily arrived at and not appropriate for the
specific project
There is a tendency to double count risk because some estimators are inclined to
include contingencies in their best estimate
A percentage addition still results in a single-figure prediction of estimated cost,
implying a degree of certainty that is simply not justified
The percentage added indicates the potential for detrimental or downside risk; it does
not indicate any potential for cost reduction and may therefore hide poor
management of the execution of the project
Because the percentage allows for all risk in terms of a cost contingency, it tends to
direct attention away from time, performance and quality risks
It does not encourage creativity in estimating practice, allowing it to become routine
and mundane, which can propagate oversights.

Eden et al. (2005) point out that it may be important to require different contingencies for
different elements of a project. However, the establishment of a range of contingencies can
require a considerable amount of work by estimators, so they simply add on a 10%
contingency across the board for example in order to acknowledge the difficulty of pinning
down project uncertainty.

When Euro Tunnel (the private company that owns the tunnel under the English Channel)
went public in 1987 to raise funds for the project, investors were told that building the tunnel
would be relatively straightforward. Under Water (1989:37) reported that, in respect to cost
escalation, the prospectus read:
Whilst the undertaking of a tunneling project of this nature necessarily involves certain
construction risks, the techniques to be used are well proven . . . . The Directors,
having consulted the Mitre dOeuvre, believe that 10% would be a reasonable
allowance for the possible impact of unforeseen circumstances on construction costs.
Cooper et al. (1985) points out that, in estimating the cost of a large hydroelectric
development, the cost variability and uncertainty was acknowledged by incorporating a
contingency allowance in the estimate of 10%. This was calculated as a proportion of the

71
Risk factors leading to cost overrun in the delivery of highway construction projects.

total construction cost after subtracting engineering, management and owners costs. In this
case, the contingency proportion reflects past experience industry practice and the feel of the
cost estimating team.

Touran (2003) proposed a probabilistic model for the calculation of project cost contingency
to counter initial project cost estimates by considering the expected number of changes and
the average cost of change. The model assumed a Poisson arrival pattern for change orders
and independent random variables for various change orders. From these elements, Touran
(2003) calculates the probability of cost overrun for a given contingency level. Touran
(2003) also asserts that project owners, such as transportation agencies, who are usually
engaged in specific types of construction projects can, by reviewing historical data of a
specific transit agency, calculate rates of change, size and distribution of changes and
prepare risk profiles or cumulative probability curves for various values of contingency.
Touran (2003) also suggests that such outcomes can be used at the budgeting phase of new
projects to ensure consideration is given to potential cost overrun after projects commence.

Where there is some form of tender documentation provided for bidders, a portion of the
contingency will usually be transferred to the provisional sums section in these documents.
For construction projects that usually use a governments fixed quantities contract, the
magnitude of the final account variations that comprise additions and omissions can be
compared with the contingencies included in estimates. This comparison can be used to
assess the accuracy of the allowance made for the contingencies at the early estimate stage.
With the traditional approach of informed guessing at contingencies, it can then be perceived
that the size and the level of quality of projects will be affected by the contingency amount.

Estimators tend to include an inflated buffer in the contingency estimate. Raftery (1994)
identifies personal bias and differences in personal risk attitude. Kahnaman and Tversky
(1972) refer to this as conservatism. The term conservatism originated from studies of
human information processing in that individuals tended to revise their opinions in the light
of new evidence to a lesser degree than would be expected of an optimal information
processing system. This tendency for humans to be less extreme than optimal in their
judgements has been termed conservatism in probabilistic information processing.

Moreover, due to the effect of negative sanctions (i.e. imposing a penalty for an
underestimate, where tender bids are above the pretender estimate but no reward/penalty for
an overestimate), an over-exaggerated contingency is not uncommon in many project
estimates. For public works projects, this leads to misallocation of resources as more than
sufficient funds are locked up in projects. Musgrave and Musgrave (1984) reported that the
mis-allocation of resources severely disturbs the important fiscal functions of public sector
spending in the areas of:
1. provision of social goods
2. distribution of income and wealth
3. maintenance of a stable economy in the aspects of employment and price levels.

In the case of public expenditure, the task becomes one of distributing the available fund
allocations among competing projects. Having chosen projects for inclusion, the budgeted
capital expenditure is then committed for the duration of the program. Sometimes project
teams can inflate the contingency allowances in an attempt to avoid the need to seek

72
CHAPTER 2
Literature review into project risks and cost overrun

additional funds if budgets become over spent. However, this inflation can become
exaggerated if there is no heavy call on the contingency fund beyond what might reasonably
have been expected for the project. Consequently, project budgets can be seriously under
spent. The magnitude of under-spending can be so large that it is possible to identify
facilities that were previously foregone but could have been included in a construction
program in the first place. Explaining situations such as this can be just as embarrassing for
clients as seeking additional funds because of budgets being inadequate to meet unforeseen
costs.

In some areas of the public sector, there is a tendency to remove contingency provisions in
budget submission, as contingencies are often seen as fats (Yeo, 1990). Consequently there
is no allowance to express the anticipation of risk or for the lack of confidence in project
estimates. As well, the engineering and construction complexities of projects are often
overshadowed by economic, societal and political challenges. In addition to these challenges,
a number of observers suggest that project estimates are purposely misrepresented in
quantum in an effort to secure project approval (Flyvbjerg et al., 2002).

Contingency can have a major impact on project outcome for a project owner. If contingency
is too high it might encourage poor cost management, cause the project to be uneconomical
and so aborted. It may also lock up funds not available for other projects or activities
(Flyvbjerg et al., 2002). On the other hand, if the contingency allocation is too low, then it
may be too rigid and set an unrealistic financial environment, resulting in unsatisfactory
performance outcomes (Dey et al., 1996).

Under many companies risk management strategies, risks are reviewed at intervals
throughout the life cycle of the project and assessments updated to reflect the current level of
uncertainty surrounding the project (Flyvbjerg et al., 2002). Risks for which contingencies
are provided early in a project may some later time be overcome by further investigation or
design modifications. For example, a contingency allowance for rock in cuttings early in the
project may be replaced by specific quantities and costs following geotechnical
investigations to minimise the specific risk exposure. The amount of contingency is
reassessed at project review points to reflect current knowledge and level of uncertainty of
the project with a view to forecasting the most likely outcome (Dey et al., 1996).

HM Treasury (1993) identifies two major categories of contingency that can be incorporated
into construction projects:
Design contingency this allows for changes during the design process for such
factors as incomplete scope definition and inaccuracy of estimating methods and data
(Clark and Lorenzoni, 1985).
Construction contingency this is for changes during the construction process. Under
a traditional procurement arrangement, the project owner engages others to produce
the design before competitively selecting the construction contractor. Subsequently a
contract is signed between the project owner and the contractor, which typically
contains a variations clause to allow for changes and provide a mechanism for
determining and valuing variations. Construction contingency exists to cater for these
variations allowable under the contract between the project owner and contractor
(Staugas, 1995).

73
Risk factors leading to cost overrun in the delivery of highway construction projects.

Mak and Picken (2000) state that contingency can be compared with the total approved value
of contract variations to assess the accuracy of the contingency.

Baccarini (2004) analysed project cost data of 48 road construction projects from an
Australian government road authority for the estimation of construction contingency. He
reports that the organisation uses a traditional percentage approach for estimating
contingency. The main findings of his analysis include:
Construction contingency is on average 5% of award contract value, whilst variations
were 10% of award contract value. This shows a shortfall in contingency of 4.6%
The amount of estimated contingency is significantly inadequate to cater for the total
value of contact variations, by an average shortfall of 47%
There are no significant correlations between project variables and cost contingency
that might be used to predict cost contingency.

2.25 Literature summary


This chapter has presented some of the crucial findings in the existing theoretical and
empirical literature on risks associated with the delivery of construction projects, particularly
associated with highways and on project cost overrun.

The literature supports the notion that accurate, early cost estimates for engineering and
construction projects are extremely important to the sponsoring organisation. Accurate cost
estimates are vital for business unit decisions that include strategies for asset development,
potential project screening, and resource commitments for further project development. The
literature survey has revealed several research studies on highway construction projects
which attempt to predict the amount a construction contract might increase while taking into
account various factors that could be used in such predictions. Research to date has generally
revolved around the cost increase in contracts within projects. Several research studies have
demonstrated that changes initiated during construction projects have a large effect on their
financial performance. Research also demonstrated that estimating methodology and
accuracy of cost estimates can be major reasons for cost increases. Research studies have
also been conducted in order to predict the extent to which the cost of a construction contract
might increase, taking into account various project prediction factors.

Most research has involved considerable effort investigating the construction aspects of
project delivery and the impact of that on the performance and other aspects of projects.
Changes in construction contracts lead not only to increased costs, but also to contract delays
which then affect project delivery. In the history of construction, the nature of construction
risks has led to many cost overruns. The first step in clients managing risks causing cost
overrun is their identification. In the area of highway project construction, the literature
review has unearthed little empirical research that has determined client risks leading to cost
overrun associated certain types of highway projects and their delivery methods.

The literature review has identified many important stages during the delivery of projects
where the management of construction risks are important. The literature review concludes
that, although many of the risk techniques are effective for the particular types of projects
they were applied to, the approaches generally treat projects as independent entities with
little attempt to categorise projects into specific project sub-types from which detailed

74
CHAPTER 2
Literature review into project risks and cost overrun

analyses can be undertaken. In the past, highway cost estimating models have been
established that describe construction risks as a function of factors believed to influence
construction costs. Typically, the models established in this manner have been used to
estimate the cost of individual contracts only, not project budgets.

Empirical research is now required to assess whether certain highway projects properties and
delivery methods indicate higher propensity to cost overrun. The research needs to be
focused on the client, not the contractor, and with a particular focus on overrun relating to
the decision-to-build baseline budget. The outcome from such an analysis would enable
clients to be in a better position to take advantage of these findings when considering
specific types of future highway construction. Data from different highway types should be
studied to identify if there is any correlation between project cost overrun and the type of
highway project constructed.

Chapter 3 follows and describes the methodology adopted in the research to assess client
cost overruns in highway projects.

75
Risk factors leading to cost overrun in the delivery of highway construction projects.

76
CHAPTER 3
Research methodology

CHAPTER 3

Research methodology

3.1 Introduction
Research methodology is the collection of methods to change or create new beliefs and
knowledge. The term methodology means different things to different people and its
meaning continues to evolve (McCuen, 1996). Research methodology deals with the
methods for creating knowledge about the world and the interpretation of this knowledge in
light of the ontological and epistemological positions (Reich, 1994). Ontology deals with the
nature of the things we know about the world or the nature of the world, while epistemology
deals with the relation between humans and their knowledge. Typical epistemological
questions are:
What can we know?
How do we know?
What is truth?
Is there a priori knowledge, and if so, of what?

The following section provides a general description of the research strategy adopted for this
thesis, as well as justification of the methodology.

3.2 Research strategy


The term research refers to the development a new body of knowledge. Scientific research
refers to the systematic, controlled, rigorous, empirical and critical investigation of a
hypothetical proposition about a presumed relation in order to find the solution to a problem
or discover and interpret new knowledge. McCuen (1996) describes scientific research as
being the investigation of phenomena via practices consistent with the method of science.
Scientific investigation and the verification of beliefs about real world phenomena involve
empirical research based on the belief that all knowledge originates in experience (Stone,
1978). Empirical research deals with facts that have objective reality and is the generic
process followed in the research presented in this thesis.

Engineering and construction management research are seen as systematic processes of


discovering, acquiring, and using new knowledge to solve problems of theory or practice.
The steps followed in an empirical study of a phenomenon are:
1. Observation: an informed and critical questioning of an existing phenomenon leading
to the problem statement and the research question
2. Hypothesis: a formal expression of a preconceived factual relationship which provides
a tentative explanation or solution to the problem
3. Experimentation: the design of the study leading to a systematic and controlled testing
of the hypothesis
4. Induction: a generalisation of the experimental results that leads to a conclusion about
the formal statement of the theory.

77
Risk factors leading to cost overrun in the delivery of highway construction projects.

As well, there are a number of different approaches to empirical research as shown in Figure
3.1.

This figure is not available online.


Please consult the hardcopy thesis
available from the QUT Library

Source: Stone, 1978


Figure 3.1: Empirical research strategies

A common misconception in research is that the various research strategies should be


arranged hierarchically in the following manner (Yin, 2003):
case studies are appropriate for the exploratory phase of an investigation
surveys are appropriate for descriptive phase
experiments are the only way of developing explanations for casual inquires.

However, this hierarchical view of research strategies is incorrect in that experiments with an
explanatory motive have always existed. Yin (2003) also points out that each research
strategy is not distinguished by this hierarchy, but by conditions such as the:
type of research question posed
extent of control that an investigator has over actual behaviour events
degree of focus on contemporary as opposed to historical events.

The first and most important condition for differentiating among the various research
strategies is the identification of the type of research question being asked. The second
condition is the current state of knowledge of the variables involved in the research (Bennett,
1991). In Chapter 1, the following two research questions were formulated:

1. What client risks are present during the delivery of highway construction projects in
Queensland, Australia that lead to significant project cost overruns?
2. How does the amount of highway cost overrun in such highway projects correlate
with their project types, size, delivery processes and client project risks when
historical project data is analysed?

78
CHAPTER 3
Research methodology

Table 3.1 displays the conditions for various research strategies. The what and how research
questions are likely to favour the use of archival analysis, history or case study research
strategies

This table is not available online.


Please consult the hardcopy thesis
available from the QUT Library

Source: Yin, 2003


Table 3.1: Situations for differing research strategies

Historical research is concerned with historical events or approach to contemporary events or


problems. As well, historical research can be utilised to help solve a current problem through
an examination of what has happened in the past (Bennett, 1991). The three basic steps in the
historical method are the collection of data, the analysis and criticism of the data and finally
its presentation. Bennett (1991) points out that when the problem under investigation is of
more recent historical origin, then data and facts can be available but may not necessarily be
collected in the form needed in order to describe and understand the problem. There are two
ways to look at the historical approach to a research problem:
Data may be collected to describe the field at a particular point in time (cross-
sectional study), or
The development of the problem may be described over a period of time (referred to
as a longitudinal historical study).

On the other hand, although a survey is a strategy that allows a researcher to collect data
directly from sources in a systematic fashion, there are some important disadvantages (Stone,
1978). These include:
decreased willingness or refusal of people to respond to survey probes, because of
suspicion, fear and other form of resistance
most surveys are one-offs and so their capacity to generate data with which to test
causal connections among variables is limited
the sample survey can be an extremely expensive research strategy because of
administrative and personal costs
standardised response formats of many sample surveys may force respondents to
subscribe to statements they dont fully endorse
surveys that are used to collect data may have low response rates.

79
Risk factors leading to cost overrun in the delivery of highway construction projects.

This research adopts the historical analysis approach as the required methodology as it
provides an insight into the current research problem through the examination of what had
happened in the past using analysis, analogy and trend extrapolation of historic data.

3.3 The research procedure


The research procedure for this thesis includes for the following:
clear understanding of the problem being studied
definition of the research objectives
description and justification of the point of departure
identification of fundamental research issues
definition of all the elements and components that comprise the investigation
a clear methodology to perform the investigation.

The approach entails researching construction delivery practices to identify risk occurrences
as well as risk constraints and processes to minimise client risk exposure during project
delivery that lead to cost overrun. It has also provided a means for the development of a
consensus of risk factors based on expert opinions and trend exploration and model
development of cost overrun based on historical project data and project attributes. The main
activities of this investigation have been presented in Figure 3.2 which provides a detailed
explanation of the research process based on the research plan.

Data / information/
knowledge/
experience Results

Literature review Project


construction
risks
Problem identification

Project attributes.
Establish study data. Factor analysis Modelling of cost
Build databases for of cost overrun overrun factors
Conclusions
data collection. data for using multivariate
Recommendation
highways regression
Further research
analysis.
options
Determine cost Develop
overrun factors. principal cost
Determine highway overrun factors
project types. in project types

Figure 3.2: Main research activities

80
CHAPTER 3
Research methodology

3.4 Research steps


The five stages involved in the conduct of the research are outlined in Table 3.2 below.

Stage Research procedure


1 Literature research to determine research focus.

2 Establish data sources of highway construction projects.

a) Determine cost overrun factors from historic project data


3
b) Use factor analysis (principal component analysis) and factor rotation on cost
overrun factors to consolidate data.

Use nominal group technique (NGT) to elicit, review and prioritise principal cost overrun
4
risk groupings and highway project types.

Undertake data analysis and statistical modelling using multivariate linear regression
5 analysis. Establish correlations between client risks causing cost overrun, project attributes
and project programmed cost.

Table 3.2: Research procedures

The following sections explain the justification and conduct of the individual methodology
stages adopted in the research.

3.5 Stage 1: Review literature


The aim of the literature review was to examine previous research and identify the gaps in
current knowledge. This stage also assisted in determining the context of the research study
and help position this work relative to previous works. It also assisted in the
conceptualisation of the research areas sufficiently to develop the main focus of the research,
influence the research design and generate specific hypotheses to be tested.

This first stage focused on a thorough review and evaluation of the research literature
relating to the research topic. This included topics such as:
nature of project risk and uncertainty
organisation risk culture
project risk management
project procurement practices in managing construction risk
improving project delivery methods so as to manage risk
pre-qualification linkages to contract default
bid evaluation and contract selection practices
project budget estimating procedures
final project cost forecasting
role of contingency in managing cost overrun
expert elicitation of project risks.

81
Risk factors leading to cost overrun in the delivery of highway construction projects.

Different media modes, such as project contract documents, electronic databases,


direct/telephone interviews, as well as internet search engines were used. The literature
review also focused on determining risk cost factors from previous research studies that
influence cost changes in construction projects. Also, in this first stage, unstructured
interviews were conducted to initially collect ideas rather than collect data. The primary
objective of these interviews was for them to serve as fact-finding missions, and their largely
unstructured format aided in the identification of the important research concepts.
Discussions and meetings were held with project clients, construction industry project
managers, estimators and construction management academics.

3.6 Stage 2: Establish data source of highway construction projects


Semi-structured interviews of construction industry representatives identified project data
sources for construction cost overrun. This process also provided some opportunity to
evaluate individual practitioners tacit knowledge, based on their project management
experience.

The research stage required a sample of highway infrastructure projects that was appropriate
for this area of research. The data sample was required to be large enough to allow statistical
analyses of cost overrun factors and project costs. Data on actual costs in transportation
infrastructure projects were relatively difficult to come by. One reason is that such data is
time consuming to generate. For private projects, such data are often classified as
commercial-in-confidence and thus kept from the hands of competitors. Unfortunately, this
also tends to keep private project data from the hands of researchers. For both public and
private projects, data on actual costs have been held back by project owners because more
often than not, actual costs reveal substantial cost escalation that was often considered an
embarrassment to project owners. For public sector projects, funding and accounting
procedures often made it difficult to keep track of the multiple and complex changes that
occur in total project costs over time. For large public projects, reconstructing their actual
total costs would typically entail long and difficult archival work and complex accounting.

The study for this research into cost overrun into various types of highway construction
projects focused on a state highway authority that manages a network of highways and
bridges network within the state of Queensland, Australia. The authority is the Queensland
Department of Main Roads (QDMR) and it is responsible for the 34,000 kilometres of the
states highway network, representing 20% of Queenslands total road network of 174,000
kilometres. It also manages 2740 bridges and 20,000 major culverts. This highway network
represents the states largest single physical asset, with a replacement value in 2005 of
A$26.6 billion.

Queenslands highway network traverses a wide variety of geographic features that make its
highway network unique in Australia. These features include:
freight/tourist passenger routes that traverse coastal topography requiring high
capacity hydraulic designs to accommodate high flood immunity and speedy water
runoff
highway routes that traverse mountainous topography requiring limits on climbing
and descent design grades to accommodate heavy highway freight movements
high traffic density urban highway networks

82
CHAPTER 3
Research methodology

low volume rural main road network interconnecting low rainfall semi-arid regional
centres
high volume national highway and main road networks that are located in coastal
tropical climates with extremely high seasonal rainfalls
medium volume national highway freight corridor that is located predominately in
low rainfall semi-arid and arid rural regions but with expansive soils and unseasonal
extreme weather conditions necessitating specialised pavement designs
limited availability of high quality road-making materials in most rural areas,
necessitating long distance haulage of road making materials
regional transport regulations that allow volume loading of multiple articulated cattle
road trains requiring a network of high speed, high strength, all-weather and wide
highway pavements.

The research was validly limited to the highway network of the state of Queensland. No
other highway network in Australia that has this combination of unique and diversified
geographic and functional constraints and limitations are managed by the one highway
organisation.

The research focused on highway infrastructure projects from QDMR that contained data on
substantial project cost overruns.The highway project construction data was collected from
the published Roads Implementation Program Yearbooks of the Queensland Department of
Main Roads (QDMR) over the period from 1995 to 2003 with a portfolio of projects in the
sample worth approximately A$1 billion. The data were available as published documents.

The project construction cost data was selected on the basis of data availability and all
projects that were known to have information on substantial cost overrun were considered
for inclusion. The construction projects covered 78 different local authority geographic areas
of Queensland out of a total of 125. They represent state highway works in 65% of the
administrative areas of Queensland over the stated time period.

All projects subsequently analysed were those delivered by the traditional design-bid-build
method. The use of project data using this delivery mechanism was justified as there is
considerable support worldwide for delivery of infrastructure projects, such as highways,
using the traditional method. In a global perspective, the delivery of capital infrastructure
investment projects varies in practice from country to country, however, highway
infrastructure project delivery in such countries as Australia, Canada, Great Britain, New
Zealand, Sweden and the US all use the traditional model of design-bid-build in the great
majority of cases (Pakkala, 2002).

It is important to note that the project programmed cost was defined as budgeted project
construction cost at the time of the decision to build the project. This was consistent with
Flyvbjerg et al. (2002) who pointed out that the decision-to-build estimate method focused
on decision making and hence on the accuracy of the information available to decision
makers. It was this cost estimate at the time of making the decision to build that was of
primary interest in the research. This decision-to-build value was also the international
standard for measuring the inaccuracy of cost estimates (National Audit Office and
Department of Transport, 1992; Nijkamp and Ubbels, 1999). For the purpose of the research,
the total project cost estimate included the estimated costs of all component activities from
the initiation of the project design to construction finalisation.

83
Risk factors leading to cost overrun in the delivery of highway construction projects.

These included the costs of:


conducting investigations and developing the design
detailing the design
acquiring land
altering public utility plant
construction
project administration and handover.

The sampling criterion was that of data availability. The highway project construction data
available was only available in a consistent format from 1995 and so did not allow an
assessment of cost overrun prior to 1995. While the project sample was not perfect, it was
considered by the researcher to be the best obtainable, given the limited availability of useful
data in the public domain in this field of research. A data integrity process also required to
ensure that the data presented was true and factual representations of the highway
organisation's historic data. since that data was contained within documents which
represented public statements of the organisations planning, construction and maintenance
activities of the state government, then it was considered that the facts contained within these
documents were true and factual. Each document was authorised by both the state
government Minister and the Director General of the state highway organisation.

3.6.1 Indexing of historical road project prices

Indicators of price movement of construction outputs are a valuable tool in economic


analysis and construction industry output price indexes have been developed to enable the
measurement of changes over time in the price of new construction outputs of building roads
and bridges. A price index is different to a cost index in that it does not provide an indication
of the actual cost of constructing and maintaining roads. Its main purpose is to provide a way
of deriving constant prices for inputs to road expenditure and maintenance. The input
components to the index consist of labour, materials and plant. The prices that have the most
influence on the index are those for the provision of labour, fuel, bitumen, quarry products
and plant hire. Among these inputs labour, bitumen and fuel have had the largest average
increase over the life of the index .These industry output price indexes are primarily used as
deflators in the calculation of volume estimates of capital expenditure in the Australian
National Accounts. Construction output indexes are also used for contract adjustment and
asset revaluation. Two forms of indices have been specifically available from the Australian
Bureau of Statistics (ABS). These are:
1. Price Index of the Output of the Road and Bridge Construction Industry
2. The Road Input Cost Index.

Price Index of the Output of the Road and Bridge Construction Industry: This index was first
produced in an experimental form in the March quarter 2000, and first published in the
September 2002 issue of Producer Price Indexes, Australia (ABS catalogue no. 6427.0).

The Road Input Cost Index (RICI): Price indexes for highway projects in Queensland have
been indexed since 1984 and up to 30 June 2004 by the application of a calculated index.

The RICI was used in this research to index up the historical highway costs because it
provided the only continuous highway focused price indices for the financial years
1995/1996 through to 2002/2003 for which the historic project data were available. The

84
CHAPTER 3
Research methodology

Road and Bridge Construction Price Index was not adopted as the index was only time-series
back calculated to an index reference period of 199899 = 100.

3.7 Stage 3: (a) Determine cost overrun factors from


historic project data.

The first step in stage three the research required the determination of highway work types
and project cost overrun factors. The available highway data contained individual
descriptions of all the work types as well as the reasons for individual projects having
exceeded the clients programmed budget. These work types and reasons for cost overrun
were recorded in Excel spreadsheets by the researcher. Where common work types or cost
overrun factors occurred across projects, single work types and cost factors were recorded to
cover incidences. All unique work types and reasons for cost overrun were recorded
individually. The research process used the experience in highway construction and the
professional judgement of the researcher to determine the listings of work types and reasons
for cost overrun.

The focus of this analysis was based on the clients exposure to project cost overrun, not that
of contractors delivering the projects. The client focus required that a number of
considerations that were identified in the literature research had to be taken into account
when reporting the cost overrun factors. These included:
the use of design-bid-build contracts that could lead to higher client exposure to
design risks
pre-qualification of contractors that has the potential to limit client risk exposure to
contract default
contract payment types that focused on schedule of rates and bill of quantities
contract clauses that were designed to reduce the clients exposure to certain
construction risks
tender evaluation techniques
contract provisions that limit the client's exposure to adverse physical and latent
conditions and wet weather events.

3.8 Stage 3: (b) Factor analysis using principal component


analysis and factor rotation on cost overrun factors to consolidate
data
The second step in stage three of the research required the development of consolidated
groupings of high level project risk factors contributing to cost overrun in highway
construction projects. The most relevant classical risk research on qualitative aspects of risk
is that of Slovic et al. (1980) in which they utilised factor analysis (principal component
analysis) to reduce many qualitative risk characteristics or attributes to a much smaller
number of higher order factors. In discussing this original research, Gregory and Mendelson
(1993) noted that the original factor analysis conducted by Slovic, Fischhoff and Lichenstein
has been granted classic status in the field of risk perception.

3.8.1 Factoring methods

There are different methods of extracting the factors from a set of data. The method chosen
matters more when the sample is small, the variables are few, and/or the communality

85
Risk factors leading to cost overrun in the delivery of highway construction projects.

estimates of the variables differ. By far the most common form of factor analysis is Principal
components analysis (PCA). PCA seeks a linear combination of variables such that the
maximum variance is extracted from the variables. It then removes this variance and seeks a
second linear combination which explains the maximum proportion of the remaining
variance, and so on. This is called the principal axis method and results in orthogonal
(uncorrelated) factors. PCA analyses total (common and unique) variance.

The PCA technique of factor analysis was considered appropriate because of the limited a
priori knowledge available about the number of different cluster relationships that could be
expected for the data sample. The literature also indicated that PCA provided a deterministic
method to group elements into meaningful subdivisions in order to overcome
multicollinearity problems in the project data. As well, it was a statistical procedure that
could uncover relationships among many variables and in the context of this research the
variables were the specific cost overrun reasons in highway construction projects. In the
factor analysis technique, correlations and interactions among variables are summarised into
a small number of underlying factors. The method aimed at identifying key variables or
groups of variables that controlled the cost overrun system under study.

In adopting PCA, there were four decisions that needed consideration as part of the factor
analysis methodology. These were:
1. method of factor extraction
2. sample size
3. type of factor rotation
4. number of reduced factors (components) to be adopted.

The next sections look at these four requirements.

3.8.2 Method of factor extraction

There are different methods of extracting the factors from a set of data. The method chosen
matters more when the sample is small, the variables are few, and/or the communality
estimates of the variables differ. By far the most common form of factor analysis is Principal
components analysis (PCA). PCA seeks a linear combination of variables such that the
maximum variance is extracted from the variables. It then removes this variance and seeks a
second linear combination which explains the maximum proportion of the remaining
variance, and so on. This is called the principal axis method and results in orthogonal
(uncorrelated) factors. PCA analyses total (common and unique) variance. The PCA
technique is appropriate where a limited a priori knowledge is available concerning the
number of different cluster relationships that could be expected for the data sample (Hair et
al., 1998). PCA also provides a deterministic method to group elements into meaningful
subdivisions in order to overcome multicollinearity problems in the project data.

3.8.3 Sample size for factor analysis

Guidelines for the minimum sample size needed to conduct factor analysis suggested a
minimum sample size of 100 to 200 observations (Guadagnoli and Velicer, 1988). Some
researchers have suggested the ratio of sample size to number of variables as a criterion, with
recommendations ranging from 2:1 through to 20:1. PCA requires a large sample size. It is
based on the correlation of the variables involved, and correlations usually need a large

86
CHAPTER 3
Research methodology

sample size before they stabilise. Tabachnick and Fidell (2001: 588) have advised the
following regarding sample size: 50 observations is very poor, 100 is poor, 200 is fair, 300 is
good, 500 is very good and 1000 or more is excellent. As a rule of thumb, a bare minimum
of 10 observations per variable is desirable to avoid computational difficulties.

3.8.4 Type of factor rotation employed

In order to facilitate the interpretation of factors, factor analysis requires the rotation of axes.
The rotation procedure does not affect the goodness-of-fit of the factor solutions but serves
to make the output more understandable. Three rotation techniques are in general use:
varimax, equimax and quartermax. Of these, the most popular is Kaiser's varimax algorithm,
which is known to provide the best parsimonious analytical solution (Harman, 1967). This
minimises the number of variables with high loadings on factors, thus causing the factor
loadings of each variable to be more clearly differentiated.

3.8.5 Number of factors in analysis

An important decision is the determination of the number of factors to be extracted and


several guidelines are available for this. One of the most common is the minimum
eigenvalue criterion. Essentially this method involved taking the principal components of all
the variables, ranking their eigenvalues from highest to lowest, then the number of
eigenvalue greater than one was selected as the criteria for the number of factors included in
the analysis.

The scree plot of eigenvalues against the number of factors was also used as part of this
process. The plot was used to show the point at which the eigenvalues began to level off and
this plot was used as a cut-off point to support the adoption of the desired number of factors
(Velicer and Jackson, 1990).

3.8.6 Characteristics of samples in the factor analysis

Several pre-tests are available to measure the sample characteristics necessary for successful
factor analysis. One is the Kaiser Meyer Olkins test (KMO) for sampling adequacy. KMO
values vary from 0 to 1.0 and values closer to 1 are better. An overall KMO should be 0.60
or higher to develop successful factor analysis (Hutcheson and Sofroniou, 1999). Another
test is the Bartlett Test of Sphericity, which checks if the sample was randomly drawn from a
population in which the correlation matrix was an identity matrix. This uses the determinant
of the correlation matrix to tests the null hypothesis that the correlation matrix is an identity
matrix using a chi-square approximation (Bartlett, 1947) and is particularly relevant when
dealing with a relatively small sample of data (<100) and with a relatively large number of
variables (>10). The Bartlett test sets up a chi-square approximation to determine whether
the developed correlation matrix is an identical matrix in the analysis. Bartletts sphericity
test is particularly relevant when dealing with a relatively small sample of data (<100) and
with a relatively large number of variables (>10). A minimum value of 700 was adopted for
the Bartlett test (Hutcheson and Sofroniou, 1999).

A further test is to examine the Anti-Image correlation matrix. The diagonals on the matrix
should have an overall Measure of Sampling Adequacy (MSA) of 0.5 or above (Hair et al.,
1998). Individual variables can be considered for elimination from the analysis if they are

87
Risk factors leading to cost overrun in the delivery of highway construction projects.

low on this measure.

3.9 Stage 4: Use nominal group technique (NGT) to elicit, review and
prioritize cost overrun risk groupings and highway project types

Stage four of the research methodology involved the elicitation of the grouping of cost
overrun factors from experts. Elicitation using experts has been a formal process of obtaining
information or answers to specific questions where the information was highly subjective.
The process has been used by quite a number of disciplines (Ayyub and McCue, 1997).
Koskinen et al. (2002) explain tacit knowledge as expressing itself in human actions in the
form of evaluations, attitudes, points of view, commitments and motivation. The expert
elicitation was adopted in order to obtain a comparison between the factors derived from the
factor analysis technique and those obtained from carrying out an expert elicitation process.

From previous interviews by the researcher, it was important to take note of interviewees
concerns about time management. In the rapidly paced world of construction management, it
was found that an expert elicitation method needed to be efficient because experts in
construction management were continually confronted with insufficient time (Laufer, 1996).
The selection of the elicitation technique was therefore determined to a large extent by the
time that experts were prepared to allocate to the research project.

A number of techniques were available that provided the opportunity to evaluate tacit
knowledge based on the experience of individual practitioners. The three expert elicitation
techniques considered for the research project were:
1. focus group
2. Delphi technique
3. nominal group technique.

3.9.1 Focus group

Focus group research had long been prominent in marketing studies (Morgan, 1997), in part
because market researchers sought to tap emotional and unconscious motivations not
amenable to the structured questions of conventional survey research. It was reported that the
interaction among focus group participants brought out a range of perspectives through the
language that was used by the members. The reactions of each person spark ideas in others,
and one person may fill in a gap left by others.

The difference between focus group research and group interviewing was important in
considering the appropriate technique. In group interviewing, a standard survey instrument is
administered to respondents simultaneously. In contrast, there is no standard instrument in
focus group studies, only a topic being explored through the exchange of group discussion.
Survey research required a priori theory or at least a list of subtopics as a guide for selection
of items to be included in the survey instrument. In focus group research, there was no a
priori theory.

3.9.2 Delphi technique

Linstone and Turoff (1975) identified the Delphi technique as one form of anonymously
eliciting the opinions of experts concerning events and the reasoning behind the opinions. In

88
CHAPTER 3
Research methodology

the process, experts are asked to revise their opinions in the light of the information
contained in the feedback. This sequence of questionnaire and revision is repeated until no
further significant opinion changes are expected. Sackman (1972) identified important
shortcomings in the Delphi which were important in considering the form of elicitation that
was adopted in this research project. These shortcomings were characterised as:
information and questions provided to experts needed to be carefully reviewed to
ensure objectivity
difficulty in summarising and presenting a common evaluation scale to a group that
could be interpreted uniformly by the experts
benefits of experts participating in active dialogue was missed
difficult and time consuming in exploring disagreements between experts.

3.9.3 Nominal group technique

Originally developed as an organisational planning technique by Delbecq, Van de Ven and


Gustafson in 1971, the nominal group technique is a consensus planning tool that helps
prioritise issues (Delbecq et al., 1986). In the nominal group technique, participants are
brought together for a discussion session led by a moderator. The nominal group technique
has been used as an alternative to the focus group and the Delphi techniques. It presents
more structure than the focus group, but still takes advantage of the synergy created by group
participants. As its name suggests, the nominal group technique is only nominally a group,
since the rankings are provided on an individual basis. The nominal group technique
involves a process similar to the Delphi method (Dalkey, 1968) with the objective of the
technique being the exploration of ideas for decisions from a team of experts (Adler and
Ziglio, 1996). The prime difference between NGT and the Delphi technique was that
communication does take place between participating individuals within the NGT method.
As well, NGT separated out the process of independent ideas generation, structured
feedback, evaluation and aggregation of opinions. It increases individual participation.
Detailed research by Gustafson et al (1973) showed that NGT was superior to Delphi.
Advantages of NGT were that:
voting was anonymous
there were opportunities for equal participation of group members
distractions (communication noise) inherent in other group methods were minimised.

Delbecq et al. (1986) summarises the NGT decision making process used as:
1. silent generation of ideas
2. round-robin feedback from group members to record ideas
3. discussion of each recorded item for clarification and evaluation
4. individual voting on priority of items with the group decision being mathematically
derived through rank-ordering or rating.

The use of face-to-face meetings to reach agreement sometimes causes problems because:
a senior member of the group (e.g. a boss or person with a dominant personality)
could sway opinions in a manner inconsistent with the information presented
people could be unwilling to change opinions when stated publicly
people could grandstand or posture by sticking to beliefs that may not have been
appropriate, and so show they were actively engaged in the process.

89
Risk factors leading to cost overrun in the delivery of highway construction projects.

All these issues are needed to be managed properly in an elicitation process (Lifson, 1972).
The Nominal group technique was seen as providing the most appropriate method for
eliciting expert opinion as it had to potential to demand less valuable time from the experts
and still provide the appropriate focus and outcome sought.

3.9.4 Selection of experts for NGT process

Possible candidates to the nominal group panel were considered from within several sources:
professional organisations
project management consultants
contracting organisations
client organisations.

All potential group members were contacted via telephone to determine their willingness to
participate in the research and whether they met the following criteria for selection:
over ten years of contract management experience in highway construction projects
had acted in the role of the client representative in at least three infrastructure
construction projects
willing to participate in the entire process
willing to share ideas regarding construction/contract risk assessment and analysis
techniques as part of the research.

A questionnaire was used to obtain relevant information about individuals that profiled
potential members. The quality expert elicitation process involves at least three types of
participants:
1. specialist
2. analyst, and
3. generalist (Keeney and von Winterfeldt, 1991).

1. Specialist: The specialist should be at the forefront of knowledge in their field, and be
recognised as leaders by their peers. They should have the command of knowledge and
flexibility of thought to apply their expertise to the issue at hand. As well, they should be
capable of translating their knowledge into judgements relevant to the problem.

2. Analyst: The analyst conducts the elicitation of the judgement of specialists. Analysts
have knowledge and expertise in statistics, probability theory and decision analysis, as well
as having experience with expert elicitation processes. Their task was seen as assisting the
specialists to formulate the issues, to decompose them, to articulate their judgements, to
check consistency and to help document the specialists reasoning.

3. Generalist: It was important to include the generalist in any elicitation in any complex
technological problems where the application of the specialist knowledge to the overall
problem is not obvious. Generalists are experts with broad knowledge about many or all of
the issues under study. Generalists do not need to be at the forefront of their field, but they
should excel at communicating with the specialists, especially in the translation of project
needs into specialist language. Generalists facilitate the essential bridging between various
issues.

90
CHAPTER 3
Research methodology

3.9.5 Group composition

Group composition and characteristics are determined by its size and member characteristics.
When considering the size of the group, there were two conflicting tendencies to consider.
An increase in the group size would be accompanied by an increase in diversity of skills,
experience and knowledge. However, the increased group size could also result in a decrease
in individual participation as the larger a group gets the more distorted the issues become in
favour of those members with low thresholds of participation (Chapman, 1998). Also, as the
size of the group increases, the intimacy of interaction decreases, with more members feeling
threatened and inhibited from participation because of the increased impersonality of the
situation. In addition, the size of group membership tends to be related to cohesiveness with
the greater the size of the group, the lower the cohesiveness. Many studies have identified
the conditions under which groups tend to become more cohesive. These include physical
proximity, similarity of work, homogeneity or similarity of attitudes and values, ease of
communication and limiting the size of the group to ideally below 12 (Chapman, 1998).

Research in expert elicitation suggested that five specialists were usually sufficient to cover
most of the expertise and breadth of opinion (Clemen and Winkler, 1985). As well, they
suggested that there may be a need for two or three additional generalists and two or three
analysts. For some issues, the diversity of opinions of the set of experts was important, as
was the individuals expert credentials.

3.9.6 Ranking process

A Likert scale was used in the NGT process to record the comfort level that workshop
participants felt in regard to decisions made by the group. Likert scales and Likert-type
scales (the latter also known as rating scales) are a type of scale that is commonly used to
measure human constructs (Vojir, et al.) The direct application of the Likert scale has often
been adopted in multi-criteria decision making models. The one disadvantage of this scale
method is that it does not allow a fuzzy range of importance to fit through a weighting
assessment.

For ranking the importance of project risk factors to the potential for cost overrun, it was
considered that a collation of the mean and standard deviation of all the participant scores
provided for each grouping would not adequately determine an overall relative ranking as
this would not reflect any relationship between the groupings (Chan and Kumaraswamy,
1997). Therefore the ranking was determined by calculating the Importance Index for each
group, using the following formula:

Importance Index = 100 ( w f )


WF

Where w was the weighting, ranging from 1 to 10, given to each factor; W was the highest
weight, i.e. 10; f was the frequency of the response; and F was the total number of NGT
workshop participants.

91
Risk factors leading to cost overrun in the delivery of highway construction projects.

3.9.7 NGT workshop evaluation

The final step in the nominal group technique involved the workshop evaluation completed
by the expert group. This sought feedback on the NGT process, the process data provided
and the timing and composition of the workshop.

3.10 Stage 5: Undertake data analysis and statistical modelling


This final stage of the research process involved the investigation into statistical models
which can explain the correlation between the cause, effect and other relationships relating to
cost overrun in highway construction projects. While the term model can be used in many
ways (Emory, 1980), for this research it referred to the dynamic framework or schema that
helps portray key concepts and propositions of the research phenomenon.

A model may be highly conceptual or theoretical, developed at the start of a piece of


research, and then tested through the process of data gathering, analysis and reasoning. On
the other hand, a model may be the end product of research, with little by way of a
conceptual framework available at the start of this research (Bennett, 1991). The research
model was developed as the end product of the overall research into cost overrun of highway
project costs.

Results from analysis of models can often provide valuable contributions to knowledge bases
used for decision making (Nilsen and Aven, 2003). However, the development of the model
also implies the trading off of complexity in order to provide satisfactory representation of
the system under study. The ultimate goal of the statistical modelling process was not just to
produce a model but also provide one that was sufficiently credible and acceptable to
decision makers. In addition, a robust statistical technique was needed that would cope with
any undetected data outliers, otherwise the results of the model could have proved
misleading. Within the general classification of a model, there have been a variety of model
techniques that have been applied in the analysis of risk variables. Some are shown in Table
3.4 below.

This table is not available online.


Please consult the hardcopy thesis
available from the QUT Library

Source: Bennett, 1991


Table 3.4: Model techniques

92
CHAPTER 3
Research methodology

The method of quantification and the analysis techniques that can be used are dependent on
each other, and both are restricted by the information available. Some of the techniques
noted, particularly the network-based solutions, require a large amount of information that is
not always available. Monte Carlo analysis technique has often been used in simulation and
sensitivity analysis to determine the significance of individual sources of project risk and
other project factors such as cost overrun (Flanagan and Norman, 1993). However, given
that a sensitivity analysis is univariate and the effects of project cost overruns are numerous
and vary simultaneously, the use of Monte Carlo analysis in this research was not considered
appropriate.

Data mining was seen as a useful research tool for pre-processing structured information
from available data and using statistical analysis to uncover patterns and relationships hidden
in project related databases. It was reported that data mining compresses even more value
out of repositories of information (Marco, 2000).

Multivariate statistical analysis is a scientific inference used in analytical work where the
problem of inferring from sets of performance measurements on a number of individuals of
objects is constantly faced. The history of science confirms that such inferences can be
successful, and can handle inferred reality as well as a means of reducing the number of
variables. Researchers in sciences such as behavioral, biological or physical have long since
abandoned sole reliance on classical analysis methods (El-Choum, 1994). The construction
industry has been seen as a good example as each project is unique and therefore, separate
treatment is needed to overcome major difficulties that cannot be noticed otherwise.

With multivariate statistical techniques two functions can be derived these correspond to
the distinction between descriptive and inferential statistics. Descriptive statistics requires no
assumptions whatever about the distributions from which observations have been sampled,
while most common multivariate significance tests have been based on homogeneity and
normality assumptions.

Multivariate regression technique was seen as the most effective tool to manage multiple
project variables in the development of a model to determine relationships between projects,
project risks and project cost overrun. Multivariate regression has been the most common
method of modelling construction costs in the past (Koppula, 1981; Blair et al., 1993; Elhag
and Boussebaine, 1998). Multivariate regression is the estimation of the conditional
expectation of a random variable given other random variables and involves providing model
solutions which could be used as the basis for decision making (Mason et al., 1989; Neter et
al., 1990).

Preliminary data analysis showed, on examination, a degree of linear relationship between


dependent and individual independent project variables. This indicated that multivariate
regression was ideal for examining project variable relationships in this type of data (Lewis-
Beck, 1993). Linear statistical models have been used for several reasons:
they can easily be used by construction site engineers and management
visual data inspection shows linear trends in initial project cost data using scatter
diagrams.

The multivariate statistical analysis method is designed for an assortment of descriptive and
inferential techniques that can either predict or measure sets of variables as found in
construction cost forecasting. Regression analysis can summarise data and qualify the nature

93
Risk factors leading to cost overrun in the delivery of highway construction projects.

and strength of relationships among the variables. New values of dependent variables based
on observed values can also be predicted by using regression analysis. The method was used
to assesses the strength of the relationship between each of a set of explanatory variables
(sometimes known as independent variables) and a single response (or dependent) variable.
Although there were several alternative techniques available in regression, the research
method adopted was the method of least squares.

Before using regression analysis, it was necessary to understand assumptions and limitations
of the processes. The following key factors were considered when the multivariate
regression model was developed (Carver and Nash, 2005):
problem formulation
adequate, high quality project data
selection of appropriate project variables.

Problem formulation: Studying the relationship of multiple project and cost overrun
variables is especially troublesome because the desired knowledge is complex in nature and
many different combinations of factors are needed to be examined. As well, it is impractical
and difficult to make use of a large number of parameters in the model. However, with the
complexities in construction, these parameters were amplified and it was necessary to
identify the key factors before they were used in the model. The focus of this part of the
research project was a decision-oriented model in the highway project construction
environment which had a statistical approach and which used the relationship between
qualitative project variables in order to define the correlation between project cost overrun
and the number of variables associated with the projects being analysed.

Adequate, high quality data: The project data consisted of two types quantitative and
qualitative. Quantitative data represented the quantity or amount of an element. As an
example, the dependent variable of the proposed model (cost estimate percentage overrun) is
a quantitative variable (Marco, 2000). In contrast, qualitative (or categorical) data, for
example the project delivery method or the reasons for the cost overrun, require no
quantitative interpretation and so are only classified into categories (Kantardzic, 2003).

Selection of appropriate variables: The aim of this stage of the research was to identify if
any project variables had a relationship to the accuracy of project cost contingency, for
example project size or location. Any project variables that were found to have a relationship
could then be used to predict more accurate project cost contingencies; or simply highlight to
estimators that when these variables were present, then there was a need to pay particular
attention to them in estimating.

Variable relationships can take on many different forms, most of which can be extremely
difficult to handle in a regression analysis. In many instances it may not be reasonable to
assume a linear relationship between the dependent variable and the independent variables.
This fact has often become obvious when constructing useful scatter diagrams of sample
observations. For this thesis, it has been assumed that the variables are linearly related and
the relationship between Y and each of the independent variables was linear.

Multivariate regression analysis was used and applied to the set of historical data to
investigate the development of a cost overrun model in terms of a regression coefficient for
each explanatory variable. The multiple regression took the form of the following model:

94
CHAPTER 3
Research methodology

Source: Lewis-Beck, 1993.

where Y was a dependent variable (i.e. % or project cost overrun), a0 was a constant
indicating the intersect with Y axis, bn were partial regression coefficients, Xn were
independent variables, and e was the error term. The standardised versions of the bn
coefficients were the beta weights, and the ratio of the beta coefficients was the ratio of the
relative predictive power of the independent variables under consideration.

The purpose of the model was to predict the value of an observable quantity Y = (X) in
terms of a set of quantities X = (X, X2, X3,.Xn.), and the functional relationship ()
between Y and X. The function was typically established on the basis of a mixture of
accepted intuitive assumptions developed from the researchers experience in highway
construction regarding the data being analysed (Nilsen and Aven, 2003).

The usefulness of the multiple regression models was judged by the value of the multiple
correlation coefficients and by the examination of residuals. The performance of the model
was tested using Pearson's correlation coefficients.

Applying multivariate regression analysis to a set of data results in what are known as
regression coefficients, one for each explanatory variable. These coefficients give the
estimated change in the response variable associated with a unit change in the corresponding
explanatory variable, conditional on the other explanatory variables remaining constant. The
fit of a multivariate regression model can be judged in various ways, for example,
calculation of the multiple correlation coefficient or by the examination of residuals.

The reason is that the regression coefficients and their associated standard errors are
estimated conditional on the other explanatory variables in the current model. Consequently,
if a variable is removed from the model, the regression coefficients of the remaining
variables (and their standard errors) will change when estimated from the data excluding this
variable. As a result of this complication, other procedures have been developed for selecting
a subset of explanatory variables, most associated with the response.

3.10.1 Regression analysis basis assumptions

The basic assumptions/requirements that needed to be satisfied in the model analysis using
least squares estimation to yield reliable estimates of a and b in the regression models, the
following are to be satisfied:
Normality: at each possible value of X , the random disturbances are normally
distributed
Zero mean: at each possible value of X, the mean of the random disturbances is zero
Homogeneity of variance: at each possible value of X, the variance of the random
disturbance is constant
Independence: at each possible value of X, the value of the variance is independent of
all other deviations.

If these conditions are not satisfied then there is the risk that any inferences about tests for
significance and confidence intervals will become misleading. Because random disturbances
cannot be directly observed in a model as the location of a true regression line cannot be

95
Risk factors leading to cost overrun in the delivery of highway construction projects.

known, then it was planned to examine the hypothesised relationship that is known as
residuals or the differences between an estimated regression line and observed Y values.

3.10.2 Correlation analysis

In order to identify any project variables that may be correlated with project cost overrun, a
correlation analysis is undertaken. This technique examines the performance of the models
and the relationship between variables. The correlation coefficient (R) is a measure of how
the actual and predicted correlate to each other in terms of direction. Values for R range
from 0 to 1. The closer the correlation value is to 1, the more correlated the actual, and
predicted values are. Pearson's correlation (R) was used to examine the relationship between
data that was collected on an interval or ratio scale (Norusis, 2005).

Whilst there are several different criteria that can be used for developing the rank order of
regression models in terms of goodness of fit, the most often used criteria was the R2 and
adjusted R2 statistics. The R2 was adopted in the research as it allowed direct comparison of
the best model identified (Neter et al., 1990). R2 (coeffiecient of multiple determination) is a
statistical indicator usually applied to multiple regression analysis. It compares the accuracy
of a regression model to the accuracy of a trivial benchmark model wherein the prediction is
the average of all the example output values.

3.10.3 Statistical regression

Statistical regression is a way of computing the method of least squares in stages. In stage
one, the independent best correlated with the dependent is included in the equation. In the
second stage, the remaining independent with the highest partial correlation with the
dependent, controlling for the first independent, is entered. This process was repeated, at
each stage for previously-entered independents, until the addition of a remaining
independent does not increase R2 by a significant amount (or until all variables are entered).

The methodology involved testing within the established multivariate regression analysis for
sets of independent variables that explained a proportion of the variance in a dependent
variable at a determined significant level (R2). This established the relative predictive
importance of the independent variables by comparing beta weights. Hierarchical regression
analysis was adopted that determined how much variance in a dependent highway project
variable that was explained by one or a set of new independent highway project variables.

Testing of the significance of the difference of R2 was adopted and carried out in order to
determine if the addition or subtraction of targeted independent variables helped the model
significantly. The use of residual analysis was important because most assumptions of
multiple regressions cannot be tested explicitly but gross violations, such as outliers or
extreme cases, can be detected. When excluded, this can yield a better set of results.

The most commonly used multivariate analysis method is the stepwise selection method
(Norusis, 2005). However all three of the following methods were adopted in selecting the
included and excluded independent variables in the statistical regression analysis:
forward selection
backward selection
stepwise selection.

96
CHAPTER 3
Research methodology

Forward selection This method starts with a model containing none of the explanatory
variables. In the first step, the procedure considers variables one by one for inclusion and
selects the variable that results in the largest increase in R2. In the second step, the procedure
considered variables for inclusion in a model that only contained the variable selected in the
first step. In each subsequent step, the variable with the largest increase in R2 is selected,
until, according to an F-test, further additions are judged not to improve the model.

Backward selection This method starts with a model containing all the variables and
eliminated variables one by one. At each step the variable chosen for exclusion was that
leading to the smallest decrease in R2. The procedure was repeated until, according to an
F-test, further exclusions did not represent a deterioration of the model.

Stepwise selection This method involved the combination of the previous two approaches.
It starts with no variables in the model. Then variables are added, as with the forward
selection method. In addition, after each inclusion step, a backward elimination process is
carried out to remove variables that are no longer judged to improve the model. Caution in
this process is needed as the stepwise procedure is claimed to be controversial because it
includes independent variables based on statistical criteria and not theoretical ones (Bryman
and Cramer, 1999).

Automatic variable selection procedures are exploratory tools and the results from a
multivariate regression model selected by a stepwise procedure should be interpreted with
caution. Different automatic variable selection procedures can lead to different variable
subsets since the importance of variables is evaluated relative to the variables included in the
model in the previous step of the procedure. Care was required in the automatic procedures
for selecting subsets of variables (Agresti, 1996).

3.10.4 Sample size of data

The regression analysis required the adoption of an adequate sample size of project data for
analysis (Tabachnick and Fidell, 2001)
For testing b coefficients, the sample size adopted was N >= 104 + m where m =
number of independent variables
For stepwise regression, N >= 40m was adopted since the stepwise method would
easily train to noise and not be generalised in a smaller dataset
There needed to be at least 10 to 20 times as many samples of data as there were
variables otherwise the estimate of the regression was very unstable and unlikely to
be replicable
For the significance test of R2, the sample size adopted was N >= 50 + 8m where m =
number of independent variables.

3.10.5 p-value

In the multivariate regression analysis, the statistical model required the reporting of
appropriate F-tests and t-tests. For each test, the p-value was reported. The p-value derived
depended on a given sample and provided a measure of the strength of the results of tests, in
contrast to a simple reject or do not reject criteria.

The p-value is a measure of how much evidence existed against a null hypothesis, with the
smaller the p-value, the more evidence of the null. The p-value is combined with the

97
Risk factors leading to cost overrun in the delivery of highway construction projects.

significance level to make decisions on a given test of hypothesis. In such a case, if the p-
value is less than some threshold (usually 0.05, sometimes a bit larger e.g. 0.1, or a bit
smaller e.g. 0.01) then the null hypothesis is rejected. If the null hypothesis is true and the
chance of random variation is the only reason for sample differences, then the p-value
provides a quantitative measure of the strength of the model.

Traditionally, p-values less than 0.01 are considered highly significant and less than 0.05
significant. A larger p-value means that a deviation can be due to chance. If the p-value is
measured less than some threshold (usually 0.05, sometimes a bit larger like 0.1 or a bit
smaller like .01) then the null hypothesis is rejected. Typical interpretation values for p are
shown in the following Table 3.5.

This table is not available online.


Please consult the hardcopy thesis
available from the QUT Library

Source: Flyvbjerg et al., 2002


Table 3.5: Interpretation of p-values

When a p-value is associated with a set of data, it is a measure of the probability that the data
could have arisen as a random sample from some population described by the statistical
model. A p-value is a measure of how much evidence you have against the null hypothesis
(H0). The smaller the p-value, the more evidence you have. It is possible to combine the
p-value with the significance level to make a decision on a given test of hypothesis.

The distribution of p-values under null hypothesis H0 is uniform, and thus does not depend
on a particular form of the statistical test. In a statistical hypothesis test, the p-value is the
probability of observing a test statistic at least as extreme as the value actually observed,
assuming that the null hypothesis is true. The value of p is defined with respect to a
distribution. Therefore, we could call it model-distributional hypothesis rather than the null
hypothesis. This means that if the null had been true, the p value is the probability against the
null in that case. The p-value is determined by the observed value.

3.10.6 t-test

The t-test is used to test that the regression coefficient is zero and to assess the significance
of individual b coefficients. All variables not significant at the 0.05 level or better are
removed from the equation. The t-test assumes randomly sampled data for the significance
tests and the t-test is not used for dummy variables.

98
CHAPTER 3
Research methodology

3.10.7 Other considerations

A major disadvantage of using the '% cost over' as the dependent variable is that it can
provide a wider range of data outliers in the regression analysis. One approach in reducing
this potential problem may be to divide the projects into different delivery types and then
recalculating the '% over-cost' variable according to each project delivery type. This may
require more data that are presently not available to the research project.

As well, one of the assumptions in using regression analysis is that the independent variables
have a constant variance. If this assumption is violated then the '% over-cost' model will be
required to be transformed in order to satisfy the assumption.

Multivariate linear regression assumes the relationship between variables to be linear. In


practice this assumption can virtually never be confirmed. Multivariate regression
procedures are not greatly affected by minor deviations from the assumption of linearity and
hence no transformation of variables or explicitly allowing for nonlinear components was
considered in the analysis. Multivariate regression should not be used for predictions outside
the range of the explanatory variables, for example beyond highway projects or the
geographic areas of Queensland. Predictions at levels of unobserved variables which are not
comparable to the observed research data can result in very misleading predictions (Harrell,
2000).

3.11 Ethical considerations


The use and publication of confidential of commercial-in-confidence project data can be of
concern to organisations that have provided the information. This can also limit broader
publication of research findings. Because the data compiled for this research were derived
from publicly sourced documents, there are no ethical considerations required in publishing
the data and its subsequent analysis in this thesis.

3.12 Conclusion
This methodology describes the process of investigating and assessing the correlations
between project risks, project types and cost overruns on highway projects procured within a
public highway agency. Aspects of the methodology adopted included: reviewing literature
on project risk and project cost overrun, determining and establishing a source of historic
project data, recognising project risk factors, determining highway project types and
undertaking statistical modelling to establish correlations between project cost overrun
elements and project attributes. These research methods were applied to research data
consisting of public records of highway construction projects, their budgeted estimates and
final costs at completion on projects which had exceeded budget by more than 10 % between
1995 and 2003. These public records were published by the QDMR.

The description of the highway project data collected for the research, the analysis
techniques using the methodology and the statistics are described in the following Chapter 4.

99
Risk factors leading to cost overrun in the delivery of highway construction projects.

100
CHAPTER 4
Data collection, analysis techniques and statistics

CHAPTER 4

Data collection, analysis techniques and statistics

4.1 Preamble
The research methodology has specified five stages for approaching the research questions.
Previous Chapter 2 has focused on Stage 1 of the methodology, namely the literature review
This chapter focuses on stages 2 through 5 of the research questions.

To address the first research question of: What client risks are present during the delivery of
highway construction projects in Queensland, Australia that lead to significant project cost
overruns? Stages 2, 3 and 4 of the research process have been developed as follows:
Stage 2: Establish data sources of highway construction projects
Stage 3 (a): Determine cost overrun factors from historic project data
Stage 3 (b): Use factor analysis (principal component analysis) and factor rotation on
cost overrun factors to consolidate data
Stage 4: Use nominal group technique (NGT) to elicit, review and prioritise principal
cost overrun risk groupings and highway project types.

To address the research question of: How does the amount of highway cost overrun in such
highway projects correlate with their project types, size, delivery processes and client
project risks when historical project data are analysed? Stage 5 was developed to undertake
data analysis and statistical modelling using multivariate linear regression analysis and to
establish correlations between client risks causing cost overrun, project attributes and project
programmed costs.

4.2 Stage 2: Establish data sources of highway construction projects


All road construction project information was collected from the published Roads
Implementation Program documents of the Queensland Department of Main Roads (QDMR)
over the financial years from 199596 to 200203. As well, further related contract data for
this research were selectively available from within the project databases of QDMR. Table
4.1 summarises the projects that were available for the analyses.

Year project completed Number of projects


199596 13
199697 24
199798 31
199899 39
199900 36
200001 39
200102 21
200203 28
Total for all years 231

Table 4.1: Number of projects analysed

101
Risk factors leading to cost overrun in the delivery of highway construction projects.

It was ascertained that the data presented was true and factual representations of the highway
organisations historic data. since that data was contained within documents which
represented public statements of the organisations planning, construction and maintenance
activities of the state government and each document was authorised by both the state
government Minister and the Director General of the state highway organisation.

A sample of that data is given in Table 4.2 below. This sample data referred to highway
construction projects completed in the 20022003 financial year.

Description Method Programmed Actual


Project
Location of works of cost $m cost $m %
number
delivery
13/25A/48 Mount Lindesay Construct Open 8.649 9.835 13.7
Highway (Brisbane interchange tender 1
Beaudesert Road)
Cost overrun reason: increase due to contract cost higher than originally estimated
and change of project scope to include raised central median

Table 4.2: Sample of data of completed highway

As shown in Table 4.2 above, the various columns contained important project data. These
data are described in the following sections.

4.2.1 Project number and location

The first column of Table 4.2 contains the Project number. This provides a systematised
identifier that includes the geographic Local Authority in which the project was constructed,
the name of the road on which it was built, and a sequential number that this project is the
x th project constructed on that particular road. It provides the following information about
project 13/25A/48:

Local Authority 13 (Beaudesert Shire Council)


Road Name 25A Mount Lindsay Highway (Brisbane Beaudesert
Road)
Sequential Number The 48th project ever constructed on the Mount
Lindesay
Highway between Brisbane and Beaudesert.

4.2.2 Description of works

The third column of Table 4.2 contains the Description of works and describes the type of
highway project constructed for the particular project. This description also indicates
whether the project was a highway or bridge-related project. A refined listing of works
descriptions was produced by combining all duplicate work type descriptions and by
consolidating like construction processes into representative processes. Table 4.3 below
shows the final 17 work types that were developed from the full listing of work descriptions
for use in further analysis.

102
CHAPTER 4
Data collection, analysis techniques and statistics

Highway project work types


1 Construct interchange
2 Realignment of two lanes
3 Rehabilitate then widen pavement
4 Widen shoulders and sealing
5 Asphalt resurfacing
6 Replace bridge approaches
7 Construct to sealed two-lane standard
8 Widen four to six lanes
9 Replace bridge(s)
10 Pavement overlay (strengthening)
11 Duplicate two to four lanes
12 Construct to sealed standard
13 Widen and overlay
14 Pavement overlay (>75 mm)
15 Realign four lanes
16 Miscellaneous works
17 Widen bridge

Table 4.3: Refined listing of highway project work types

4.2.3 Method of project delivery

Column four of Table 4.2 shows the Method of delivery. All projects analysed used the
traditional procurement method of having separate design and construction steps. At the time
of this research, QDMR supported three viable and performing project delivery sectors
across Queensland the private contracting sector, local governments and RoadTek
which was a constituted government-owned-enterprise operating under the National
Competition Policy and Trade Practices Act 1974 which required evidence of procurement
best-value-for-money through competitive bids or comparisons for sole invitee work. Five
types of delivery methods were recorded in the project data that have been variously
employed on projects to satisfy the clients project delivery policy.

The following delivery methods were recorded:


1. Open tender: This is a contract carried out by a pre-qualified private or government-
owned enterprise highway contractor in an open tender environment. The project uses
the schedule of rates contract format
2. Agreed Price Internal Contract (APIC): This represents a negotiated internal contract
that forms a formal agreement between the client highway organisation and its
internal workforce, but before that internal workforce was constituted as a
government-owned-enterprise. The agreement is on the basis that the construction
price is a negotiated price and is based on an agreed schedule of rates for the project
construction. (This form of delivery was superseded by method 5 described below
during 2001.)
3. Agreed Price Performance Contract (APPC): This type of project is an agreement
between the client highway organisation and a particular Local Authority and forms a
performance agreement for the delivery of a project at a negotiated contract price

103
Risk factors leading to cost overrun in the delivery of highway construction projects.

4. The project is located in the Local Authoritys geographic area and uses the Local
Authoritys own workforce and its sub-contractors
5. Sole invitee Local Authority: This is a formal agreement entered into between the
client highway organisation and a particular Local Authority. The agreement is on the
basis that the construction of the project is carried out by the nominated Local
Authority in order to provide continuity to that clients workforce. (This form of
delivery was superseded by method 3 described above in 2001.)
6. Sole invitee RoadTech: This is a project delivery method where a formal agreement is
entered into between the client highway organisation and its internal workforce. The
contract price is a negotiated price based on agreed schedule of unit rates for the
project construction items. It is carried out by the clients own workforce in order to
provide continuity to their own workforce.

In the highway data analysed, there were 140 projects categorised as open tender and this
constituted 60.6% of the total projects analysed. Forty six (19.6%) APIC contracts were
identified and 23 (10%) were APPC contracts. The number of sole invitee Local Authority
projects and sole invitee RoadTech projects were 8 (3.5%) and 14 (6.0%) respectively. Table
4.4 shows the composition of the methods of delivery for the projects analysed.

Method of delivery Number of projects Percentage of projects


Open tender 140 60.6%
APIC 46 19.9%
APPC 23 10%
Sole invitee local authority 8 3.5%
Sole invitee RoadTech 14 6.0%

Table 4.4: Composition of project delivery methods

The APIC project delivery method and the Sole invitee RoadTech delivery methods became
essentially the same over the duration of the research data period as the client organisation
used their workforce to deliver projects on a negotiated price basis. These two recorded
delivery methods were combined for the purpose of future analysis. As well, the APPC
project delivery method and the Sole invitee local authority delivery method were also
considered essentially similar for the purpose of the research. The client organisation
contracted particular local authority organisations to deliver the highway projects using their
workforce on a negotiated price basis. Therefore these two recorded delivery methods were
combined for the purpose of future analysis. A code was attached to each of the three revised
project delivery methods to allow for future analysis. These are shown in Table 4.5.

Delivery description Revised delivery description Projects represented


(revised)
Open tender Open tender 60.6%
APIC
Negotiated price internal workforce 25.9%
Sole invitee RoadTek
APPC
Negotiated price external workforce 13.5%
Sole invitee local government

Table 4.5 Project delivery code

104
CHAPTER 4
Data collection, analysis techniques and statistics

Column three of Table 4.5 shows the combined revised percentages of projects representing
open tender and the negotiated price for internal and external workforce project delivery
methods.

4.2.4 Programmed cost

The programmed cost shown in Column five of Table 4.2 was the client-allocated budget to
deliver the project in millions of A$. This was the project budget at the decision-to-build
stage of the project. This budget was derived from the traditional engineering analysis of the
design plans and drawings and the estimate was typically decomposed into line items
representing the major activities and acquisition costs of the project. These included:
conducting investigations and developing the design
detailing the design
acquiring land
altering public utility plant
construction
project administration and handover.

Project cost variability and project uncertainty was included in each programmed cost by the
incorporation of a contingency allowance in the budget. This was calculated as a percentage
on cost to the estimate totals of the six cost elements above. The policy of the client
organisation was that the same level of project contingency of 10% was attributed across all
project budgets over the analysis period. Table 4.6 shows the minimum, maximum, average
and standard deviations of the project programmed costs for the analysis period.

Year Number Minimum Maximum Average Standard


project of projects programmed programmed programmed deviation of
completed cost $m cost $m cost $m programmed
cost
199596 13 1.05 6.40 2.37 1.52
199697 24 0.88 37.00 4.46 7.93
199798 31 1.00 93.30 12.31 25.05
199899 39 1.06 41.50 4.09 6.46
199900 36 1.00 110.95 10.29 24.25
200001 39 1.02 154.66 12.00 32.29
200102 21 1.00 31.64 4.58 7.59
200203 28 1.00 40.24 6.91 10.10
All years 231 0.88 154.66 7.81 19.67

Table 4.6: Programmed costs of projects

4.2.5 Actual cost

The actual cost shown in Column six of Table 4.2 was the projects reported information
about the actual outcome of the project as incurred by the client to deliver the project in
millions of A$. The reported actual cost included the total value of change orders etc. in
addition to the original programmed cost. It included the actual final costs of the component
costs included in the projects programmed cost. Table 4.7 shows the range of actual projects
costs over the analysis timeframe.

105
Risk factors leading to cost overrun in the delivery of highway construction projects.

Year Number Minimum actual Maximum Average actual Standard


project of projects $m actual cost $m deviation of
completed cost $m actual cost
199596 13 1.38 8.93 3.11 2.12
199697 24 1.46 41.66 5.68 9.16
199798 31 1.14 121.83 15.17 31.06
199899 39 1.21 52.00 5.23 8.15
199900 36 1.33 144.59 13.10 32.08
200001 39 1.21 171.80 14.42 39.97
200102 21 1.24 39.97 5.69 9.43
200203 28 1.28 46.89 8.39 12.25
All Years 231 1.28 171.80 9.69 24.17

Table 4.7: Actual costs of projects

4.2.6 Percentage (%)

The % cost overrun shown in Column seven of Table 4.2 was determined as the difference
between the clients actual project cost and their programmed cost, expressed as a percentage
of the programmed cost for each project. Table 4.8 shows the range of percentages of cost
overrun in the projects analysed.

Year Number Standard


project of Minimum % Maximum % Average % deviation of
completed projects %
199596 13 12.4 50.0 30.30 11.1
199697 24 11.9 187.20 40.94 39.13
199798 31 7.00 113.20 27.62 23.13
199899 39 10.00 113.31 30.45 25.01
199900 36 10.77 95.10 27.51 17.11
200001 39 10.49 91.82 26.56 16.70
200102 21 10.31 65.54 25.53 15.48
200203 28 10.88 60.45 24.58 11.93
All years 231 7.00 187.16 28.88 21.96

Table 4.8: Percentage of cost overrun for analysis periods

4.2.7 Indexing of project costs to 200203 out-turn prices

In order to evaluate the size of highway projects by means of the individual project
expenditure over the full analysis period, all the reported project expenditures were indexed
up to 2003 project prices. This process involved the application of price indices to the client
project costs for the years 1997 through to 2002.

Price indexes for highway projects in Queensland have been available since 1984 and in
intervening years up to 30 June 2004 by the application of the Road Input Cost Index (RICI)
as detailed in Chapter 3. Price increases since 199900 included the impact of the
introduction of the Australian governments 10% Goods and Services Tax (GST). It should
be noted that the RICI was an input price adjuster index, rather than a cost of construction
index. (A price index is different from a cost index in that it does not provide an indication

106
CHAPTER 4
Data collection, analysis techniques and statistics

of the actual cost of constructing roads rather, its main purpose is to provide a way of
deriving constant prices for inputs to road expenditure.).

Appendix A contains the RICI indices that have been compiled form the Australian Bureau
of Statistics for the period 1984 to 2004.

Table 4.9 details the RICI indices adopted over the analysis period. Column 3 lists the
percentage factor used to factor up the historical project cost information. These factors
ranged from 3.4% to 16.3% and were applied to projects programmed and actual costs for
the corresponding financial years in which the projects were constructed.

Year RICI index Factor for 200203 prices


199596 97.33 16.3%
199697 98.44 15.0%
199798 100.00 13.2%
199899 102.15 10.9%
199900 104.29 8.6%
200001 106.60 6.2%
200102 109.49 3.4%
200203 113.23

Table 4.9: RICI indices and factors applied to project costs

All the historic project cost data of the clients programmed costs and actual costs were
adjusted to 200203 financial year figures by using the % factors in Table 4.9 above.
Appendix B contains a full listing of adjusted programmed and adjusted actual project costs
that were used in subsequent data analyses.

4.3 Stage 3 (a): Determine cost overrun factors from


historic project data
This step in the research required the determination of project cost overrun factors from
historic data. The focus of this analysis was based on the clients exposure to project cost
overrun, not that of contractors delivering the projects. A client focus required a number of
considerations identified in the literature to be taken into account when reporting the cost
overrun factors. These included:
the use of design-bid-build contracts that could lead to higher client exposure to
design risks
pre-qualification of contractors that has the potential to limit client risk exposure to
contract default
contract payment types that focused on schedule of rates and bill of quantities
contract clauses that were designed to reduce the clients exposure to certain
construction risks
tender evaluation techniques
contract provisions that limit the clients exposure to adverse physical and latent
conditions and wet weather events.

107
Risk factors leading to cost overrun in the delivery of highway construction projects.

The available highway data contained individual descriptions of all the reasons for individual
projects stated by the client as having caused the clients programmed budget for the project
to be exceeded by 10% or more. A sample of this data was shown under Columns two to
seven of Table 4.2.

It was considered that the reasons documented were true and factual representations of the
historic project data. Since that data was contained within documents which represented
public statements of the organisation's planning, construction and maintenance activities of
the state government, then it was considered that the individual reasons for projects
overrunning in costs contained within these documents were true and factual as each
document was authorised for publication by both the state government Minister and the
Director General of the state highway organisation.

These reasons were transferred from the public documents and recorded in an Excel
spreadsheet by the researcher for further analysis. Where common cost overrun factors
occurred across projects, single cost factors were recorded to cover incidences. All unique
reasons were recorded individually. This step in the research process drew on the experience
in highway construction and the professional judgement of the researcher to extract a
consistent group of reasons for the project overruns.

Where there were common cost overrun factors identified across a number of projects, then a
common cost factor was recorded to cover all incidences of those common factors. The
research identified 37 factors from the highway data analysed. The final list of cost overrun
variables, their symbols and the number of times they occurred across projects are shown in
Table 4.10.

Incidences across
Reason for cost overrun Code
projects
Project acceleration requirement A 5
Constructability difficulty costs C 10
Constructability under traffic CT 17
Design/project scope change D 95
Design scope change drainage DD 33
Design scope change environmental issues DE 19
Design scope change design error DF 2
Design scope change pavement materials/depth DM 23
Design preload requirement DPL 1
Design change to subgrade DSG 1
Design scope change safety audit requirement DSA 4
Extras unspecified EU 6
Government initiative employment continuity G 1
Government initiative contribution by developer GCD 3
Government initiative contribution by local government GCLG 1
Government initiative contribution by rail GCR 1
Cultural heritage issues H 4
Latent condition requires design change LD 4
Latent condition rock encountered LR 7
Latent condition additional stabilising LSG 3
Latent condition removal and replacement of unsuitable material LUS 21
Material cost increase asphalt MA 1

108
CHAPTER 4
Data collection, analysis techniques and statistics

Material cost increase bitumen price MB 1


Material cost increase earthworks ME 3
Material cost increase pavement materials MP 11
Material cost increase client supplied components/materials MPS 4
Material/process quality issue MQ 2
Contract failure new contract establishment costs N 1
Remote location costs O 7
Project administration cost increase P 8
Quantity increased measure Q 31
Resumption/accommodation works R 10
Services relocation costs S 12
Specification change SC 7
Contract tender price higher than original estimate TH 35
Contract tender price increase due to inflation TCI 1
Wet weather effects/rework WW 8

Table 4.10: Project cost overrun factors derived from historic highway data

Column two of Table 4.10 shows the Code. This was an alphabetic code assigned to each
of the Reason for cost overrun entries. This was to allow further data analysis at a later
date. There was no logic to the allocation of the alphabetic code letters, other than a very
coarse alignment of the code letter(s) with the major descriptor of the reason. As an example,
A = Project Acceleration Requirements; WW = Wet Weather effects/rework.

4.3.1 Exclusion of some initial historical project data

For the purpose of the research, cost overrun variable EU Extras unspecified occurred
across six projects. These projects also had other identified variables also attributed to cost
overrun in those specific projects. Review of the project data revealed that those six
occurrences of EU Extras unspecified were all attributed to one type of construction
project, namely the upgrading from four lanes to eight lanes of highway. These projects
made up the various stages of the Pacific Motorway project that linked Brisbane to the Gold
Coast in the south-east corner of Queensland. An interview with a senior motorway project
staff member advised that more detailed cost overrun details for the specific projects were
not available as research materials as this information now formed parts of various contract
finalisation arrangements under specific deeds of agreements between the client and the
specific motorway constructors (Creedy, 2004). Therefore, those six motorway projects were
excluded from further data analysis of cost overrun reasons.

4.4 Stage 3 (b): Use factor analysis (principal component analysis)


and factor rotation on cost overrun factors to consolidate data
Guidelines for the minimum sample size and ratio limits for the number of variables for
factor analysis have been discussed in Chapter 3. For the data set in this project, the sample
size was 231 and the number of factors was 28. This gave an acceptable ratio of 8.3
(Guadagnoli and Velicer, 1988).

Factors which had produced an incidence of one (1) in Table 4.9 were excluded from the
factor analysis because they each related to only one incidence. Nine such factors had an

109
Risk factors leading to cost overrun in the delivery of highway construction projects.

incidence of one. The 37 identified cost overrun factors were reduced to 28 for the factor
analysis process. Those cost overrun factors were then formed into an index matrix using
MS Excel, with the 231 recorded projects displayed down the y-axis.

A scaling of zero (0) and one (1) was then established and the matrix completed for all the
projects. A one (1) was recorded against the cost overrun factor for a project when a
particular cost overrun factor was identified. A zero (0) was inserted in the data file when no
other factor occurred in the project. Where a project had multiple cost overrun factors
recorded against it, then multiple ones (1) were inserted in the matrix row. Table 4.11 shows
a sample of the data matrix developed in Excel for uploading into SPSS Version 12 for the
factor analysis.

Project number A C CPI CT D DN DD DE DF DM DPL DSG DSA EU


99/332/10 0 0 0 0 0 0 1 0 0 0 0 0 0 0
63/17D/302 0 0 0 0 0 0 0 0 0 0 0 0 1 0
119/32B/27 0 0 0 0 0 0 0 1 0 0 0 0 0 0
150/548/301 0 0 0 1 0 0 0 1 0 0 0 0 0 0
30/10N/88 0 0 0 0 0 0 0 0 0 0 0 0 0 0
128/43/304 1 0 0 0 0 0 0 0 0 0 0 0 0 0
25/40A/812 0 0 0 1 0 0 0 0 0 0 0 0 0 0

Table 4.11: Sample display of project and cost overrun matrix data used in analysis

4.4.1 Factor analysis test parameters

The Kaiser Meyer Olkin (KMO) test that measured sampling adequacy gave a sampling
adequacy of 0.460. This was much less than 0.6 that was sought in the Chapter 3
methodology (Kaiser, 1974; Hutcheson and Sofroniou, 1999). This low figure threw initial
doubt on the adequacy of the planned factor analysis technique in overcoming
multicollinearity in the data.

A further test using the Bartlett test of sphericity gave an approximate chi-square of 482.183
and 378 degrees of freedom The associated significance level was small at p = 0.000 for all
the factors as shown in Table 4.12.

Kaiser Meyer Olkin measure of sampling adequacy 0.460

Approx. chi-square 482.18


Bartlett test of sphericity df 378
Sig. .000

Table 4.12: KMO and Bartlet tests

Both the KMO and Bartlett tests indicated that any factor analysis process carried out on the
data would produce marginal results (the Bartlett Test was less than the adopted 700 even
though the Bartlett sphericity test is particularly relevant to small samples of data <100 and
not so relevant to the larger sample of around 230 in this application). After considering the
marginal sample characteristic test results, the principal component/factor analysis method
was still used as the preliminary method for reducing the large number of cost overrun
factors down to a more significant number.

110
CHAPTER 4
Data collection, analysis techniques and statistics

An initial analysis of the 28 factors ascertained the proportion of each variables variance
that could be explained by principal components. Column two of Table 4.12 shows that
initial communalities of the 28 cost overrun variables were 1.000 because, by definition, the
full orthogonal principal component analysis showed all of the variances in the variables to
be explained by all the factors. The extraction communality shown in Column three of Table
4.13 gave the percent of variance in a given variable Variables with high values were
represented in the common factor space, while variables with low values were moderately
represented.

Cost overrun variable Initial communality Extraction communality


A 1.000 0.724
C 1.000 0.655
CT 1.000 0.690
D 1.000 0.746
DD 1.000 0.667
DE 1.000 0.621
DF 1.000 0.637
DM 1.000 0.458
DSA 1.000 0.631
EU 1.000 0.469
GCD 1.000 0.505
H 1.000 0.684
LD 1.000 0.559
LR 1.000 0.629
LSG 1.000 0.613
LUS 1.000 0.608
ME 1.000 0.519
MP 1.000 0.661
MPS 1.000 0.485
MQ 1.000 0.767
O 1.000 0.468
P 1.000 0.661
Q 1.000 0.664
R 1.000 0.556
S 1.000 0.542
SC 1.000 0.682
TH 1.000 0.714
WW 1.000 0.664
Extraction method: Principal component analysis

Table 4.13: Initial and extraction communalities for cost overrun variables

4.4.2 Principal component analysis

The principal component analysis was undertaken with the view of reducing the number of
initial cost overrun factors by the redistribution of the variance to the first components
extracted in a correlation matrix. The method of eigenvalue decomposition was used. Table
4.14 shows the total variance derived from the principal component analysis before rotation.

111
Risk factors leading to cost overrun in the delivery of highway construction projects.

Extraction sums of squared


Component Initial eigenvalues loadings
% of Cumulative % of Cumulative
Total variance % Total variance %

1 1.894 6.76 6.76 1.894 6.76 6.76


2 1.718 6.13 12.89 1.718 6.13 12.89
3 1.601 5.71 18.61 1.601 5.71 18.61
4 1.467 5.23 23.85 1.467 5.23 23.85
5 1.407 5.02 28.88 1.407 5.02 28.88
6 1.342 4.79 33.67 1.342 4.79 33.67
7 1.318 4.70 38.38 1.318 4.70 38.38
8 1.191 4.25 42.63 1.191 4.25 42.63
9 1.134 4.05 46.68 1.134 4.05 46.68
10 1.096 3.91 50.60 1.096 3.91 50.60
11 1.060 3.78 54.38 1.060 3.78 54.38
12 1.042 3.72 58.11 1.042 3.72 58.11
13 1.008 3.59 61.70 1.008 3.59 61.70
14 .979 3.49 65.20
15 .943 3.36 68.57
16 .920 3.28 71.85
17 .886 3.16 75.02
18 .826 2.94 77.97
19 .798 2.85 80.82
20 .764 2.72 83.55
21 .760 2.71 86.26
22 .709 2.530 88.79
23 .636 2.27 91.06
24 .593 2.11 93.18
25 .572 2.04 95.22
26 .522 1.86 97.09
27 .446 1.59 98.68
28 .367 1.31 100.00

Extraction method: Principal component analysis


Table 4.14: Total variance explained unrotated

Column one of Table 4.14 shows the 28 components analysed. There were as many
components extracted during the principal components analysis as there were variables
initially used in the analysis, namely 28. The total % variance explained by each cost
overrun factor was listed in the 'Initial eigenvalue Column' of Table 4.14. The initial
eigenvalues derived were from standardised variables. Column two shows the total
eigenvalues in descending order of magnitude with component one accounting for the most
variance (96.76%) in the analysis and hence the highest eigenvalue. Component two
accounted for as much of the leftover variance as it could, and so on. Column three
contained the % of variance that was accounted for by each principal component. Column
four of Table 4.13 contained the cumulative percentage of variance accounted for by the
current and all preceding principal components. The factors were listed in descending order

112
CHAPTER 4
Data collection, analysis techniques and statistics

of variance explained. The third row showed a value of 18.61 which meant that the first three
components together account for 18.61 % of the total variance.

The three columns of the right half of Table 4.14 represented the extraction sums of squared
loadings and reproduced the values given on the same row on the left side of the table. The
number of rows reproduced on the right side of the table was determined by the number of
principal components whose eigenvalues were 1.00 or greater. There were 13 principal
factors that had eigenvalues greater than one (1.000). Column seven displayed the computed
variance of each variable explained by the 13 factor model. Since the factors were
uncorrelated, the total proportion of the variance explained was the sum of the variance
proportions of each factor. The figures in Column seven show that variation was relatively
even across almost all components and this indicated a low significance of the principal
components in reducing the dimensionality of the original set of cost overrun variables. It
showed that the first 13 components collectively accounted for only 61.7 % of the total
variability, while the other 15 components together accounted for the remaining 38.3 %.

4.4.3 Scree plot

A further test using a scree plot was carried out on the project data. As explained in the
methodology in Chapter 3, the scree plot graphed the eigenvalue against the number of
initial factors (component numbers) so as to support a particular eigenvalue cut-off
level. The plot in Figure 4.1 shows the plotted values that have been derived from the first
two columns of Table 4.14. From the 13th component point on, the slope of the line flattened
slightly indicating that each successive component was accounting for smaller and smaller
amounts of the total variance out to component 28. Components with an eigenvalue of less
than 1 accounted for less variance than did the original variable which had a variance of 1.
The scree plot indicated that a weak model, comprising of 13 component factors, was
feasible and warranted further investigation.

2.0

1.5

Eigenvalue

1.0

0.5

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Component number

Figure 4.1: Scree plot of cost overrun components

113
Risk factors leading to cost overrun in the delivery of highway construction projects.

4.4.4 Factor rotation

Factor rotation was performed based on the varimax method with 16 iterations. It was found
that a rotated and ordered factor loading matrix established 13 component groups for the 28
cost overrun variables as supported by the scree plot. The shaded portions of Table 4.15
show clearly the 13 groupings of the 28 cost-overrun factors.

114
CHAPTER 4
Data collection, analysis techniques and statistics

Component
1 2 3 4 5 6 7 8 9 10 11 12 13
LUS .717 -.067 .009 .048 -.130 -.010 -.063 .043 -.001 -.002 .079 .239 .028
EU -
.638 .044 -.020 -.020 .150 .006 .060 -.034 -.110 -.061 .021 -.125
.024
DM .375 -.213 -.099 .019 -.004 -.129 -.085 -.199 .186 .176 -.188 -.148 .275
H .016 .758 .026 .000 .014 .012 .014 -.088 -.180 -.216 -.063 -.036 .123
ME -
-.005 .689 -.029 .035 -.014 -.006 -.011 .022 .155 .131 -.010 .024
.007
O -
-.098 .509 -.042 -.038 -.083 -.122 -.020 .012 .250 .324 -.026 -.021
.065
R -
-.056 -.070 .706 -.015 .113 -.039 -.008 .160 -.011 .022 -.053 .054
.042
GCD -.065 -.061 .622 .071 -.208 .057 .025 -.085 .137 -.118 -.128 .024 .029
S .101 .129 .622 .022 .145 -.080 -.062 -.137 -.194 .021 .132 -.115 .098
TH -.220 -.058 -.165 -.744 .003 -.122 -.022 .070 -.084 -.080 -.141 .160 .049
D -.363 -.114 -.086 .606 -.073 -.180 -.058 -.102 -.391 -.128 -.032 -.068 .027
DE -
-.038 .237 -.141 .358 .332 .303 -.070 .076 .098 -.127 -.134 .249
.310
SC .049 -.035 .016 .007 .815 -.045 -.033 -.074 -.017 .024 .017 -.048 .049
MPS -
-.036 -.014 .237 -.256 .450 -.044 -.007 .345 -.105 .077 .055 -.094
.099
LR -
.051 -.022 -.016 .046 -.046 .774 -.117 .005 -.012 -.015 -.090 .027
.015
C -.162 -.066 -.042 -.022 -.028 .667 .295 -.054 -.070 .192 .152 -.112 .097
MQ -.056 .004 -.008 -.062 -.003 .072 .860 -.069 .008 -.048 .062 -.055 .032
WW -
.504 -.031 -.059 .123 -.067 -.124 .565 .152 -.045 .045 -.139 .061
.033
P -
.058 -.024 .019 -.170 .025 .020 .025 .787 .031 -.053 -.045 .023
.030
LD -.083 -.025 -.114 .270 -.133 -.082 -.086 .555 -.058 -.061 -.027 -.171 .297
MP -
-.065 .157 -.009 -.062 -.094 -.053 -.036 .003 .772 .028 .088 -.093
.039
DSA -.087 -.127 -.078 .197 .421 -.026 .064 -.103 .511 -.182 -.158 .090 .207
CT -.056 .061 -.059 -.052 .057 .168 -.095 -.108 -.030 .774 -.073 -.110 .086
Q -
.132 .030 .022 .155 -.056 -.122 .264 .057 .006 .539 .073 .482
.042
LSG -.148 -.053 -.056 .140 -.006 .067 .032 .069 -.006 .056 .734 .118 .006
DD .282 -.041 -.019 -.085 .018 -.114 -.014 -.180 .067 -.144 .695 -.135 .070
DF .019 -.021 -.012 -.168 -.045 -.010 -.081 -.085 -.062 -.070 .005 .756 .106
A -
-.017 -.086 -.058 .036 -.052 -.065 -.031 -.079 -.008 -.041 -.061 -.122
.823

Extraction method: Principal component analysis


Rotation method: Varimax with Kaiser normalisation
Table 4.15: Rotated and ordered component matrix

115
Risk factors leading to cost overrun in the delivery of highway construction projects.

These 13 component factor groupings were expanded into their full descriptions in Table
4.16 below

Component group Code Description


LUS Latent condition removal and replacement of unsuitable
material
Component group 1
EU Extras unspecified
DM Design scope change pavement materials/depth
H Cultural heritage issues
Component group 2 ME Material cost increase earthworks
O Remote location costs
R Resumption/accommodation costs
Component group 3 GCD Government initiative contribution by developer
S Services relocation costs
TH Contract tender price higher than original estimate
Component group 4 D Design/project scope change
DE Design scope change environmental issues
SC Specification change
Component group 5
MPS Material cost increase client supplied components/materials
LR Latent condition rock encountered
Component group 6
C Constructability difficulty costs
MQ Material/process quality issue
Component group 7
WW Wet weather effects/rework
P Project administration cost increase
Component group 8
LD Latent condition requires design change
MP Material cost increase pavement materials
Component group 9
DSA Design scope change safety audit requirement
CT Constructability under traffic
Component group 10
Q Quantity increased measure
LSG Latent condition additional stabilising
Component group 11
DD Design scope change drainage
Component group 12 DF Design scope change design error
Component group 13 A Project acceleration requirement

Table 4.16: Principal factor groupings from rotated component matrix

A review of the 13 groupings lead to the conclusion that no common factor component
names were developed in the principal component analysis that could be allocated to the
individual component groups so as to allow consistency in purpose of the group of factors.
There appeared to be no evidence of strong correlations within any of the 13 groupings, even
after rotation. This was particularly evidenced by the diversity in the construction processes
associated with each of the principal component groups. These findings, supported by the
weak scree plot demonstrated the invalidity of the factor analysis process in this research.
This finding was further supported by the weak sampling adequacy of the initial highway
cost overrun data available as determined previously by both the KMO test and the Bartlett
test of sphericity.

The 13 principal component factor model derived in the factor analysis process could not be
used in any subsequent model development. Instead a process of using expert elicitation

116
CHAPTER 4
Data collection, analysis techniques and statistics

produced an acceptable number of reduced higher level component factors that could be
used in analysis.

The development of this elicitation process is explained in the following section.

4.5 Stage 4: Use nominal group technique (NGT) to elicit, review and
prioritise principal cost overrun risk groupings and highway
project types
This step of the research methodology was planned to confirm the principal component
factors from the factor analysis. Since the factor analysis was unsuccessful, this stage was
redefined so as to be used for the elicitation of a final grouping and ranking of cost overrun
factors. Nominal group technique (NGT) was used to obtain expert agreement on:
groupings of highway cost overrun factors and apply a ranking of importance of each
in terms of exposure to project cost overrun potential
a group of generic highway project types and apply a ranking of importance of each
to their exposure to cost overrun potential.

4.5.1 Identification and selection of experts

Potential group members were initially contacted via telephone to determine their
willingness to participate in the research. A questionnaire was then emailed to the potential
participants to ascertain their suitability within the group. Members were identified and
selected from within the highway organisation from which the cost overrun data was
obtained. A copy of the pro-forma questionnaire is contained as Appendix C and the
responses to the questionnaire have been summarised in Appendix D.

Clemen and Winkler (1985) have recommended five specialists and an additional two or
three generalists and two or three analysts comprise a group. For the purpose of the research,
a generalist was assumed to be one who had a broad range of experience across all of the
stated areas. A specialist was assumed to be a member having at least 10 years experience,
predominantly in one of the identified disciplines of estimating, design, construction and
management. The expert panel finally adopted included an analyst from a consulting
organisation, two generalists and five specialists those seven from the QDMR. Table 4.17
shows the final group composition of the nine participants.

Group type Member Member Member Member Member Member Member Member Member
1 2 3 4 5 6 7 8 9
Analyst *
Generalist * *
Specialist * * * * *
Researcher *

Table 4.17: Expert group composition

The primary qualifications of the nine members all were in civil engineering. Secondary
qualifications were also reported by seven panel members in their completed questionnaire
and included:
1 x PhD in Engineering
2 x Master of Engineering Science

117
Risk factors leading to cost overrun in the delivery of highway construction projects.

1 x Bachelor of Economics
3 x Business Management.

The reported spread of minimum, maximum and mean years of project-related experience of
the group from the questionnaires are shown in Table 4.18. The mean years shown in
Column four indicated a good balance of project management expertise across the group.

Experience area Minimum years Maximum years Mean years


Estimating 5 14 10.7
Design 1 17 8.5
Construction 2 15 8.5
Management 3 15 12.2

Table 4.18: Experience profile of expert group membership

As recommended by Keeney and von Winterfeldt (1991), the group members were presented
with an overview of the complete study and the issues in preliminary form and given an
overview of the formal expert judgement process that they would be involved in. This was to
ensure that the members understood what was requested of them and how it fitted into the
project. As a way of providing preliminary training of the group in the elicitation process,
each member was emailed an overview of the NGT process as well as background
information on the project and the project data. A copy of Table 4.10 (Project cost overrun
factors derived from highway data) was also provided as well as the detailed explanation of
each highway cost overrun factor. Seven examples of high level risk groupings from
previous research identified in the literature review were provided to each member in order
to give them an idea of what was anticipated of the group.

The workshop elicitation process covered six workshop items as follows:

4.5.2 Agenda Item 1: Research project background

This involved a presentation to the eight members by the researcher on the background to the
research project.

4.5.3 Agenda item 2: Workshop aims/desired outcomes and explanation of


NGT for workshop

Group members were provided with details of the workshop aims and desired outcomes. As
well, a more detailed explanation was provided to the members on the NGT technique and
the importance of the process to the development of a cost overrun model.

4.5.4 Agenda Item 3: Principal cost overrun grouping exercise

The aim of agenda item three was to obtain expert agreement on groupings of highway cost
overrun factors.

The members were again provided with a copy of Table 4.10 (Project cost overrun factors
derived from highway data). The factor 'EUextras unspecified' had been excluded from the
list as previously discussed in Stage 2 of the research process.

118
CHAPTER 4
Data collection, analysis techniques and statistics

The workshop considered each of these 36 factors and came up with consolidated groupings.
The process adopted was as follows:
1. silent generation of grouping ideas in writing
2. round-robin feedback from group members to record each idea of groupings
3. discussion of each recorded member groupings for clarification and evaluation
4. individual voting on grouping options
5. agreement on groupings.

The following list of 10 groupings was agreed by the participants during the NGT process:
design and scope change (change on project definition)
services relocation
deficient documentation (specifications and designs)
right-of-way costs
insufficient investigations and latent conditions
constructability
environment
contractor risks
price escalation
client project management costs.

The next step in Item 3 was to group the 36 cost overrun factors into the 10 groupings. A
matrix grid of the risk factors and the groupings as shown in Table 4.19 was produced and
handed out in the workshop
Services relocation

Right-of-way costs

management costs
investigations and

Contractors risks
Design and scope

latent conditions

Constructability

Price escalation
documentation

Client project
(Spec/design)

Environment
Insufficient
Deficient

Analysed
change

risk
factors

A
C
CT
D
DD
DE
DF
DM
DPL
DSG
DSA
G
GCD
GCLG
GCR
H
LD
LR

119
Risk factors leading to cost overrun in the delivery of highway construction projects.

LSG
LUS
MA
MB
ME
MP
MPS
MQ
N
O
P
Q
R
S
SC
TH
TCI
WW

Table 4.19: Cost overrun risk factor grouping worksheet

Members then went through the NGT process again and agreed on the matrix composition so
that each of the 36 cost overrun factors mapped to one of the 10 groupings. A Likert scale of
1 for poor fit, 2 for an acceptable fit and 3 for an excellent fit of each factor to its grouping
was agreed and then applied by the group. The final mapping and the corresponding agreed
Likert scale number are shown in Table 4.20.
Services relocation

Right-of-way costs

management costs
(Spec and design)

investigations and
Design and scope

latent conditions

Contractor risks
Constructability

Price escalation
documentation

Client project
Environment
Insufficient
Deficient

Analysed
change

risk
factors

A 3
C 3
CT 3
D 3
DD 3
DE 3
DF 3
DM 2
DPL 3
DSG 2
DSA 3
G 3
GCD 3
GCLG 3
GCR 3
H 3
LD 3
LR 3

120
CHAPTER 4
Data collection, analysis techniques and statistics

LSG 3
LUS 3
MA 3
MB 3
ME 3
MP 3
MPS 3
MQ 3
N 3
O 1
P 3
Q 3
R 3
S 3
SC 3
TH 3
TCI 3
WW 3

Likert scale: 1 = a poor fit, 2 = an acceptable fit, 3 = an excellent fit

Table 4.20: Agreed mapping of cost overrun factors to groupings

4.5.5. Agenda Item 4: Ranking of risk groupings

This ranking exercise required the workshop participants to provide numerical scores that
expressed their individual opinions on the level of importance of each of the 10 principal
cost overrun factors in terms of their cost impact to highway projects. A scale of 1 to 10 was
adopted, where a score of one indicated the least impact, and 10 indicated the most impact.
All scores of the eight participants were recorded and an overall ranking of each of the
groupings was derived.

A collation of the mean and standard deviation of all the participant scores that was provided
for each grouping was considered to not adequately determine an overall relative ranking as
such a method did not reflect any relationship between the groupings (Chan and
Kumaraswamy, 1997). The cost overrun group rankings were determined by calculating the
Importance index for each grouping, using the following formula:

Importance index = 100 ( w f )


WF

Where w was the weighting, ranging from 1 to 10, given to each factor; W was the highest
weight, i.e. 10; f was the frequency of the response; and F was the total number of
respondents.

Each rank in Table 4.21 presents the degree of importance assigned to the groupings.

121
Risk factors leading to cost overrun in the delivery of highway construction projects.

Importance
Expert 1

Expert 2

Expert 3

Expert 4

Expert 5

Expert 6

Expert 7

Expert 8

index %

RANK
Cost overrun
grouping

Design and
scope change 8 10 10 10 9 10 10 9 95 I

Insufficient
investigations
and latent 9 9 7 8 8 7 9 10 84 II
conditions
Deficient
documentation
(Spec and 7 5 9 5 4 9 8 8 69 III
design)
Client project
management 10 8 8 7 10 8 1 1 66 IV
costs

Services
relocation 4 6 3 8 4 1 6 6 48 V

Constructability 4 6 3 4 3 4 6 5 44 VI

Price escalation 2 4 5 3 7 6 3 3 41 VII

Right-of-way
6 3 6 6 6 1 2 2 40 VIII
costs

Contractor risks 1 1 2 2 1 5 5 6 29 IX

Environment 3 2 1 1 2 3 4 4 25 X

Table 4.21: Ranked groupings derived from importance index

The following section describes the composition of the final groupings in their rank I
(highest) to X (lowest) order of their cost impact on highway projects.

Rank I: Design and scope change (HL/1)

122
CHAPTER 4
Data collection, analysis techniques and statistics

Design and project scope change was identified as the most important factor by participants
(a score of 95% in the importance index) and was ranked first. The group found that the
potential for cost increases in the design or scope change projects was very real and their
choice in ranking supported historical data previously analysed and provided in previous
Table 4.10. Below are the percentages of analysed projects which fell into this first ranked
grouping.
Design/project scope change (23.6% of projects represented)
Design scope change resulting from drainage, environmental issues, pavement
materials/depth (8.2% of projects represented)
Design scope change as a result of carrying out a safety audit on project
(1.0% of projects represented)
Quantity increase (7.7% of projects represented)
Specification change (1.7% of projects represented).

Rank II: Insufficient investigations and latent conditions (HL/2)


Insufficient investigations and latent conditions were identified as the second most important
factor group by participants with a score of 84% in the importance index. The group reported
that highway project construction incurred significant additional costs if there were
insufficient project investigations which ultimately could lead to latent conditions.
Contractor claims for latent conditions were usually passed on to the client under most
contract provisions. Increases in measured quantities in schedule of rated contracts have
contributed to project cost overruns and some of these quantity increases were as a result of
adverse latent conditions flowing on to the client in Schedule-of-Rates contracts. The
relevant percentages of projects represented in Table 4.10 have also been inserted in the
brackets.

Design preload requirement (0.2% of projects represented)


Design change to subgrade (0.2% of projects represented)
Latent condition requiring design change (1.0% of projects represented)
Latent condition rock encountered (1.7% of projects represented)
Latent condition additional stabilising (0.7% of projects represented)
Latent condition removal and replacement of unsuitable material (5.2% of projects
represented).

Rank III: Deficient documentation (specification and design) (HL/3)


Deficient documentation (specification and design) was ranked as the third most important
factor by participants with score of 69% in the importance index. The group argued that
highway project construction could incur significant additional costs if there were
deficiencies in project documentation. Contractor claims for deficient documentation can
expose the client to additional project costs. The relevant Table 4.10 percentage of project
data has also been inserted.
Design scope change Design error (0.5% of projects represented).

Rank IV: Client project management costs (HL/4)


Client project management cost was ranked as the fourth most important factor by
participants (a score of 66% in the importance index). The group argued that highway
project construction could incur significant additional costs if there were deficiencies in
project documentation. The relevant Table 4.10 percentages of project data have also been
inserted.

123
Risk factors leading to cost overrun in the delivery of highway construction projects.

Project acceleration requirement (1.2% of projects represented)


Government initiative employment continuity, contribution by developer,
contribution by local government, contribution by rail (1.3% of projects represented)
Material/process quality issue (0.5% of projects represented)
Contract failure new contract establishment costs (0.2% of projects represented)
Project administration cost increase (2.0% of projects represented)
Contract tender price higher than original estimate (8.7% of projects represented).

Rank V: Services relocation (HL/5)


Costs for services relocation was ranked as the fifth most important factor by participants
with a score of 48% in the importance index. The group noted the reason for their ranking
was that poor scoping and estimates for utility service relocations could result in significant
client costs. The relevant Table 4.10 percentage of project data has also been inserted.
Services relocation costs (3.0% of projects represented).

Rank VI: Constructability (HL/6)


Constructability of highway projects was ranked as the sixth most important factor by
participants (a score of 44%) in the importance index. The group noted the poor input by
highway construction engineers into the project planning and design steps could lead to cost
overrun for the client. The relevant Table 4.10 percentages of project data have also been
inserted.
Constructability difficulty costs (2.5%)
Constructability under traffic (4.2%).

Rank VII: Price escalation (HL/7)


Price escalation of material components was ranked as the seventh most important factor by
participants (a score of 41%) in the importance index. The group noted that, although there
was usually adequate provision made in project documentation and budgeting, there were
occasions on projects when price escalation outside the normally expected provisions may
result in additional costs to the client. The relevant Table 4.10 percentages of project data
have also been shown below.
Material cost increase asphalt, bitumen price, earthworks,
and pavement materials (3.8%)
Principal supplied components/materials (1.0%)
Contract tender price increase due to inflation (0.2%).

Rank VIII: Right-of-way costs (HL/8)


Property acquisitions and adjustments to properties adjacent to highway projects were
ranked as eighth by participants with a score of 40% in the importance index. Protracted
resumption disputes and settlements were offered as areas of potential additional client costs.
The relevant Table 4.10 percentage of project data has also been shown below.
Resumption/accommodation works (2.5% of projects represented).

Rank IX: Contractor risks (HL/9)


Contractors risks was ranked ninth by participants (a score of 29%) in the importance index.
The group noted that projects that were constructed in remote locations had the potential to
incur costs because of the difficulties in obtaining and maintaining adequate project
resources. In addition, un-seasonal or excessive wet weather sometimes have the potential to

124
CHAPTER 4
Data collection, analysis techniques and statistics

lead to unbudgeted costs for the client where project provisions were silent in such instances.
The relevant Table 4.10 percentages of project data have also been shown below.
Remote location costs (1.7% of projects represented)
Wet weather effects/rework (2.0% of projects represented).

Rank X: Environment (HL/10)


Environment was ranked last by participants with a score of 25% in the importance index.
The group noted that cultural heritage issues had the potential to draw out planned project
timeframes and scopes, and thus incur costs because of the difficulties in obtaining approvals
and clearances.
The relevant Table 4.10 percentage of project data has also been shown below
Cultural heritage issues (1.0% of projects represented).

4.5.6. Agenda Item 5 of workshop: Development of highway project types

The aim of this activity was to obtain expert agreement on a fully inclusive grouping of
highway project types that could be used as a means of collating historic projects for further
analysis.

Members were provided with a copy of Table 4.3 that contained a broad listing of highway
project works which had previously been compiled by the researcher from the initial
historical project data. In considering the projects types in Table 4.3, the workshop members
discussed the possibility of additional project types or the option of combining existing
project types. The workshop members agreed that the list of projects could then be
categorised into three broad highway project groupings of highway projects, bridge projects
and a miscellaneous category.

The NGT allowed for further round robin, workshop discussion and then a voting step that
developed the final groupings. The final list of project types consisted of nine road types,
two bridge types and one miscellaneous type. These are shown in Table 4.22.

Project construction type


Reference
Highway project type
R1 Construct to sealed standard (2 lanes)
R2 Widen shoulders and sealing
R3 Rehabilitate/Strengthen
R4 Realignment of two lanes
R5 Realignment of four lanes
R6 Duplicate two into four lanes
R7 Widen four into six/eight lanes
R8 Asphalt resurfacing
R9 Construct intersection/interchange
Bridge project type
B1 Bridges and approaches
B2 Widen bridges
Miscellaneous project type
M1 Miscellaneous roadworks/traffic furniture and devices

Table 4.22: Final NGT highway project construction types

125
Risk factors leading to cost overrun in the delivery of highway construction projects.

The group also agreed that it would be desirable to differentiate between certain project
types where the complexity or location of some projects might require identification at a
more specific level. The workshop members agreed that the following project aspects needed
to be considered if appropriate historical data became available in the future. Those aspects
were whether:
a rehabilitation project included pavement widening or not
a realignment project incorporated some of the existing road and was built under
traffic (The group referred to this type of project as being constructed at a brownfield
site.)
the project was on a completely new alignment away from the existing highway that
it had replaced, thus having none or only a small exposure to highway traffic (The
group referred to this type of project as being constructed at a greenfield site.)
an interchange/intersection or bridge and approaches were to be in an urban or rural
environment.

Table 4.23 shows the desired extensions to the agreed project types suggested by the
participants if appropriate project data were made available.

Reference Highway project type


R1 Construct to sealed standard (2 lanes)
R2 Widen shoulders and sealing
R3 Rehabilitate/strengthen
R3(NW) Rehabilitate/strengthen (no widening)
R3(WW) Rehabilitate/strengthen (with widening)
R4 Realignment of two lanes
R4(G) Realignment of two lanes greenfield site
R4(B) Realignment of two lanes brownfield site
R5 Realignment of four lanes
R5(G) Realignment of four lanes greenfield site
R5(B) Realignment of four lanes brownfield site
R6 Duplicate two into four lanes
R6(G) Duplicate two into four lanes greenfield site
R6(B) Duplicate two into four lanes brownfield site
R7 Widen four into six/eight lanes
R7(G) Widen four into six/eight lanes greenfield site
R7(B) Widen four into six/eight lanes brownfield site
R8 Asphalt resurfacing
R9 Construct intersection/interchange
R9(U) Construct intersection/interchange urban
R9(R) Construct intersection/interchange rural
Bridge project type
B1 Bridges and approaches
B1(U) Bridges and approaches urban
B1(R) Bridges and approaches rural
B2 Widen bridges
Miscellaneous project type
M1 Miscellaneous roadworks/traffic furniture and devices

Table 4.23: Desired workshop project construction types for future grouping

126
CHAPTER 4
Data collection, analysis techniques and statistics

4.5.7 NGT Workshop Agenda Item 6: Workshop feedback and assessment

As part of the NGT process, an evaluation of the overall workshop process was carried out.
Workshop participants completed four questions about the workshop. A Likert scale was
also provided for each question as shown in Table 4.24. As well, a fifth question was
provided which gave the participants an opportunity to comment on the workshop in general.
The following details the responses of the four questions in the order presented. Seven out of
the eight participants completed the Workshop Evaluation document.

Question 1: The workshop was well paced and easy to understand.


Two participants said that workshop was well paced and easy to understand and five
participants said they agreed (Table 4.24).

Participant Strongly agree Agree Disagree Strongly disagree


1 *
2 *
3 *
4 *
5 *
6 *
7 *

Table 4.24: Workshop evaluation for Question 1

Question 2: The information provide in the week prior to the workshop was useful in
preparing for and also contributing to the workshop outcome.
Two participants strongly agreed that information provided prior to the workshop was useful
in preparing for and contributing to the workshop outcome and five participants said they
agreed (Table 4.25).

Participant Strongly agree Agree Disagree Strongly disagree


1 *
2 *
3 *
4 *
5 *
6 *
7 *

Table 4.25: Workshop evaluation for Question 2

Question 3: The use of the NGT gave me adequate opportunity to provide input into the
workshop.
Two participants also strongly agreed that the use of the NGT provided adequate opportunity
to provide input into the workshop and five participants said they agreed (Table 4.26).

127
Risk factors leading to cost overrun in the delivery of highway construction projects.

Participant Strongly agree Agree Disagree Strongly disagree


1 *
2 *
3 *
4 *
5 *
6 *
7 *

Table 4.26: Workshop evaluation for Question 3

Question 4: The range and number of attendees was adequate for the workshop outcome
Three participants strongly agreed that the range and number of attendees were adequate for
the workshop outcome and four participants said they agreed (Table 4.27).

Participant Strongly agree Agree Disagree Strongly disagree


1 *
2 *
3 *
4 *
5 *
6 *
7 *

Table 4.27: Workshop evaluation for Question 4

The following general comments were also provided by five of the participants:
1. Difficult issue to have a one-on-one relationship. Many causes are multi-
dimensional
2. Not certain it consistently sorted out the conceptual levels of causes
3. Good
4. Good
5. Worked well.

Overall, the NGT workshop worked well as supported by the response rankings of the
workshop evaluation questions.

The expert elicitation in the research adopted the NGT process. The process was
straightforward and used the available time of the experts efficiently. Participants in the
overall expert elicitation process were very supportive of the application of NGT in the
difficult area of identifying client risk in the delivery of projects.

There were two important outcomes that were derived during the NGT process. Firstly, 10
project risk groupings were developed that were ranked in importance by the group with the
application of the importance index. Secondly, a generic set of 12 highway project types was
developed. Both sets of outputs were acceptable for use in the proposed modelling of project
cost overrun using multivariate regression analysis.

128
CHAPTER 4
Data collection, analysis techniques and statistics

4.6 Application of NGT workshop findings to project data

The high-level (HL) risk groupings that were developed by the experts and mapped to the
initial 36 cost overrun factors, as contained in previous Table 4.20, were then mapped back
to the initial projects. This was accomplished with the aid of an Excel spreadsheet. Table
4.28 shows a small sample of the Excel spreadsheet that was produced to map the
associations of (say) the low level cost overrun risks of D Design/project scope change,
DD Design scope change for drainage and DE Design scope change for environmental
issues.
Project Number Risk D HL/1 Risk DD HL/1 Risk DE HL/1
47/16B/302 1 1 0 0
36/15A/301 &302 0 0 0
140/900/2 0 0 0
116/26B/31 1 1 0 0
148/17B/302 1 1 0 0
80/10A/772 1 1 1 1 0
150/10M/301 0 1 1 0
8/26A/302 0 0 0
94/36b/19 1 1 0 0
140/902/2 1 1 0 1 1
160/12B/5 0 0 0
30/6204/13 1 1 0 1 1
5/10K/19 1 1 0 1 1
55/99C/15 0 1 1 0
160/103/3 0 1 1 0
99/323/13 1 1 0 0
160/103/6 1 1 0 1 1
140/U18B/61 0 0 0
140/U18B/61 1 1 0 0
80/133/734 1 1 0 0
36/93E/706 1 1 0 0

Table 4.28: Sample of low level to high level risk group mapping to projects

For the purpose of analysis, 1 was inserted in the master data file for each low level risk and
its associated HL risk grouping for each project. As well, a 0 was inserted in all low level
risk columns when there was no association with a particular HL risk. This provided a
visually complete 'picture' of the project mappings.

129
Risk factors leading to cost overrun in the delivery of highway construction projects.

An analysis was carried out to ascertain which HL groupings of cost overrun factors had the
most occurrences across the projects analysed. There were 42 HL risk combinations
recorded across the project data. Table 4.29 shows the incidences of the HL groupings across
the projects.

Row HL/ risk grouping Incidence


1 1 92
2 2 1
3 3 2
4 4 1
5 5 6
6 6 7
7 7 1
8 8 3
9 9 1
10 10 22
11 1.2 5
12 1.3 5
13 1.4 4
14 1.5 19
15 1.6 5
16 1.7 1
17 1.8 1
18 1.9 2
19 2.4 2
20 3.8 2
21 5.6 3
22 5.8 1
23 1.10 10
24 1.2.5 1
25 1.2.6 1
26 1.2.7 1
27 1.3.5 1
28 1.5.6 3
29 1.5.8 3
30 1.6.8 1
31 3.10 1
32 5.10 1
33 6.10 2
34 7.8.9 1
35 9.10 3
36 1.3.6.9 1
37 1.8.10 2
38 2.4.10 1
39 2.9.10 1
40 4.5.10 1
41 1.4.9.10 1
42 1.6.8.10 1

Table 4.29: Incidences across projects for the HL/ risk groups

130
CHAPTER 4
Data collection, analysis techniques and statistics

Column one of Table 4.29 shows the HL/1. A decimal format has been used to record when
more than one HL risk grouping occurred in a particular project. Rows 1 to 10 of Column 2
of Table 4.29 display the incidences of single HL/1s. Whereas, Row 11 shows that there
were five projects where both HL/1 and HL/2 occurred.

HL/1 recorded the highest incidences with 92 projects. The next highest recorded 22
incidences recorded for HL/2. There were 19 recorded incidences where a combination of
HL/1 and HL/5 occurred in projects. As a further explanation of Table 4.29 above, the last
row shows that there was one project which had HL/1, HL/6, HL/ 8 and HL/10 risk
groupings that collectively contributed to cost overrun in the one recorded project.

It was identified that a significantly high number (92) of incidences were recorded for HL/1,
when compared with the rest of the incidences recorded. The composition of HL/1 consisted
of the following low-level risk factors that were determined in the previous expert elicitation
process:
Design/project scope change (23.6% of projects represented)
Design scope change resulting from drainage, environmental issues, pavement
materials/depth (8.2% of projects represented)
Design scope change as a result of carrying out a safety audit on project (1.0% of
projects represented)
Quantity increase (7.7% of projects represented)
Specification change (1.7% of projects represented).

There had been 31 incidences of quantity increase previously recorded against projects as
shown in previous Table 4.10. As this amount was comprised of 34% of the HL/1 grouping,
it was decided to extract the quantity increase incidences from the HL/1 risk group and
create an eleventh grouping of Quantity increase (HL/Q) for incorporation in the model
analysis.

4.7 Step 4: Undertake data analysis and statistical modelling

The aim of this step was to analyse of historical project data based on statistical theories and
concepts that identified direct correlations between particular highway construction project
types and project cost overrun.

4.7.1 Model dependent variable

The dependent variable adopted in the model was the continuous variable % cost overrun
and was the difference between the clients actual project cost and their programmed cost,
expressed as a percentage of the programmed cost for each project.

4.7.2 Model prediction variables

The initial analysis of the highway cost data has indicated that substantial cost overrun
factors needed to be considered when looking at the reasons for project cost overrun. The
approach identified project variables that had relationships with projects reporting high cost
overrun. The following prediction variables were selected for model investigation and were
based on the availability of historical project data:

131
Risk factors leading to cost overrun in the delivery of highway construction projects.

1. Highway geographic project type


1. Highway project construction type
2. Highway project delivery type
3. Indexed highway project programmed cost
4. Highway project high level risk grouping.

Each of these five variables is explained in the following sections.

4.7.3 Geographic project type

The reason for including the geographic project type in the proposed model was because
there appeared to exist a strong relationship between the remoteness of a project from
established workforces and from proven materials and component manufactures that could
lead to increases in project costs above those estimated. Drew and Skitmore (1992) identified
the density of population and the extent of geographic area as important factors for
competitive bidding in building projects.

It was therefore postulated that the rural geographic type of highway projects had a higher
potential to overrun budgeted costs.

4.7.4 Geographic data and model coding

An analysis was carried out on the project data to split projects down into the geographic
area in which the project was constructed. This split was on the basis of a project being built
in an urban or rural environment. The criterion adopted was whether a project was
constructed in a city or a shire area. The adopted split was based on the Local Government
Regulation s. 5. This provided the following declaration of classes of local government (LA)
areas (Queensland Government, 1993):

Local government areas are classified as shires unless they meet the criteria to be
declared a City or Town and are so declared. They are generally rural areas with
significant rural uses or large tracts of undeveloped land in its natural state.
The criteria for City status require the area to be a regional centre with a total
population of at least 25,000, and a population in the urban centre of at least 15,000
at a population density of at least 150 persons for each square kilometre in that urban
centre.

There were 60 'rural' local authority areas identified in the data and 13 'urban' areas. The
splits into rural/urban are shown in Table 4.30 and were based on the previous shire/city
definitions.

LA number LA name Geographic type


5 Burdekin Shire Council Rural
8 Banana Shire Council Rural
9 Barcaldine Shire Council Rural
10 Mount Isa City Council Rural
12 Bauhinia Shire Council Rural
13 Beaudesert Shire Council Rural

132
CHAPTER 4
Data collection, analysis techniques and statistics

17 Bendemere Shire Council Rural


19 Boulia Shire Council Rural
20 Broadsound Shire Council Rural
22 Bungil Shire Council Rural
23 Burke Shire Council Rural
24 Hervey Bay City Council Urban
25 Caboolture Shire Council Rural
27 Calliope Shire Council Rural
30 Cardwell Shire Council Rural
33 Chinchilla Shire Council Rural
34 Redland Shire Council Rural
35 Clifton Shire Council Rural
36 Cloncurry Shire Council Rural
37 Cook Shire Council Rural
40 Crows Nest Shire Council Rural
41 Croydon Shire Council Rural
42 Dalrymple Shire Council Rural
44 Diamantina Shire Council Rural
45 Douglas Shire Council Rural
47 Duaringa Shire Council Rural
48 Eacham Shire Council Rural
50 Emerald Shire Council Rural
55 Flinders Shire Council Rural
58 Boonah Shire Council Rural
59 Herberton Shire Council Rural
60 Burnett Shire Council Rural
63 Inglewood Shire Council Rural
64 Isis Shire Council Rural
66 Johnstone Shire Council Rural
70 Logan City Council Urban
72 Kilkivan Shire Council Rural
73 Kingaroy Shire Council Rural
76 Caloundra City Council Urban
79 McKinlay Shire Council Rural
80 Maroochy Shire Council Rural
83 Miriam Vale Shire Council Rural
88 Murweh Shire Council Rural
89 Nanango Shire Council Rural
90 Nebo Shire Council Rural
92 Noosa Shire Council Rural
94 Paroo Shire Council Rural
95 Peak Downs Shire Council Rural
97 Pine Rivers Shire Council Rural
99 Pittsworth Shire Council Rural
100 Whitsunday Shire Council Rural
104 Rosalie Shire Council Rural
107 Sarina Shire Council Rural
113 Tara Shire Council Rural
114 Gatton Shire Council Rural
116 Taroom Shire Council Rural

133
Risk factors leading to cost overrun in the delivery of highway construction projects.

119 Atherton Shire Council Rural


120 Mackay City Council Urban
122 Waggamba Shire Council Rural
125 Bowen Shire Council Rural
128 Cooloola Shire Council Rural
130 Wondai Shire Council Rural
133 Mareeba Shire Council Rural
134 Richmond Shire Council Rural
140 Brisbane City Council Urban
141 Bundaberg City Council Urban
146 Maryborough City Council Urban
148 Ipswich City Council Urban
149 Toowoomba City Council Urban
150 Townsville City Council Urban
158 Cairns City Council Urban
160 Gold Coast City Council Urban
161 Gladstone City Council Urban

Table 4.30: Split of rural and urban geographic types

For the purpose of analysis, 1 was inserted as a categorical variable in the master data file for
all projects constructed in a rural environment and a dummy value of' 0 for when the project
was not a rural project. Conversely, a 1 was inserted when a project was classified as urban,
and a dummy 0 for the null case. A sample of this data coding for the geographic area is
shown in Table 4.31.

Project number Rural projects Urban projects


37/91A/20 1 0
160/203/3 0 1
76/153/3 0 1
45/655/18 1 0
5/10K/809 1 0
148/3042/2 0 1
140/U15/44 0 1
140/U16/819 & 820 0 1
37/90C/36 1 0
25/126/23 1 0
70/108/300 0 1
120/856/3 0 1
48/21A802 1 0
66/814/5 1 0
48/6404/3 1 0
34/1102/17 1 0
92/140/11 1 0

Table 4.31: Data coding for geographic types

134
CHAPTER 4
Data collection, analysis techniques and statistics

4.7.5 Highway project construction type reference number

The type of project construction in the proposed model was included because it was thought
that a strong relationship existed between the degree of difficulty in scoping, designing and
constructing highway projects which had multiple lanes and high strength pavements. It was
therefore postulated that highway projects involving duplication to multiple lanes had a
higher potential to overrun budgeted costs. Conversely, it could have been postulated that
bridge projects would have less cost overrun potential because it was easier to design and
construct typically generic highway bridge types.

4.7.6 Construction type data and model coding

Twelve individual highway project construction types were developed as part of the expert
elicitation process. They were detailed in Table 4.22. For the purpose of further data analysis
individual reference numbers were coded to each of the 12 project construction types in
Table 4.32.

Code Construction project type Reference number


R1 Construct to sealed standard (2 lanes) Project type 1
R2 Widen shoulders and sealing Project type 2
R3 Rehabilitate/Strengthen Project type 3
R4 Realignment of two lanes Project type 4
R5 Realignment of four lanes Project type 5
R6 Duplicate two into four lanes Project type 6
R7 Widen four into six/eight lanes Project type 7
R8 Asphalt resurfacing Project type 8
R9 Construct intersection/interchange Project type 9
B1 Bridges and approaches Project type 10
B2 Widen bridges Project type 11
M1 Miscellaneous roadworks/traffic furniture and devices Project type 12

Table 4.32: Construction project type reference number

For the purpose of analysis, 1 was inserted as a categorical variable in the master data file for
all projects constructed in a project type 1 and a dummy value of' 0 for when the project was
not a project type 1. As well, 1s were inserted when a projects were successively project
types 2 to 12 inclusive, with the dummy value of' 0 inserted for when the projects were null
for the particular type.

135
Risk factors leading to cost overrun in the delivery of highway construction projects.

Project Project Project Project Project Project


Project number
type 1 type 2 type 3 type 4 type 5 type 6

37/91A/20 0 0 0 0 0 0
160/203/3 0 0 0 0 0 1
76/153/3 0 0 0 0 0 0
45/655/18 0 0 0 0 0 0
5/10K/809 0 0 0 0 0 0
148/3042/2 1 0 0 0 0 0
140/U15/44 0 0 0 0 0 0
140/U16/819 0 0 1 0 0 0
37/90C/36 1 0 0 0 0 0
25/126/23 0 0 0 0 0 1
70/108/300 0 1 0 0 0 0
120/856/3 0 0 0 0 0 0
48/21A802 0 0 1 0 0 0
66/814/5 0 1 0 0 0 0
48/6404/3 0 0 0 1 0 0
34/1102/17 0 0 0 0 0 0
92/140/11 0 0 0 0 0 0

Table 4.33: Sample data coding for only project types 1 to 6

4.7.7 Project delivery types

The reason for including the type of project delivery of the highway construction in the
proposed model was because there may be a strong relationship between the competitiveness
generated in an open tender environment that should produce lower than client estimate bids
as opposed to a negotiated price contract. As well, sometimes in high risk projects, clients
use of their own internal workforce can be the best option for assuming risks that may
eventuate and hence be managed such that all risk flows back to the client. Conversely, it
could be postulated that open tender contracts have the potential to generate excessive
change order variations brought about by the initial competitive contract price environment.

4.7.8 Project delivery data and model coding

Three project delivery types were initially developed in Table 4.5 as open tender, negotiated
price internal workforce and negotiated price external workforce. The delivery codes are
shown in Table 4.34.

Revised delivery description Delivery code


Open tender Delivery code 1
Negotiated price internal workforce Delivery code 2

Negotiated price external workforce Delivery code 3

Table 4.34: Project delivery codes

136
CHAPTER 4
Data collection, analysis techniques and statistics

For the purpose of analysis, 1 was inserted as a categorical variable in the master data file for
delivery code 1 and a dummy value of' 0 for when that delivery code did not apply to a
project. A similar treatment of 1s and 0s was applied for delivery code 2 and delivery code 3.
A sample of this data coding for the project delivery codes is shown in Table 4.35.

Project number Delivery code 1 Delivery code 2 Delivery code 3


37/91A/20 1 0 0
160/203/3 1 0 0
76/153/3 1 0 0
45/655/18 1 0 0
5/10K/809 0 1 0
148/3042/2 1 0 0
140/U15/44 1 0 0
140/U16/819 1 0 0
37/90C/36 0 1 0
25/126/23 1 0 0
70/108/300 1 0 0
120/856/3 1 0 0
48/21A802 1 0 0
66/814/5 1 0 0
48/6404/3 1 0 0
34/1102/17 0 1 0

Table 4.35: Sample data coding for project delivery codes

4.7.9 Indexed highway project programmed cost continuous variable

Generally there is a correlation between the cost of a project and the size of the project. In
this research it was adopted that, if projects costs are indexed to a common year, then the
project cost can be used as a surrogate for project size. The reason for including the indexed
highway programmed cost in the proposed model was because it was thought that there was
a strong relationship between the size of a project and the percentage a project might
overrun. For highway projects, the greatest risk lays below ground level due to the relatively
greater physical footprint of the project, and the larger the footprint, then the larger the risk
cost should be. Williams (2003) reported results that suggested that large highway projects
tended to have much higher relative cost increases than small projects.

Hence it was postulated that larger projects overrun budget more so than smaller projects
when indexed to a common year. The minimum project size was limited to A$1m.

For the purpose of the research analysis, the programmed cost data in A$m from financial
years 199596 through to 200102 were adjusted by way of a cost index (refer Table 4.9) up
to 200203 out-turn year was the continuous variable used.

A sample of this continuous variable data is shown in Table 4.36.

137
Risk factors leading to cost overrun in the delivery of highway construction projects.

Indexed program
Project number
cost $m
37/91A/20 4.73
160/203/3 1.36
76/153/3 2.55
45/655/18 1.90
5/10K/809 1.30
148/3042/2 1.81
140/U15/44 2.30
140/U16/819 & 820 1.80
37/90C/36 1.77
25/126/23 1.28
70/108/300 1.30
120/856/3 3.81
48/21A802 1.13
66/814/5 2.06
48/6404/3 8.69
34/1102/17 2.00
92/140/11 1.70

Table 4.36: Sample of indexed programmed cost $m continuous variables

4.7.10 Project high level risks

The reason for including client risks associated with highway project construction in the
model was that there was very strong research and historical project data evidence that
suggested strong linkage to between the realisation of unplanned or under-budgeted project
risks and cost overrun of constructed projects. Smith (1995a) has confirmed that
inappropriate risk management can also lead to higher costs for the client. As well, El-
Choum (1994) identified project cost overrun parameters for public infrastructure projects.

Risks associated with varying types of highway construction projects were considered to
have possible effects on the differences observed in cost overrun. Possible correlations may
have existed between the prevalence of certain risks with certain levels of cost overrun. It
was postulated that particular groupings of historical risks which clients have been exposed
to in highway project delivery bear a relationship to the size of project cost overruns.It was
further postulated that risks that were ranked most important in terms of impact on project
cost overrun by a team of experts would produce higher cost overruns in the model.

4.7.11 Project high level risk data and model coding

Ten high level risk groupings were initially developed using the NGT process. A further
analysis demonstrated the need to have extracted quantity increase from HL/1 into its own
HL/Q. Table 4.37 shows the 11 groupings used in the model

138
CHAPTER 4
Data collection, analysis techniques and statistics

High level risk description Code


Design and scope change HL/1
Insufficient investigations and latent conditions HL/2
Deficient documentation (specification and design) HL/3
Client project management costs HL/4
Services relocation HL/5
Constructability HL/6
Price escalation HL/7
Right of way costs HL/8
Contractor risks HL/9
Environment HL/10
Quantity HL/Q

Table 4.37: High level risk groupings codes

For the purpose of analysis, a 1 was inserted as a categorical variable in the master data file
against projects which had a HL/1 associated with them and a dummy value of' 0 for when
the high level risk design and scope change did not apply to the projects. A similar
treatment of 1s and 0s was applied for HL/2 through to HL/10 and HL/Q. A sample of this
data coding for the project delivery codes is shown in Table 4.38.

Project
HL/1 HL/2 HL/3 HL/4 HL/5 HL/6 HL/7 HL/8 HL/9 HL/10 HL/Q
number
37/91A/20 1 0 0 0 1 0 0 0 0 0 0
160/203/3 1 0 0 0 0 0 0 0 0 0 0
76/153/3 1 0 0 0 0 0 0 0 0 0 0
45/655/18 1 0 0 0 0 0 0 0 0 0 0
5/10K/809 1 0 0 0 1 0 0 0 0 0 0
148/3042/2 1 0 0 0 0 0 0 0 0 0 0
140/U15/44 1 0 0 0 0 0 0 0 0 0 0
140/U16/819 0 0 0 0 0 0 0 0 0 1 0
37/90C/36 1 0 0 0 0 0 0 0 0 0 0
25/126/23 1 1 0 0 0 0 0 0 0 0 0
70/108/300 1 0 0 0 0 0 0 0 0 0 0
120/856/3 0 0 0 0 0 0 1 0 0 0 0
48/21A802 1 0 0 0 0 0 0 0 0 0 0
66/814/5 1 0 0 0 0 0 0 0 0 1 0
48/6404/3 1 0 0 0 0 0 0 0 0 0 0
34/1102/17 0 0 0 0 0 0 0 0 0 1 0
92/140/11 1 0 0 0 0 0 0 0 0 0 0

Table 4.38 Sample of high level risk grouping codes against projects

4.8 Regression modelling


4.8.1 Outlying data values

As a preliminary step in the analysis process, the 231 project cases identified in Section 4.3
were analysed for random disturbance. For the purpose of specifically identifying any

139
Risk factors leading to cost overrun in the delivery of highway construction projects.

project outliers, a linear regression analysis was carried out using the dependent variable as
'project cost overrun $m' and the predictor variable as 'indexed programmed cost $m'. A
value of two standard deviations from the initial estimated line was set to measure the
variability of the random disturbance. It was postulated that about 95% of observed points
should have fallen within the adopted two standard errors, assuming normality. This analysis
generated a table of project cases with residuals more than the adopted value. This was
helpful in identifying potential outlying data values.

The following Table 4.39 details the casewise diagnostics that were produced from the
analysis of the two nominated variables.

Case number Std. residual Cost overrun $m Predicted value Residual


12 8.703 17.1 34.911 17.7705
57 3.124 12.0 18.344 6.3783
138 2.164 34.7 30.230 4.4197
168 3.643 28.5 21.111 7.4384
196 9.451 42.4 23.108 19.2991
Dependent variable: cost overrun $m
Table 4.39: Case-wise diagnostics

As can be seen in Table 4.39, there are five cases identified with standardised residuals
exceeding 2 in absolute value. An analysis of the data behind the case numbers identified in
the diagnostics revealed the following projects in Table 4.40 as being potential data outliers

Case Year of Corresponding project


Project description
number project number
Pacific Highway (Pacific Motorway)
12 20002001 160/12A/8.561 *
Logan Motorway Stapylton
57 19971998 160/12A/8.562 Pacific Motorway (Logan Nerang)
Pacific Highway (Pacific Motorway)
138 20002001 160/12A/8.564 #
Oxenford Gaven
168 19971998 160/12A/8.561 # Pacific Motorway (Logan Nerang)
Pacific Motorway (Logan Nerang)
196 19992000 160/12A/8.564 *
Oxenford Gaven

Table 4.40: Project outlier details

The projects * and # were reported on in successive years. It was noted that all five cases
above related to the Pacific Motorway project that had been constructed during the period
19972001 and all had been classified as R7 (Widen four lanes into six/eight lanes). Since
the standardised residuals of these five cases exceeded 2 in absolute terms, then it was
considered appropriate to exclude these five cases from any future model analysis. The
sample size was subsequently reduced from 231 highway projects down to 226.

A further analysis of the remaining project data for all R7 projects showed that only three
projects remained in this category. It was then decided to remove those remaining three R7
projects. This step removed all project type 7 from all further model analysis and provided
223 projects for further analysis.

140
CHAPTER 4
Data collection, analysis techniques and statistics

4.8.2 Multivariate regression analysis

The statistical tool of multivariate regression was used to analyse the correlation between the
following project variables that were simultaneously associated with the dependent variable
of cost overrun percentage:
1. Highway geographic project type (urban/rural projects)
2. Highway project construction type (project types 1 to 12)
3. Highway project delivery type (delivery code 1, 2 or 3)
4. Indexed highway project programmed cost (indexed prog. cost $m)
5. Highway project high level risk grouping (HL/1 to 10 and HL/Q).

Due to wide spectrum of highway projects, delivery methods and client risks that caused cost
overrun, many regression models were possible. According to 5 variable listings above, there
were 2 geographic location types, 12 project types, 3 project delivery methods, and 11 high
level risk groupings that were hypothesised as influencing the amount of project cost overrun
for the projects analysed.

The null hypothesis adopted for Pearson's correlation test was that there was no correlation
between the size of cost overrun of projects (and their geographic location, construction
type, delivery process, project size, and client project risks).

Model testing was applied to confirm or otherwise that the given independent (prediction)
variables in the model did not correlate against the dependent variable of project cost
overrun with any significant level of accuracy.

For the purpose of research, the statistical models were considered linear normal models (i.e.
regression analysis with the appropriate f -tests and t-tests). For each test, the p-value was
reported as a measure for rareness if identity of groups was assumed. A p-value less than
0.01 was considered highly significant and less than 0.05 significant. Whereas a larger p-
value meant that the deviation could be due to chance.

Three stages of statistical regression were computed using the method of least squares
The following three methods were used to include and exclude independent variables
in the analysis:
forward selection
backward selection
stepwise selection.

In stage one, the independent best correlated with the dependent was included in the
equation. In the second stage, the remaining independent with the highest partial correlation
with the dependent, controlling for the first independent, was entered. This process was
repeated at each stage for previously-entered independents, until the addition of a remaining
independent did not increase R2 by a significant amount or until all variables were entered.

The next step was to inspect the residuals as surrogates for random disturbances and to make
further judgements on the validity of the data and the linear regression model. The following
sections detail the three selection modes applied to the project data for this purpose.

141
Risk factors leading to cost overrun in the delivery of highway construction projects.

4.8.3 Forward selection mode for multivariate regression analysis

Forward selection this method started with a model that contained none of the
explanatory variables. In the first step, the procedure considered variables one by one for
inclusion and selected the variable that results in the largest increase in R2. In the second
step, the procedure considered variables for inclusion in the model that only contained the
variable selected in the first step. In each subsequent step, the variable with the largest
increase in R2 was selected, until, according to an f -test, further additions were judged to not
improve the model.

The forward selection was next carried out on the data with each of the independent
variables entered separately. Table 4.41 shows the independent variables entered and
removed during the forward selection method. The dependent variable entered was % over
cost.

Variables
Model Variables entered Method
removed
Forward
1 Indexed prog cost $m Nil (Criterion: Probability-of-f-to-enter <=
0.050)
Forward
2 Project type 12 Nil (Criterion: Probability-of-f-to-enter <=
0.050)
Forward
3 HL/1 Nil (Criterion: Probability-of-f-to-enter <=
0.050)

Table 4.41: Variables entered/removed in forward selection mode

As the forward selection mode had been used, there were no variables removed. Only those
variables which had a probability of f <= 0.050 were entered. Three models were produced
in the forward selection analysis.

The regression model summary for the forward selection mode is shown in Table 4.42. R
represents the correlation between the linear regression prediction and the actual % over
cost. The R values for models 1 and 2 were <0.2 and thus had negligible correlation. Model
3 had an R value of 0.245 which indicated a low correlation that was not very significant.
The R2 values 0.019, 0.037 and 0.060 for models 1, 2 and 3 were statistically very poor.
Column 4 shows the coefficient of multiple determination as adjusted R2 and was the
adjustment applied to R2 to account for the number of variables in the model and the sample
size used). The adjusted R2 for models 1, 2 and 3 were 0.015 (1.5%), 0.028 (2.8%) and 0.047
(4.7%) respectively. This meant that by moving to model three, there was an increase of only
3.2% in the total variation in the % over cost dependent variable.

142
CHAPTER 4
Data collection, analysis techniques and statistics

Model R R2 Adjusted R2 Std. error of the estimate


1 0.139(a) 0.019 0.015 22.0986
2 0.192(b) 0.037 0.028 21.9501
3 0.245(c) 0.060 0.047 21.7318

Table 4.42: Forward selection mode summary using dependent variable of % over cost

The following predictor variables were used in the models:


a. Model 1: Indexed prog. cost $m
b. Model 2: Indexed prog. cost $m, Project type 12
c. Indexed prog cost $m, Project type 12, HL/1.

Unstandardised and standardised regression coefficients, as well as t and significance values


for each of the three models were derived. These are shown in Table 4.43. The beta
standardised coefficients for each variable, as shown in Column five of Table 4.43, gave the
relative importance of each variable and measured the change in the dependent variable %
over cost in units of its standard deviation. It showed that for Model 3, the variable 'Project
Type 12' (beta = 0.158) had a marginally greater impact on the dependent variable % over
cost than HL/1 (beta = 0.155).

Unstandardised Standardised
coefficients coefficients
Model Std. t Sig.
B Beta
error

(Constant) 31.048 1.773 17.509 0.000


1 Indexed prog.
-0.414 0.198 -0.139 -2.086 0.038
Cost $m
(Constant) 30.148 1.818 16.584 0.000
Indexed prog.
2 -0.403 0.197 -0.135 -2.043 0.042
Cost $m
Project type 12 11.083 5.541 0.132 2.000 0.047
(Constant) 26.105 2.499 10.448 0.000
Indexed prog.
-0.436 0.196 -0.146 -2.226 0.027
3 Cost $m
Project type 12 13.208 5.561 0.158 2.375 0.018
HL/1 6.989 2.996 0.155 2.333 0.021

Dependent variable: % over cost $m


Table 4.43: Coefficients for forward selection mode

The variables excluded from the forward selection mode, along with beta, t and significance
(f) values are shown in Table 4.44. The significance values of excluded variables that are
shown in Column five of Table 4.44 were all >0.05. The observed slope of the model was
given by the t value in Column four and was found to be significantly greater than 0. The
results of the forward mode analysis indicated that the overall f results showed moderate
evidence that the three models were statistically significant.

143
Risk factors leading to cost overrun in the delivery of highway construction projects.

Excluded
Model Beta t Sig.
variable
1 Rural projects -0.101(a) -1.449 0.149
Urban projects 0.101(a) 1.449 0.149
Project type 1 -0.041(a) -0.612 0.541
Project type 2 -0.073(a) -1.098 0.273
Project type 3 -0.096(a) -1.415 0.158
Project type 4 -0.008(a) -0.116 0.907
Project type 5 -0.038(a) -0.573 0.567
Project type 6 0.000(a) -0.006 0.995
Project type 8 0.028(a) 0.424 0.672
Project type 9 0.104(a) 1.560 0.120
Project type 10 0.006(a) 0.097 0.923
Project type 11 0.038(a) 0.575 0.566
Project type 12 0.132(a) 2.000 0.047
Delivery code 1 0.058(a) 0.828 0.408
Delivery code 2 0.024(a) 0.351 0.726
Delivery code 3 -0.106(a) -1.579 0.116
HL/1 0.129(a) 1.950 0.052
HL/2 -0.016(a) -0.235 0.814
HL/3 -0.051(a) -0.762 0.447
HL/4 -0.107(a) -1.615 0.108
HL/5 -0.006(a) -0.083 0.934
HL/6 0.009(a) 0.128 0.899
HL/7 0.053(a) 0.794 0.428
HL/8 -0.024(a) -0.354 0.723
HL/9 -0.055(a) -0.823 0.411
HL/10 -0.062(a) -0.934 0.351
HL/ Q -0.090(a) -1.358 0.176
2 Rural Projects -0.068(b) -0.939 0.349
Urban Projects 0.068(b) 0.939 0.349
Project type 1 -0.026(b) -0.390 0.697
Project type 2 -0.062(b) -0.926 0.355
Project type 3 -0.075(b) -1.104 0.271
Project type 4 0.002(b) 0.024 0.981
Project type 5 -0.034(b) -0.512 0.609
Project type 6 0.015(b) 0.215 0.830
Project type 8 0.034(b) 0.509 0.612
Project type 9 0.115(b) 1.740 0.083
Project type 10 0.021(b) 0.313 0.755
Project type 11 0.044(b) 0.661 0.509
Delivery code 1 0.073(b) 1.043 0.298
Delivery code 2 -0.004(b) -0.059 0.953
Delivery code 3 -0.091(b) -1.357 0.176
HL/1 0.155(b) 2.333 0.021
HL/2 -0.006(b) -0.095 0.924
HL/3 -0.062(b) -0.934 0.352

144
CHAPTER 4
Data collection, analysis techniques and statistics

HL/4 -0.099(b) -1.501 0.135


HL/5 -0.003(b) -0.039 0.969
HL/6 -0.002(b) -0.028 0.978
HL/7 0.060(b) 0.899 0.370
HL/8 -0.039(b) -0.583 0.561
HL/9 -0.047(b) -0.701 0.484
HL/10 -0.065(b) -0.981 0.328
HL/ Q -0.117(b) -1.756 0.081
3 Rural Projects -0.065(c) -0.911 0.363
Urban Projects 0.065(c) 0.911 0.363
Project type 1 -0.023(c) -0.344 0.731
Project type 2 -0.066(c) -0.998 0.319
Project type 3 -0.073(c) -1.080 0.281
Project type 4 0.002(c) 0.034 0.973
Project type 5 -0.036(c) -0.548 0.584
Project type 6 0.022(c) 0.326 0.745
Project type 8 0.016(c) .247 0.805
Project type 9 0.113(c) 1.724 0.086
Project type 10 0.022(c) 0.332 0.740
Project type 11 0.048(c) 0.724 0.470
Delivery code 1 0.059(c) 0.846 0.398
Delivery code 2 0.011(c) 0.157 0.875
Delivery code 3 -0.090(c) -1.351 0.178
HL/2 0.005(c) 0.074 0.941
HL/3 -0.052(c) -0.790 0.430
HL/4 -0.086(c) -1.313 0.191
HL/5 0.003(c) 0.050 0.960
HL/6 0.031(c) 0.462 0.645
HL/7 0.084(c) 1.265 0.207
HL/8 -0.012(c) -0.183 0.855
HL/9 -0.023(c) -0.346 0.729
HL/10 -0.009(c) -0.127 0.899
HL/ Q -0.059(c) -0.788 0.432

Table 4.44: Excluded variables in forward selection mode

The following predictor variables were used in the derived models:


a. Model 1: Indexed prog. cost $m
b. Model 2: Indexed prog. cost $m, Project type 12
c. Model 3: Indexed prog cost $m, Project type 12, HL/1.

4.8.4 Backwards selection mode for multivariate regression analysis

Backward selection This method started with a model containing all the variables and
eliminated variables one by one. At each step the variable chosen for exclusion was that
leading to the smallest decrease in R2. The procedure was repeated until, according to the f
test, further exclusions did not represent a deterioration of the model. Only those variables
which had a probability of f >= 0.100 were removed in the backwards selection process. A

145
Risk factors leading to cost overrun in the delivery of highway construction projects.

total of 24 models was produced and produced R2 values ranging from 0.110 (11%) down to
0.073 (7.3%), which indicated very poor coefficient of variations for the models developed.

The analysis output for the backwards selection mode was very large, and so it was not
reproduced in this section.

4.8.5 Stepwise selection mode for multivariate regression analysis

Stepwise selection This third method involved the combination of the previous two
approaches and started with no variables in the model. Variables were then added, as with
the forward selection method. In addition, after each inclusion step, a backward elimination
process was carried out to remove variables that were no longer judged to improve the
model. Caution in this process was required as the stepwise procedure was claimed to be
controversial because it included independent variables based on statistical criteria and not
theoretical ones (Bryman and Cramer, 1999). f statistics with probabilities of 5% and 10%
were employed for entry and removal criteria.

The stepwise analysis produced three models. Table 4.45 shows the variables entered, with
no variables being able to be removed under the above f criteria.

Variables Variables
Model Method
entered removed
Indexed prog. Stepwise (Criteria: Probability-of- f -to-enter <= .050,
1 Nil
cost $m Probability-of- f -to-remove >= .100).
Stepwise (Criteria: Probability-of- f -to-enter <= .050,
2 Project type 12 Nil
Probability-of- f -to-remove >= .100).

Stepwise (Criteria: Probability-of- f -to-enter <= .050,


3 HL/1 Nil
Probability-of- f -to-remove >= .100).

Table 4.45: Variables entered/removed in stepwise selection mode

4.9 Summary of variable selection modes for multivariate


linear regression analysis
The R, R2, adjusted R2 and standard error of the estimate outputs from the forward,
backwards and stepwise multivariate linear regression analysis were collated and are shown
in Table 4.46
for the three selection modes

Method Model number R R2 Adjusted R2 Std. error of the estimate


Forward 1 0.139 0.019 0.015 22.0986
Forward 2 0.192 0.037 0.028 21.9501
Forward 3 0.245 0.060 0.047 21.7318
Backwards 1 0.333 0.111 -0.007 22.3395
Backwards 2 0.333 0.111 -0.002 22.2827
Backwards 3 0.333 0.111 0.003 22.2265

146
CHAPTER 4
Data collection, analysis techniques and statistics

Backwards 4 0.333 0.111 0.008 22.1712


Backwards 5 0.333 0.111 0.013 22.1162
Backwards 6 0.333 0.111 0.018 22.0632
Backwards 7 0.333 0.111 0.023 22.0109
Backwards 8 0.332 0.110 0.027 21.9600
Backwards 9 0.332 0.110 0.032 21.9103
Backwards 10 0.331 0.109 0.035 21.8674
Backwards 11 0.329 0.108 0.039 21.8252
Backwards 12 0.327 0.107 0.042 21.7906
Backwards 13 0.325 0.106 0.045 21.7538
Backwards 14 0.323 0.105 0.049 21.7133
Backwards 15 0.321 0.103 0.052 21.6807
Backwards 16 0.317 0.100 0.054 21.6604
Backwards 17 0.314 0.099 0.056 21.6325
Backwards 18 0.311 0.096 0.058 21.6059
Backwards 19 0.307 0.094 0.060 21.5854
Backwards 20 0.300 0.090 0.061 21.5799
Backwards 21 0.293 0.086 0.060 21.5818
Backwards 22 0.284 0.081 0.059 21.5934
Backwards 23 0.270 0.073 0.056 21.6346
Stepwise 1 0.139 0.019 0.015 22.0986
Stepwise 2 0.192 0.037 0.028 21.9501
Stepwise 3 0.245 0.060 0.047 21.7318

Table 4.46 Summary of multivariate linear regression for three modes

The forward and stepwise analysis both produced three identical models, while the
backwards mode produced 13 models. The R2 values ranged overall from 0.019 (1.9%) up to
0.111 (11%) and these values indicated a very poor coefficient of variation. As well,
adjusted R2 values ranged overall from 0.002 to 0.061 which again indicated very weak
models. The standard error of the regression estimate shown in Column 6. The values were
consistently large and only showed a slight reduction in each of the models for the forward,
backwards and stepwise modes.

This fact, combined with the low estimates for R2 and adjusted R2, indicated that the models
had not fitted the data very well.

4.10 Sensitivity testing of project data used in regression analyses


Sensitivity testing was investigated for the stepwise regression models developed in order to
ascertain whether additional outlier data still unduly influenced the models.

The Project type 12 in model 2 showed prima facie, that these 17 miscellaneous projects
were catch-alls for the undefined projects in the initial data categorisation. On review of the
project data, the majority of the Project type 12 (Miscellaneous) was associated with the
construction of sound attenuation structures to the boundary lines of urban highways or
traffic infrastructure such as signalisation and signage. In particular, Project 140/U16/301
was categorised as Project type 12 (Miscellaneous roadworks/traffic furniture and devices)

147
Risk factors leading to cost overrun in the delivery of highway construction projects.

project in the initial data compilation. A review of the project's specific data indicated that
this project was described as a traffic management devices project on the Ipswich Highway
(Cunningham Arterial). The open tender project included the installation of permanent
separator concrete barriers, guardrails and fencing as well as temporary traffic control
devices. The works were reported to have been carried out totally at night and under heavy
traffic flows. The programmed cost in 2001 was $7.43m and the project experienced a cost
overrun of 54.3%. Because of the unique nature of the project it was considered an outlier
and removed from further regression analysis.

In addition, project 160/12A/8.57-59 was categorised as a Type 12 (Miscellaneous


roadworks/traffic furniture and devices) project in the initial data compilation. A review of
the project's data indicated that this project was described as ancilliary works on the eight-
lane Pacific Motorway (Pacific Highway). The open tender project involved the fabrication
and installation of signage, noise amelioration, landscaping and roadworks. The programmed
cost in 2001 was $28.2m and the project experienced a cost overrun of 27.7%. Because of
the unique nature of the specific project and its location within the larger Pacific Motorway
eight-lane project (R7 project type), the project was removed from further analysis. (All
other R7 projects have already been removed from the regression analysis.)

The data were re-analysed with the omission of the two outlier projects using stepwise mode
and the analysis produced the following models.

Unstandardised Standardised
Model Variable coefficients coefficients t Sig.
B Std. error Beta
(Constant) 27.257 1.325 20.572 0.000
1
Project type 9 10.143 4.924 0.138 2.060 0.041
(Constant) 28.952 1.563 18.522 0.000
2 Project type 9 10.031 4.891 0.136 2.051 0.041
Indexed prog. cost $m -0.340 0.169 -0.134 -2.009 0.046
(Constant) 26.123 2.096 12.463 0.000
3 Project type 9 9.769 4.859 0.133 2.011 0.046
Indexed prog. cost $m -0.366 0.169 -0.144 -2.170 0.031
HL/1 5.137 2.558 0.133 2.009 0.046

Dependent variable: % over cost $m


Table 4.47: Sensitivity testing of coefficients for secondary stepwise selection mode

As each of the revised models contained Project type 9, all these projects were investigated
for data outliers. It was identified that Project 76/153/3 was an open tender at-grade
intersection improvement project with an initial indexed programmed cost of $2.55m that
was completed in 1999 and had a cost overrun of 110.9%. This case gave a predicted value
of $40.09m and a residual of 70.1 which was outside two standard errors and it was
considered appropriate to discard the project as an outlier.
The data was re-analysed with the further omission of Project 76/153/3 using stepwise mode.
The following single model shown in Table 4.48 was derived.

148
CHAPTER 4
Data collection, analysis techniques and statistics

Model R R2 Adjusted R2 Std. error of the estimate


1 0.135 0.018 0.014 18.1997

Table 4.48: Sensitivity testing for stepwise selection mode summary

The following predictor variable was used in the model:


Predictor: (Constant), Indexed prog. cost $m
Dependent variable: % over cost

Unstandardised and standardised regression coefficients, as well as t and significance values


for the model are shown in Table 4.49. The beta standardised coefficient for the variable is
shown in Column 5 of Table 4.49 and measured the change in the dependent variable % over
cost in units of its standard deviation. It showed that for the model 1, the variable
IndexedProgCost$m had a beta = -0.135.

Unstandardised Standardised
Model coefficients coefficient t Sig.
B Std. Error Beta
(Constant) 29.249 1.472 19.870 0.000
1
IndexedProgCost$m -0.328 0.164 -0.135 -2.007 0.046

Dependent variable: % over cost $m


Table 4.49: Coefficients for stepwise selection mode

The variables excluded from the stepwise selection mode on the revised data set, along with
beta, t and significance (f) values are shown in Table 4.50. The significance values of
excluded variables that are shown in Column five were all >0.05. The observed slope of the
model was given by the t value in Column four and was found to be greater than 0. The
results of this stepwise mode analysis indicated that the overall f results showed moderate
evidence that the model was statistically significant.

Model Beta in t Sig.


1 Rural projects -0.046 -0.651 0.516
Urban projects 0.046 0.651 0.516
Project type 1 -0.021 -0.317 0.752
Project type 2 -0.063 -0.932 0.352
Project type 3 -0.067 -0.983 0.327
Project type 4 0.011 0.162 0.871
Project type 5 -0.039 -0.581 0.562
Project type 6 0.023 0.326 0.745
Project type 8 0.047 0.698 0.486
Project type 9 0.072 1.074 0.284
Project type 10 0.036 0.539 0.590
Project type 11 0.059 0.883 0.378
Project type 12 -0.027 -0.395 0.693
Delivery code 1 0.115 1.645 0.101
Delivery code 2 -0.046 -0.672 0.502

149
Risk factors leading to cost overrun in the delivery of highway construction projects.

Delivery code 3 -0.094 -1.390 0.166


HL/1 0.125 1.869 0.063
HL/2 -0.001 -0.011 0.991
HL/3 -0.044 -0.656 0.513
HL/4 -0.114 -1.703 0.090
HL/5 -0.025 -0.371 0.711
HL/6 -0.098 -1.459 0.146
HL/7 0.079 1.177 0.241
HL/8 -0.011 -0.163 0.871
HL/9 -0.051 -0.759 0.449
HL/10 -0.037 -0.547 0.585
HL/Q -0.129 -1.941 0.054

Predictor in the Model: (Constant), Indexed prog. cost $m


Dependent variable: % over cost $m

Table 4.50: Excluded variables in stepwise selection mode using revised data

The residual statistics for the stepwise model are detailed in Table 4.51 below and shows the
standard deviation for the residuals at a relatively wide 18.1581 for the revised 220 projects.

Minimum Maximum Mean Std. deviation N


Predicted value 13.561 28.921 27.617 2.4678 220
Residual -18.3199 85.6141 0.0000 18.1581 220
Std. predicted value -5.696 0.528 0.000 1.000 220
Std. residual -1.007 4.704 0.000 0.998 220

Dependent Variable: %Over Cost


Table 4.51: Residual statistics for stepwise selection mode for revised project data

The stepwise analysis for the revised project data produced the one model. f statistics with
probability of 5% and 10% were employed for entry and removal criteria. Table 4.52 shows
the variables entered, with no variables being removed under the above f criteria.

Variables Variables
Model Method
entered removed
Indexed prog. Stepwise (Criteria: Probability-of-f-to-enter <= .0050,
1 Nil
cost $m Probability-of-f-to-remove >= 0.100).

Dependent Variable: % Overcost


Table 4.52: Variables entered/removed in stepwise selection mode

4.11 Testing the general assumptions of regression and residual analysis


The preceding residual and significance results produced from the stepwise mode analysis on
the revised 220 projects had indicated that the model developed using only
IndexedProgCost$m as the predictor variable was statistically significant.

150
CHAPTER 4
Data collection, analysis techniques and statistics

An inspection of the residuals as surrogates for random disturbances enabled further


judgements on the validity of the data and the regression model. Graphical plots were used
for testing the normality and homogeneity for model validation as they had the advantage
over numerical methods of readily illustrating the relationship between models and data.

4.11.1 Normality of error testing

A normality of error test on the regression model was carried out to test the robustness
around the regression line. This was tested by plotting the normal probability of the sorted
values of the residuals versus the associated theoretical values from the standard normal
distribution. This was to check whether or not it was reasonable to assume that the random
errors inherent in the process had been drawn from a normal distribution. The assumption
adopted was that the variability of data around the regression line should have been constant
for all values of X in the regression model. The normal probability plot was ascertained to
see if the residuals were normally distributed by lying along a 45 degree upward sloping
diagonal line. The null hypothesis was that the residuals were normal, and to the extent that
the graph deviated moderately from the 45 degree pattern then the normality assumption
needed to be questioned. Figure 4.2 shows the Normal probability plot of the revised project
cases.

Dependent Variable: % over cost


1.0
Expected Cumulative Probability

0.8

0.6

0.4

0.2

0.0
0.0 0.2 0.4 0.6 0.8 1.0

Observed Cumulative Probability

Figure 4.2: Normal probability plot of regression standardised residuals

The plot was inspected to see if the random errors were normally distributed with the plotted
points lying close to a straight line. The distinct curvature deviations from the straight line
indicated that the random errors were probably not normally distributed. As can be seen, the

151
Risk factors leading to cost overrun in the delivery of highway construction projects.

graph demonstrated poor conformance to a 45 degree diagonal line with some values
plotting away from the straight line.

The next section describes the test carried out for homegeneity of variance.

4.11.2 Standardised residuals testing

The next graph produced was the scatterplot of the standardised residuals versus the
estimated standardised (or fitted) values. This was to provide an insight into the assumption
of equal variances, as well as the assumption that X and Y had a linear relationship in the
regression equation. Figure 4.3 shows the scatterplot of the standardised residuals versus
predicted values of the original 220 cases.

Dependent variable: % over cost


Regression standardised residual

-1

-2

-6 -5 -4 -3 -2 -1 0 1

Regression standardised predicted value

Figure 4.3: Scatterplot of the standardised residuals versus predicted values of 220 cases

The plot is decreasingly dispersed across left to right. This suggested that the variances were
not constant along the regression line and indicated a violation of the homogeneity-of-
variance assumption (homoskedasticity). This rendered the inference unreliable by not
having a more randomly scattered plot in an even, horizontal band around the residual value
of zero. One reason for the shape of the plot was that the project data used in the research
was limited to the inclusion of projects => 10% cost overrun. As well, the lower project
programmed cost was limited to => $1m. In further examining the plot, a number of points
exceeded +2. Under the model assumption, 95% of the standardised residuals were expected
to be within the range of -2 to +2.

The bulking of the data to the right of the plot indicated that some form of data
transformation may have been required so as to satisfy random disturbances. This is
discussed in the following section.

152
CHAPTER 4
Data collection, analysis techniques and statistics

4.11.3 Data transformation investigation

A histogram showing the frequency of the regression standardised residuals was next
produced (Figure 4.4) to ascertain whether the shape was consistent with the assumption of
normality.

Dependent Variable: % over cost

60

50
Frequency

40

30

20

10

Mean =1.63E-16
0 Std. Dev. =0.998
N =220
-2 0 2 4

Regression standardised residual

Figure 4.4: Histogram of standardised residuals

The histogram showed a relatively heavy positive skew of the data. This indicated that data
transformation was required to improve the model. Hutcheson and Sofroniou (1999)
suggested taking the reciprocal of X where X is an observed value for heavy positive
skewness.

4.11.4 Data transformation using reciprocal of X

The indexed programmed cost transformed using the reciprocal of the observed values.
Table 4.53 shows a sample from the 220 projects with transformed indexed programmed
costs.

Project number Indexed prog. cost $m Reciprocal indexed prog. cost $m % over cost
140/U88/3 47.79 0.02092 18.0
160/12A/8.566 46.02 0.02173 25.3
160/12B/5 42.55 0.02350 12.6
70/25A/13 40.42 0.02474 14.7

153
Risk factors leading to cost overrun in the delivery of highway construction projects.

150/10L/55 35.40 0.02825 32.5


70/25A/13 32.71 0.03057 25.7
160/12A/8.57-59 29.95 0.03339 27.7
160/12A/8.565 28.23 0.03543 23.9

Table 4.53: Sample of data using reciprocal transformation

4.11.5 Re-testing of general assumptions of residuals

A re-inspection of the residuals as surrogates for random disturbances was carried out so as
to make further judgements on the validity of the transformed data and an associated
regression model. Graphical plots were again used for testing the normality and homogeneity
for the revised model's validation. Figure 4.4 shows the revised Normal Probability Plot
when using the transformed project data.

Normal P-P pot of regression standardised residual

Dependent variable: % over cost


1.0
Expected cumulative probability

0.8

0.6

0.4

0.2

0.0
0.0 0.2 0.4 0.6 0.8 1.0

Observed cumulative probability

Figure 4.4: Normal probability plot with transformed variable

The scatter plot of the standardised residuals versus the estimated standardised transformed
values is contained in Figure 4.5.

154
CHAPTER 4
Data collection, analysis techniques and statistics

Dependent variable: % over cost


Regression standardised residual

-1

-2

-2 -1 0 1 2

Regression standardised predicted value

Figure 4.5: Scatterplot of standardised residuals versus predicted of transformed data

It was observed that the plot was dispersed uniformly from left to right. By having a
randomly scattered plot in an even, horizontal band around the residual value of zero, this
rendered the inference of homogeneity reliable. There were still a number of data points
which exceeded +2 for the standardised residuals.

4.12 Regression analysis using reciprocal indexed prog. cost $m


The transformed data using reciprocal indexed prog. cost $m were re-analysed. The
predictor variable used in the model was reciprocal of prog. cost $m and the dependent
variable used was % over cost . The regression model summary is shown in Table 4.54. The
R value for the model was <0.2 and thus indicated negligible correlation. The R2 value of
0.039 was statistically very poor. Column 4 shows the adjusted R2 at only 3.5%.

Model R R2 Adjusted R2 Std. error of the estimate


1 0.198 0.039 0.035 18.78958

Table 4.54: Model summary using reciprocal indexed prog. cost $m transformed data

Unstandardised and standardised regression coefficients, as well as t and significance values


for the model are shown in Table 4.55. The beta standardised coefficient for the variable is
shown in Column 5. This measured the change in the dependent variable % over cost in units
of its standard deviation. It showed that the variable Reciprocal indexed prog. cost $m had a
beta = 0.198 for the model.

155
Risk factors leading to cost overrun in the delivery of highway construction projects.

Unstandardised Standardised
T Sig.
Model Variable coefficients coefficients
B Std. error Beta
1 (Constant) 21.751 2.467 8.816 0.000
Reciprocal of prog.cost$m
14.519 4.872 0.198 2.980 0.003

Dependent variable: % over cost $m


Table 4.55: Regression coefficients for transformed data model

The residual statistics for the model are detailed in Table 4.56 below and show the standard
deviation for the residuals at a relatively wide 18.746 for the 220 projects analysed.

Minimum Maximum Mean Std. deviation N


Predicted value 22.0551 36.2701 28.0604 3.78353 220
Residual -22.11134 88.48981 0.00000 18.74663 220
Std. predicted value -1.587 2.170 0.000 1.000 220
Std. residual -1.177 4.710 0.000 0.998 220

Dependent Variable: %OverCost


Table 4.56: Residual statistics for transformed project data

4.13 Sensitivity testing using discrete rural and urban data sets
Further univariate regression testing was carried out on separate rural and urban project data
sets to ascertain if statistically stronger correlations could be developed by separating out the
project data into two discrete datasets. There were 134 rural project cases and 86 urban
project cases available for analysis and these agreed with the 220 cases previously derived
after the identified outliers were removed.

The predictor variable used in the analysis was reciprocal of prog. cost $m and the
dependent variable used was % over cost .

4.13.1 Rural project data regression analysis

The rural project data were analysed and the model summary was derived as shown in
Table 4.57.

Model R R2 Adjusted R2 Std. error of the estimate


1 0.153 0.0299 0.016 18.0554

Table 4.57: Model summary using rural project data

The R value for the model was <0.2 and thus had negligible correlation. The R2 value of
0.016 was statistically very poor. Column four shows the adjusted R2 at only 1.6%.

156
CHAPTER 4
Data collection, analysis techniques and statistics

Unstandardised and standardised regression coefficients, as well as t and significance values


for the model are shown in Table 4.58. The beta standardised coefficient for the variable, as
shown in Column five, measures the change in the dependent variable % over cost in units of
its standard deviation. It showed that the variable 'Reciprocal indexed prog cost $m' had a
beta = 0.153.

Unstandardised Standardised
t Sig.
Model coefficients coefficient
B Std. error Beta
1 (Constant) 22.158 3.427 6.467 0.000
Reciprocal of prog.cost$m
11.534 6.476 0.153 1.781 0.077

Dependent variable: % over cost $m


Table 4.58: Regression coefficients for rural data model

The residual statistics for the model are detailed in Table 4.59 below and show the standard
deviation for the residuals at a relatively wide 17.9879 for the 134 projects analysed

Minimum Maximum Mean Std. deviation N


Predicted value 22.762 33.692 27.597 2.7782 134
Residual -20.9922 88.7141 0.0000 17.9879 134
Std. predicted value -1.741 2.194 0.000 1.000 134
Std. residual -1.163 4.913 0.000 0.996 134

Dependent variable: % over cost $m


Table 4.59: Residual statistics for rural project data

4.13.2 Testing of general assumptions of residuals for rural project data

An inspection of the residuals as surrogates for random disturbances was carried out on the
rural data so as to make further judgements on the validity of the transformed data and an
associated regression model. Graphical plots were again used for testing the normality and
homogeneity for the revised models validation as shown Figures 4.6 and 4.7.

157
Risk factors leading to cost overrun in the delivery of highway construction projects.

Normal P-P plot of regression standardised residual

Dependent variable: % over cost

1.0
Expected cumulative probability

0.8

0.6

0.4

0.2

0.0
0.0 0.2 0.4 0.6 0.8 1.0

Observed cumulative probability

Figure 4.6: Normal probability plot of rural project data

The scatterplot of the standardised residuals versus the estimated standardised transformed
values is contained in Figure 4.7.

Scatterplot

Dependent variable: % over cost


Regression standardised residual

-1

-2

-2 -1 0 1 2

Regression standardised predicted value

Figure 4.7: Scatterplot of standardised residuals versus predicted values for rural projects

158
CHAPTER 4
Data collection, analysis techniques and statistics

The plot was dispersed uniformly from left to right and rendered the inference of
homogeneity reliable by having a randomly scattered plot in an even, horizontal band around
the residual value of zero. A number of data points still exceeded +2 for the standardised
residuals.

4.13.3 Urban project data regression analysis

The 86 urban projects were analysed and the model summary was derived as shown in Table
4.60.

Model R R2 Adjusted R2 Std. error of the estimate


1 0.244 0.060 0.048 20.045

Table 4.60: Model summary using urban project data

The R value for the model was slightly >0.2 and thus had minimal correlation. The R2 value
of 0.060 was statistically poor. Column four shows the adjusted R2 at only 1.6%.

Unstandardised and standardised regression coefficients, as well as t and significance values


for the model are shown in Table 4.61. The beta standardised coefficient for the variable is
shown in Column five measured the change in the dependent variable % over cost in units of
its standard deviation. It showed that the variable Reciprocal indexed prog. cost $m had a
beta = 0.244.

Unstandardised Standardised
Model coefficients coefficients t Sig.
B Std. Error Beta
(Constant) 21.920 3.617 6.059 0.000
1 Reciprocal of prog.
17.465 7.574 0.244 2.306 0.024
cost $m

Dependent variable: % over cost $m


Table 4.61: Regression coefficients for urban data model

The residual statistics for the model are detailed in Table 4.62 below and show the standard
deviation for the residuals at a relatively wide 19.923 for the 86 projects analysed

Minimum Maximum Mean Std. deviation N


Predicted value 22.286 38.811 28.609 5.0133 86
Residual -23.548 81.452 0.0000 19.923 86
Std. predicted value -1.261 2.035 0.000 1.000 86
Std. residual -1.175 4.063 0.000 0.994 86

Dependent variable: % over cost $m


Table 4.62: Residual statistics for urban project data

159
Risk factors leading to cost overrun in the delivery of highway construction projects.

4.13.4 Testing of general assumptions of residuals for urban project data

An inspection for random disturbances of the residuals as surrogates permitted further


judgement on the validity of the transformed data and an associated regression model.
Graphical plots were again used for testing the normality and homogeneity for the revised
model's validation.

Figure 4.8 shows the revised Normal probability plot when using the urban project data.

Normal P-P plot of regression standardised residual

Dependent variable: % over cost

1.0
Expected cumulative probability

0.8

0.6

0.4

0.2

0.0
0.0 0.2 0.4 0.6 0.8 1.0

Observed cumulative probability

Figure 4.8: Normal probability plot of urban project data

The scatterplot of the standardised residuals and the estimated standardised transformed
values is contained in Figure 4.9.

160
CHAPTER 4
Data collection, analysis techniques and statistics

Scatterplot

Dependent variable: % over cost


Regression standardised residual

5.0

2.5

0.0

-1 0 1 2

Regression standardised predicted value

Figure 4.9: Scatterplot of standardised residuals versus predicted values of urban projects

Again it was observed that the predicted value plot was dispersed relatively uniformly from
left to right and rendered the inference of homogeneity reliable by having a randomly
scattered plot in an even, horizontal band around the residual value of zero but with a slight
overflow of data points towards +2. A number of data points still exceeded +2 for the
standardised residuals.

4.14 Sensitivity testing using open tender and negotiated price data sets
Further univariate regression testing on separate open tender and negotiated price project
data sets was then carried out to ascertain if a statistically stronger correlation would be
developed within the separate project clusters. There were 131 open tender project cases and
89 negotiated price projects analysed.

All relevant predictor variables were used with the dependent variable % over cost in the
stepwise multivariate regression anlaysis on both individual data sets. The predictor variable
used was reciprocal of prog. cost $m with the dependent variable again being % over cost.
Both data set analyses were unremarkable in their statistical significance and again showed
no increased correlation properties over the full data set of 220 projects.

161
Risk factors leading to cost overrun in the delivery of highway construction projects.

4.15 Regression analysis model summary


This section has sought to demonstrate correlations between highway construction projects,
their delivery methods and cost overrun by using multivariate regression analysis to develop
robust models. The primary concern in developing such a model has been that of validation.
This was an important step because of the highly variable nature of the project data used.

The presence of the many considered variables here may create results contrary to what has
been posed and what would normally have been expected. It was anticipated that the results
of the research would contribute strongly in providing rational correlations between highway
projects and their cost overrun. The validation process was an important step to see if any
developed model best fitted the available data. All models were tested statistically to
determine whether they confirmed a correlation between real project attributes and real
project cost overruns. However, it was found that the regression models so developed
perform poorly in representing correlations within the current project data.

4.15.1 Correlated model

The regression analysis did demonstrate a weak correlation between the size of highway
projects, as measured in indexed programmed cost and the size of cost overruns. The
correlation evolved after data transformation was carried out to improve the model.

For the regression formulae y = bx + c, the correlated model so devised had the following
form, as extracted from Table 4.55.

% project cost overrun = 14.519 x reciprocal of indexed programmed cost $m.+ 21.751

In effect, this model has shown that as the size of a project increases in budgeted
programmed cost, then the percentage cost overrun reduces in value. It further suggests that
to counter the potential cost overrun, the over-and-above additional contingency percent that
should be factored into all types of highway projects by the client to compensate for
undefined (or under-defined) project risks can be varied depending on the project size. Such
indicative over-and-above contingency percentages that have been derived from the model
are shown in Table 4.63.

Project programmed cost Over-and-above percentage


$1m 36.3%
$5m 24.7%
$10m 23.2%
$15m 22.7%
$25m 22.3%
$50m 22.0%

Table 4.63: Indicative over-and-above contingency percentages for project size

162
CHAPTER 4
Data collection, analysis techniques and statistics

4.15.2 Summary of regression analysis

The statistical tool of multivariate regression was used to analyse the correlation between the
following project variables that were simultaneously associated with the dependent variable
of cost overrun percentage:
Highway geographic project type (urban/rural projects)
Highway project construction type (project types 1 to 12)
Highway project delivery type (delivery code 1, 2 or 3)
Indexed highway project programmed cost (indexed prog. cost $m)
Highway project high level risk grouping (HL/1 to HL/10 and HL/Q).

A wide spectrum of highway projects, delivery methods and client risks were analysed using
three separate modes of variable selection in the regression analysis. There were 2
geographic location types, 12 project types, 3 project delivery methods, and 11 high level
risk groupings that were hypothesised to have a correlation to the amount project overrun in
cost for the various projects analysed. The null hypothesis adopted for Pearson's correlation
tests was that there was no correlation between the size of cost overrun of projects (and their
geographic location, construction type, delivery process, project size, and client project risks.
Model testing was applied to confirm or otherwise that the given independent (prediction)
variables in the model did not correlate against the dependent variable of project cost
overrun to any significant level of accuracy.

Three modes of statistical regression were computed using:


forward selection
backward selection
stepwise selection.

All models were tested statistically and practically to determine whether they are efficient in
predicting real project cost overrun results and based on the adopted statistical checks, all the
regression models perform poorly in representing the project data.

4.16 Chapter summary


The objectives of the research were to:
1. identify the project risk factors that lead to cost changes in highway construction
projects
2. rank the different factors according to their incidence in historical project data
3. identify particular highway construction project types and groupings of cost overrun
factors
4. conduct an analysis of project data using statistical theories and concepts to identify
correlations between particular highway construction project types and project cost
overrun.

It was hypothesised that there existed a defined relationship between the measure of the
percentage of cost overrun in highway construction projects and:
construction risks
types of highway construction projects
project delivery methods
project location

163
Risk factors leading to cost overrun in the delivery of highway construction projects.

project size.

The correlation relationship of the multiple project variables was troublesome because the
sought-after knowledge about cost overrun in highway projects was complex and had many
different combinations of factors that had to be examined. The statistical modelling and
analysis of the research data has found no strong correlations between project types, work
types and project risk factors in producing cost overrun in highway construction projects.
There was, however a weak model that showed that as the size of a project increased in
budgeted programmed cost, then the percentage cost overrun reduced in value.

Chapter 5 follows and discusses the research findings in fulfillment of the research
objectives and documents its contribution to original research. It also suggests areas of
further research.

164
CHAPTER 5
Discussion, recommendations and conclusions

CHAPTER 5

Discussion, recommendations and conclusions

This chapter discusses the research findings in fulfillment of the research objectives and
documents its contribution to original research. It also suggests areas of further research in
highway project management.

5.1 Discussion
The overall objective of this research has been to identify the factors that influence
significant project cost overruns for the client and to provide an analytical model that
correlates project attributes to the level of their cost overruns and client project risks relating
to decision-to-build budgets.
The research methodology has been structured to seek out answers to the following research
questions:

1. What client risks are present during the delivery of highway construction projects in
Queensland, Australia that lead to significant project cost overruns?

2. How does the amount of highway cost overrun in such highway projects correlate
with their project types, size, delivery processes and client project risks when
historical project data are analysed?

In order to provide adequate answers to these questions, the following research stages were
adopted:
1. the establishment of a data source for highway construction projects
2. the determination of project work types and cost overrun factors from historic case
study data
3. the utilisation of principal component analysis and factor rotation on cost overrun
factors in order to consolidate data
4. the use of the nominal group technique with highway construction experts to elicit
groupings of cost overrun factors and highway project types
5. the use of statistical analysis using multivariate linear regression analysis to
investigate correlations between cost overrun risk factors and project attributes by
using historic project data.

The research investigations have revealed the following findings.

5.2 Highway project data


The data has been collected from 231 highway projects published in the RIP documents of
the Queensland Department of Main Roads over the financial years from 199596 to 2002
03. In the highway data analysed, there were 140 projects categorised as open tender
contracts and this constituted 60.6% of the total projects analysed and 91 (39.4%) were sole
invitee negotiated price contracts.

The client-allocated budgets to deliver the projects included the following costs:

165
Risk factors leading to cost overrun in the delivery of highway construction projects.

conducting investigations and developing the design


detailing the design
acquiring land
altering public utility plant
construction
project administration and handover.

In order to carry out a valid analysis on the project data over the research period it was
necessary to bring all relevant project cost data to a common out-turn financial year of 2002
03. The Road Input Cost Index (RICI) was adopted and applied to the research cost data.
Table 5.1 details the RICI indices for the analysis period. The % adjustment in highway
input costs has increased from 1.3% in 199596 up to 3.4% in 200102. The average
increase over the seven-year analysis period was 2.4% per year and the index data shows a
16.3% increase in highway costs over the period.

Year Adjustment for 200203 Inter-year


out-turn price price adjustment
199596 16.3% 1.3%
199697 15.0% 1.8%
199798 13.2% 2.3%
199899 10.9% 2.3%
199900 8.6% 2.6%
200001 6.2% 2.8%
200102 3.4% 3.4%
200203 Mean = 2.4%

Table 5.1: Project price adjustment percentages derived from RICI

Wilmot and Cheng (2003) carried out research to predict the cost escalation for future
highway construction projects in the US. They used the Bureau of Economic Analysis of the
Department of Commerce for predictions of future construction worker wages. The predicted
worker wages were transformed into an index of construction labor cost with a value of 100
in 1987. Data on the cost of highway construction equipment and material for the period
19842015 were purchased from the commercial supplier of industrial data, Data Resources
Incorporated and were transformed to an index with a value of 100 in 1987. Their model
predicted that future overall highway construction costs would double in the period 1998
2015, representing a growth rate of approximately 4.2% per year, considerably higher than
the current rate of general inflation of 2.5% in the US.

5.3 Cost overrun project risk factors


The research identified 37 initial risk factors from the analysis of 231 highway projects
which had reported significant cost overrun (i.e. in excess of 10% of the projects' initial
cost). These were collated and Table 5.2 shows the top 12 factors in order of their magnitude
of occurrence.

166
CHAPTER 5
Discussion, recommendations and conclusions

%
Cost overrun variable Occurrence
occurrence
1 Design/project scope change 95 31%
2 Contract tender price higher than original estimate 35 11%
3 Design scope change drainage 33 10%
4 Quantity increased measure 31 10%
5 Design scope change pavement materials/depth 23 7%
6 Latent condition remove and replace
unsuitable material
21 7%
7 Design scope change environmental issues 19 6%
8 Constructability under traffic 17 5%
9 Services relocation costs 12 4%
10 Material cost increase pavement materials 11 3%
11 Resumption/accommodation works 10 3%
12 Constructability difficulty costs 10 3%

Table 5.2: Top twelve highway risk factors causing cost overrun

Detailed descriptions of significant cost overrun variables have been provided in Appendix
E.

5.4 Factor analysis


Factor analysis was initially adopted in the research methodology to statistically isolate the
large number of project risks that had relationships to cost overrun in the highway project.
The factor analysis reduced the number of independent cost overrun factor variables to 13.
Guidelines had been reported for the minimum sample size and ratio limits for the number of
variables for factor analysis and suggested a minimum sample size of 100 to 200
observations (Guadagnoli and Velicer, 1988) and the research data sample size of 231
satisfied this. Principal component analysis required a large sample size as it is based on the
correlation of the variables involved. Sample testing found that the data sample used in the
research was much less than that recommended by Kaiser (1974) and Hutcheson and
Sofroniou (1999). As well, the Bartlett Test was less than recommended, even though
Bartletts sphericity test was particularly relevant to small samples of data (<100) and not so
relevant to larger samples as in the research case.

The number of component variables reproduced in the analysis was determined by the
number of principal components with eigenvalues of 1.00 or greater. Factor variation was
relatively even across all components and this indicated low success in reducing the
dimensionality of the original set of cost overrun variables using factor analysis.

In order to facilitate a better interpretation of factors, the factor analysis required the rotation
of axes that did not affect the goodness-of-fit of the factor solution. The varimax method of
rotation, as developed by Kaiser, was adopted and provided the best parsimonious analytical
solution. Computationally, the varimax rotation minimised the number of variables that had
high loadings on the factors and caused the factor loadings of each variable to be marginally
more clearly differentiated.

A review of the 13 groupings led to the conclusion that no common factor components
demonstrated consistency in purpose from the principal component analysis. There was no

167
Risk factors leading to cost overrun in the delivery of highway construction projects.

evidence of strong correlations within any of the 13 groupings, even after rotation. A weak
scree plot also indicated the derived model of 13 component factors was not a reliable
representation of the total factors for use in the model analysis.

5.5 Expert elicitation findings


Expert elicitation used in the research to develop a reduced combination of cost overrun risk
factors.The expert elicitation used civil engineering highway experts. Nominal group
technique (NGT) was used as it offered more structure than focus groups, but still took
advantage of the synergy created by a group. NGT provided the most appropriate method for
eliciting expert opinion as it demanded less valuable time from the industry experts and still
provide the appropriate focus and outcome. NGT produced rank-ordered, weighted, semi-
qualitative data on client risks and project types associated with significant cost overrun.

The advantages of the NGT process were numerous. NGT provided a constructive, problem-
solving approach that permitted equal participation by all the group members, and avoided
the disproportionate influence by vocal individuals who are often present in group processes.
It also reduced the pressure for individual members to conform to group opinion. In the
feedback obtained during the process, participants appreciated the opportunity to give
meaningful input.

The NGT group composed of two generalists, five specialists, an analyst who took on the
role of moderator and a researcher. This membership is supported by Clemen and Winkler
(1985) who have suggested that five specialists are usually sufficient to cover most of the
expertise and breadth of opinion but with an additional two or three generalists and two or
three analysts for specific elicitation tasks.

The spread of project-related experience of the members as shown in Table 5.3 demonstrated
the good balance of project management expertise that existed across the group.

Experience area Minimum years Maximum years Mean years


Estimating 5 14 10.7
Design 1 17 8.5
Construction 2 15 8.5
Management 3 15 12.2

Table 5.3: Experience profile of expert group membership

One problem encountered during the elicitation process was the poor definition of some cost
overrun factors provided to the group and the lack of specific project histories. To overcome
this issue, the definitions of the factors causing the cost overrun were redefined as necessary.

5.6 High level project risks


The research developed 10 importance ranked high level risk groupings (and their associated
factors) that are present in the delivery of highway projects in Queensland. The research has
associated these ten with significant project cost overruns. Highway project clients would
benefit from these findings and thereby benfitting from achieving enhanced estimating
accuracy in future highway projects.

168
CHAPTER 5
Discussion, recommendations and conclusions

Further research has also identified the project phases in which the risks can highly impact
project cost. A Likert scale of L for low phase impact, M for a medium phase impact and H
for a high phase impact has been used to identify the most susceptible project development
areas. The final mapping is shown in Table 5.4. This supports the previous findings in Table
5.2 that the major propensity for significant cost overrun is predominantly located in the
design phase of project development.

Construction
Preliminary
Concept

Design
Risk group Cost overrun factors

Design/project scope change M H H L


Design scope change resulting from drainage,
environmental issues, pavement L M H M
Design and scope change
materials/depth
(change in project
Design scope change as a result of carrying out
definition) L L H M
a safety audit on project
Quantity increase L L H M
Specification change L L M H
Design preload requirement L M H L
Design change to subgrade L L H M
Insufficient investigations Latent condition
and latent conditions requiring design change
rock encountered L M H M
additional stabilising
removal/replacement of unsuitable material
Deficient documentation Design scope change - design error L L H M
Project acceleration requirement L L M H
Government initiative
employment continuity
L M H L
developer contribution,
Client project management local government/rail contribution,
costs
Material/process quality L L H H
Contract failure new contract establishment L L M H
Project administration cost L L M H
Tender price higher than client estimate L L H M

Services relocation Services relocation costs L M H M

Constructability Constructability difficulty costs L M H H


Constructability under traffic L L M H
Material cost increase asphalt, bitumen price,
L L H H
Price escalation earthworks, pavement materials
Principal supplied components/materials
L M H M
Contract tender price increase due to inflation
Right-of-way costs Resumption accommodation works L M H M
Contractor risks Remote location costs L M H M
Wet weather effects/rework L L H M
Environment Cultural heritage issues L M H M

169
Risk factors leading to cost overrun in the delivery of highway construction projects.

L = Low impact on potential cost overrun


M = Medium impact on potential cost overrun
H = High impact on potential cost overrun

Table 5.4: Ranked principal highway cost overrun risk groups

Further research findings have been developed in Table 5.5 to show risk sources capable of
causing potential project cost overrun. Highway clients need to take these into account when
they are developing new projects in order to reduce the possibility of their projects
significantly exceeding budget.

Rank Risk group Cost overrun factors Description of risk impact


Design/project scope
change
Design and scope resulting from drainage,
Incomplete or missing design elements
change environmental issues,
1 Potential increased cost, schedule delay
in project pavement materials/depth
and poor technical performance
definition Safety audit on project
Quantity increase
Specification change
Design preload
requirement
Design change to
Insufficient subgrade
investigations Latent condition Undefined underground or hidden site
2 and latent requiring design change conditions that can cause cost and schedule
conditions rock encountered growth
additional stabilising
removal and
replacement
of unsuitable material
Incomplete or missing design elements that
take into account construction aspects
Deficient Design scope change
3 Uncertain design experience level
documentation from design error
Poor team cohesiveness or composition

Project acceleration
Government initiative
employment continuity
Developer, local
Potential for poor quality and technical
government,
non-performance
rail contributions
Client project Uncertain design experience level
4 Material/process quality
management Poor team cohesiveness or composition
Contract failure
Estimates uncertain as they can be based on
new contract
past projected costs
establishment
Project administration
Tender price higher than
client estimate
Relocation of utility Approvals and environmental concerns for
Services
5 services alignments can cause time delays and/or
relocation
in road reserve cost escalation
6 Constructability Constructability Level of difficulty increases the potential

170
CHAPTER 5
Discussion, recommendations and conclusions

difficulty for cost and schedule growth


under traffic Potential for accidents and consequences of
injuries resulting in costs
Material cost increase
asphalt, bitumen,
earthworks,
Price escalation pavement materials Potential for material an labour price
7
Principal supplied increases
components/materials
Contract tender price
increase due to inflation
Resumption Regulatory settlement approvals can cause
8 Right-of-way
accommodation works project time delays or cost escalation
Labour strength and productivity
uncertainties
Potential for poor quality and technical
non-performance
Remote location costs
Contractor Non-performance from vendors, sub-
9 Wet weather
risks contractors or suppliers can cause impacts
effects/rework
to cost and schedule
Delay causing cost impact and technical
non-performance from unseasonal weather
patterns
Regulatory approvals and mitigation
processes of environmental concerns may
10 Environment Cultural heritage issues cause time delays and/or cost escalation
can cause project time delays or cost
escalation

Table 5.5: Client risk sources during project

Twelve highway project types that collectively described all of the 231 highway projects in
the data have been developed using the NGT process as shown in Table 5.6. Clients need to
consider the standardized project types shown in order to be in a position to effectively
analyse highway project data across organizations. The non-adoption of a standardized group
of highway project types will only further perpetuate inefficiency in analyzing historical
highway project data.

Project type
Reference
Highway
R1 Construct to sealed standard (2 lanes)
R2 Widen shoulders and sealing
R3 Rehabilitate/Strengthen
R4 Realignment of two lanes
R5 Realignment of four lanes
R6 Duplicate two into four lanes
R7 Widen four into six/eight lanes
R8 Asphalt resurfacing
R9 Construct intersection/interchange
Bridge
B1 Bridges and approaches
B2 Widen bridges

171
Risk factors leading to cost overrun in the delivery of highway construction projects.

Miscellaneous
M1 Miscellaneous roadworks/traffic furniture and devices

Table 5.6: Highway project construction types

The research also found it desirable to differentiate between certain project types where
complexity or location need to be identified at a more specific level. The research found that
the following project aspects needed to be considered in interrogating future details were
readily available:
rehabilitation projects include pavement widening or not
a realignment project incorporated some of the existing road and was built under
traffic this type of project is referred to as being constructed at a brownfield site
the project was on a completely new alignment away from the existing highway that
it had replaced, thus having none or only a small exposure to highway traffic this
type of project is referred to as being constructed at a greenfield site
an interchange/intersection or bridge and approaches were located in an urban or
rural environment.

The determination of the highway project types aligned well with the literature research
finding of Persad et al. (1995) who reported on a highway project classification developed
by the Texas Department of Transport (TDoT) in 1986. It reported 14 types of highway
projects as detailed in Table 5.7.

This table is not available online.


Please consult the hardcopy thesis
available from the QUT Library

Source: Persad et al.(1995)


Table 5.7: 1986 Texas Department of Transport highway project classifications

5.7 Model development using multivariate regression analysis


Multivariate regression has been the most common method of modelling construction costs
in the past (Koppula, 1981; Blair et al., 1993; Elthag and Boussebaine, 1998; Williams,
2003) and it has been effectively used in this research to manage the multiple project
variables and relationships between projects, project risks and project cost overrun.

172
CHAPTER 5
Discussion, recommendations and conclusions

The dependent variable adopted in the model was the continuous variable percentage (%)
cost overrun and has been defined as the difference between the clients actual project cost
and their programmed cost, expressed as a percentage of the programmed cost.

The research has analysed the correlation between the following project variables:
1. Highway geographic project type (urban/rural projects)
2. Highway project construction type (project types 1 to 12)
3. Highway project delivery type (delivery code 1, 2 or 3)
4. Client project high level risk grouping (HL/1 to 10 and HL/Q)
5. Indexed highway project programmed cost (Indexed prog. cost $m).

Many regression models were possible due to the wide spectrum of highway projects,
delivery methods and client project risks that were associated with cost overrun. Two
geographic location types, 12 project types, three project delivery methods and 10 high level
client risks were hypothesised as influencing the amount of cost overrun in highway project.
The null hypothesis adopted was that there was no correlation between the size of cost
overrun of location of projects, construction type, delivery process, project size or client risk
factors.

Three stages of statistical regression were computed using the method of least squares. For
the purpose of research, the statistical models were considered linear normal models (i.e.
regression analysis with the appropriate f -tests and t-tests). For each test, the p-value was
reported as a measure for rareness if identity of groups was assumed. The forward selection,
backward selection and stepwise selection regression methods were used in the analyses.
The stepwise method delivered the most appropriate model after excluding outlier data and
data transposition.

Correlation analysis was undertaken to identify project variables that correlated with project
cost overrun. The technique examined the performance of various models and the
relationships between variables. Pearson's correlation coefficient (R) was used to examine
the relationship between the data and for developing the rank order of regression models in
terms of goodness of fit. The research used the coeffiecient of multiple determination R2
and adjusted R2 statistics as they allowed direct comparison of the best model identified.

A number of important analysis findings were revealed from the regression analyses as
follows:
1. The research found no strong correlation between the geographic location of the
highway projects and project cost overrun. This finding did not support Drew and
Skitmore (1992) who identified that the density of population and the extent of
geographic area were important factors for competitive tenders in building projects.
The difference may have been because the research focused on highways, whereas
Drew and Skitmore focused on building projects. As well, highway projects
researched were all located in the one area, Queensland and not a broader geographic
survey as was the case for Drew and Skitmore (1992).

2. The research found no strong correlation between highway project types and project
cost overrun. However, the research found that projects involved in constructing six
or eight lanes from four lanes demonstrated excessive cost overruns when analysed
for discordance. These were subsequently excluded as outliers so no data for six/eight

173
Risk factors leading to cost overrun in the delivery of highway construction projects.

lane projects was incorporated in the final analysis. On a broader transportation


research base of analysing rail, fixed-line and road projects, Flyvbjerg, et al (2002)
found that the type of transportation project had a statistical effect on a projects cost
overrun. The difference in the research finding can be attributed to the much broader
range of project types, other than just highway projects. As well, the Flyvbjerg
research covered a number of differing countries.

3. The research found no strong correlation between the type of project delivery method
of highway projects and cost overrun. Projects that were delivered by open contract,
as apposed to negotiated price, were no less susceptible to significant cost overrun.

4. It was postulated in the analyses that strong correlations existed between the groups of
client project risks and degree of cost overrun. The research found that no correlation
between the client project risks and project cost overrun existed.

The research found correlation between indexed highway programmed cost and cost overrun
after data translation. For the regression formulae y = bx + c, the correlated model had the
following form:

% project cost overrun = 14.519 x reciprocal of indexed programmed cost $m.+ 21.751

This model indicates that, as the size of a project increases in budgeted programmed cost, so
then does the size of the percentage cost overrun reduce. In contrast to this finding, research
carried out in 1992 by the Transportation Research Board evaluated construction cost
overruns on 468 transport projects completed for the Washington State Department of
Transportation. Results of their analysis indicated that cost overruns, expressed as a
percentage of the original contract amount, increased with the size of the project.

This research finding has also been inconsistent with the research of Williams (2003) who
analysed transportation projects in both the UK and the US. He found a (log.) linear
relationship between contract size and cost overrun. The reasons for the inconsistency
appeared to be the fact that Williams analysed only contract elements of projects and also the
size of projects. Williams (2003) analysed projects which included contract values below the
equivalent of A$1m in predominately highway rehabilitation projects. As well, he initially
included dredging contracts in his data analysis in order to demonstrate linkages across
project types in the US. In contrast, only highway construction and rehabilitation projects in
Queensland that were >A$1m formed the basis for the data analysis. Both sets of projects
were based on the design-bid-build delivery model. Presumably the differing broad findings
are due to the unique geography of highway construction projects in Queensland, as opposed
to that of the US.

The research indicated that the percentage of project cost overrun is linked to the economy
of scale of projects, such that smaller dollar projects can attract larger percentages of cost
overruns, and larger dollar projects have the potential for smaller percentages of cost
overruns.

Smaller projects have a tendency towards a higher percentage increase in cost. The actual
dollar magnitude of the cost overrun for the large project may still be greater, even though its

174
CHAPTER 5
Discussion, recommendations and conclusions

percentage change is less. For example, a 5% cost increase on a $1 million dollar project is
$50, 000, whereas a 1% cost increase on a $100 million dollar project is $1,000,000.

The research also lends itself to the assertion that additional contingency percentages can be
derived from the model that can be applied to projects sizes when decisions have to be made
on the size of individual projects. These proportional contingency percentages to projects'
decision-to-build budgets of particular sizes are shown in Table 5.8.

Project programmed cost Over-and-above %


$1m 36.3%
$5m 24.7%
$10m 23.2%
$15m 22.7%
$25m 22.3%
$50m 22.0%

Table 5.8: Over-and-above contingency percentages for varying project sizes

Statistical models assume error-free measurement, at least of the independent (predictor)


variables and close attention was paid to the effects of noisy data (Helberg, 1996).
Sensitivity testing was carried out on the research data in order to determine whether
additional outlier data unduly influenced the models. Discordance tests were used to
ascertain whether data observations were unreasonably extreme (Barnett and Lewis, 1984).
The incidence of data outliers constituted less than 3% of the initial research data and this
was considered only mildly contaminated with outliers. Rocke and Woodruff (1996) have
pointed out that the detection of outliers can be more problematic if inconsistent data is
found to be more than 25%.

A check on the regression model was carried out in order to ascertain if a wider range of data
outliers existed in the regression analysis. The approach undertook sensitivity testing on the
data by dividing it into discrete data types. Regression re-testing was carried out on four
separate data sets:
rural projects
urban projects
open tender projects
negotiated price projects.

There was no discernable improvement in the correlation model produced from any of the
four discrete datasets.

5.8 Implications for highway cost management 'body of knowledge'


The presented research has used a sound technique of undertaking post-mortems of historic
projects as a risk analysis technique in identifying significant cost overruns. Specifically this
research has:
combined risk assessment and expert elicitation techniques in investigating project
management estimating and cost control issues when estimating highway projects
provided a quantitative and qualitative project assessment that will help highway
project decision makers define unforeseeable disturbances more reliably ahead of

175
Risk factors leading to cost overrun in the delivery of highway construction projects.

time, so that corrective measures can be better taken into account in project design
and estimating
provided an in-depth post mortem analysis of client risks that have led to significant
project cost overrun and thus has strengthened the understanding of why highway
projects can overrun substantially above project decision-to-build budgets.
identified client risk factors that are aimed at simply providing a better understanding
of the risk parameters and management contingency requirements in project, thus
validating better risk contingency weightings in budget estimates
provided a standardised set of highway project types against which future highway
project data can be collated and analysed
provided importance ranked groupings of client project risks and descriptions of
potential risk sources which clients need to take into account when developing new
project budgets
established NGT as a suitable method for risk elicitation and used it in the research
project in a way that required minimal impact on the time of construction experts, but
at the same time providing an acceptable outcome to a difficult elicitation
requirement
accounted for uncertainty when developing client project cost estimates by proposing
a range of over and above % contingency to account for economy of scale in
highway projects for varying sizes of highway projects.

The construction industry is unique in that it rarely builds something the same way, at the
same place, or with the same set of people. Because construction professionals tend to
describe risk in linguistic terms based on their experience and judgement, the research has
aimed at providing the client with the background knowledge for representing project budget
cost estimates in an ideal situation where all epistemic (lack of knowledge) uncertainty has
been identified. As well, the construction industry is in need of project management tools
that are straightforward and take advantage of the industrys tendency to use engineering
judgement to solve problems. The use of a sound elicitation risk assessment technique, such
as in this research, provides a structured format to harness the experience and judgement of
experts in assessing the financial impact of risks on projects in an efficient and time
conscious manner.

5.9 Implications for cost estimating practices


Most highway organisations have a relatively fixed annual budget for programmed
construction and require that fairly accurate cost estimates before allocating individual
project budgets. One could speculate that large cost under-estimation would be less likely in
such situations.

The research has detected no real trend in improvement in cost estimating over the seven
years covered by the highway projects analysed. However, in the historic data analysis
period adopted for this research, there was evidence that a good proportion of highway
projects achieved their budget at project completion. This suggests that the project estimators
associated with those projects have done a good job in terms of estimate accuracy. In this
research, the project factors that have been analysed have not proven strong correlation to
project overrun and so it can be implied that highway project estimators are, on the whole,
making substantial allowances to cover project parameters that cause budget overrun.

176
CHAPTER 5
Discussion, recommendations and conclusions

While the research has been unable to supply any single and definitive answer to the
predominant reasons for project cost overruns, the persistent underestimation of costs and
the over-optimistic assumptions about performance of some project budget estimates raises
questions about why client highway organisations have not been able to adjust their
expectations over the years. Several possible remedial actions can be derived from the
research.

Firstly, the literature research has shown that contingency percentages of around 10% are
commonly allocated to project estimates at the decision-to-build time to allow for unforeseen
and unquantified client risks. The client organisation is reported to include a 10%
management contingence to its decision-to-build budget estimates in the research period to
take into account any underestimated client risks. The research now indicates that a higher
order percentage in management contingency may be required for all highway projects
(excluding six and eight-lane projects). This higher order contingent percentage is required
to minimise the protential for projects to significantly exceed the client budgeted cost
because of undefined, or under-defined, client risks. Therefore, an estimating procedure
which includes revised levels of management reserve contingencies, ranging from 35% for
projects up to $3m, down to 25% for larger projects, should be considered. This revised
contingency would reduce the potential for projects to be reported as having incurred
significant budget over-cost during delivery.

Secondly, client estimating procedures for highway projects should take into account the
potential cost impacts from the risk factors identified in this research. Failure to
systematically evaluate the project risk potential of all of the risk factors could severely
impact on the favourable outcomes of projects and on a client's overall highway construction
program.

Thirdly, the research found that design and scope changes are the highest contributing risk
factor to project cost overrun in highway projects analysed. This finding is supported by
Tilley et al. (2000) who found that the quality of project design and design documentation
has fallen considerably over the past 15 to 20 years. McLennan and Jorss (2006) reported
that poor design documentation includes the following root causes:
inadequate project briefs based on unrealistic expectations of time and cost
lack of integration along the supply chain linking parties, and between project phases
poor understanding and low skills in risk assessment and management
inadequate use of CAD/computer technology in the design process and in the
compilation of specifications.

To further manage cost overruns from design and scope changes the following qualitative
measures need to be considered:

(1) Design changes


fix design standards for the life of the project as at the decision-to-build time
limit changes due to field conditions
limit any scope changes after the preliminary design has been accepted
undertake thorough checks on existing project conditions
ensure comprehensive and coordinated project design documentation
ensure better buildability/constructability through comprehensive site surveys
ensure better designer/client initiated scope change feedback processes

177
Risk factors leading to cost overrun in the delivery of highway construction projects.

ensure better feedback from previously constructed highway projects


ensure construction/maintenance engineers are part of the design team from the start
so as to eliminate most changes
initiate more preliminary field investigations during design phase
improve design quality
minimise changes after decision-to-build
improve independent design reviews
minimise unforeseen site conditions by ensuring detailed site surveys and
measurements.

(2) Scope changes


define the purpose of project and detailed scope to eliminate unnecessary changes
limit any scope change after preliminary design
review and sign-off of design scope by client
minimise scope change after the decision-to-build is made
ensure client involvement in scope development and preliminary design
ensure better communication of project objectives before execution
use feedback from previous projects.

The tight control of any scope creep by the client can limit variation works during
construction and this is absolutely necessary for successful financial outcomes of projects.

5.10 Research limitations


Studying the relationship of multiple variables is especially troublesome because the desired
knowledge is complex in nature and many different combinations of factors need to be
examined. There are a number of ways that statistical techniques can be misapplied to
problems in the real world. These types of errors can lead to invalid or inaccurate results.

The statistical model assumed error free measurement, at least of independent (predictor)
variables. However, measurements are seldom perfect. Therefore, close attention is needed
to be paid to the effects of measurement errors. This is especially important when dealing
with noisy data or processes which are difficult to measure precisely (Helberg, 1996).

Multivariate linear regression assumes the relationship between variables to be linear. In


practice this assumption can virtually never be confirmed. Multivariate regression should not
be used or predictions outside the range of the explanatory variables, for example beyond
highway projects or the geographic areas of Queensland. Predictions at levels of unobserved
variables which are not comparable to the observed research data can result in very
misleading predictions (Harrell, 2000).

This research was confined to the study of highway projects in the state of Queensland,
Australia. Since construction costs can be specific to geographical/economic areas and time
periods, caution is required when comparing the data and results to another situation.

The research findings lend significance to a broad range of highway client organisations.
However, it needs to be said that the historic data used in this research were founded on the
following:

178
CHAPTER 5
Discussion, recommendations and conclusions

projects were all of the design-bid-build project delivery method which may have
lead to higher client exposure to design risks
project contractors were all pre-qualified under a maximum capacity rating
assessment and this pre-qualification process had the potential to limit client risk
exposure to contract default
contract payments were on the basis of schedule-of-rates and projects used bill of
quantities in their contract elements
specifically tailored contract provisions can have potential to limit the client highway
organisation to the exposure of adverse physical and latent conditions events which
sometimes occur in highway projects under certain circumstances.

5.11 Further research


The model developed in this research could be refined by one or more of the following
factors:
adding one or more important project variables (e.g. estimator) to the model
using different type or market sector groupings such as toll roads
using a wider range of project sizes such as projects less than $1m to explore further
the preferred project size ranges at which projects are less susceptible to cost overrun
using other tests to examine violations of the regression assumptions and other
approaches to correct assumption violations
testing further data transformations of project variables
exploring other regression approaches to modelling project cost overrun in project
delivery.
As well, the dramatic increase in the quantum percentage of project contingency across
highway programmes by up to 35% may have certain negative effects on highway program
deliveries which future research needs to undertake. In particular, both project managers and
contractors involved in these types of project developments and construction will somehow
manage to increase their payments even within competitive procurement environments.

Further research could be undertaken by testing the model by implementing two contingency
allocation percentages on half the number of highway programme projects each, and the
differences in budget cost reporting observed and reported on. Figure 5.1 shows this future
research proposal that is designed to see if project managers try harder to keep payments
down.

179
Risk factors leading to cost overrun in the delivery of highway construction projects.

Highway
construction projects
=>$1m budget

Open tender Negotiated price


highway construction highway construction
projects contracts

Status quo Over-and-above Status quo Over-and-above


10% contingency to contingency % model 10% contingency to contingency % model
spread of projects to spread of projects spread of projects to spread of projects

Figure 5: 1: Future research proposal on project risk contingencies

The proposal could also be modified further by the inclusion of a blind placebo test to a
small number of projects by the inclusion of unmodified contingency % within the modified
contingency program. This mt ascertain if there is any a placebo effect that leads to further
project cost savings.

The linkage between the risk assessment and determining the appropriate probability
distributions for various highway project types should be researched for a more analytical
connection. Perhaps an Analytical Hierarchy Process (AHP) or another decision technique
could be used. The level of effort required to produce this tighter linkage needs to be
balanced against the potential increase in accuracy of the results. Project risk assessment is
readily adaptable to fuzzy set theory where it is preformed in linguistic terms and then
reduced to mathematical expressions. This may provide a convenient linkage between the
evaluation of various highway risks and a numerical cost control technique for differing
highway project types.

This research effort has identified and quantified the risk drivers that affected the degree that
projects significantly overrun in the highway infrastructure sector. Future research is needed
to adequately identify and quantify the project cost overrun drivers as they relate to the
construction of buildings and other infrastructure project types.

Finally, there is a need for further studies into the storage and retrieval of historical project
data. Historical data of finished projects have to be made more accessible. In view of the
nature of construction projects with data being stored in different formats such as site diaries,
calculation sheets, payment systems and even annotated drawings, the use of sophisticated
information technology is very desirable. This further research into insufficient access to
historical data will ultimately allow estimators to generate and deliver better project cost
estimates.

180
CHAPTER 5
Discussion, recommendations and conclusions

5.12 Concluding remarks


Project risks can be identified by a number of methods. The risk identification process used
in this research has relied on documented experience gained during similar projects in the
past. The accurate analysis the identification process is very important: in fact, it can be
concluded that the main benefits of risk management come from the identification rather
than the analysis stage. The primary basis of the research for identifying risks has been the
use of available historical data, experience and insight. However, each construction project is
unique, and similar risks may not recur on similar projects. Because there are no unerring
procedures which may be consistently used to identify construction risks, the process relies
heavily on the experience, interpretation and insight of key project personnel. The success of
the research has rested on the importance of being able to assemble a group of suitably
qualified people for the expert elicitation process undertaken during the research.

The research into high cost overrun required a robust sample of highway infrastructure
projects that was appropriate for this area of research. The data was required to be large
enough to allow statistical analyses of cost overrun factors and project costs and research
investigations found that data on actual costs in transportation infrastructure projects were
relatively difficult to come by. One reason is that such data is time consuming to generate.
The publication of confidential of commercial-in-confidence project data has been scarce as
it can be of concern to organisations that have provided the information.
The research utilised price movement indicators of construction outputs as a valuable tool in
the analysis output price indexes so as to enable the measurement of changes over time in the
price of new roads and bridges.

RICI indices were used over the analysis period to factor up the historical project cost
information. These factors ranged from 3.4% to 16.3% and were applied to the project
programmed and actual costs for the corresponding financial years in which the project was
delivered.

The focus of the research analyses were based on client exposure to project cost overrun, not
that of contractors delivering the projects. The literature research identified a number of
considerations to be taken into account when adopting the cost overrun factors. These
included:
the use of design-bid-build contracts that could lead to higher client exposure to
design risks
pre-qualification of contractors that has the potential to limit client risk exposure to
contract default
contract payment types that focused on schedule of rates and bill of quantities
contract clauses that were designed to reduce the clients exposure to certain
construction risks
tender evaluation techniques
contract provisions that limit the client's exposure to adverse physical and latent
conditions and wet weather events.

The risk identification process in this research has been beneficial as it focused the attention
of the client on the detection and control strategies of risks. The research has provided an
analytic procedure that allows the recognition of realistic cost overrun contingencies to
projects and investigates the influences of risk factors on clients' risk handling decisions

181
Risk factors leading to cost overrun in the delivery of highway construction projects.

The research has not looked at the whole project development life cycle but rather that part
where major cost overrun occurs, namely from the time the decision-to-build has been made
by the client and sound lessons have been drawn from the researchers post-mortems of the
many highway projects considered. The analysis has produced important findings about the
reasons that highway projects have overrun and has provided conclusive evidence of the
most important risks that highway agencies need to focus their efforts on. Of particular
concern is that of changes in project designs and scope changes during project development.

The research process used the experience in highway construction and the professional
judgement of the researcher to determine the listings of work types and reasons for cost
overrun using the NGT process. From initial interviews by the researcher, it was important to
take note of interviewees concerns about time management. In the rapidly paced world of
construction management, it was reinforced that an expert elicitation method needed to be
efficient because experts in construction management were continually confronted with
insufficient time. The selection of the NGT elicitation technique was therefore determined to
a large extent by the time that experts were prepared to allocate to the research project.

The final stage of the research process has involved the investigation into statistical models
which can explain the correlation between the cause, effect and other relationships relating to
cost overrun in highway construction projects. While the term model can be used in many
ways, however for this research it has referred to the dynamic framework or schema that
helps portray key concepts and propositions of the research phenomenon.

The regression analysis demonstrated a weak correlation between the size of highway
projects, as measured in indexed programmed cost and the size of cost overruns. The
correlation evolved after data transformation was carried out to improve the model. It can
also be concluded from the research that the arbitrary application of a base contingency
percentage figure, such as 10%, to accommodate project risk can lead to those projects
reporting substantial budget overrun. The provision of more realistic contingency
percentages across such projects will go a long way in providing for better reporting of
highway project and programme results and associated key project performance
indicators.Sensitivity testing was investigated for the stepwise regression models developed
in order to ascertain whether additional outlier data still unduly influenced the models.

The model developed has demonstrated that as the size of a project increases in budgeted
programmed cost, then the percentage cost overrun reduces in value. It further suggests that
to counter the potential cost overrun, the over-and-above additional indicative contingency
percent that should be factored into all types of highway projects by the client to compensate
for undefined (or under-defined) project risks can be varied depending on the project size

To aid in the identification of future highway risks, this research has identified and compiled
listings of highway project risks that have lead to cost overrun, as well as the incidence of
each risk across the sample highway projects. The development of such listings should help
to prevent projects risks from being overlooked by clients. The research has also illustrated
how highway projects have overrun and have done so beyond any reasonable
expectations. The research has considered historical projects where the cost overrun was
significantly beyond what might have ever been anticipated. The aim of the research was to
contribute to the understanding of how highway projects go wrong, when they do, and in
particular to draw some lessons from this exploration.

182
BIBLIOGRAPHY

BIBLIOGRAPHY

AACE. 2000. International Risk Management Dictionary. Journal of Cost Engineering.,


42 (4).

Abbasi, G. and H. Al-Mharmah. 2000. Project management by the public sector in a


developing country. International Journal of Project Management., 18 (2): 105-09.

Abrahamson, M. W. 1984. Risk management. International Construction Law Review, 1 (3):


241-264.

Adameitz, M. 2003. Short Report on Risk Management.


ttp://members.ozemail.com.au/~sqain/meeting_reports/Risk_report.htm (accessed 21
October 2003, 2003).

Adler, M. and E. Ziglio. 1996. Grazing into the oracle, The Delphi method and its
application to social policy and public health. London: Cromwell press.

Agresti, A. 1996. Introduction to Categorical Data Analysis. New York: Wiley.

Ahmed, S. M., R. Ahmed and D. E. Saram. 1999. Risk management trends in the Hong
Kong construction industry: a comparison of contractor and owners perceptions. Journal of
Engineering, Construction and Architectural Management 6/3:225-234., 6.

Akinci, B. and M. Fischer. 1998. Factors affecting contractors' risk of cost overburden.
Journal of Management in Engineering, 14 (1): 67-76.

Akpan, E. O. P. 1987. Stochastic network scheduling system for optimum resource


utilisation, University of Bradford, Bradford, England.

Akpan, E. O. P. and O. Igwe. 2001. Methodology for determining price variation in project
execution. Journal of Construction Engineering and Management, 127 (5): 367-73.

Al-Bahar, J. F. and K. C. Crandall. 1990. Systematic risk management approach for


construction projects. Journal of Construction Engineering and Management, 116 (3): 533-
546.

Albino, V. and A. C. Garavelli. 1998. A neural network application in sub-contractor rating


in construction firms. International Journal of Project Management, 16 (1): 9-14.

Alsagoff, S. A. and P. McDermott. 1994. Relational Contracting: A Prognosis for the UK


Construction Industry? In Proceedings of CIB W92, Procurement Joint risk management and
relational contracting, 11-19. Hong Kong.: University of Hong Kong.

Al-Sobiei, O. S., D. Arditi and G. Polat. 2005. Managing Owner's Risk of Contractor
Default. Journal of Construction and Engineering Management, 131 (9): 973-78 (accessed
September 2005).

183
Risk factors leading to cost overrun in the delivery of highway construction projects.

Anderson, S. D., D. Fischer and S. Rahman. 1999. Constructability issues for highway
projects. Journal of Management Engineering, 15 (3): 60-68.

Anderson, S. D. and R. L. Tucker. 1994. Improving project management of design. Journal


of Management Engineering, 10 (4): 35-44.

Ang, A. H.-S. and W. H. Tang. 1984. Probability Concepts in Engineering Planning and
Design, Volume II Decision, Risk and Reliability. Vol. II - Decision, Risk and Reliability.
New York, NY: John Wiley and Sons.

Arditi, D. and F. Yasamis. 1997. Incentive/disincentive contracts: perceptions of owners and


contractors. Journal of Construction Engineering and Management, 124 (5): 361-73.

Arndt, R. 1999. Efficient risk allocation in privately funded infrastructure projects. PhD,
Civil Engineering, University of Melbourne, Melbourne.

ASCE. ed. 1989. Avoiding and Resolving Disputes in Underground Construction: Successful
Contracting Practices and Guidelines. New York: American Society of Civil Engineers.

Ashley, D. B. 1987. Knowledge-based approaches to construction project planning. In New


Trends in Project Management, Proc. 11th International Expert Seminar, April 1987, 163-
188. Zurich: International Project Management Association.

Ashley, D. B. 1989. Project risk identification using inference subjective expert assessment
and historical data. In Transactions of Internet International Expert Seminar, 9-28. Atlanta.:
Atlanta Institute of Technology.

Ashworth, A. 1994. Cost Studies of Building. London: Longman Scientific and Technical.

Ashworth, A. and M. Skitmore. 1983. Accuracy in estimating. Chartered Institute of


Building (Occasional Paper No. 27).

Avots, I. 1984. Information systems for matrix organisations. In Matrix Management


Systems Handbook, ed. D. I. Cleland (ed.). New York.: Van Nostrand Reinhold.

Ayyub, B. M. and A. Haldar. 1984. Project Scheduling Using Fuzzy Set Concepts. Journal
of Construction Engineering and Management, 110(2).

Ayyub, B. M. and R. H. McCue. 1997. Probability, Statistics and Reliability for Engineers.
Boca Raton, FL.: CRC Press.

Ayyub, B. M. and R. Wilcox. 2000. A Risk-based Compliance Approval Process for


Personal Flotation Devices. Potomac, MD.: BMA Engineering.

Baccarini, D. 2004. Accuracy in estimating project cost construction contingencies - A


statistical analysis. In COBRA 2004. Leeds Metropolitan University: RICS Foundation.

Baker, S., D. Ponniah and S. Smith. 1999. Survey of risk management in major U.K.
companies. Journal of Professional Issues in Engineering Education and Practice, 125 (3):
94-102.

184
BIBLIOGRAPHY

Banks, J., J. S. Carson and B. L. Nelson. 1996. Discrete - Event System Simulation 2nd
edition. 2nd ed. Upper Saddle River, NJ.: Simon and Schuster.

Bannister, D. and S. Fransella. 1989. Inquiring Man: The Psychology of Personal


Constructs. 3rd edition ed. London: Routledge.

Barnes, M. 1981. Project management by motivation. In Proc., PMI/ INTERNET 1981 Joint
Symposium, 101-123. Boston.

Barnett, V. and T. Lewis. 1984. Outliers in Statistical Data. 2nd Ed. ed. New York: John
Wiley & Sons, Inc.

Barrie, D. S. and B. C. Paulson. 1992. Professional Construction Management. New York:


McGraw-Hill, Inc.

Bathurst, E. P. and D. A. Butler. 1977. Building Cost Control Techniques and Economics.
London: Heinemann.

Begg, D., S. Fisher and R. Dornbusch. 2000. Economics. London: McGraw-Hill.

Bennett, R. 1991. How is management research carried out? In The Management Research
Handbook, eds. N. C. Smith and P. Danity, 85-103. London: Routledge.

Bent, J. A. 1988. Project control: An introduction. In Project Management Handbook, 2nd


ed., eds. C. D.I and W. R. King (eds.). New York: Van Nostrand Reinhold.

Berny, J. 1989. A new distribution function for risk analysis. Journal of the Operational
Research Society, 40: 1121-7.

Blair, A. N. 1999. Risk Analysis of Cost and Schedule of Complex Engineering Systems.
Doctoral Thesis, University of Maryland, College Park, MD.

Blair, A. N., B. M. Ayyub and W. J. Bender. 2000. Fuzzy Stochastic Risk-Based Decision
Analysis: MOB Case Study. Marine Structures Journal, Society of Naval and Marine
Engineers, Sept. 2000.

Blair, A. N., L. M. Lye and W. J. Campbell. 1993. Forecasting construction cost escalation.
Canadian Journal of Civil Engineering, 20: 602-12.

Blake, E. H. 1900. Extras and omissions in building contracts. The Surveyors' Institutuion
transactions, XXXII: 525-72.

Blok, F. G. 1982. Contingency: definition, classification and probability - Congress Paper B-


3. In 7th International Cost Engineers Congress. London.

Bradley, R., M, M. Powell, G and M. Soulsby, R. 1990. Quantifying variations in project-


cost estimates. Journal of Management in Engineering, 6 (1): 99-106.

185
Risk factors leading to cost overrun in the delivery of highway construction projects.

Bramble, B. B. and M. D. Cipollini. 1998. Resolution of disputes to avoid construction


claims. In National Cooperative Highway Research Program Synthesis of Highway
Practice: 214. Washington, D.C: Transportation Research Board, National Research
Council.

Bryman, A. and D. Cramer. 1999. Qualitative Data Analysis with SPSS Release 8 for
Windows: A Guide for Social Scientists. London: Routledge.

BSI. 1999. Guide to project management: in British Standard BS 6079. Vol. 2. London.:
British Standards Institution.

Burger, R. 2003. Contingency, qualifying the uncertainty. Journal of Cost Engineering., 45


(8): 12-17.

Camerer, C. F. 2003. Behavioral game theory: experiments in strategic interaction.


Princeton: Princeton University Press.

Carelli, G. 1989. The Manus Opera House. Icaro, Varig Inflight Magazine, 17.

Carmichael, D. G. 2000. Contracts and International Project Management. Rotterdam: A.A.


Balkema Publishers.

Carver, R. H. and J. G. Nash. 2005. Doing Data Analysis with SPSS Version 12. Ontario:
Brooks/Cole Thompson Learning.

Chan, D. W. M. and M. M. Kumaraswamy. 1997. A comparative study of causes of time


overruns in Hong Kong construction projects. International Journal of Project Management,
15 (1): 55-63.

Chang, A. S.-T. 2002. Reasons for cost and schedule increases for engineering design
projects. Journal of Management in Engineering, January 2002: 29-36.

Chapman, C. B. and S. Ward. 1997. Project Risk Management: Processes, Techniques, and
Insights. Chichester: Wiley N.Y.

Chapman, R. J. 1998. Effectiveness of working group risk identification and assessment


techniques. International Journal of Project Management, 16 (6): 333-43.

Charette, R. 1989. Software Engineering Risk Analysis and Management. New York:
McGraw-Hill.

Charles, T. J. and M. A. Andrew. 1990. Predictors of cost overrun rates. Journal of


Construction Engineering and Management: ASCE., 116 (3): 569-79.

Chee, T. S. and K. T. Yeo. 1995. Risk analysis of a build-operate transfer (BOT) power plant
project. In IEEE Annual International Engineering Management Conference, 275-80.

CII. 1989. Management of project risks and uncertainty; Publication 6-8. Cost/Schedule
Controls Task Force. Austin, Texas: Construction Industry Institute.

186
BIBLIOGRAPHY

CII. 1996. The Partnering Process - Its Benefits, Implementation, and Measurement, .
Austin, TX.: Construction Industry Institute,.

Clark, F. D. and A. B. Lorenzoni. 1985. Applied Cost Engineering; 2nd Edition. New York:
Marcel Dekker, Inc.

Clemen, R. B. and R. L. Winkler. 1985. Limits in the precision and value of information
from dependent sources. Operations Research, 33: 427-42.

Clough, R. H. 1986. Construction Contracting. New York: John Wiley & Sons, Inc.

Cohen, S. S. 1985. Operational research. London: Edward Arnold.

Cooper, D. F., D. H. MacDonald and C. B. Chapman. 1985. Risk analysis of a construction


cost estimate. International Journal of Project Management, 3 (3): 141-9.

Cowie, G. 1987. Enough scope yields better estimates. Journal of Construction Engineering
and Management, 28 (8): 21-27.

Creedy, G. D. 2004. Discussions with A. McLennan on Pacific Motorway Contract


Finalisations. Brisbane.

Crowley, L. G. 1993. Risk Assessment of Competitive Procurement in Public Agencies. PhD,


Texas A&M University, Texas.

Crowley, L. G. and D. E. Hancher. 1995. Evaluation of competitive bids. Journal of


Construction and Engineering Management, 121 (2): 238-45.

Curole, M. A. 1995. Mars Risk Management Program. In 1995 Offshore Technology


Conference Proceedings. Houston, TX.

Curtis, B., S. Ward and C. B. Chapman. 1991. Roles, responsibilities and risks in
management contracting: Construction Industry Research and Information Association
(CIRIA) Special Publication 81.

Cvethovich, G. and T. C. Earle. 1992. Environmental hazards and the public. Journal of
Social Issues, 48 (4): 1-20.

Dake, K. 1992. Myths of nature and the public. Journal of Social Issues, 48 (4): 21-38.

Dalcher, D. 1993. The new project management mindset for the 21st century. In Proceedings
of 1st British Project Management Colloquium. Henley-on-Thames, UK.

Dalkey, N. C. 1968. The Delphi Method: An experimental study of group opinion. Santa
Monica, California: The Rand Corporation.

de Cano, A. and P. E. de le Cruz. 2002. Integrated Methodology for Project Risk


Management. Journal of Construction and Engineering Management, 128 (6): 473-84.

187
Risk factors leading to cost overrun in the delivery of highway construction projects.

de Neufville, R. D. and D. King. 1991. Risk and need-for-work premiums in contractor


bidding. Journal of Construction Engineering and Management, American Society of Civil
Engineers, 117 (4): 659-73.

del Cano, A. 1992. Continuous project feasibility study and continuous project risk
assessment. International Journal of Project Management, 10 (3): 165-70.

Delbecq, A. L., A. H. Van de Ven and D. H. Gustafson. 1975. Group Techniques for
Program Planning: A Guide to Nominal Group and Delphi Processes. Glenview, IL.: Scott,
Foresman and Company.

Delbecq, A. L., A. H. Van de Ven and D. H. Gustafson. 1986. Group Techniques for
Program Planning: A Guide to Nominal Group and Delphi Processes. Wis.: Green Briar
Press.

Dey, P. K. 1999. Process re-engineering for effective implementation of projects.


International Journal of Project Management, 17. (3): 147-59.

Dey, P. K. 2001. Decision support system for risk management: a case study. Management
Decisions, 39 (8): 634-49.

Dey, P. K., M. T. Tabucanon and S. O. Ogunlana. 1996. Petroleum pipeline construction


planning: a conceptual framework. International Journal of Project Management, 14 (4):
231-40.

Dias, A., and P. G. Ioannou. 1995. A desirability model for the development of privately-
promoted infrastructure projects.' UMCEE Report No. 95-09. Ann Arbor, Mich: Civil
Engineering Dept., University of Michigan.

Dozzi, S. P., S. M. AbouRizk and S. L. Schroeder. 1996. Utility theory model for bid
markup decisions. Journal of Construction and Engineering Management, 122 (2): 119-24.

Drew, D. S. and M. Skitmore. 1992. Competitiveness in bidding: a consultant's perspective.


Journal of Construction Management and Economics, May: 227-47.

Dyer, D. and J. H. Kagel. 1996. Bidding in common value auctions: how the commercial
construction industry corrects for the winner's curse. Management Science Journal, 42 (10.):
1463-75.

Eden, C., F. Ackerman and T. Williams. 2005. The amoebic growth of project costs. Project
Management Journal, 36 (2): 15-27.

Edum-Fotwe, F. T., A. Thorpe and R. McCaffer. 1999. Organisational relationships within


the construction supply chain. In Proceedings of the Joint Triennial CIB Symposium of W55
and W65, 186-94. Cape Town: CIB.

Edwards, L. 1995. Practical Risk Management in the Construction Industry, . London:


Thomas Telford Publications.

188
BIBLIOGRAPHY

Egan, S. J. 1998. Rethinking Construction. The report of the Construction Task Force:
Department of the Environment, Transport and the Regions.

Eggleston, B. 1996. The New Engineering Contract - A Commentary. London: Blackwell


Science.

El-Choum, M. K. 1994. Identification and modelling of construction cost overruns


parameters for public infrastructure projects using multivariate statistical methods. PhD,
Stevens Institute of Technology, Castle Point, Hoboken, New Jersey.

Elhag, T. M. S. and A. H. Boussebaine. 1998. Statistical analysis and cost models


development: Research Report No. 2. Liverpool, U.K.: School of Architecture and Building
Engineering, University of Liverpool.

Elkington, P. and C. Smallman. 2002. Managing project risks: a case study from the utilities
sector. International Journal of Project Management,, 20 (1): 49-57.

Elsam, R. 1826. The Practical Builder's Perpetual Price Book. London: Kelly.

Emhjellen, M., K. Emhjellen and P. Osmundsen. 2003. Cost estimation overruns in the
North Sea. Project Management Journal, March: 23-31.

Emory, C. W. 1980. Business Research Methods, 2nd Edition. Illinois: Irwin & Co..

Farnum, N. R. and L. W. Stanton. 1987. Some results concerning the estimation of beta
distribution parameters in PERT. Journal of the Operational Research Society, 38 (3): 287-
90.

Fayek, A., D. M. Young and C. F. Duffield. 1998. Survey of tendering practices in the
Australian construction industry. EMJ - Engineering Management Journal, 10 (4): 29-34.

FDOT. 2003. Chapter 3: General management principles for transit capital projects. In
Project and Construction Management Guidelines, Vol. 2003 Update. New York: US
Department of Transportation.

Fellows, R., D. Langford, R. Newcombe and S. Urry. 2002. Construction Management in


Practice. 2nd ed. Oxford: Blackwell Science Ltd. Original edition, 1983.

Fishburn, P. C. 1984. Foundations of risk measurement: Risk as probable loss. Management


Science Journal, 30 (4): 396-406.

Fisk, E. R. 1997. Construction Project Administration. 5th Edition ed. Englewood Cliffs, NJ:
Prentice-Hall.

Flanagan, R. and G. Norman. 1993. Risk Management and Construction. Oxford: Blackwell
Scientific Press.

Flyvbjerg, B., N. Bruzelius and W. Rothengatter. 2003. Megaprojects and Risk: An anatomy
of ambition. Cambridge, UK: Cambridge University Press.

189
Risk factors leading to cost overrun in the delivery of highway construction projects.

Flyvbjerg, B., M. S. Holm and S. Buhl. 2002. Underestimating Costs in Public Works
Projects: Error or Lie? Journal of the American Planning Association, 68 (3): 279-95
(accessed 2002).

Freudenburg, W. R. 1988. Perceived risk, real risk: social science and the art of probabilistic
risk assessment. Science, 242: 44-49.

Freudenburg, W. R. and S. K. Pastor. 1992. NIMBY's and LULU's: stalking the syndromes.
Journal of Social Issues, 48 (4): 39-62.

Friedman, L. 1956. A competitive bidding strategy. Journal of Operations Research, 1 (4):


104-12.

Glower, W. J. 1990. The US perspective on procedures for subsurface ground conditions


claims. International Construction Law Review, 7 (2): 155-86.

Gransberg, d. and M. Ellicot. 1997. Best-value contracting criteria. Cost Engineering, 39 (6):
31-4.

Gregory, R. 1989. Improving risk communication; questions of content and intent. In


Prospects and problems in risk communication. Institute of Risk Research, ed. W. Leiss.
Ontario: University of Waterloo Press.

Gregory, R. and R. Mendelson. 1993. Perceived risk, dread, and benefits. Risk Analysis, 13
(3): 259-64.

Guadagnoli, E. and W. F. Velicer. 1988. Relation of sample size to the stability of


component patterns. Psychological Bulletin, 103 (2.): 265-75.

Gustafson, D. H., R. M. Shukla, A. L. Delbecq and G. W. Walster. 1973. A comparative


study of differences in subjective likliehood estimates made by individual, interacting
groups. Delphi groups and nominal groups. Organisational Behavior Human Performance,
9: 280-91.

Hackney, J. W. 1986. Contingency allowances and overrun probabilities: Paper B3. In


Proceedings of the 9th International Cost Engineering Congress. Oslo, Norway.

Hair, J. F., J. Anderson, R. L. Tatham and Black. 1998. Multivariate Data Analysis. 5th
edition ed. Upper Saddle River, N.J: Prentice Hall, c1998.: Prentice Hall.

Hair, J. F. and R. L. Tatham. 1995. Multivariate Data Analysis. 4th edition ed. New York:
Macmillan.

Hairston, D. E., P. DeLise and W. J. Skerpan. 1997. Delivered into providence. Civil
Engineering (New York), 67 (2): 54-56.

Halligan, D. W., W. T. Hester and H. R. Thomas. 1987. Managing unforeseen ground


conditions. Journal of Construction Engineering and Management, 113 (2): 273-87.

190
BIBLIOGRAPHY

Halpin, D. W. 1985. Financial and Cost Concepts for Construction Management. New
York, N.Y.: John Wiley and Sons.

Halpin, M. G. 1998. Risk Management and Client Satisfaction, School of Construction


Management and Property, Queensland University of Technology, Brisbane.

Harman, H. H. 1967. Modern Factor Analysis. 2nd ed. Chicago: University of Chicago
Press.

Harrell, E. E. 2000. Regression Modelling Strategies with Applications to Linear Models,


Logistic Regression and Survival Analysis. New York: Springer.

Harris, F. C. and R. McCaffer. 1995. Modern Construction Management. London, UK:


Blackwell Science Ltd.

Hartgen, D. T., V. B. Bowman and M. W. Horner. 1997. Baseline market forecasts for state
highway construction engineering, maintenance and administration programs 1997-2001:
Transportation Publication Number 151. Charlotte, N.C: Centre for Interdisciplinary
Transportation Studies, University of North Carolina.

Hartgen, D. T. and A. P. Talvitie. 1995. Comparative performance of transportation systems:


pitfalls and prospects. In World Conference on Transit Research. Sydney, Australia.

Hartman, F., P. Snelgrove and R. Ashra. 1997. Effective wording to improve risk allocation
in lump sum contracts. Journal of Construction Engineering and Management, 123 (4): 379-
87.

Hartman, F. T. 2000. Don't Park Your Brain Outside-a practical guide to improving
shareholder value with SMART management: NC:PMI Publications.

Hatush, Z. and M. Skitmore. 1998. Contractor selection using multicriteria utility theory: an
additive model. Building and Environment Journal, 33 (105-115).

Hegazy, T. and A. Ayed. 1998. Neural network model for parametric cost estimation of
highway projects. Journal of Construction Engineering and Management, May/June 1998:
210-18.

Hegazy, T. and O. Moselhi. 1995. Elements of cost estimation: a survey in Canada and the
United States. Cost Engineering, 37 (5): 27-33.

Helberg, C. 1996. Pitfalls of data analysis. Practical Assessment, Research and Evaluation, 5
(5). http://PAREonline.net/getvn.asp?v=5&n=5.

Herbsman, Z. J. 1986. Model for forecasting highway construction cost:. In Transportation


Research Record 1056. Washington, D.C.: Transportation Research Board.

Hertz, D. B. 1964. Risk analysis in capital investment. Harvard Business review, 42 (1): 95-
106.

191
Risk factors leading to cost overrun in the delivery of highway construction projects.

Hester, W. T., J. A. Kuprenas and T. C. Chang. 1991. Construction Changes and Change
Orders: Their Magnitude and Impacts. Berkeley: University of California.

Hetland, P. W. 1994. Towards ultimate control of megaprojects in the North Sea. In Global
Project Management Handbook, eds. D. I. Cleland and R. Gareis. New York: McGraw-Hill
Book Co. Ltd.

Hibbert, P., D. Merrifield and A. Taylor. 1990. Key Factors On Contractual Relationships.
London: RICS.

Hillebrandt, P. M. and J. Cannon. 1990. The Modern Construction Firm. London:


Macmillan.

Hillson, D. 1999. Developing effective risk responses. In PMI Annual Seminar and
Symposium. Philadelphia: Project Management Institute.

Hillson, D. 2002. Extending the risk process to manage opportunities. International Journal
of Project Management, 20 (3): 225-40.

Hinze, J. and K. Walsh. 1997. Shoring as a bid item. Managing Engineered Construction in
Expanding Global Markets; ASCE Construction Congress Proceedings: 226-32.

HM Treasury. 1993. CUP Guidance: No. 41 - Managing risk and contingency for works
projects. London: HM Treasury Central Unit on Procurement.

Ho, O. S. 2000. Enhancing construction technology through strategic partnering: a


contractor's perspective. In Symposium on Quality Housing: Partnering Symposium 2000.
Hong Kong.

Holt, G. D., P. O. Olomolaiye and F. C. Harris. 1993. A conceptual alternative to current


tendering practice. Building Research and Information., 21: 167-72.

Holt, G. D., P. O. Olomolaiye and F. C. Harris. 1994. Factors influencing UK construction


clients' choice of contractor. Building and Environment Journal, 29: 241-48.

Holt, G. D., P. O. Olomolaiye and F. C. Harris. 1995. A review of contractor selection


practice in the UK construction industry. Building and Environment Journal, 30 (.): 553-61.

Holt, G. D., P. O. Olomolaiye and F. C. Harris. 1996. Applying cluster analysis to


construction contractor classification. Building and Environment Journal, 31: 557-568.

Holt(a), G. D., P. O. Olomolaiye and F. C. Harris. 1994. Evaluating pre-qualification criteria


in contractor selection. Building and Environment Journal, 29: 437-448.

Hughes, W. 1997. Construction management contracts: law and practice. Journal of


Engineering, Construction and Architectural Management, 4 (1): 59-79.

Hutcheson, G. and N. Sofroniou. 1999. The multivariate social scientist: Introductory


statistics using generalised linear models. Thousand Oaks, CA: Sage Publications.

192
BIBLIOGRAPHY

Hutchings, D. M. and J. P. Christofferson. 2000. A study of management practices in small-


volume home building companies. In ASC Proceedings of the 36th Annual Conference.
Purdue University, Indiana.

Ibbs, C. W. and W. E. Allen. 1995. Quantitative Impacts of Project Changes. Berkeley:


University of California.

Ibbs, W. C. and D. B. Ashley. 1987. Impact of various construction contract clauses. Journal
of Construction Engineering and Management, 113 (3): 501-21.

ICE. 1998. Institution of Civil Engineers: Risk analysis and management for projects
(RAMP). London: Thomas Telford.

In't veld, J. and J. Peeters. 1989. Keeping large projects under control: the importance of
contract type selection. Journal of Project Management, 7 (3): 155-62.

Iseley, T. and S. Gokhale. 2003. Equipment Productivity. South Carolina: CRC Press LLC.

Jaafari, A. and A. Schub. 1990. Surviving failure: Lessons from field study. Journal of
Construction and Engineering Management, 116 (1): 68-86.

Jackson, J. 1989. Response to Gregory section. In Prospects and problems in risk


communication. Institute of Risk Research, ed. W. Leiss (ed.). Ontario: University of
Waterloo Press.

Jergeas, G. F. and F. T. Hartman. 1994. Contractors protection against construction claims.


AACE Transactions.

Jones, D. S. 1996. Philosophies of risk allocation - the case for foreseability. International
Construction Law Review, 13 (4): 570-85.

Jones, D. S. 2000. Project Alliances. In Proceedings of Conference on 'Whose Risk?


Managing Risk in Construction - Who Pays?' Hong Kong.

Kahnaman, D. and A. Tversky. 1972. Subjective probability: A judgement of


representativeness. Cognitive Psychology, 3: 430-54.

Kaiser, H. F. 1958. The varimax criterion for analysis rotation in factor analysis.
Psychometrika, 23: 187-200.

Kangari, R. 1995. Risk management perceptions and trends of US construction. Journal of


Construction Engineering Management, 121 (4): 422-29.

Kangari, R. and L. S. Riggs. 1989. Construction risk assessment by linguistics. IEEE


Transactions in Engineering Management, 36 (2): 126-31.

Kantardzic, M. 2003. Data Mining : Concepts, Models, Methods and Algorithms.


Piscataway, N.J.: IEEE Press.

193
Risk factors leading to cost overrun in the delivery of highway construction projects.

Kaplan, S. 1991. The General Theory of Quantitative Risk Assessment. In Proceeding of the
Fifth Conference - Risk-Based Decision Making in Water Resources. Reston, VA: ASCE.

Kaplan, S. and B. J. Garrick. 1984. On the quantitative definition of risk. Risk Analysis., 1:
11-28.

Kayode, M. O. 1979. The Art of Project Evaluation. Ibadan, Nigeria: University Press.

Keeney, R., L and D. von Winterfeldt. 1991. Eliciting probabilities from experts in complex
technical problems. IEEE Transactions in Engineering Management, 38 (3): 191-201.

Khan, Z. 1998. Risk premiums associated with exculpatory clauses. Masters, University of
Calgary, Canada, Alberta.

Khosrowshahi, F. 1999. Neural network model for contractors' pre-qualification for local
authority projects. Journal of Engineering, Construction and Architectural Management, 6
(3): 315-28.

Kim, S. and D. Bajaj. 2000. Risk Management in Construction: An Approach for


Contractors in South Korea. Cost Engineering, Association for the Advancement of Cost
Engineering, 42 (1).

Kirszner, L. G. and S. R. Mandell. 1992. The Holt Handbook. 3rd Ed. ed. New York.:
Harcourt Brace Jovanovich,.

Kohrs, R. H. and G. C. Welngarten. 1986. Measuring successful technical performance - A


cost/schedule/technical control system, in: Measuring Success,. In Proceedings of the 18th
Annual Seminar/Symposium of the Project Management Institute, 158-64. Montreal, Canada.

Kometa, S. T., P. O. Olomolaiye and F. C. Harris. 1996. Review of client-generated risks to


project consultants. International Journal of Project Management, 14 (5): 273-79.

Koppula, S. D. 1981. Forecasting engineering costs: two case studies. Journal of


Construction Division; ASCE, 107 (4): 733-43.

Koskinen, K. U., P. Pihlanto. and H. Vanharanta. 2002. Tacit knowledge acquisition and
sharing in a project work context. International Journal of Project Management, 21: 281-
290.

Kozek, J. and C. Hebberd. 1998. Contracts: share the risk. Journal of Construction
Engineering and Management, 111 (2): 356-61.

Kumamoto, H. and E. J. Henley. 1996. Probabilistic Risk Assessment and Management for
Engineers and Scientists. 2nd Edition ed. New York, NY: IEEE Press.

Kumaraswamy, M. M. 1997. Common categories and causes of construction claims.


Construction Law Journal, 13 (1): 21-34.

Kumaraswamy, M. M. and S. M. Dissanayaka. 1998. Linking procurement systems to


project priorities. Building Research & Information, 26 (4): 223-38.

194
BIBLIOGRAPHY

Kumaraswamy, M. M. and J. D. Mathews. 2000. Improved sub-contractor selection


employing partnering principles. Journal of Management in Engineering, 16 (3): 47-57.

Kumaraswamy, M. M. and D. H. T. Walker. 1999. Multiple performance criteria for


evaluating construction contractors. In CIB W92 Procurement Systems: A Guide to Best
Practice in Construction, eds. S. Rowlinson and E. McDermott, 228-51. London: CIB.

Lam, K. C., T. Ng, M. Skitmore and O. Cheung. 2002. Decision support system for
contractor pre-qualification - artificial neural network model. Journal of Engineering,
Construction and Architectural Management, 7 (3): 251-66.

Langford, D. A., P. Kennedy, J. Conlin and N. McKenzie. 2003. Comparison of construction


costs on motorway projects using measure and value and alternative tendering initiative
contractual arrangements. Journal of Construction Management and Economics, 21
(December): 831-40.

Lansdown, J. 1982. Expert Systems: Their Impact on the Construction Industry. London:
RIBA.

Latham, S. M. 1994. Constructing the Team - Final Report of the Government / Industry
Review of Procurement and Contractual Arrangements in the UK Construction Industry.
London.

Laufer, A. 1996. Simultaneous Management: Managing Projects in a Dynamic Environment.


New York, NY: American Management Association.

Law, A. and W. D. Kelton. 1991. Simulation Modeling and Analysis. 2nd ed. New York:
McGraw-Hill, Inc.

Leavitt, D., S. Ennis and M. P. 1993. The cost escalation of rail projects: Using previous
experience to re-evaluate the Calspeed estimates; Working Paper No. 567. Berkeley:
Institute of Urban and Regional Development, University of California.

Leu, S. S., A. T. Chen and C. H. Yang. 2001. A GA-based optimal model for construction
time-cost trade-off. International Journal of Project Management, 19: 47-58.

Levine, H. 1995. Risk management for dummies: managing schedule cost and technical risks
and contingencies. PM Network, October: 30-32.

Lewis-Beck, M. S. 1993. Applied regression: An introduction. In Regression Analysis, ed.


M. S. Lewis-Beck. London: Sage Publications, Ltd.

Linstone, H. A. and M. Turoff. 1975. The Delphi Method Techniques and Applications.
Reading, MA.: Addison-Wesley.

Loftus, J. 1999. Project Management of Multiple Projects and Contracts. London: Thomas
Telford Ltd.

195
Risk factors leading to cost overrun in the delivery of highway construction projects.

Macaulay, S. 1963. Non-contractual relations in business: a preliminary study. American


Sociological Review, 28: 55-67.

MacCrimmon, K. R. and D. A. Wehrung. 1986. Taking Risks: The Management of


Uncertainty. New York: Free Press.

Macneil, I. R. 1980. The New Social Contract: An Inquiry into Modern Contractual
Relations. New Haven, NJ.: Yale University Press.

Mahdi, I. M., M. J. Riley, S. M. Fereig and A. P. Alex. 2002. A multi-criteria approach to


contractor selection. Journal of Engineering, Construction and Architectural Management, 9
(1): 29-37.

Mak, S. and D. Picken. 2000. Using risk analysis to determine construction project
contingencies. Journal of Construction Engineering and Management, 126 (2): 130-36.

Mak, S., J. Wong and D. Picken. 1998. The effect of contingency allowances of using risk
analysis in capital cost estimating: a Hong Kong case study. Journal of Construction
Management and Economics, 16: 615-19.

Marco, D. 2000. Building and Managing the Meta Data Repository: The Full Lifecycle
Guide. New York: John Wiley.

Marks, R. E. 2000. Efficient, competitive, and informed markets: Australian Corporations


Law and Auctions. Sydney: University of New South Wales/University of Sydney.

Mason, R. L., R. F. Gunst and J. l. Hess. 1989. Statistical Design and Analysis of
Experiments - With Application to Engineering and Science. New York: John Wiley and
Sons, Inc.

Masterman, J. W. E. 1994. A study of the basis upon which clients in the construction
industry choose their building procurement systems. PhD, Institute of Science and
Technology, University of Manchester, Manchester, UK.

Matthews, J. 1996. A project partnering approach to the main contractor sub-contractor


relationship. PhD thesis, Civil Engineering, Loughborough University, Loughborough.

McCoy, F. A. 1986. Measuring success: Establishing and maintaining a baseline. In


Proceedings of the 18th Annual Seminar/symposium of the Project Management Institute,,
47-52. Montreal, Canada.

McCuen, R. H. 1996. The Elements of Academic Research. New York: ASCE Press.

McDermott, P. ed. 1999. Strategic and emergent issues in construction procurement. Edited
by S. Rowlinson, E. McDermott and F. N. Spoon, CIB W92 "Procurement Systems: A Guide
to Best Practice in Construction". London: E and F.N. Spon,.

McGowan, P. H., R. Malcom, W. Horner, D. Jones and P. A. Thompson. 1992. Allocation


and Evaluation of Risk in Construction Contracts, Occasional Paper No. 52. Ascot:
Chartered Institute of Building.

196
BIBLIOGRAPHY

McKim, R. A. 1992. Risk Management Back to Basics. Cost Engineering, Association for
the Advancement of Cost Engineering, 34(12).

McLennan, A. and P. Jorss. 2006. Getting it right the first time: A plan to reverse the
declining standards in project design documentation within the building and construction
industry. In Clients Driving Innovation: Moving Ideas into Practice: Second International
Conference 2006. Gold Coast, Queensland, Australia: Cooperative Research Centre for
Construction Innovation.

Merkhover, M. W. 1987. Quantifying judgemental uncertainty: Methodology, experiences


and insights. IEE Transactions on Systems, Management, and Cybernetics, 17 (5): 741-52.

Merrow, E. W. 1978. Understanding the outcomes of mega-projects: Rand/R3360 PSSP.


Santa Monica, CA: Rand Corporation.

Might, R. 1984. An evaluation of the effectiveness of project control systems. IEEE


Transactions on Engineering Management, 31 (3): 127-37.

Milgrom, P. R. and R. J. Weber. 1982. A theory of auctions and competitive bidding.


Econometrica, 50 (5): 1089-122.

Minato, T. and D. B. Ashley. 1998. Data driven analysis of "corporate risk" using historical
cost data. Journal of Construction Engineering and Management, 124 (1): 42-47.

Molenaar, K. R. 2005. Programmatic cost risk analysis for highway megaprojects. Journal of
Construction Engineering and Management, 131 (3): 343-53 (accessed March 1, 2005).

Morgan, D. L. 1997. Focus groups as qualitative research. Second ed. London: Sage
Publications.

Morris, P. W. G. 1988. Managing project interfaces - Key points for project success. In
Project Management Handbook, eds. D. I. Cleland and W. R. King, 06-55. New York: Van
Nostrand Reinhold.

Morris, P. W. G. and G. Hough. 1987. The Anatomy of Major Projects. New York: John
Wiley.

Moselhi, O. 1997. Risk assessment and contingency estimating. In AACE Transactions 13-
16 July Conference. Dallas: AACE.

Musgrave, R. A. and P. B. Musgrave. 1984. Public Finance in theory and practice. New
York: McGraw-Hill.

NAS. 2003. Completing the Big Dig: Managing the final stages of Boston's Central
Artery/Tunnel Project. In Report to the National Academy of Sciences. Washington D.C: The
National Academies Press.

National Audit Office/Department of Transport. 1992. Contracting for roads. London:


National Audit Office.

197
Risk factors leading to cost overrun in the delivery of highway construction projects.

Ndekugri, I. and B. McDonnell. 1999. Differing site conditions risks: a FIDIC/engineering


and construction contract comparison. Engineering, Construction and Architectural
Management, 6 (2): 177-87.

NEDO. 1982. Target cost contracts: A worthwhile alternative: National Economic


Development Office, HMSO.

Neter, J., W. Wasserman and M. Kutner. 1990. Applied Linear Statistical Models. Third Ed.
ed. Homewood, Boston: Richard Irwin Inc.

Newton, S. and B. S. Logan. 1988. Causation and its effect: the blackguard in CAD's
clothing. Design Studies, 9 (4): 196-201.

Ng, S. T. 1996. Case-based reasoning decision support for contractor prequalification. PhD
Thesis, University of Manchester of Institute of Science and Technology, Manchester,
England.

Nijkamp, P. and B. Ubbels. 1999. How reliable are estimates of infrastructure costs: a
comparative analysis? International Journal of Transport Economics, 26 (1): 23-53.

Nilsen, T. and T. Aven. 2003. Models and model uncertainty in the context of risk analysis.
Reliability Engineering & System Safety, 79 (3): 309-17.

Niwa, K. and M. Okuma. 1982. Know-how transfer method and its application to risk
management for large construction projects. IEEE Transactions on Engineering
Management, 29/4 (4): 146-53.

Norusis, M. J. 2005. SPSS 13.0 Statistical Procedures Companion. Chicago: SPSS, Inc.

Oakes, M. 1986. Statistical Inference: A Commentary for the Social and Behavioural
Sciences. Chichester, UK: Wiley.

Oberlender, G., D and S. Trost, Michael. 2001. Predicting accuracy of early cost estimates
based on estimate quality. Journal of Construction Engineering and Management
(May/June): 173-82.

OGC. 2002. Managing Successful Projects With PRINCE 2. 3rd ed. London: The Stationary
Office.

Ogunlana, O. 1989. Accuracy in Design Cost Estimating. PhD, Loughborough University of


Technology.

Ogunlana, O. 1991. Learning from experience in design cost estimating. Journal of


Construction Management and Economics, 9 (1): 133-50.

O'Reilly, M. 1995. Risk, construction contracts and construction disputes. Construction Law
Journal, 11 (5): 343-54.

198
BIBLIOGRAPHY

Orji, H. O. 1988. Construction Financing in Nigeria: A banking perspective. Financial


review, 1 (4): 12-13.

Paek, J. H., Y. W. Lee and J. H. Ock. 1993. Pricing Construction Risk: Fuzzy Set
Application. Journal of Construction Engineering and Management, ASCE, 117(3).

Pakkala, P. 2002. Innovative Project Delivery Methods for Infrastructure - An International


Perspective. Helsinki: Finnish Road Enterprise.

Palaneeswaran, E. and M. Kumaraswamy. 2001. Recent advances and proposed


improvements in contractor pre-qualification methodologies. Journal of Building and
Environment, 36: 73-87.

Palaneeswaran, E. and M. M. Kumaraswamy. 2000. Benchmarking Contractor Practices in


Public-sector Construction - A Proposed Model. Journal of Engineering, Construction and
Architectural Management, 7 (3): 285-99.

Palaneeswaran, E., M. M. Kumaraswamy and P. W. M. Tam. 1999. Identifying best


practices in contractor selection for enhanced harmony and profit. In Proceedings of CIB
W92 Construction Procurement Symposium, pp. 637-47. Chiang Mai: CIB.

Panagiotokopoulos, D. 1977. Cost-time model for large CPM project networks. Journal of
Construction Engineering and Management, ASCE, 103 (C02): 201-11.

Patrascu, A. 1988. Construction Cost Engineering Handbook. New York: Dekker.

Patton, M. Q. 1986. Utilization-focused Evaluation. 2nd ed. New York.: Sage.

Paul, A. and G. Gutierrez. 2005. Simple probability models for project contracting.
European Journal of Operational Research, 165 (2): 329-38.

Perry, J. G. and R. W. Hayes. 1985. Risk and its management in construction projects.
Proceedings of the Institute of Civil Engineering, 78 ( 1): 499-521.

Persad, K. R., J. T. O'Connor and K. Varghese. 1995. Forecasting engineering manpower


requirements for highway preconstruction activities. Journal of Management Engineering,
11 (3): 41-7.

Peurifoy, R. and G. Oberlender. 1989. Estimating Construction Costs. 4th ed. New York:
McGraw-Hill Book Co. Inc.

Potter, S. 1987. On the right lines? The limits of technological innovation. London.: Frances
Pinter.

Powell, C. G. 1980. An Economic History of the British Building History. London:


Architectural Press.

Project Management Institute, S. C. 2000. A Guide to the Project Management Body of


Knowledge. 2nd ed. North Carolina, USA.: PMI Communications Publishing.

199
Risk factors leading to cost overrun in the delivery of highway construction projects.

Queensland Department of Main Roads. ed. 2000. Main Roads' Project Delivery System -
Major Works Pre-qualification System. Vol. Three. Brisbane: Queensland Department of
Main Roads.

Queensland Department of Main Roads. 2005. Roads Implementation Program 2004-05 to


2008-09. Main Roads Department Queeensland.
http://www.mainroads.qld.gov.au/MRWEB/Prod/Content.nsf/1b117feddfff9cdb4a2569f100
19412f/2f1dc785a18cc2ca4a256f4d00243e89!OpenDocument.

Raftery, J. 1994. Risk Analysis in Project Management. London.: E & FN Spoon.

Raftery, J. and S. T. Ng. 1993. Knowledge Based Approaches to Construction Risk Analysis.
In International Symposium on Electronic Evaluation and the Built Environment, CIB W55
and W95, 152-65. Lisbon, Portugal.

Rahman, M. M., E. Palaneeswaran and M. M. Kumaraswamy. 2001. Applying transaction


costing and relational contracting principles to improved risk management and contractor
selection. In Proceedings of the International Conference on Project Cost Management.
Beijing.

Reich, Y. 1994. Layered models of research methodologies: artificial intelligence for


engineering design. Analysis and Manufacturing, 8: 263-74.

Reutlinger, S. 1970. Techniques for project appraisal under uncertainty. In World Bank Staff
Occasional Papers. Baltimore, Md: Johns Hopkins University.

Revay, S. G. ed. 1992. Can construction claims be avoided? Edited by P. F. R. Gameson,


Construction Conflict Management and Resolution. London: E & FN Spoon.

RIBA. 1984. Handbook of Architectural Practice and Management. 4th ed. London: The
Royal Institute of British Architects.

Robinson, J. 1987. Comparison of tendering procedures and contractual arrangements.


International Journal of Project Management, 5 (1): 19-24.

Robinson, R. B., C. D. Cox and K. Odom. 2005. Identifying outliers in correlated water
quality data. Journal of Environmental Engineering, 131 (4): 651-57 (accessed April 2005).

Rosenberg, L. H., T. Hammer and A. Gallo. 1999. Continuous risk management at NASA.
http://satc.gsfc.nasa.gov/support/ASM-FEB99/crm-at-nasa.html.

Rowlinson, S. ed. 1999. A definition of procurement systems. Edited by S. M. Rowlinson, E.


and Spon, F.N. (Eds), CIB W92 "Procurement Systems: A Guide to Best Practice in
Construction". London: E and F.N. Spon,.

Royer, P. S. 2000. Risk management: The undiscovered dimension of project management.


Project Management Journal, 31 (1): 6-13.

Rummel, R. J. 1970. Applied Factor Analysis. Evanston: Northwestern University Press.

200
BIBLIOGRAPHY

Russell, J. S., D. E. Hancher and M. J. Skibniewski. 1992. Contractor pre-qualification data


for construction owners. Construction Management Economics, 10: 117-35.

Russell, J. S. and M. J. Skibniewski. 1988. Decision criteria in contractor prequalification.


Journal of Management in Engineering., 4: 148-64.

Russell, J. S., M. J. Skibniewski and D. R. Cozier. 1990. Qualifier-2: knowledge-based


system for contractor prequalification. Journal of Construction Engineering and
Management, 116: 157-71.

Rutgers, A. and D. H. Haley. 1997. Project risk and risk allocation. Cost Engineering, 39 (9):
27-9.

Sackman, H. 1972. Delphi Critique: Expert Opinion, Forecasting and Group Process.
Lexington, MA: Lexington Books.

Salapatas, J. N. and W. S. Sawte. 1986. Measuring success of utility projects past, present
and future. In Proceedings of the 18th Annual Seminar/symposium of the Project
Management Institute. Montreal,.

Schexnayder, C. and L. G. Ohrn. 1997. Highway specifications quality versus pay. Journal
of Construction Engineering and Management, 123 (4,): 437-43.

Seppalla, C. R. 1991. Contractor's claims under FIDC civil engineering contract.


International Business Lawyer (October): 457-60.

Shadbolt, R. A. 1990. Unexpected ground conditions - English Law Perspective.


International Business Lawyer (June): 277-81.

Shafer, G. 1976. A Mathematical Theory of Evidence. Princeton, NY: Princeton University


Press.

Shen, L. Y., W. lu, Q. Shen and H. Li. 2003. A computer-aided decision support system for
assessing a contractor's competitiveness. Automation in Construction, 12: 577-87.

Shepherd, B. 1997. Managing Risk. In The 29th Annual Project Management Institute
Seminars and Symposium, 79-87. Chicago: Project Management Institute.

Sidwell, A. C., R. J. Kennedy and A. P. C. Chan. 2002. Re-engineering the Construction


Delivery Process. Brisbane: Construction Industry Institute, Australia.

Simon, P., D. Hillson and K. Newland. 1997. PRAM-Project risk analysis and management
guide. High Wycombe, UK: Association for Project Management.

Skitmore, R. M. 1996. The Raftery Curve. In Proceedings: International Council for


Building Research Studies and Documentation, 241-352: CIB.

Slovic, P., B. Fischhoff and S. Lichenstein. 1980. Facts and fears: understanding perceived
risk. In Societal Risk Assessment: How safe is enough?, eds. R. C. Schwing and W. A.
Albers (eds.), 181-214. New York: Plenum Press.

201
Risk factors leading to cost overrun in the delivery of highway construction projects.

Smith, A. J. 1995a. Estimating, Tendering and Building for Construction. London:


Macmillam Press Ltd.

Smith, G. R. and C. M. Bohn. 1999. Small to medium contractor contingency and


assumption of risk. Journal of Construction Engineering and Management, 125 (2): 101-8.

Smith, M. A. ed. 1996. Construction Insurance, Bonding, and Risk Management. Edited by
W.J Palmer, J. M. Maloney and J. l. Heffron. New York: McGraw-Hill.

Smith, R. J. 1995b. Risk identification and allocation: saving money by improving contracts
and contracting practices. International Construction Law Review, 12 (1): 40-71.

Smith(a), R. 1995. International construction review. Engineering News Record, January: 7-


8.

Soanes, C. and A. Stevenson. eds. 2003. Oxford Dictionary of English. Oxford: Oxford
University Press.

Spooner, J. E. 1974. Probabilistic estimating. American Society of Civil Engineers, Journal


of Construction Division, March 1974: 65-77.

Standards Australia. 1999. AS/NZS 4360: Risk Management. Strathfield NSW: Standards
Association of Australia.

Statman, M. and T. T. Tyebjee. 1984. The risk of investment in technological innovation.


IEEE Transactions on Engineering Management, 31 (4): 165-71.

Staugus, J. 1995. Variations. Journal of Building and Construction Law, 11 (3): 156-58.

Steiner, G. A. 1969. Top management planning. In Project Management Handbook, eds. D.


I. Cleland and W. R. King. New York: Van Nostrand Reinhold.

Stevens, J. D. 1995. Cost estimating and forecasting for highway work in Kentucky:
Research Report KTC 95-12. Lexington, Ky.: Kentucky Transportation Centre, University of
Kentucky.

Stewart, V. and A. Stewart. 1981. Business Applications of Repertory Grid. London:


McGraw-Hill.

Stone, E. F. 1978. Research Methods in Organisational Behaviour. Santa Monica, Ca:


Goodyear Publishing Company.

Summers, R. 1967. Cost estimates as predictors of actual costs: A statistical study of military
developments.. In Strategy for R&D: Studies in the microeconomics of development, eds. T.
Marschak, T. K. Glennan and R. Summers, 14089. Berlin: Springer-Verlag.

Sykes, A. 1982. Reducing neglected risks on giant projects. In New Dimensions of Project
Management, ed. A. J. Kelley(ed). Lexington, MA: Lexington Books.

202
BIBLIOGRAPHY

Szyliowicz , J. S. and A. R. Goetz. 1995. Getting realistic about megaproject planning. The
case of the Denver International Airport. Policy Sciences, 28: 347-67.

Tabachnick, B. G. and L. S. Fidell. 2001. Using Multivariate Statistics, Fourth Edition.


Boston: Allyn and Bacon.

Tagliaventi, M. R. 1991. Civil Engineering Contracts: Organisational and Managerial


Aspects and Economic Effects. Rome: Gangemi Editor.

Tah, J. H. M. and V. Carr. 2001. Towards a framework for project risk knowledge
management in the construction supply chain. Advances in Engineering Software, 32: 835-
46.

Taha, M. A., S. C. Park and J. S. Russell. 1995. Knowledge based DSS for construction
contractor pre-screening. European Journal of Operational Research, 84: 35-46.

Taylor, M. 1993. Raising awareness of risk. Architects Journal, May: 26.

Thomas, H. R. 1985. Comparative analysis of time and schedule performance on highway


construction projects involving project claims. Washington, DC: Federal Highway
Administration Report No. FHWA-TS-85-217.

Thompson, P. A. and J. G. Perry. 1992. Engineering construction risks: A guide to project


risk analysis and risk management. SERC Project Report. London: Thomas Telford Ltd.

Thompson, P. J. and S. R. Sanders. 1998. Partnering continuum. Journal of Management in


Engineering ASCE, 14 (5): 73-8.

Tilley, P. A., S. L. McFallen and S. N. Tucker. 2000. Design and documentation quality and
its impact on the contract process. Brisbane: CSIRO.

Tiong, R. L. K. 1995. Risks and guarantees in BOT tender. Journal of Construction


Engineering and Management, 121. (2): 183-88.

Toakley, A. R. 1995. Risk management applications - a review. Australia Institute of


Building Papers, 6: 77-85.

Topcu, Y. I. 2004. A decision model proposal for construction contractor selection in


Turkey. Journal of Building and Environment, 39: 469-81.

Touran, A. 2003. Probabilistic model for cost contingency. Journal of Construction


Engineering and Management :ASCE, May/June, 2003: 280-84.

Tran, V. H. Q. 2002. Practical frontier in construction pre-qualification using data envelope


analysis. MASc. thesis, Department of Civil Engineering, University of Toronto, Toronto.

Trost, S., Michael and G. Oberlender, D. 2003. Predicting accuracy of early cost estimates
using factor analysis and multivariate regression. Journal of Construction and Engineering
Management, March/April: 198-204.

203
Risk factors leading to cost overrun in the delivery of highway construction projects.

Tummala, V. M. R. and Y. H. Leung. 1999. Applying a risk management process (RMP) to


manage cost risk for an EHV transmission line project. International Journal of Project
Management, 17 (4): 223-35.

Tuohey, P. 2002. The use of risk management processes in construction contracts. In The
Contract in Successful Project Management Conference. Christchurch, NZ: Worley Group.

Turner, J. R. 1999. The Handbook of Project-based Management. New York: McGraw-Hill.

Tversky, A. and D. Kahneman. 1981. The framing of decisions and the psychology of
choice. Science, 211: 453-58.

Uff, J. and A. Odams. 1995. Contract Documents and the Division of Risk. In Risk
Management and Procurement Practices, eds. J. Uff and A. Odams. Kings College, London:
Centre for Construction Law and Management.

Uher, T. 1994. A general risk classification model for construction. Australian Institute of
Building Papers, 5: 25-33.

Under water, o. b. 1989. Under water, over budget. The Economist, October: 37-8.

Velicer, W. F. and D. N. Jackson. 1990. Component analysis versus common factor analysis:
Some issues in selecting an appropriate procedure. Multivariate Behavioral Research, 25
(1): 1-28.

Vickrey, W. 1961. Counter-speculation, Auctions, and Competitive Sealed Tenders. Journal


of Finance, 16: 8-37.

Victorian-Government. 1999. Private Provision of Public Infrastructure: Risk Identification


and Allocation Project: Victorian Government, Department of Treasury and Finance;
University of Melbourne, Department of Civil and Environmental Engineering.

Vojir, C.P., K.R. Jones, R. Fink. And E. Hutt. 2006. Scientific Enquiry: What a difference a
point makes. Journal of Specialists in Pediatratic Nursing, 11 (4) 257-59.

Walker, D. H. T., K. Hampson and R. Peters. 2000. Project alliancing and project partnering
- what's the difference? - Partner selection on the Australian National Museum project: a
case study. In Proceedings of the CIB W92 Conference, 641-55. Chile.

Walker, D. H. T. and K. D. Hampson. 2002. Procurement Strategies. A Relationship Based


Approach. Oxford: Blackwell Publishing.

Wallace, I. N. D. 1995. Hudson's Building and Engineering Contracts. 11th edition ed.
London: Sweet & Maxwell.

Wang, J. X. and M. L. Roush. 2000. What Every Engineer Should Know About Risk
Engineering and Risk Management. New York, NY.: Marcel Dekker.

Wang, M.-T. and H.-Y. Chou. 2003. Risk allocation and risk handling of highway projects in
Taiwan. Journal of Management in Engineering, 19 (2): 60-8.

204
BIBLIOGRAPHY

Wang, W.-C. 2003. SIM-UTILITY: Model for project ceiling price determination. Journal
of Construction and Engineering Management, 1218 (1): 76-84.

Ward, S. 1999. Requirements for an Effective Project Risk Management Process. Project
management Journal, 30(3).

Ward, S. and C. Chapman. 2003. Transforming project risk management into project
uncertainty management. International Journal of Project Management, 21 (2): 97-105.

Weverbergh, M. 2002. A comment of 'predicting the probability of winning sealed bid


auctions: a comparison of models'. Journal of the Operational Research Society, 45 (11).

White, D. and J. Fortune. 2002. Current practice in project management: An imperial study.
International Journal of Project Management, 25 (4).

Wilcox, R. C., Z. I. Karaszewski and B. M. Ayyub. 1996. Methodology for Risk-based


Technology Applications to Marine System Safety. In Proceedings of the Ship Structures
Symposium, 1-15. Arlington: SSC.

Williams(a), T. M. 1993. Risk management infrastructures. International Journal of Project


Management, 11 (1): 5-10.

Williams(b), T. M. 1993. Using the risk register to integrate risk management in project
definition. International Journal of Project Management, 12: 17-22.

Williams, T. M. 1995. A classified bibliography of recent research relating to project risk


management. European Journal of Operational Research., 85 (1): 18-38.

Williams, T. M. 1999. The need for new paradigms for complex projects. International
Journal of Project Management, 17 (5): 269-73.

Williams, T. M., F. R. Akermann and C. L. Eden. eds. 1997. Project risk: systemicity, cause
mapping and a scenario approach. Edited by K. Kahkonen and K. A. Arto, Managing Risks
in Projects. London: E & F.N. Spoon.

Williams, T. P. 2003. Predicting final cost for competitively bid construction projects using
regression models. International Journal of Project Management, 21: 593-99.

Williams, T. P., J. C. Miles and C. J. Moore. 1999. Predicted cost escalations in


competitively bid highway projects. Proceedings of the Institution of Civil Engineers-
Transport, 135 (4): 195-99.

Wilmot, C. G. and C. Cheng. 2003. Estimating future highway construction costs. Journal of
Construction Engineering and Management, May/June: 272-79 (accessed May/June 2003).

Winch, G. 1989. The construction firm and the construction project: a transaction cost
approach. Construction Management and Economics,. 7: 331-45.

205
Risk factors leading to cost overrun in the delivery of highway construction projects.

Woodward, J. F. 1975. Quantitive Methods in Construction Management and Design.


London: Macmillan.

World Bank. 1994. World Development Report 1994: Infrastructure for development.
Oxford, UK: Oxford University Press.

Yeo, K. T. 1990. Risks, classification of estimates, and contingency management. Journal of


Management in Engineering,, 6 (4): 458-70.

Yin, R. K. 2003. Case Study Research: Design and Methods, 3rd Ed. 3rd ed. ed. Thousand
Oaks, Calif.: Sage Publications.

Young, T. L. 1996. The Handbook of Project Management: A Practical Guide to Effective


Policies and Procedures. London: Kogan Page.

Zack, J. G. J. 1996. Claims prevention: offense versus defense. AACE International.


Transactions of the Annual Meeting. http://www.sciencedirect.com/science/article/B6WPV-
3THVNX0-3FD/2/0532d489e2d4228267f87857cda1881d.

Zaghloul, R. and F. Hartman. 2003. Construction contracts: the cost of mistrust.


International Journal of Project Management, 21: 419-24.

Zeitoun, A. A. and D. O. Oberlender. eds. 1993. Early Warning Signs of Project Changes:
Document 91. Edited by C. I. Institute. Austin, Texas: Construction Industry Institute.

206
APPENDIX A

APPENDIX A
Road Input Cost Indices for the period 1995-96 to 2002-03

Compiled from Australian Bureau of Statistics data

207
Risk factors leading to cost overrun in the delivery of highway construction projects.

Month Year RICI RICI Percent

September 1984 61.21 0


December 1984 61.38 0.28
March 1985 61.70 0.52
June 1985 63.20 2.43
Financial year average 61.78 Datum

September 1985 63.66 0.73


December 1985 65.63 3.09
March 1986 66.00 0.56
June 1986 66.41 0.62
Financial year average 65.15 5.45

September 1986 68.06 2.48


December 1986 68.64 0.85
March 1987 70.55 2.78
June 1987 70.92 0.52
Financial year average 69.14 6.12

September 1987 71.57 0.92


December 1987 72.90 1.86
March 1988 74.96 2.83
June 1988 75.86 1.20
Financial year average 73.40 6.16

September 1988 77.79 2.54


December 1988 78.68 1.14
March 1989 80.36 2.14
June 1989 81.29 1.16
Financial year average 78.95 7.56

September 1989 82.62 1.64


December 1989 84.40 2.15
March 1990 85.52 1.33
June 1990 86.92 1.64
Financial year average 84.30 6.78

September 1990 87.74 0.94


December 1990 88.21 0.54
March 1991 88.85 0.73

208
APPENDIX A

June 1991 89.30 0.51


Financial year average 88.33 4.78

September 1991 90.64 1.50


December 1991 91.12 0.53
March 1992 91.37 0.27
June 1992 92.06 0.76
Financial year average 91.01 3.03

September 1992 92.39 0.36


December 1992 92.63 0.26
March 1993 93.00 0.40
June 1993 93.22 0.24
Financial year average 92.72 1.88

September 1993 93.68 0.49


December 1993 93.96 0.30
March 1994 94.42 0.49
June 1994 94.79 0.39
Financial year average 94.07 1.46

September 1994 95.00 0.22


December 1994 95.48 0.51
March 1995 95.82 0.36
June 1995 96.84 1.06
Financial year average 95.68 1.71

September 1995 97.17 0.34


December 1995 97.17 0.00
March 1996 97.26 0.09
June 1996 97.73 0.48
Financial year average 97.25 1.64

September 1996 97.99 0.27


December 1996 98.34 0.36
March 1997 98.54 0.20
June 1997 98.90 0.37
Financial year average 98.37 1.15

September 1997 99.31 0.41


December 1997 99.74 0.43
March 1998 100.25 0.51
June 1998 100.70 0.45

209
Risk factors leading to cost overrun in the delivery of highway construction projects.

400.00
Financial year average 100.00 1.66
September 1998 101.50 0.79
December 1998 101.98 0.47
March 1999 102.41 0.42
June 1999 102.69 0.27
408.58
Financial year average 102.15 2.15
September 1999 103.50 0.79
December 1999 104.05 0.53
March 2000 104.56 0.49
June 2000 105.05 0.47
417.16
Financial year average 104.29 2.10
September 2000 105.36 0.30
December 2000 106.41 1.00
March 2001 107.04 0.59
June 2001 107.60 0.52
426.41
Financial year average 106.60 2.22
September 2001 108.54 0.87
December 2001 109.10 0.52
March 2002 109.78 0.62
June 2002 110.54 0.69
437.96
Financial year average 109.49 2.71
September 2002 111.85 1.19
December 2002 112.87 0.91
March 2003 113.80 0.82
June 2003 114.38 0.51
452.90
Financial year average 113.23 3.41
September 2003 115.21 0.73
December 2003 116.10 0.77
March 2004 116.79 0.59
June 2004 118.18 1.19
466.28
Financial year average 116.57 2.95

Source: Australian Bureau of Statistics

210
APPENDIX B

APPENDIX B
Programmed and actual project costs indexed to year 2003

211
Risk factors leading to cost overrun in the delivery of highway construction projects.

Project number Year project Indexed prog cost Indexed actual cost
completed $m $m
12/46C/803 1996 2.152 2.849
107/852/804 1996 1.396 1.997
80/140/13 1996 2.908 4.380
160/11A/2 1996 7.443 10.395
25/126/22 1996 1.251 1.605
100/851/26 1996 5.338 6.891
24/162/13 1996 2.239 2.744
122/31A/804 1996 2.326 2.873
30/8202/803 1996 2.291 2.777
146/166/15 1996 1.215 1.700
113/35A/807 1996 1.977 2.710
94/36b/19 1996 2.093 2.353
128/48/15 1996 3.256 3.838
66/814/5 1997 2.059 3.337
140/U16/819 & 820 1997 1.803 3.131
158/10P/811 1997 2.300 2.574
22/18E/807 1997 1.854 2.293
25/10A/802 1997 3.565 4.879
130/45B/14 1997 1.550 1.880
5/10K/19 1997 1.495 1.691
150/10L/38 & 39 1997 9.051 10.567
160/103/2 1997 5.290 7.418
160/12B/5 1997 42.550 47.909
24/10C/22 & 64/10C/3 1997 1.351 1.692
25/126/23 1997 1.283 2.214
158/20A/2 1997 2.990 4.156
70/25A/11 1997 22.749 29.937
92/133/11 1997 2.415 2.887
45/655/18 1997 1.898 3.908
158/647/15 1997 3.283 4.016
37/90B/43 1997 2.482 2.828
30/8202/303 1997 2.645 3.148
148/17B/20 1997 2.530 3.146
25/126/24 1997 1.196 1.680
S140/U12B/28 1997 1.021 2.933
140/U18B/61 1997 1.567 1.796
134/14C/301 1997 4.165 6.138
23/78A/17 1998 16.980 18.678
70/108/300 1998 1.301 2.177
36/15A/301 &302 1998 6.905 7.647
25/1204/301 1998 2.151 2.390
89/41A/17 1998 2.830 3.113
24/1632/12 1998 1.366 1.519
40/22A/28 1998 3.034 3.588
150/10L/38 & 1998 8.857 11.030
39;150/10M/26
160/102/3 1998 4.528 6.012

212
APPENDIX B

160/103/6 1998 15.848 18.112


160/203/3 1998 1.358 2.897
48/641/301 1998 3.283 3.736
70/204/20 1998 7.083 8.420
140/U15/44 1998 2.297 4.098
140/U96/738 1998 1.193 1.735
92/140/11 1998 1.698 2.691
76/132/19 1998 5.660 6.674
45/655/18 1998 4.356 5.284
30/6204/13 1998 2.264 2.558
36/89A/303 1998 1.456 1.796
83/182/18 1998 4.811 5.637
97/403/32 1998 1.613 2.206
160/104/4 1998 1.132 1.288
140/U18B/61 1998 1.872 2.142
125/88B/40 1998 1.878 2.395
148/2104/8 1998 3.076 3.639
88/23C/20 1998 2.377 2.728
148/3042/2 1999 1.808 3.265
20/85C/32 1999 4.436 5.196
80/133/734 1999 3.538 4.055
17/18D/301 1999 7.763 9.308
104/416/301 1999 2.955 3.432
35/22B/802 1999 2.229 2.963
80/497/301&76/497/801 1999 4.347 5.232
150/832/2 1999 8.611 9.713
160/102/2 1999 5.989 6.579
148/18A/2 1999 11.090 16.635
140/U88/9 1999 7.228 7.981
160/12A/8.566 1999 46.024 57.668
148/17B/301 1999 1.664 2.239
140/904/301 1999 1.792 2.197
76/153/3 1999 2.551 5.362
34/110/18 1999 1.557 1.800
140/U18B/63 1999 2.995 3.793
37/91A/20 1999 4.731 10.092
42/83A/21 1999 2.551 2.950
25/493/3 1999 2.218 2.867
83/1821/18 1999 5.578 7.332
19/93D/17 1999 2.218 3.124
37/90C/36 1999 1.774 3.075
95/27B/302 1999 1.222 1.363
36/93E/706 1999 1.170 1.342
72/44A/303 1999 2.551 2.994
13/25B/301 1999 1.331 1.641
22/4397/14 1999 3.771 4.464
160/203/3 1999 2.838 3.438
150/10M/301 1999 4.225 4.701
114/313/12 1999 1.664 2.287
140/U18A/14 1999 2.102 2.734

213
Risk factors leading to cost overrun in the delivery of highway construction projects.

41/92A/27 1999 3.848 4.602


125/88B/42 1999 2.556 2.971
55/99C/15 1999 5.046 5.719
60/176/15 1999 1.673 2.237
134/14C/305 1999 1.885 2.131
64/19B/301 1999 2.218 2.693
22/4397/15 1999 3.327 4.158
140/902/2 2000 16.412 18.469
47/16B/302 2000 2.415 2.726
80/10A/772 2000 4.344 5.647
141/19A/806 2000 2.389 3.334
148/3042/2 2000 2.830 3.844
148/17B/302 2000 3.475 3.855
148/18A/708 2000 1.685 2.048
20/10G/301 2000 5.321 6.081
128/10B/808 2000 2.672 3.898
80/496/301 2000 2.818 3.606
48/6404/3 2000 8.688 14.016
160/11A/3 2000 4.997 5.713
160/103/3 2000 11.947 13.603
34/110/16 2000 6.065 7.140
160/12A/8.565 2000 28.225 34.968
140/U13A/729 2000 1.195 1.617
140/900/2 2000 15.542 17.215
148/3042/300 2000 2.323 2.896
37/91A/17 2000 8.362 9.519
66/626/4 2000 1.140 1.553
107/8509/8 2000 1.200 1.856
13/202/16 2000 1.738 2.020
97/122/801 2000 2.744 3.204
140/U90/301 2000 3.367 4.375
37/91A/32 2000 2.715 3.527
25/493/4 2000 3.329 4.154
8/26A/302 2000 2.606 2.902
89/41A/18 2000 2.172 2.715
97/403/27 2000 4.980 5.741
160/11B/313 2000 1.195 1.529
72/41A/9 2000 1.086 1.444
150/831/801 2000 1.412 1.596
80/495/897 2000 1.195 2.340
134/14C/302 2000 5.104 6.506
114/18A/764 2001 1.455 1.711
80/10A/772 2001 5.448 6.053
120/8506/301 2001 2.760 3.210
47/16B/302 2001 2.737 3.028
148/302/2 2001 1.228 1.435
22/18E/807 2001 2.118 2.974
90/33B/302 2001 2.549 2.971
128/143/301 2001 1.646 1.874
47/46C/306 2001 4.237 5.092

214
APPENDIX B

48/21A802 2001 1.134 1.867


148/18A/2 2001 14.682 16.409
36/15A/13 2001 6.075 7.668
160/103/4 2001 10.636 13.710
120/854/6 2001 1.805 2.091
148/17B/21 2001 5.522 6.397
140/U88/3 2001 47.790 56.403
160/12A/8.57-59 2001 29.948 38.232
140/U16/301 2001 7.434 11.476
148/17A/49 2001 1.629 1.888
34/112/38 2001 2.124 2.634
120/854/3 2001 1.373 1.635
44/93D/8 2001 2.156 2.851
55/99C/13 2001 2.055 2.322
66/8108/302 2001 1.417 2.091
50/27A/305 2001 1.109 1.286
30/6204/14 2001 1.900 2.393
76/490/3 2001 2.438 3.108
5/10K/809 2001 1.299 2.491
140/U12B/727 2001 1.087 1.406
125/88B/42 2001 4.086 5.127
59/32C/25 2001 2.177 2.670
55/99C/13 2001 5.477 7.716
20/85C/302 2001 2.177 2.628
79/14D/304 2001 2.018 3.063
161/46A/17 2001 2.784 3.076
128/141/18 2001 2.124 2.713
133/89B/49 2001 1.701 2.243
80/151/2 2002 17.578 19.749
140/12A/301 2002 1.499 1.872
148/17B/805 2002 2.895 3.259
140/U91/813 2002 1.241 1.448
33/18C/301 2002 1.654 1.865
70/25A/13 2002 32.713 41.123
120/856/3 2002 3.810 6.307
5/10K/22 2002 1.143 1.448
10/15C/2 2002 15.675 20.404
13/202/18 2002 2.569 2.953
9/16D/302 2002 2.016 2.224
99/332/301 2002 1.241 1.448
58/214/301 2002 1.034 1.286
27/46A/16 2002 1.068 1.391
160/12B/802 2002 1.034 1.633
99/323/13 2002 3.743 4.262
76/493/7 2002 1.034 1.564
73/45A/20 2002 1.241 1.453
140/U18A/14 2002 2.543 2.818
149/18A/23 2002 2.792 3.629
160/101/302 2002 1.034 1.344
150/10L/55 2003 35.4 46.890

215
Risk factors leading to cost overrun in the delivery of highway construction projects.

37/91A/26 2003 6.755 7.950


80/151/2 2003 19.1 22.500
30/10N/88 2003 1.12 1.340
25/40A/812 2003 1.275 1.590
128/43/304 2003 1.25 1.800
97/407/11 2003 1.483 2.301
160/105/5 2003 9.049 11.300
70/25A/13 2003 40.424 46.350
160/204/2 2003 18.59 21.098
158/10P/17 2003 5.82 7.320
160/103/4 2003 12.193 14.850
140/U15/721 2003 3.227 4.013
13/25A/48 2003 8.649 9.835
160/200/12 2003 1.898 2.186
25/40A/35 2003 2.5 2.862
37/91A/36 2003 7.021 8.055
116/26B/31 2003 1.498 1.661
128/483/303 2003 1.7 2.200
134/14D/302 2003 2.25 2.900
99/332/10 2003 1 1.246
150/548/301 2003 1.082 1.365
63/17D/302 2003 1 1.127
36/14E/301 2003 2.1 2.682
25/401/302 2003 2.8 3.600
125/88A/806 2003 1.3 1.550
34/1102/17 2003 2 3.209
119/32B/27 2003 1.018 1.273

216
APPENDIX C

APPENDIX C
Questionnaire format to establish NGT membership

217
Risk factors leading to cost overrun in the delivery of highway construction projects.

Questionnaire:

Date of Completion: ..

Dear interviewee,
The aim of this questionnaire is to elicit expert information on the process of preparing total project
cost estimates at the time of design, ideally in road construction.

For the purpose of this questionnaire and research, the total project cost estimate includes the
estimated costs of all component activities from the initiation of the project proposal to finalisation.
This total project cost estimate is usually prepared at the design stage of a project and can often
include the costs of the following:
conducting investigations and developing altering public utility plant,
the design, construction,
detailing the design, project administration, and handover
acquiring land,

The information supplied in this completed questionnaire will be used for broad research purposes
only. All specific company and interviewee information will be kept confidential at all times.
Only generalised analysis of the information contained within this completed questionnaire will be
utilised in the research process.
Regards,
Garry Creedy
7 December 2004

Section 1: Company Information

1.1 Company Name (optional):


1.2 Volume of Construction Work/year in A$
1.3 Predominant activity for company: Project Owner/Client
General Contractor
Consultant
Other
1.4 Describe types of projects predominantly involved in:

Section 2: Information about Interviewee

2.1 Name (optional)


2.2 Phone contact/email (optional)
2.3 Related Qualifications
2.4 Years employed in company
2.5 Related experience:
Estimating (years)
Design (years)
Construction (years)
Management (years)

218
APPENDIX C

(This section refers to the whole of the project estimate not just the construction estimate.)
Section 3: Total Project Estimating

3.1 In your opinion, what are the four most important factors/issues in project estimating?

3.2 In your experience, what role does value engineering and/or value management play in total
project cost estimating and also in design?

3.3 What are the estimating methods most often used in your organisation for total project
estimating at the design stage?
e.g. parametric
factored
basic cost
unit rate
Explain.

3.4 Do you use a computerised system for project design estimating?

Also, describe in brief any off-the-shelf software utilised..

3.5 Describe the typical project scope definition information available to you for project design
estimating.

3.6 What approach do you use for contingency analysis in project design estimates?
Probability based
Historical values
Decision analysis
Experience based
Other (explain)

3.7 List items at the project level that you normally include as contingencies?
e.g. - Design allowances
- Force majeure
-
-

3.8 List the main factors that you take into account for contingency analysis and
evaluation ranked according to their importance.
e.g. Nature of project
Level of design completeness

219
Risk factors leading to cost overrun in the delivery of highway construction projects.

3.9 In your experience contingency is usually allocated as:


Per item basis
Associated with main project components
Bottom line of project estimate amount
Other---define.

3.10 Please list four of the most frequent caused errors, mistakes, omissions in project design
estimating.

3.11 What are four main problems or constraints encountered in project design estimates?

3.12 What is your percent confidence in the expected accuracy level of project design estimates
for the following?
Roads
Bridges
Miscellaneous (road related)

3.13 Do you have any comments on how to improve total project estimates and how to achieve
this?

3.14 What is your ideal profile of an expert project design estimator?


(background, experience, skills, training, etc)

Section 4: Project Delivery

4.1 In your experience, what percentage of projects is usually delivered as:


Design-Bid-Build
Design and Build

Other (specify)

4.2 What percentage of projects is usually delivered as:


Schedule of Rates Contracts
Lump Sum Contracts
Alliance
Other (specify)

220
APPENDIX C

Section 5: Other:

5.1 Would you like to participate in a personal interview to expand your answers or provide
more
nformation about total project design estimating?
Yes
No

5.2 Any other comments you wish to provide:

Please return this completed questionnaire to:

Garry Creedy
Queensland University of Technology
School of Construction Management and Property,
Level 4, L Block, Gardens Point Campus
GPO Box 2434,
Brisbane 4001.
or
Fax 38641170

Version 1.0 dated 7/12/2004

221
Risk factors leading to cost overrun in the delivery of highway construction projects.

222
APPENDIX D

APPENDIX D
Completed Questionnaire details of NGT membership

223
Risk factors leading to cost overrun in the delivery of highway construction projects.

Questionnaire:

Date of Completion: 14/12/04..

Dear interviewer,

The aim of this questionnaire is to elicit expert information on the process of preparing total
project cost estimates at the time of design, ideally in road construction.

For the purpose of this questionnaire and research, the total project cost estimate includes the
estimated costs of all component activities from the initiation of the project proposal to
finalisation. This total project cost estimate is usually prepared at the design stage of a
project and can often include the costs of the following:

conducting investigations and developing the design


detailing the design
acquiring land
altering public utility plant
construction
project administration, and handover

The information supplied in this completed questionnaire will be used for broad research
purposes only.

All specific company and interviewee information will be kept confidential at all times.
Only generalised analysis of the information contained within this completed questionnaire
will be utilised in the research process.

Regards,
Garry Creedy
7 December 2004

224
APPENDIX D

Section 1: Company Information

1.1 Company Name (optional):


Department of Main Roads, Queensland
1.2 Volume of Construction Work/year in A$ 500+m.
1.3 Predominant activity for company: Project Owner/Client 50%
General Contractor 50%
Consultant
Other
1.4 Describe types of projects predominantly involved in:
Road and Bridge Construction
Road Rehabilitation and Maintenance

Section 2: Information about Interviewee

2.1 Name (optional)


1.
2.
3.
4.
5.
6.
7.
2.2 Phone contact/email (optional)
2.3 Related Qualifications
1. Associate Diploma Civil Engineering, Diploma in Business Admin.
2. Bachelor of Engineering. PhD
3. Bachelor of Engineering (Civil). Diploma in Business Administration
4. Bachelor of Engineering (Civil). Bachelor of Economics.
5. Bachelor of Engineering (Civil).
6. Bachelor of Engineering (Honours). Master Engineering Science
7. Associate Diploma Civil Engineering. Master in Business Admin.
2.4 Years employed in company
1. 41
2. 35
3. 32
4. 39
5. 14
6. 17
7. 40
2.5 Related experience:

Estimating (years)
2. 10
3. 10
4. * embodied in construction and maintenance
5. 14 (Continuous, ongoing role)
7. 5
Design (years)
2. 17
3. 10
4. * embodied in construction and maintenance
5. 1
6. 12
7. 5

225
Risk factors leading to cost overrun in the delivery of highway construction projects.

Construction (years)
1. 10
2. 3
3. 10
4. 10*
6. 2
7. 15
Management (years)
2. 16
3. 15
4. 29*
5. 6
6. 3
7. 15

(This section refers to the whole of the project estimate not just the construction estimate.)
Section 3: Total Project Estimating

3.1 In your opinion, what are the four most important factors/issues in project estimating?
2. Detailed geotechnical investigation. Competent design. Detailed quantity
calculations. database for tender bids on similar projects over >5 years.
3. Knowing and understanding project scope. Historical costs.
Identification and management of risks.
4. Knowledge of construction processes/techniques/materials etc.
Understanding the real needs of the project. Clients expectations. Risk
assessment.
5. Knowing the scope of the project. Suitable allowances for risks and
contingencies. Breaking the project down into significant detail to
estimate cost of works; i.e. not using $/km. Using correct items and
quantities in breakdown.
6. Understanding the design and specifications, and knowing what work
the designers intend to be included in each of the items in the schedule.
Having sufficient contingency where the nature of the work is not well
understood. Experience not only in estimating but in all phases of the
project eg. planning, design, and construction. Local knowledge of
materials, conditions, prices.
7. Completeness of scope. Ensuring estimate is in out-turn $s. Adequate
time allowed for estimating costs. Experienced estimators.

3.2 In your experience, what role does value engineering and/or value management play in total
project cost estimating and also in design?
2. Clarify scope. Set design performance standards.
3. Very important.
4. Identifying likely issues/problems and bringing together a broadly based
view on likely solutions; i.e. facilitating an understanding across the
supply chain.
5. Useful in ensuring scope is adequately understood and defined.
7. Allows completeness of adequate design and completeness of scope.

3.3 What are the estimating methods most often used in your organisation for total project
estimating at the design stage?
e.g. parametric 7.
factored

226
APPENDIX D

basic cost 3. (For Commercial use)


5.
unit rate 2.
3. (For Corporate use)
4.
5.
7.

Explain.
4. Contracts are basically schedule of rates type. Separation of the
organisation into purchaser/provider has resulted in less ability of the
client to do basic cost estimating.
5. Mainly unit rate. Some major items are calculated using basic cost.
Many staff have insufficient experience to effectively use basic cost
estimates.
7. Bridges initial estimate using parametric method. design estimate for
road and bridge projects use unit rate and bill of quantities.

3.4 Do you use a computerised system for project design estimating?


2. Standard schedules. Quantities calculations. Databases for tender
prices.
3. No
5. Use an in-house system for assembling the schedule. The program will
accept unit rate but has no capability to assist with basic cost estimates.
7. No

Also, describe in brief any off-the-shelf software utilised.


5. RoadTek use Expert Estimator
7. P3 used on larger projects for schedule, etc.

3.5 Describe the typical project scope definition information available to you for project design
estimating.
2. Bridge fixings width, length, height of bridge.
3. Extent of physical project scope. Survey data. Planning layouts.
4. DMR is introducing a formalised project management approach with a
tight scope definition profile.
5. Extremely variable. Often fairly limited at concept phase, usually fairly
well defined by detailed design.
7. Services. resumption requirements. Planning studies. Native title
clearances. Consultation outcomes.

3.6 What approach do you use for contingency analysis in project design estimates?
Probability based 4.
Historical values 2., 7.
Decision analysis 3.
Experience based 2., 3.
Other (explain)
5. Risk identification. Risk register. Assessment. Management plan.
Re-assessment. Likelihood. Potential cost. Contingency pool.

3.7 List items at the project level that you normally include as contingencies?
e.g. - Design allowances
- Force majeure
1. Resumptions. Services Relocation. Administration Costs.

227
Risk factors leading to cost overrun in the delivery of highway construction projects.

2. Remote project location. Non-competitive bids. Variation in founding


levels for substructures. Varition in materials, eg excavation in piles.
Flood delays effects on falsework, cofferdams. Variation in materials
cost/supply shortages. Industry capacity issues on major projects.
Effects of major projects on other (resource competing) minor projects
3. Public utility conflicts. Adverse weather. Unsuitable material.
Community requests for scope change.
5. Needs to be project specific and be reviewed and updated throughout
the project life-cycle.
7. Management reserve for scope increase. Rise and fall costs for contract
process. Contract variations. Services relocation overrun. Extension of
time (Project management costs increase). resumption accommodation
works additions to severance properties.

3.8 List the main factors that you take into account for contingency analysis and evaluation
ranked according to their importance.
e.g. Nature of project
Level of design completeness
2. Nature of the project
3. Impact of risk to project scope, duration, cost (in $ terms, not as a
percentage). Probability of being able to mitigate the risks.
5. Identified risks are rated according to: a) the likelihood of the risk
occurring, b) the effect to the project id the event (risk) occurs. This
gives us a ranking. Risk management is considered for all extreme, high
and medium risks.
7. Type of delivery contract. Constructability.

3.9 In your experience contingency is usually allocated as:


Per item basis 3.
Associated with main project components 2. Mainly
Bottom line of project estimate amount 2. Sometimes. 7.
Other---define. 4. There is the question of what you mean by contingency v-
allowance for risk. i.e. you can build in some risk allowance on
an item. You can also add a contingency allowance to your final
figure.
5. Combination of per item and main project components. Some
risks are associated with a single item. Others affect a number of
items whilst others are not directly related to any items in the
schedule.

3.10 Please list four of the most frequent caused errors, mistakes, omissions in project design
estimating.
1. Amount of unsuitable material. Pipe length specified. Concrete quantities. No
allocation for rideability bonus or rise in the cost of bitumen.
2. Errors in quantities. Misinterpretation of borelogs/foundation reports. Lack of
data on similar projects eg remote location projects. Lack of market suppliers
one bidder, so no competition.
3. Overlooking whole items of cost eg. resumptions, public utilities, removal of
existing bridge of pavement after new installation. poor and conflicting scheme
documentation (plans-V-specifications). Scope increase. Using inappropriate
historical data.
4. Quantity errors. Constructability issues. inconsistent specifications.
5. Final scope of project is not what was originally estimated. Very imprecise
global estimating used at concept phase and this determines project budget.
Inadequate or no contingency allowance. Higher than expected cost escalation.

228
APPENDIX D

6. Use of historical rates not appropriate to the scale of the works. Inexperience.
Time pressure to fast track projects can lead to design errors.
7. Quantity errors. Inexperienced estimators. Poor project scope definition. Plan
and document errors in contracts.

3.11 What are four main problems or constraints encountered in project design estimates?
2. Estimates made several years ago and not updated. Rapidly changing market
prices when construction program increases rapidly.
3. Lack of input from construction experts. Pressure of time. Misuse of expert
systems.
4. Quantity errors. Constructability issues. inconsistent specifications.
5. Political pressure to produce estimates in unrealistic short timeframes. Political
influences and lobby groups resulting in change in project scope.
6. Insufficient geotechnical investigation/lack of understanding of ground
conditions. Lump sum items for traffic management and environmental
management different understanding of what is required. Need to break these
down into sub-items. In a hot market, prices can rise rapidly due to demand
exceeding supply. Design estimate may be out of date by the time the job is
tendered.
7. Time allowed. Contracting climate at time of tender v- time of estimate. Time
delay for approvals to project elements. Inexperienced estimators in road and
bridge projects.

3.12 What is your percent confidence in the expected accuracy level of project design estimates
for the following?
Roads
1. 75%
3. Within +20% and -5%.
4. Within +- 10% for design estimates
5. +- 10% at detailed design.
7. 85%
Bridges
1. 90%
2. Coefficient of variation 10% on standard projects.
3. Within +15% and -5%.
4. Within +- 10% for design estimates
5. +- 10% at detailed design
7. 95%
Miscellaneous (road related)
3. within +30% and -5%.
7. 85%

3.13 Do you have any comments on how to improve total project estimates and how to achieve
this?
1. Use a quantity surveyor who specialises in Road/Bridge estimates.
2. Adequate geotechnical info. Competent design. Accurate schedule of quantities.
3. Knowing and understanding project scope. Historical costs. Identification and
management of risks.
4. Better risk assessment. Better documentation i.e. plans, specifications, etc. Use
of basic cost estimating by client. Adequate time allowed for design. Clear scope
definitions.
5. Ensure project scope is adequately defined. Allow sufficient time and resources
to estimate the cost of the project.

229
Risk factors leading to cost overrun in the delivery of highway construction projects.

7. Value engineering. Peer review of designs and of estimates. Freeze scope of


project at time of tender. Reduce provisional quantities in bill of quantities
schedule.

3.14 What is your ideal profile of an expert project design estimator?


(background, experience, skills, training, etc)
2. To have done both design and construction supervision of many similar projects
over 15+ years. Has access to up-to-date tender data.
3. It is a job for a team, including experience in design, construction, relationships
with suppliers, contractors. (Relying on one will end up in errors).
4. Knowledge and experience in construction. Understanding of contracts and
contractual processes. A person with a good level of attention to detail.
5. Project engineers are technicians with a number of years of construction.
6. Someone who has extensive estimating experience but who has also had some
experience in the other phases of the project eg. involvement in design activities,
use of specification, on site supervising construction. Someone who has
estimated for a range of different project sizes. Someone who has local
knowledge including local prices, availability of materials, local conditions.
7. Civil design background. Site draftsman experience. Good time management
skill. Good database management skills. Trained in and uses project
management software for probability scheduling and estimating.

Section 4: Project Delivery

4.1 In your experience, what percentage of projects is usually delivered as:


Design-Bid-Build
2. 95%
3. 90%
4. 95%
5. 98%
7. 97%
Design and Build
1. One design-construct-maintain project in metropolitan area south
Brisbane. One Design and construct in metropolitan area of north
Brisbane.
2. A few major projects.
3. 8%
4. 5%
5. 2%
7. 2%
Other (specify)
3. Alliance 2%
7. 1%

4.2 What percentage of projects is usually delivered as:


Schedule of Rates Contracts
1. 100% in Metropolitan Brisbane
2. 95%
3. 98%
4. 98%
7. 99%
Lump Sum Contracts
3. Nil
4. 1%
7. 1%

230
APPENDIX D

Alliance
2. 5%
3. 2%
4. 1%
5. 5%
7. 1%
Other (specify)

Section 5: Other:

5.1 Would you like to participate in a personal interview to expand your answers or provide
more
information about total project design estimating?
Yes
No

5.2 Any other comments you wish to provide:

2. The issue in MRD appears to revolve around our inability to develop a program
over several years, and accept that initial project concept estimates can vary
widely from final project cost, and that the estimate should be refined through
the following stages: Concept Estimate; Preliminary Design Estimate; Final
Design & Documentation Estimate; Contractors Tender Price and
Contingencies Estimate. Being realistic about the project development and cost
development phases, and adjusting the RIP to fit, would solve many problems.

4. I think you need to send the questionnaire to hands on people. I am too far and
too long removed from the detail to effectively answer the questions accurately.

Please return this completed questionnaire to: Garry Creedy


Queensland University of Technology
School of Construction Management and Property,
Level 4, L Block, Gardens Point Campus
GPO Box 2434, 4001.
Fax 38641170
Version 1.1 compiled on 15/04/2005 to incorporate seven detailed responses.

231
Risk factors leading to cost overrun in the delivery of highway construction projects.

232
APPENDIX E

APPENDIX E
Client risks in highway project delivery

233
Risk factors leading to cost overrun in the delivery of highway construction projects.

The following client project risks which have prevailed in historical highway projects and
caused significant cost overruns.

Detailed descriptions of those risks are included here so that project estimators and project
managers can be made more aware of their potential to impact costs in highway project
budgets.

A Project acceleration requirement


This is a requirement imposed on the project by the client for the contractor to vary their
working schedule. This can be imposed for a number of reasons. The most pressing would
be because of severe disruption to the motoring public either because of ongoing, severe
traffic congestion during the construction not identified pre-contract stage, or because of the
sudden loss of a facility such as a bridge washout or landslide that necessitated accelerated
effort by way of longer working hours or even round-the-clock effort. In certain agreed
cases, the costs associated with such acceleration direction would be recovered from the
client by the contractor.

C Constructability difficulty costs


This project cost can occur where the tender price is based on an approved construction
process or sequence and this has to be varied by the client for certain reasons. The most
prevalent cause of this cost can be that the foundation design criterion was not achievable
due to unforseen site conditions. Also, constructability difficulty costs can be incurred in a
project where certain traffic arrangements are required to be maintained. This can then
severely restrict the economy of scale of certain construction processes, such as paving runs
as well as concrete placement in drainage and bridge structures.

Poorly coordinated designs, plans and specifications can lead to contractors claims during
construction because of conflicting project information that, when clarified, causes the
contractor to perform differently than was planned at the time of preparing the bid.

When multiple contractors are planned to be working simultaneously on a project site, the
designer should develop a site utilisation plan that will define the area(s) each contractor has
jurisdiction over and how to accommodate the other contractor(s). If this has not been done
properly, there will be contractor claims usually based on delays that will result in costs to
the owner as well as potential time delays in achieving project completion.

At the project estimating stage, studies are often required for significant items of work to
determine the feasibility and efficiency of alternative production methods. In estimating the
construction component of a project for example, the project manager may need to examine
the mass haul diagram for earthworks to evaluate haul distances, borrow and spoil
requirements and the most effective construction fleet for the particular site conditions.
Similarly, for major road projects in high traffic areas, it may be necessary to develop traffic
management and construction-staging plans in order to evaluate traffic management
requirements.

CT Constructability under traffic


Increases in project costs resulting from carrying out certain road construction processes
under flowing traffic conditions can be substantial in highly trafficked areas. While generally
all contracts for projects in such situations are specific in detailing the construction risks of

234
APPENDIX E

process continuity and efficiency, situations can arise in contracts where the contractors
obligations are compromised by client instructions and directions that require the contractor
to incur costs other than provided for in the contract provisions. Limiting a contractors work
schedule to out-of-peak traffic times as a result of unforseen peak hour traffic congestion is
one example where lower daily productivity and additional project costs might need to be
borne by the client. In urban areas, even say a traffic problem occurring on a nearby (arterial)
road can force traffic through construction projects which normally would not have attracted
higher flows, resulting in subsequent traffic congestion and safety issues through the project
site.

Side tracking of traffic is some urban and rural projects is also a safe and efficient means of
managing traffic during construction. Again, there are times when contingent emergencies or
processes can occur that will disrupt this orderly traffic management strategy that results in
construction processes having to be carried out under flowing traffic conditions. This may be
outside the control of the contractor and then could be deemed the cost responsibility of the
client.

D Design/project scope change


This is a general category into which all non-defined project scope changes that increase the
cost are allocated. They exclude the specific areas of: drainage, environment, design error,
pavement materials and pavement depth, earthworks preload, changes to pavement subgrade
and changes as a result of physical site safety audits.

This variation category includes such design scope changes as vertical and horizontal
alignment changes that can result in changes in quantities, as well as rework. It can include
scope changes in traffic guardrail, traffic signage and kerb and channel and traffic island
changes. Changes in this category are generally limited to one or a number of locations
within the project and would not generally include a major design change such as the
addition of further traffic lanes to the full length of the project.

DE Design scope change environmental issues


Large costs can be incurred in environmental assessments that not only include the client but
also a large amount of public involvement. If the process is not executed properly, then it can
lead to further costs and schedule delay in projects. Environmental assessment is becoming
more complex and requires experienced professional input into project designs. Over the
years, environmental laws concerning toxic and contaminated wastes in the ground have
required project owners to be careful about construction in such areas. Where environmental
audits have been inadequately carried out, the cost of clean up during construction can be
excessive. Even when a site environmental audit has been carried out during the design and
pre-construction stages, it is possible to miss pockets of contamination that can lead to
additional project cost to the client. It has been found prudent for a project owner to identify
a disposal site and to define what treatment and disposal procedures are required to
ameliorate the situation should they be discovered during construction. Such discoveries
would almost surely require the contractor to stop work in those areas until a plan was
worked out if there had not been the pre-arranged procedures in place at pre-bid. It can also
leave the project owner in a vulnerable position when negotiating the cost of disposal. This
would almost surely lead to significant project cost overrun.

235
Risk factors leading to cost overrun in the delivery of highway construction projects.

DD Design scope change drainage


This category is for design scope changes specifically related to drainage and can include the
addition of drainage structures where pre-existing structures are deemed to be inadequate
upon detailed site inspection. In many cases, detailed site inspections cannot be adequately
carried our without heavy excavation equipment. In some cases, especially where the design
calls for the extension or addition to existing drainage structures, the condition of the
existing drainage structure is not fully revealed until excavation work is carried out in the
vicinity of the structure. Site investigation can then reveal substantial deterioration to the
extent that the existing structure requires full replacement or substantial repairs. Where
existing drainage structures have been constructed of corrugated helical steel pipes, the
inverts have often rusted through, even resulting in scouring out of fill behind the structure.
In most cases, this damage is not obvious at the time of site investigation for design because
inverts can be permanently under water, or heavily silted.

Drainage design scope changes can occur when an increase is required in the flow capacity
due to changes in hydraulic gradients due to conflicts with underground service installations
or other expensive obstructions. In some urban and semi-urban areas, changes in zoning in
upstream catchments can result in older drainage designs requiring redesign due to revised
runoff coefficients as a result of planned land use.

A small factor that sometimes requires design consideration is when new metric drainage
installations are required to join to very old imperial drainage pipes and cells. The design
modifications are small, but real and often overlooked by designers.

DF Design scope change design error


This category is for design scope changes specifically related to errors found in design or
documentation during the construction step. Such errors can result in substantial cost to the
client in the form of rework of completed works. If the design error is substantial, such
rework may even involve demolition of completed construction. This category does not
include design errors in drainage works

DM Design scope change pavement materials/depth


Pavement materials: This category occurs when there is a need to change the specified
pavement materials to a different specification. This can happen for a number of reasons.
Primarily, a change in material could be required where the excavated pavement box might
have poor drainage and there is a possibility for moisture to build up due to difficulty in
draining adequately. It may be more economical to improve the specified material quality
rather than install additional pavement drainage. This occurs sometimes in subgrades of rock
cutting where cement stabilisation might be ordered in lieu of drainage blankets or additional
sub-soil drainage lines. In some urban construction, specified granular paving materials may
be changed to asphalt material where construction is required under heavy traffic. As well,
there is the potential for granular pavement material to disperse under heavy turning traffic
or create undue dust where the material cannot be kept wet due to then slippery road
conditions that could cause traffic accidents. There also may be the need to install temporary
traffic white lining for traffic directions and control, even overnight, which requires
installation on a sound pavement surface.

236
APPENDIX E

Pavement Depth: Changes in pavement depth occur when field measured strength of
pavement subgrades are weaker than the assumed strength that the pavement designs were
based on. Revised pavement designs usually result in increased pavement depths. In most
cases, this also requires the raising of the highway vertical grade line by the same amount as
that of the pavement. Minor regrading back down to original design grade levels at bridges
and new drainage culverts may be required if the pavement redesign extends over a
substantial distance.

DPL Design preload requirements


Earthworks preload is usually required in embankments, especially where differential
settlement cannot be tolerated, such at embankment approaches to bridge structures. Change
in preload design is usually as a consequence of an embankment that is under preload not
performing as expected, usually with slower settlement rated than calculated. The design
considerations then usually require either an increase in the preload height, a further waiting
period until design settlement is achieved or a redesign to the grade line to allow for further
settlement during and possibly after construction completion.

DSG Design change to subgrade


Design change to subgrade can be brought about by the need to regrade upwards of
downwards due to some limiting constraint, such as preserving clearance to existing
underground services, bridge clearances, level crossing level compatibility etc.
Where unsuitable material is encountered at subgrade, there could be an option to carry out
further excavation with an appropriate pavement redesign.

DSA Design scope change safety audit requirement


This change in design scope can be brought about by the need to carry out a safety audit on
parts of the road under planning or design because of safety concerns about certain aspects
of the road that may not have been considered in the original project. Issues such as
ineffective guardrail installations, signage and pavement roughness or shoving can be
adequate reasons for increasing the project scope. A safety audit can also identify aspects
such as visibility and stopping distances that could warrant additional works being carried
out that were not considered in the original design brief. Existing pavement slipperiness and
pavement drainage are two further considerations that may require scope changes

EU Extras unspecified
This is a category that is intended to be a catch all for all cost increase factors that cannot be
categorised elsewhere due to inadequate project documentation or because of there being
large number of small project variations.

G Government initiative employment continuity


This category is to accommodate the additional costs associated with a Government decision
to have the project carried out by a certain workforce so as to provide employment
continuity to that particular group. The Government has a regional development policy that
guarantees a certain level of road construction funding to certain regional areas. These funds
are normally allocated through certain Local Governments specifically for use on road
construction and maintenance projects. In some instances, the cost of delivering a project
under this Government initiative can lead to additional costs above what might be budgeted
for had the road project been delivered by open tender. This is a deliberate strategy

237
Risk factors leading to cost overrun in the delivery of highway construction projects.

employed by Government in certain instances where, otherwise, the option might be


permanent job losses in that region.

GCD Government initiative contribution by developer


GCLG Government initiative contribution by Local Government
GCR Government initiative contribution by rail
These categories are to accommodate the instances where additional works are agreed to be
included into a road project that should be funded by another organisation. In certain
circumstances, there are agreed firm upper limits that can be imposed on these organisations
for the incorporation of these specific works. In limited cases the actual costs of such
incorporated works can exceed the agreed contribution and then the project estimate will be
exceeded and project overrun costs incurred by the client highway organisation.

H Cultural heritage issues


This category identifies the additional costs associated with cultural heritage issues
impacting on the particular project. The Queensland Heritage Act 1995, and the more recent
Queensland Aboriginal Cultural Heritage Act 2003, requires certain steps, consultations and
clearances be sought and obtained for the road reserve for proposed highway and bridge
projects. This consultation period can be excessive in some instances where there are
complex issues to be resolved and which can lead to additional unplanned costs.
Additionally, there can be stringent requirements placed on the design and construction steps
of the project for the identification and preservation of heritage sites, artefacts etc. that can
add significant costs to redesigns within the project. Such additional costs have not always
been identified and incorporated in project estimates. Instances can occur during the project
construction step where certain cultural heritage issues have been revealed for which no one
had knowledge. The project was then required to deal with such issues in a defined and
thorough manner. In some instances, such occurrences during construction can require
substantial redesign of project elements and additional heritage clearances.

LD Latent condition requires design change


LR Latent condition rock encountered
LSG Latent condition additional stabilising
LUS Latent condition removal and replacement of unsuitable material
These risk factors are a grouping of latent conditions that can occur when constructing a road
project. There are two types of latent conditions. Type 1 is a condition not shown or
improperly shown on the project plans or documents that substantially alters the pre-bid
anticipated performance of the contractor through delays, reduced productivity impossibility
of performance, suspension of work or extra works to fix or solve a situation. Type 2 is a
condition not normally found in the performance of work and thus not normally
contemplated by a reasonably prudent contractor in bidding work as planned and specified in
the contract. These unforseen site conditions can be very subjective, hard to document and
difficult to validate.

Highway construction contracts generally contain unforseen, latent site condition clauses
that spell out the circumstances under which they can be deemed to be additional to the
contract, and thus incur additional client costs. Four discrete latent condition occurrences are
identified and described below:

238
APPENDIX E

1. LD Latent condition requiring design change: This includes the discovery of any
unidentified underground obstructions that require modifications to the design. This
can include modifications to new drainage designs and partial to full foundation
redesigns to structures due to unsuitable foundation conditions. This can include
increases or reduction in foundation levels that can lead to adjustments to the
physical dimensions of structures, etc.
2. LR Latent condition rock encountered: This risk factor is self explanatory and
can occur in earthworks operations in cuttings with the presence of rock bars which
may not have been identified by a site inspection or bore log. Rock is normally
defined as sound and solid mass and of such hardness that it cannot be loosened or
broken down by a certain defined size and capacity of excavation equipment under
the assessment of the client. Unrecorded rock outcrops can occur in excavations for
drainage structures, underground ducting etc. and such installations might not be
able to be raised or deviated to miss the obstruction.
3. LSG Latent condition additional stabilising: During the process of new
pavement construction or the strengthening an existing pavement with a structural
overlay of paving material, an assessment should be made of the strength of the
insitu subgrade or sub-layer material so that the design strength of the paving layer is
not exceeded during the pavement service life. In most cases, in-situ testing against
the design axle loading, on which the pavement depth is designed, is carried out.
During the construction process there is a risk that the exposed subgrade material
can test weaker than its design assumption. In such a case, the in-situ strength of
such material can be improved by the addition of cement or lime by in-situ
stabilisation of the subgrade material. This process has the advantage that the design
pavement depth can still be installed without the need to regrade the pavement
levels.
4. LUS Latent condition removal and replacement of unsuitable material: This
process is used to overcome situations where foundation materials for pavement,
drainage structures and structures are found to be inferior and the material is ordered
to be removed to a specified depth and replaced with material of a certain quality. In
some situations, the knowledge of the presence of unsuitable material can be
ascertained by bore probes or other testing methods and adequate provision made in
the schedule of quantities to cover such treatments. In cases where none or limited
testing is carried out in the design stage, then it is appropriate to include only a
nominal provision in the quantities to cover the risk of discovering and having to
replace unsuitable material. Usually, contract provisions allow for such variations as
a cost to the client.

MA Material cost increase asphalt


MB Material cost increase bitumen price
ME Material cost increase earthworks
MP Material cost increase pavement materials
1. MA & MB Material cost increases asphalt and bitumen prices: There are a number
of road making components for which the manufactured cost or basic cost can vary
substantially from the time of an estimate through to its incorporation in the project.
One such major component is bitumen which is used in bitumen spraying as well as
in the manufacture of asphalt. The price of bitumen is strongly linked to the price of
oil and can fluctuate widely over time. Provision for material cost adjustments are

239
Risk factors leading to cost overrun in the delivery of highway construction projects.

usually made in projects for the risk of price increases but instances can occur where
higher than predicted price increases can impact on the final cost of bitumen.
2. ME Material cost increases earthworks: Road designers generally endeavour to
obtain a balance between the volumes of excavated material as opposed to the
compacted volume of material required for fill for roadway embankments. Instances
can occur where the risk of not achieving an economic balance can lead to large
unplanned costs for either the disposal of excess material or the cost of importing
additional material onto the project. The major reason for such a net imbalance is that
certain excavated material may not be able to be incorporated into the project as fill
because of its inferior quality or because of its contamination from some site source
that was not known at the time of design. Where measured quantities of both
excavation and fill materials substantially differ from the scheduled quantities, then
there can be circumstances demonstrated when additional costs may need to be borne
by the project.
3. MP Material cost increase paving materials: Pavement design changes can
substantially increase paving material volumes which can lead to the risk of increased
pavement materials and hence increased costs. In addition, for certain project
locations, there may be no economically suitable source of paving materials and
hence the material then has to be transported large distances from established
quarries to the project. In some rural projects, there may be raw material suitable for
paving gravel production close to a rural project but no suitable crushing equipment.
It may then be a matter of establishing crushing facilities at the material source, if
suitable equipment can be enticed there. In this case, the volume of paving material
to be produced can be the important economic factor in determining the supply price
of the paving material. Either supply option can be significantly more expensive than
conventional quarries that are close to projects. This can have significant influence
on the final cost of a project.

MQ Material process/ quality issue


The cost of having to rework or worse, replace material due to poor quality or process issues
can be a real risk factor that can lead to significant cost overruns in projects. Contract
provisions usually protect the position of the client in not incurring additional costs due to
the contractors supply of poor material quality or processes. However, there can be
occasions where material is supplied or provided by the client as a provision of the contract.
The contractor is then required to incorporate that material into the project. If the material is
found to be deficient in quality, then there may be a case where the client, and hence the
project, has to bear additional costs to replace, rework or modify the supplied materials. The
supply of material by the client can occur when there is expected to be considerable lead
time required for the supply of, say, paving gravel in stockpile in remote areas and some
forms of pre-cast bridge components, such as concrete piles and girders. Material is
generally only supplied by the client when there is the risk that long lead times in
procurement of specialist components or material in remote locations will severely impact on
the desired completion date. In some instances in remote locations, paving material is
stockpiled or concrete bridge components can be supplied at the job site by the client well
prior to the letting of the highway construction contract.

N Contract failure new contract establishment costs


Contractor default is one of the most costly events for a project owner. An existing road
contract can fail and the owner is then required to terminate the contract under the defined
steps of the contract. The outstanding contract work can be re-let as a new contract or can be

240
APPENDIX E

completed using a dedicated work force on a cost-plus basis. The method of completing the
contract works will generally be determined by the client by taking into account factors such
as the amount of works outstanding, the potential for deterioration of the already provided
works and public and works safety provisions. A number of factors can lead to a contract
termination, however there are also procedures usually adopted to minimise the risk of such
an occurrence. These include:
pre-qualification of contractors that includes financial capability checks
tender evaluation procedures to check that submitted contract rates are commercially
realistic.
Provisions to protect the client in the event of a contract failure can include the provision of
an insurance bond on the value of the work and/or the retention of a certain percentage of
progress payments during the conduct of the contract. The additional costs to a project as a
result of a contract failure usually includes the need for a complete and certified measure up
of completed works and works in progress, the making safe of the works, ongoing traffic
control provisions where the public traverse the project, legal costs associated with, say,
bankruptcy of the contractor, re-documentation and calling of a new project contract. All
these activities will consume the time of a project manager and administration support and
can add up to a considerable unplanned project cost.

O Remote location costs


In remote rural project locations, there is a need to provide adequate accommodation for
project workers. Sometimes, this can be an addition to normal project on-costs and hence
factored into project costs. When projects extend past their estimated completion dates, then
these remote location costs such as accommodation costs can add substantially to the
projects budget estimate.

P Project administration cost increase


When a project extends past its planned duration, then project on-costs can be incurred that
were not otherwise planned. Other factors can also contribute to an increase in project
administration costs, such as:
highly litigious contractor that embarks on claims to recover costs for various aspects
of the contract
concern over quality control processes in the project that calls for increased audit and
process surveillance activities on the side of the client
ongoing community consultation and additional public relations processes where
projects need to be managed in complex urban environments or under increasingly
heavy traffic congestion and pedestrian safety aspects
ongoing environmental or cultural heritage issues that were not anticipated to extend
into or present during the project delivery step.

Q Quantity increased measure


In unit rate road contracts, the final value of the project contract is determined from the final
measurement of the scheduled work that forms part of the contract. Site measured quantities
can vary substantially from scheduled quantities for a number of reasons, including:
that the original quantity was incorrect
errors in the initial measuring ground/foundation levels
increases in ordered works, dimensions and measurements
revised pavement thicknesses.

241
Risk factors leading to cost overrun in the delivery of highway construction projects.

All net increases in measured quantities can have a substantial effect on the final cost of a
project. Initial inaccurate quantity take-offs for schedule of rates contracts can mislead
contractors resulting in costly errors in bid pricing in other areas such as quality assurance
requirements.

R Resumption/accommodation works
Where private land is required on which all or part of the project is to be built, the land can
be purchased outright from the owner or can be compulsorily acquired under the powers of
the government. In the latter case, the land owner also has recourse to an appeal mechanism
that can take a considerable period of time. The outcome of this appeal mechanism can in
some circumstances increase the cost of acquiring the land for the project. In addition to
compensation for the taking part land parcels, the government is obliged to carry out
accommodation works adjacent to the resumed land so as not to affect the amenity of that
land. This can be costly and can increase project costs over that estimated at the time of
commencement of any land procurement.

Property acquisition costs can be impacted by a design that does not consider the effects that
the project has on adjoining properties. Poor or restricted access to residual and adjacent
properties can have a direct bearing on the property acquisition cost and on the potential
consequential damages to adjacent properties. Construction sequencing required to build a
project that causes multiple disruptions to the activities on abutting property can often result
in claims and/or litigation by the adjacent owners to recover damages to his operations.

S Services relocation costs


The relocation of utilities and services can be a significant part of projects and in
transportation projects in particular can cause heavy disruption to existing utilities. The road
reserve is also used by services (utility) authorities under their various legislation heads.
While pre-approval is usually required for the service authority to install their particular
facility, this approval usually obliges the road authority to pay for the cost of relocating such
existing services where the new road-design conflicts. The physical relocation work is
usually carried out on an actual cost basis and this can be substantially greater that
preliminary estimated costs. These preliminary estimate costs are what are generally used
when developing road project estimates. Actual cost figures can be greater than estimated
costs for a number of reasons, the most common is workplace safety provisions that requires
workers to sometimes work under potentially dangerous traffic conditions. This can lead to
the requirement to install additional temporary protective measures and/or the need to have
the work carried out at night or on weekends when traffic conditions, and the potential for
danger, may be lessened.

Early and careful planning and coordination with the owners of the affected utilities is the
key to minimising the cost overrun of relocating services and maintaining services to
adjacent properties. Depending on the regulations and agreements that allow the utility
owners to be in their pre-project locations, the cost of relocation could be borne by the utility
owner or the project. Poor coordination of utility relocations (i.e. requiring multiple moves
of the same utility) will result in additional costs that usually have to be borne by the project.
It should be noted that there are circumstances where multiple moves cannot be avoided, and
when recognised by both parties, the cost is usually included in the project budget. It is the
unexpected multiple relocations, which could have been avoided, that have the impact on the
project budget. The project design team usually has a major responsibility to plan for the

242
APPENDIX E

coordination of the utility relocations with the utility owner. This can have a serious effect
on the project budget if it has not been coordinated adequately well in this area.

A utility activity that involves substantial management at the design stage is the locating of
existing utilities and is often shared with the utility owner that has been designated for an
area. Regardless of any shared responsibility, the project designers should ensure that they
are getting the best information available as there can be substantial cost saving when
designing a project with the intention of not requiring relocation of certain types of utilities.
When it is discovered during construction that a utility is in fact in conflict with the
construction, then the cost impact can be large since it often requires the contractor to shut
down activities in that area of conflict or develop some expensive work-around scheme to
avoid the shutdown. In this case, these costs come back to the client who may or may not
seek to have the designer share in paying for the cost. Another utility cost overrun area is the
lack of appreciation of long lead times necessary to procure special materials, equipment, as
well as system testing of the relocated utilities before they can be placed in service.
Telecommunication and power facilities are often candidates that require longer lead times.
When this long lead time requirement is not recognised or not appreciated then there is often
a schedule as well as a cost impact to the client..

SC Specification change
The quality of specified works and/or materials can be varied by the client during the
construction of a project, however this is not done as a matter of course. This can be done to
rectify an error in the specification or drawings. It can also be done to improve the specified
quality of certain material properties that may not perform adequately under anticipated
service conditions. For example, specifications can be changed to vary the specified finishes
on concrete surfaces from wood to steel float finish for durability. As well, finishing
construction tolerances for pavements can be changed to provide improved the completed
running surface finish than that documented. In most cases, where a specification change has
been requested by the client, then it is treated as a variation under the terms of the contract.

TH Contract tender price higher than original estimate


The project estimated cost is based on the forecast tender cost of the construction component
of the project delivery. Where the actual tender cost is higher than the original estimate, then
there is an adjustment required to the project estimate.

TCI Contract tender price increase due to inflation


Contract tender prices can be adjusted for inflation costs for labour and materials when there
are provisions within the contract provisions. The project estimated cost is based on the
forecast tender cost of the construction component of the project delivery and also includes
an estimated allowance for inflation costs. Where the actual inflation costs calculated for the
contract are higher than the original estimate provision, then there is an adjustment required
to the project estimate. Adjustments to contract payments are usually made on a defined
formula which incorporates a monthly Roadworks Input Cost Index (RICI) that is published
by the Australian Bureau of Statistics. Separate adjustments are also made for the cost of
bitumen for works which incorporate predominately bitumen products.

WW Wet weather effects/rework


Because of the nature of highway construction, the works can be exposed to prolonged wet
weather that can have an adverse effect on construction productivity, especially if substantial

243
Risk factors leading to cost overrun in the delivery of highway construction projects.

parts of a project are saturated from rain. Generally contract conditions shift the risk of the
occurrence of wet weather on to the contractor and the cost of rework are deemed to be
included in the cost of particular construction processes that are contracted. The probability
of the occurrence of rain can generally be derived from the use of historic rainfall charts and
probability. A contractor can also insure against losses from the effects of rain. Where
intense rainfall periods can be predicted, contracts can be let such that the project works can
be reasonably completed outside the windows of anticipated rains. A prudent contractor
would plan to construct those portions of a road project vulnerable to the effects of
prolonged wet weather during periods of lower wet weather probability. Contract provisions
normally provide only for an extension of time to the construction period for wet weather or
its effects. Generally, the contract does not allow for any contractor cost reimbursement for
wet weather. Where there is demonstrated a case of extremely un-seasonal or exceptional
wet weather, then there may be a case where the client may incur such certain extra costs.

244