Professional Documents
Culture Documents
Identify
Program
Manager
Setup
Governance
for PMO
3. Responsibility of project
Need for
PMO manager on component
reporting.
Setup 4. Responsibility of program
Build 18 Management
months
Roadmap
System manager reporting for
programs.
By Puneet Mathur, PMP 24/03/2010 5. Definitions of Traffic light
Figure 2. Process Program Management reporting for executive
Office
dash board.
After this the setting up 6. Common formats for
Governance is very key and vital reporting.
as it would set the pace for
7. Analysis of needs for
building the entire framework. To reporting for executives
setup governance the Program and key stakeholders.
manager should first know what Once the above are in place the
are the projects and programs program manager is all set to
running in the organization. Also is
publish the first governance
she may have to look at if there report for the program
exists a clear definition of what management office.
constitutes a project and a
program. Some organizations Later part of the process is to
have a good setup of Project setup a management system in
management methodologies order for the governance to flow.
however lack the program The management system involves
management methodology. defining how the escalation
Building a framework for Program would happen for Program and
management methodology may project organization and the
also be looked at as part of the performing organization. The
governance process. Project and Governance only provides alerts
program management on project/program performance
framework are some of the for the stakeholders, however the
prerequisites for setting up the actions have to be taken through
governance process. A good a well oiled management system.
governance system for program So unless the functional hierarchy
management office should have is clearly defined the flow of
the following : governance would not happen.
1. Periodic reporting from The subsequent part of the
Projects/components on process comes into play only
triple constraints. when the governance and
management system are
integrated and are in sync with
each other. So after that the
logical step is to build an 18
month roadmap for the program
management office allowing the
executive sponsor and key
stakeholders a view of the major
milestones and deliverables. Even
more mature program
management offices look at
building an audit structure for
projects/components and
programs at a high level. They
could also look at creating the
Benefit realization plans and
Financial reporting plans.
Some people have asked me as
to what is the ideal time of setting
up a Program management
office. This varies and depends on
the size of organization and size
of projects/programs that are to
be the scope of the Program
Management office. A typical
cycle could last for 12 months
and could be customized to
setup key components that the
executive sponsor wishes to see
as part of the Office setup.