ID Task Name Duration Start

2016 2020
1st Quarter 1st Quarter 1st Quarter 1st Quarter 1st Quarter 1st Quarter
Feb Jul Dec May Oct Mar Aug Jan Jun Nov Apr Sep Feb Jul
1 Site Acquisition 6 mons Tue 22/3/16
2 Infrastructure Works 570 days Tue 22/1/19
3 Site Clearance 0.5 mons Tue 22/1/19
4 Earthwork 1 mon Tue 5/2/19
5 Drainage & culvert 4 mons Tue 5/3/19
6 Roadworks -subbase (temporary road) 1 mon Tue 5/3/19
7 Roadworks - Roadbase & surfacing 1 mon Tue 2/3/21
8 Power supply - cabling & substation 12 mons Tue 25/6/19
9 Water supply - piping & bulk meter 6 mons Tue 25/6/19
10 Building Works 500 days Tue 2/4/19
11 Piling 2 mons Tue 2/4/19
12 Substructure 1 mon Tue 28/5/19
13 Superstructure 4 mons Tue 25/6/19
14 Architectural 18 mons Tue 15/10/19
15 External 6 mons Tue 15/10/19
16 Internal wiring & plumbing 18 mons Tue 15/10/19
17 Government & statutory approval 1250 days Tue 6/9/16
18 AVTC & Subdivision 18 mons Tue 6/9/16
19 Issuance of land title 18 mons Tue 22/1/19
20 Building plan approval 3 mons Tue 2/10/18
21 Engineering drawing approval 1 mon Tue 12/6/18
22 Road certificate & Occupation permit 1 mon Tue 30/3/21
23 Sibu water board 1 mon Tue 27/4/21
24 SESCO 2 mons Tue 27/4/21
25 MOH: License & sales permit 3 mons Tue 25/12/18
26 BOMBA 1 mon Tue 27/4/21
27 Professional Consultancy & Serivces 1200 days Tue 22/3/16
28 Subdivsion plan 3 mons Tue 6/9/16
29 Land surveying 3 mons Tue 23/1/18

Page 1
ID Task Name Duration Start
2016 2020
1st Quarter 1st Quarter 1st Quarter 1st Quarter 1st Quarter 1st Quarter
Feb Jul Dec May Oct Mar Aug Jan Jun Nov Apr Sep Feb Jul
30 soil investigation 1 mon Thu 26/4/18
31 Civil & structural 2 mons Tue 17/4/18
32 Architectural 3 mons Tue 10/7/18
33 Mechanical & Electrical 1 mon
34 QS - Tendering & awarding 1 mon Tue 25/12/18
35 Legal 60 mons Tue 22/3/16
36 Accountancy & Secretarial 60 mons Tue 22/3/16
37 Project Management 60 mons Tue 22/3/16

Page 2