Activity ID Activity Name Orig % Start Finish Budgeted Total 2009 2010 2011

Dur Comp CostS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

Int. of Pr. Majid St. with Pr.Mo'hd 921 9.69% 27-Aug-08 A 07-Sep-11 SR137,820,094

Underpass & Bridge Structural Works


Underpas 921 9.69% 27-Aug-08 A 07-Sep-11 SR137,820,094

General Works
Wo 472 100% 27-Aug-08 A 27-Jul-10 SR5,471,500
Preliminary & Mobilization Works 472 100% 27-Aug-08 A 27-Jul-10 SR5,471,500
PMW010 Site Handing Over (Possession of Site) 0 100% 27-Aug-08 A SR0
PMW020 Applied for Work Permit from Muncipality 0 100% 06-Sep-08 A SR0
PMW030 Value Engineering Offer to Muncipality by Huta 0 100% 15-Sep-08 A SR0
PMW040 STOP WORK Order due to Petroleum Pipeline 0 100% 01-Nov-08 A SR0
PMW050 Proposal Approval for Value Engg - Muncipality 0 100% 23-Nov-08 A SR0
PMW060 STOP WORK Order Relese 0 100% 07-Mar-09 A SR0
PMW070 Preliminary Conceptual Design Period 59 100% 08-Mar-09 A 10-May-09 A SR0
PMW080 Approval of Preliminary Conceptual Design 30 100% 10-May-09 A 16-Sep-09 A SR0
PMW081 Preliminary Conceptual Approved 0 100% 17-Sep-09 A SR0
PMW090 Preliminary Utilities & Site Investigation 5 100% 06-Sep-08 A 11-Sep-08 A SR0
PMW100 Site Survey & General Project Layout Approval 10 100% 19-Oct-09 A 15-Jan-10 A SR0
PMW110 Project Setting Out & Boreholes Layout Approval 7 100% 09-Nov-08 A 21-Nov-08 A SR0
PMW120 Soil Investigation Tests & Reports 30 100% 26-Nov-08 A 25-Jan-09 A SR97,500
PMW130 Detail Design Submittal 90 100% 16-Sep-09 A 14-Feb-10 A SR0
PMW140 Detail Design Approval 26 50% 15-Feb-10 A 27-Jul-10 SR0
PMW150 Modified Earth Retaining Wall Shoring Submittal 12 100% 01-Jun-09 A 04-Jul-09 A SR0
PMW160 Modified Earth Retaining Wall Shoring Approval 7 100% 05-Jul-09 A 25-Nov-09 A SR0
PMW190 Work Permit Approval from Muncipality 0 100% 10-Oct-09 A SR0
PMW200 Traffic Re-routing Plan Submittal 7 100% 08-Mar-09 A 20-Mar-09 A SR0
PMW210 Traffic Re-routing Plan Approval 3 100% 21-Mar-09 A 18-Oct-09 A SR0
PMW220 Occupation of Site 0 100% 19-Oct-09 A SR0
PMW230 Mobilization of Plant & Equipment - Bridge & UP 50 100% 30-Nov-09 A 26-Feb-10 A SR0
PMW240 Kerbstones/Dividers/Side Walks removal 15 100% 20-Jun-09 A 07-Jul-09 A SR0
PMW250 Asphalting of Cable Trenches / Traffic Islands 20 100% 11-Jul-09 A 14-Sep-09 A SR0
PMW260 Traffic Diversion Works, Fence, Temp Lightings 25 100% 19-Oct-09 A 14-Nov-09 A SR5,374,000
Shop Drawings
Drawi 646 0% 22-Feb-09 A 07-Apr-11 SR0
Shop Drawings
Drawi for Underpass 606 0% 22-Feb-09 A 20-Feb-11 SR0
DDU010 Material Submittals 150 75% 22-Feb-09 A 26-Aug-10 SR0
DDU020 Approvals of Material Submittals 150 74% 12-May-09 A 30-Aug-10 SR0
DDU030 Modified Earth Retaining Wall Shop Dwg Submittal 12 100% 24-Dec-09 A 18-Jan-10 A SR0
DDU040 Modified Earth Retaining Wall Shop Dwg Approval 7 100% 23-Feb-10 A 09-May-10 A SR0
DDU050 Raft Tension Piles Shop Drg's Submittal 7 100% 16-Feb-10 A 10-Mar-10 A SR0
DDU060 Raft Tension Piles Sh. Drg's Approval 4 100% 11-Mar-10 A 07-Jul-10 A SR0
DDU070 Tunnel Portion - Raft/Walls/Col/Bridge Submittal 20 50% 25-Apr-10 A 09-Aug-10 SR0
DDU080 Tunnel Portion - Raft/Walls/Col/Bridge Approval 7 0% 10-Aug-10 17-Aug-10 SR0
DDU090 Bottom Rafts / Side Retaining Walls Submittal 50 0% 07-Aug-10 05-Oct-10 SR0
DDU100 Bottom Rafts / Side Retaining Walls Approval 14 0% 06-Oct-10 21-Oct-10 SR0
DDU110 Pump room Shop Drawing Submittal 10 0% 07-Aug-10 17-Aug-10 SR0
DDU120 Pump room Shop Drawing Approval 7 0% 18-Aug-10 25-Aug-10 SR0
DDU130 Miscellaneous Underpass Shop Drawings Submit... 150 0% 18-Aug-10 12-Feb-11 SR0
DDU140 Miscellaneous Underpass Shop Drawings Approval 150 0% 26-Aug-10 20-Feb-11 SR0
Shop Drawings
Drawi for Bridge 269 0% 15-May-10 A 07-Apr-11 SR0
DDB010 Piles & Foundation Shop Drawings Submittal 12 100% 15-May-10 A 29-May-10 A SR0
DDB020 Piles & Foundation Shop Drawings Approval 7 0% 29-May-10 A 27-Jul-10 SR0

Start Date 27-Aug-08 Data Date 08-Jul-10 Actual Work INTERSECTION OF PR. MAJID ST. WITH PR. MOHD BIN ABDUL AZIZ ST.  Date Revision Checked Approved
07-Oct-08 Baseline Schedule
Remaining Work TAHLIA) REVISION # 2 SCHEDULE
07-Apr-09 Revised Schedule
Finish Date 07-Sep-11 Must Finish Date 07-Sep11 Critical Remaining Work (FINAL DESIGN) PROJECT No. B4‐10047(555) 21-Apr-09 Resubmittal with cost correction
Milestone HUTA Hegerfeld Saudia Ltd 28-Jan-10 Time Extension Claim Schedule
(c) Primavera Systems, Inc. Page 1 of 15 08-Jul-10 As per Consultant (MTMM) Commepnts
Activity ID Activity Name Orig % Start Finish Budgeted Total 2009 2010 2011
Dur Comp CostS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

DDB030 Piers & Abutments Shop Drawings Submittals 10 0% 28-Jul-10 09-Aug-10 SR0
DDB040 Piers & Abutments Shop Drawings Approvals 7 0% 10-Aug-10 17-Aug-10 SR0
DDB050 Pot Bearings & Expansion Joint Submittal 12 0% 10-Aug-10 23-Aug-10 SR0
DDB060 Pot Bearings & Expansion Joint Approval 7 0% 24-Aug-10 31-Aug-10 SR0
DDB070 Bridge Deck Shop Drawings Submittal 20 0% 24-Aug-10 18-Sep-10 SR0
DDB080 Bridge Deck Shop Drawings Approval 7 0% 19-Sep-10 26-Sep-10 SR0
DDB090 Prestressing & Tendon Profile Design Submittal 15 0% 19-Sep-10 05-Oct-10 SR0
DDB100 Prestressing & Tendon Profile Design Approval 7 0% 06-Oct-10 13-Oct-10 SR0
DDB110 Other Bridge Shop Drawing Submittals 150 0% 06-Oct-10 30-Mar-11 SR0
DDB120 Approval of Other Bridge Shop Drawings 150 0% 14-Oct-10 07-Apr-11 SR0
Existing Utilities
Uti 791 6.45% 20-Oct-08 A 25-May-11 SR12,090,986
Utilities Ree
Reeouting 573 17.31% 20-Oct-08 A 04-Sep-10 SR4,502,516
EUR010 Utilities Inspection Trial Pits 15 100% 21-Oct-08 A 20-Oct-09 A SR0
EUR020 Light Poles removal & Reinstallation 45 89% 31-Aug-09 A 14-Jul-10 SR95,326
EUR030 Traffic Signals /Traffic Signages Removal & Rein 15 100% 20-Oct-08 A 31-Oct-09 A SR396,240
EUR040 Storm/Sewage Rerouting Design Approval from ... 0 0% 10-Jul-10 SR0
EUR050 Traffic Permission- Storm Water/Sewage Rerouting 0 0% 10-Jul-10 SR0
EUR060 Storm Water & Sewage Lines Rerouting Works 45 0% 10-Jul-10 04-Sep-10 SR2,518,300
EUR070 Initial Dewatering System for the project area 40 20% 10-Jun-10 A 31-Aug-10 SR1,492,650
Precast Fabrication
Fab 255 0% 28-Jul-10 25-May-11 SR7,588,470
PCF010 Fabrication of Underpass Bridge U Beams 75 0% 28-Jul-10 26-Oct-10 SR1,010,100
PCF020 Fabrication of Flyover Bridge U Beams North Side 75 0% 16-Sep-10 13-Dec-10 SR1,014,585
PCF030 Fabrication of Flyover Bridge U Beams South Side 72 0% 14-Dec-10 07-Mar-11 SR1,014,585
PCF040 Fabrication of Ground Bridge Deck Slab Panels 30 0% 10-Aug-10 15-Sep-10 SR894,660
PCF050 Fabrication of Flyover Bridge Slab Panels North 80 0% 16-Sep-10 19-Dec-10 SR830,115
PCF060 Fabrication of Flyover Bridge Slab Panels South 77 0% 20-Dec-10 19-Mar-11 SR830,115
PCF070 Fabrication of Street Light Poles Foundations 30 0% 28-Sep-10 01-Nov-10 SR125,918
PCF080 Fabrication of Precast Storm Water Catch Basins 30 0% 02-Nov-10 07-Dec-10 SR148,242
PCF090 Fabrication of Precast Concrete curbs 45 0% 08-Dec-10 29-Jan-11 SR831,600
PCF100 Fabrication of Precast Parapet 50 0% 30-Jan-11 28-Mar-11 SR68,350
PCF110 Fabrication of New Jersy Conc Barriers 50 0% 29-Mar-11 25-May-11 SR820,200
Underpass Structural Works 497 10.13% 25-Nov-09 A 16-Jul-11 SR70,106,865
Underpass West Side 437 15.29% 30-Nov-09 A 07-May-11 SR30,324,258
Excavation for MERW 388 43.59% 30-Nov-09 A 10-Mar-11 SR6,456,170
UWE010 Exca. of Roads from Sta 0+321.36 to 0+066 (Layer 40 100% 30-Nov-09 A 17-Jun-10 A SR2,487,100
UWE020 Excavation from Sta 0+321.36 to 0+100 (Layer 2) 22 25% 19-Jun-10 A 05-Aug-10 SR1,309,000
UWE030 Excavation from Sta 0+321.36 to 0+180 (Layer 3) 14 0% 24-Jul-10 10-Aug-10 SR916,300
UWE040 Excavation from Sta 0+321.36 to 0+260 (Layer 4) 10 0% 04-Aug-10 16-Aug-10 SR654,500
UWE050 Excavation of Remaining Underpass 25 0% 16-Aug-10 16-Sep-10 SR392,700
UWE060 Exca. with Dewatering of the Underpass 200 0% 13-Jul-10 10-Mar-11 SR696,570
Construction of MERW
Constructi 149 25.4% 09-Mar-10 A 09-Sep-10 SR6,480,000
UWC010 Const. of MERW Sta 0+321.36 to 0+066 (Layer 1... 25 80% 09-Mar-10 A 19-Jul-10 SR972,000
UWC020 Const. of MERW Sta 0+321.36 to 0+066 (Layer 1... 25 80% 09-Mar-10 A 19-Jul-10 SR972,000
UWC030 Const. of MERW Sta 0+321.36 to 0+100 (Layer 2... 20 10% 26-Jun-10 A 07-Aug-10 SR907,200
UWC040 Const. of MERW Sta 0+321.36 to 0+100 (Layer 2... 20 0% 13-Jul-10 09-Aug-10 SR907,200
UWC050 Const. of MERW Sta 0+321.36 to 0+180 (Layer 3... 18 0% 25-Jul-10 16-Aug-10 SR842,400
UWC060 Const of MERW Sta 0+321.36 to 0+180 (Layer 3)... 18 0% 28-Jul-10 19-Aug-10 SR842,400
UWC070 Const. of MERW Sta 0+321.36 to 0+260 (Layer 4... 14 0% 07-Aug-10 23-Aug-10 SR421,200
UWC080 Const. of MERW Sta 0+321.36 to 0+260 (Layer 4... 14 0% 08-Aug-10 24-Aug-10 SR421,200

Start Date 27-Aug-08 Data Date 08-Jul-10 Actual Work INTERSECTION OF PR. MAJID ST. WITH PR. MOHD BIN ABDUL AZIZ ST.  Date Revision Checked Approved
07-Oct-08 Baseline Schedule
Remaining Work TAHLIA) REVISION # 2 SCHEDULE
07-Apr-09 Revised Schedule
Finish Date 07-Sep-11 Must Finish Date 07-Sep11 Critical Remaining Work (FINAL DESIGN) PROJECT No. B4‐10047(555) 21-Apr-09 Resubmittal with cost correction
Milestone HUTA Hegerfeld Saudia Ltd 28-Jan-10 Time Extension Claim Schedule
(c) Primavera Systems, Inc. Page 2 of 15 08-Jul-10 As per Consultant (MTMM) Commepnts
Activity ID Activity Name Orig % Start Finish Budgeted Total 2009 2010 2011
Dur Comp CostS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

UWC090 Const. of MERW for Remaining U-pass 14 0% 24-Aug-10 09-Sep-10 SR194,400


Execution of Tension Piles 34 100% 15-Apr-10 A 24-May-10 A SR175,140
UWT010 Ten-Piles Raft Found'n P31,P30,P28,P26 & P24 14 100% 15-Apr-10 A 30-Apr-10 A SR28,224
UWT020 Ten-Piles Raft Found'n P22,P20,P18,P16 & P14 14 100% 20-Apr-10 A 01-May-10 A SR28,224
UWT030 Ten-Piles Raft Found'n P12,P10,P8,P6,P4 &P2 14 100% 25-Apr-10 A 06-May-10 A SR34,020
UWT040 Ten-Piles Raft Found'n P29,P27,P25,P23 & P21 14 100% 28-Apr-10 A 12-May-10 A SR28,224
UWT050 Ten-Piles Raft Found'n P19,P17,P15,P13 & P11 10 100% 04-May-10 A 20-May-10 A SR28,224
UWT060 Ten-Piles Raft Found'n P9,P7,P5,P3 & P1 10 100% 13-May-10 A 24-May-10 A SR28,224
Pile Trimming
Trimm 31 0% 16-Aug-10 23-Sep-10 SR108,180
UWP010 Exca. & P-Trimming P31,P30,P28,P26 & P24 10 0% 16-Aug-10 28-Aug-10 SR16,560
UWP020 Exca. & P-Trimming P29,P27,P25,P23 & P21 10 0% 19-Aug-10 31-Aug-10 SR16,560
UWP030 Exca. & P-Trimming P22,P20,P18,P16 & P14 10 0% 23-Aug-10 04-Sep-10 SR16,560
UWP040 Exca. & P-Trimming P19,P17,P15,P13 & P11 10 0% 29-Aug-10 09-Sep-10 SR16,560
UWP050 Exca. & P-Trimming P12,P10,P8,P6,P4 &P2 12 0% 04-Sep-10 20-Sep-10 SR25,380
UWP060 Exca. & P-Trimming P9,P7,P5,P3 & P1 10 0% 09-Sep-10 23-Sep-10 SR16,560
Underpass West Section 117 0% 22-Aug-10 09-Jan-11 SR2,218,205
UWS010 Lvelling & Compaction Sta 0+321 to 0+280 West ... 5 0% 22-Aug-10 28-Aug-10 SR1,080
UWS020 10cm Plain Conc. Slab Sta 0+321 to 0+280 West... 1 0% 28-Aug-10 29-Aug-10 SR64,838
UWS030 Waterproofing above Blinding for West Sec. 5 0% 29-Aug-10 04-Sep-10 SR87,282
UWS040 Raft Steel Reinf. Sta +321to+280 West Sec Face1 15 0% 02-Sep-10 22-Sep-10 SR216,450
UWS050 Raft Steel Reinf. Sta +321to+280 West Sec Face2 15 0% 11-Sep-10 30-Sep-10 SR216,450
UWS060 Concrete for Found's Sta 0+321 to 0+280 West S... 1 0% 30-Sep-10 02-Oct-10 SR360,750
UWS070 Curing for Foundation 7 0% 02-Oct-10 10-Oct-10 SR6,494
UWS080 Reinf. Ret-Wall Sta 0+321 to 0+280 West Sec.(Nr- 20 0% 02-Oct-10 25-Oct-10 SR238,223
UWS090 Conc.for Ret-Wall Sta 0+321 to 0+280 WestSec(... 1 0% 25-Oct-10 26-Oct-10 SR231,008
UWS100 Curing for Ret-Walls North West Sec. 7 0% 26-Oct-10 03-Nov-10 SR6,205
UWS110 Reinf. Ret-Wall Sta 0+321 to 0+280 West Sec.(St- 20 0% 10-Oct-10 02-Nov-10 SR238,223
UWS120 Conc.for Ret-Wall Sta 0+321 to 0+280 WestSec(... 1 0% 02-Nov-10 03-Nov-10 SR231,008
UWS130 Curing for Ret-Walls North East Sec. 7 0% 03-Nov-10 11-Nov-10 SR6,205
UWS140 W-proofing/Protection Board on Walls for West Se 20 0% 03-Nov-10 28-Nov-10 SR165,240
UWS150 Backfill b/w Ret wall & Shoring wall Ht=6m(WS) 23 0% 16-Nov-10 13-Dec-10 SR74,375
UWS160 Backfill b/w Ret wall & Shoring wall upt req lvl 23 0% 13-Dec-10 09-Jan-11 SR74,375
West Sec - W1 133 0% 01-Sep-10 07-Feb-11 SR2,216,640
U1W010 Lvelling & Compaction Sta 0+280 to 0+234 (W1) 5 0% 01-Sep-10 07-Sep-10 SR1,080
U1W020 10cm Plain Conc. Slab Sta 0+280 to 0+234 (W1) 1 0% 07-Sep-10 08-Sep-10 SR64,838
U1W030 Waterproofing above Blinding for W1 5 0% 08-Sep-10 16-Sep-10 SR87,282
U1W040 Protc'on Screed Conc & P-Head Treatment for W1 5 0% 15-Sep-10 21-Sep-10 SR127,544
U1W050 Raft Steel Reinf. Sta +280 to +234 - W1 Face1 17 0% 20-Sep-10 10-Oct-10 SR209,235
U1W060 Raft Steel Reinf. Sta +280 to +234 - W1 Face2 17 0% 28-Sep-10 18-Oct-10 SR209,235
U1W070 Concrete for Found's Sta 0+280 to 0+234 (W1) 1 0% 18-Oct-10 19-Oct-10 SR288,600
U1W080 Curing for Foundation 7 0% 19-Oct-10 27-Oct-10 SR6,494
U1W090 Reinf. Ret-Wall Sta 0+280 to 0+234 (Nr-West) W1 21 0% 19-Oct-10 13-Nov-10 SR226,679
U1W100 Conc. for Ret-Wall Sta 0+280 to 0+234 (Nr-West) 1 0% 13-Nov-10 14-Nov-10 SR231,008
U1W110 Curing for Ret-Walls - NW1 7 0% 14-Nov-10 23-Nov-10 SR6,205
U1W120 Reinf. Ret-Wall Sta 0+280 to 0+234 (St-West ) W1 21 0% 26-Oct-10 21-Nov-10 SR226,679
U1W130 Conc. for Ret-Wall Sta 0+280 to 0+234 -SW1 1 0% 21-Nov-10 22-Nov-10 SR231,008
U1W140 Curing for Ret-Walls SW1 7 0% 23-Nov-10 01-Dec-10 SR6,205
U1W150 W-proofing/Protection Board on Walls for (W1) 20 0% 22-Nov-10 15-Dec-10 SR145,800
U1W160 Backfill b/w Ret wall & Shoring wall Ht=6m(W1) 23 0% 15-Dec-10 11-Jan-11 SR74,375

Start Date 27-Aug-08 Data Date 08-Jul-10 Actual Work INTERSECTION OF PR. MAJID ST. WITH PR. MOHD BIN ABDUL AZIZ ST.  Date Revision Checked Approved
07-Oct-08 Baseline Schedule
Remaining Work TAHLIA) REVISION # 2 SCHEDULE
07-Apr-09 Revised Schedule
Finish Date 07-Sep-11 Must Finish Date 07-Sep11 Critical Remaining Work (FINAL DESIGN) PROJECT No. B4‐10047(555) 21-Apr-09 Resubmittal with cost correction
Milestone HUTA Hegerfeld Saudia Ltd 28-Jan-10 Time Extension Claim Schedule
(c) Primavera Systems, Inc. Page 3 of 15 08-Jul-10 As per Consultant (MTMM) Commepnts
Activity ID Activity Name Orig % Start Finish Budgeted Total 2009 2010 2011
Dur Comp CostS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

U1W170 Backfill b/w Ret wall & Shoring wall upt req lvl 23 0% 11-Jan-11 07-Feb-11 SR74,375
West Sec - W2 147 0% 21-Sep-10 13-Mar-11 SR2,257,564
U2W010 Lvelling & Compaction Sta 0+234 to 0+186 (W2) 5 0% 21-Sep-10 27-Sep-10 SR1,080
U2W020 10cm Plain Conc. Slab Sta 0+234 to 0+186 (W2) 1 0% 27-Sep-10 28-Sep-10 SR64,838
U2W030 Waterproofing above Blinding for W2 5 0% 05-Oct-10 11-Oct-10 SR87,281
U2W040 Protc'on Screed Conc & P-Head Treatment for W2 5 0% 11-Oct-10 17-Oct-10 SR139,181
U2W050 Raft Steel Reinf. Sta 0+234 to 0+186 - W2 Face1 18 0% 17-Oct-10 07-Nov-10 SR209,235
U2W060 Raft Steel Reinf. Sta 0+234 to 0+186 - W2 Face2 18 0% 24-Oct-10 14-Nov-10 SR209,235
U2W070 Concrete for Found's Sta 0+234 to 0+186 (W2) 1 0% 14-Nov-10 16-Nov-10 SR288,600
U2W080 Curing for Foundation 7 0% 16-Nov-10 24-Nov-10 SR5,772
U2W090 Reinf. Ret-Wall Sta 0+234 to 0+186 (Nr-West ) W2 22 0% 16-Nov-10 12-Dec-10 SR226,679
U2W100 Conc. for Ret-Wall Sta 0+234 to 0+186 (Nr-West) 1 0% 12-Dec-10 13-Dec-10 SR231,008
U2W110 Curing for Ret-Walls NW2 7 0% 13-Dec-10 21-Dec-10 SR6,176
U2W120 Reinf. Ret-Wall Sta 0+234 to 0+186 (St-West ) W2 22 0% 28-Nov-10 23-Dec-10 SR226,679
U2W130 Conc. for Ret-Wall Sta 0+234 to 0+186 (St-West) 1 0% 23-Dec-10 25-Dec-10 SR231,008
U2W140 Curing for Ret-Walls SW2 7 0% 25-Dec-10 02-Jan-11 SR6,176
U2W150 W-proofing/Protection Board on Walls for (W2) 19 0% 25-Dec-10 16-Jan-11 SR165,240
U2W160 Backfill b/w Ret wall & Shoring wall Ht=6m(W2) 24 0% 16-Jan-11 13-Feb-11 SR79,688
U2W170 Backfill b/w Ret wall & Shoring wall upt req lvl 24 0% 13-Feb-11 13-Mar-11 SR79,688
West Sec - W3 130 0% 11-Oct-10 13-Mar-11 SR2,082,042
U3W010 Lvelling & Compaction Sta 0+186 to 0+146 (W3) 5 0% 11-Oct-10 17-Oct-10 SR1,080
U3W020 10cm Plain Conc. Slab Sta 0+186 to 0+146 (W3) 1 0% 17-Oct-10 18-Oct-10 SR64,838
U3W030 Waterproofing above Blinding for W3 5 0% 18-Oct-10 24-Oct-10 SR87,281
U3W040 Protc'on Screed Conc. for W3 5 0% 24-Oct-10 30-Oct-10 SR87,281
U3W050 Raft Steel Reinf. Sta 0+186 to 0+146 - W3 Face1 15 0% 30-Oct-10 17-Nov-10 SR209,235
U3W060 Raft Steel Reinf. Sta 0+186 to 0+146 - W3 Face2 15 0% 07-Nov-10 25-Nov-10 SR209,235
U3W070 Concrete for Found's Sta 0+186 to 0+146 (W3) 1 0% 25-Nov-10 27-Nov-10 SR288,600
U3W080 Curing for Foundation 7 0% 27-Nov-10 05-Dec-10 SR5,772
U3W090 Reinf. Ret-Wall Sta 0+186 to 0+146 (Nr-West ) W3 19 0% 27-Nov-10 19-Dec-10 SR194,933
U3W100 Conc. for Ret-Wall Sta 0+186 to 0+146 (Nr-West) 1 0% 19-Dec-10 20-Dec-10 SR231,008
U3W110 Curing for Ret-Walls NW3 7 0% 20-Dec-10 28-Dec-10 SR6,176
U3W120 Reinf. Ret-Wall Sta 0+186 to 0+146 (St-West ) W3 19 0% 08-Dec-10 30-Dec-10 SR194,933
U3W130 Conc. for Ret-Wall Sta 0+186 to 0+146 (St-West) 1 0% 30-Dec-10 01-Jan-11 SR231,008
U3W140 Curing for Ret-Walls SW3 7 0% 01-Jan-11 09-Jan-11 SR6,176
U3W150 W-proofing/Protection Board on Walls for (W3) 19 0% 30-Dec-10 22-Jan-11 SR126,360
U3W160 Backfill b/w Ret wall & Shoring wall Ht=6m(W3) 20 0% 22-Jan-11 14-Feb-11 SR69,063
U3W170 Backfill b/w Ret wall & Shoring wall upt req lvl 20 0% 17-Feb-11 13-Mar-11 SR69,063
West Sec - W4 128 0% 24-Oct-10 23-Mar-11 SR1,982,332
U4W010 Lvelling & Compaction Sta 0+146 to 0+106 (W4) 5 0% 24-Oct-10 30-Oct-10 SR1,080
U4W020 10cm Plain Conc. Slab Sta 0+146 to 0+106 (W4) 1 0% 30-Oct-10 31-Oct-10 SR64,838
U4W030 Waterproofing above Blinding for W4 5 0% 31-Oct-10 06-Nov-10 SR87,281
U4W040 Protc'on Screed Conc. for W4 5 0% 06-Nov-10 11-Nov-10 SR87,281
U4W050 Raft Steel Reinf. Sta 0+146 to 0+106 -W4 Face1 15 0% 11-Nov-10 30-Nov-10 SR209,235
U4W060 Raft Steel Reinf. Sta 0+146 to 0+106 -W4 Face2 15 0% 21-Nov-10 08-Dec-10 SR209,235
U4W070 Concrete for Found's Sta 0+146 to 0+106 (W4) 1 0% 08-Dec-10 09-Dec-10 SR216,450
U4W080 Curing for Foundation 7 0% 09-Dec-10 18-Dec-10 SR5,772
U4W090 Reinf. Ret-Wall Sta 0+146 to 0+106 (Nr-West ) W4 19 0% 09-Dec-10 01-Jan-11 SR194,933
U4W100 Conc. for Ret-Wall Sta 0+146 to 0+106 (Nr-West) 1 0% 01-Jan-11 02-Jan-11 SR227,401
U4W110 Curing for Ret-Walls NW4 7 0% 05-Jan-11 13-Jan-11 SR6,176

Start Date 27-Aug-08 Data Date 08-Jul-10 Actual Work INTERSECTION OF PR. MAJID ST. WITH PR. MOHD BIN ABDUL AZIZ ST.  Date Revision Checked Approved
07-Oct-08 Baseline Schedule
Remaining Work TAHLIA) REVISION # 2 SCHEDULE
07-Apr-09 Revised Schedule
Finish Date 07-Sep-11 Must Finish Date 07-Sep11 Critical Remaining Work (FINAL DESIGN) PROJECT No. B4‐10047(555) 21-Apr-09 Resubmittal with cost correction
Milestone HUTA Hegerfeld Saudia Ltd 28-Jan-10 Time Extension Claim Schedule
(c) Primavera Systems, Inc. Page 4 of 15 08-Jul-10 As per Consultant (MTMM) Commepnts
Activity ID Activity Name Orig % Start Finish Budgeted Total 2009 2010 2011
Dur Comp CostS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

U4W120 Reinf. Ret-Wall Sta 0+146 to 0+106 (St-West ) W4 19 0% 21-Dec-10 12-Jan-11 SR194,933
U4W130 Conc. for Ret-Wall Sta 0+146 to 0+106 (St-West) 1 0% 12-Jan-11 13-Jan-11 SR227,401
U4W140 Curing for Ret-Walls SW4 7 0% 13-Jan-11 22-Jan-11 SR6,176
U4W150 W-proofing/Protection Board on Walls for (W4) 19 0% 13-Jan-11 05-Feb-11 SR116,640
U4W160 Backfill b/w Ret wall & Shoring wall Ht=6m(W4) 19 0% 07-Feb-11 01-Mar-11 SR63,750
U4W170 Backfill b/w Ret wall & Shoring wall upt req lvl 19 0% 01-Mar-11 23-Mar-11 SR63,750
West Sec - W5 126 0% 06-Nov-10 03-Apr-11 SR1,893,623
U5W010 Lvelling & Compaction Sta 0+106 to 0+066 (W5) 5 0% 06-Nov-10 11-Nov-10 SR1,080
U5W020 10cm Plain Conc. Slab Sta 0+106 to 0+066 (W5) 1 0% 11-Nov-10 13-Nov-10 SR64,838
U5W030 Waterproofing above Blinding for W5 5 0% 13-Nov-10 20-Nov-10 SR87,281
U5W040 Protc'on Screed Conc. for W5 5 0% 20-Nov-10 25-Nov-10 SR87,281
U5W050 Raft Steel Reinf. Sta 0+106 to 0+066-W5 Face1 15 0% 25-Nov-10 13-Dec-10 SR209,235
U5W060 Raft Steel Reinf. Sta 0+106 to 0+066-W5 Face2 15 0% 04-Dec-10 21-Dec-10 SR209,235
U5W070 Concrete for Found's Sta 0+106 to 0+066 (W5) 1 0% 21-Dec-10 22-Dec-10 SR216,450
U5W080 Curing for Foundation 7 0% 22-Dec-10 30-Dec-10 SR5,772
U5W090 Reinf. Ret-Wall Sta 0+106 to 0+066 (Nr-West ) W5 19 0% 22-Dec-10 13-Jan-11 SR194,905
U5W100 Conc. for Ret-Wall Sta 0+106 to 0+066 (Nr-West) 1 0% 13-Jan-11 15-Jan-11 SR223,765
U5W110 Curing for Ret-Walls NW5 7 0% 15-Jan-11 23-Jan-11 SR6,176
U5W120 Reinf. Ret-Wall Sta 0+106 to 0+066 (St-West ) W5 19 0% 15-Jan-11 06-Feb-11 SR194,905
U5W130 Conc. for Ret-Wall Sta 0+106 to 0+066 (St-West) 1 0% 06-Feb-11 07-Feb-11 SR223,765
U5W140 Curing for Ret-Walls SW5 7 0% 07-Feb-11 15-Feb-11 SR6,176
U5W150 W-proofing/Protection Board on Walls for (W5) 19 0% 26-Jan-11 17-Feb-11 SR77,760
U5W160 Backfill b/w Ret wall & Shoring wall Ht=4m(W5) 19 0% 17-Feb-11 12-Mar-11 SR42,500
U5W170 Backfill b/w Ret wall & Shoring wall upt req lvl 19 0% 12-Mar-11 03-Apr-11 SR42,500
West Sec - W6 74 0% 13-Jan-11 10-Apr-11 SR630,042
U6W010 Lvelling & Compaction Sta 0+066 to 0+044 5 0% 13-Jan-11 19-Jan-11 SR810
U6W020 10cm Plain Conc. Slab Sta 0+066 to 0+044 1 0% 19-Jan-11 20-Jan-11 SR17,456
U6W030 Waterproofing above Blinding for W6 5 0% 20-Jan-11 26-Jan-11 SR20,365
U6W040 Reinf. for Side Ret-Wall Sta 0+066 to 0+044 20 0% 26-Jan-11 19-Feb-11 SR194,905
U6W050 Conc. for Ret-Wall Sta 0+066 to 0+044 1 0% 19-Feb-11 20-Feb-11 SR238,195
U6W060 Curing for Ret-Walls 7 0% 20-Feb-11 28-Feb-11 SR6,176
U6W070 W-proofing/Protection Board on Walls for (W6) 13 0% 28-Feb-11 15-Mar-11 SR77,760
U6W080 Backfilling betw.Ret Wall & Shoring Wall (W6) 22 0% 15-Mar-11 10-Apr-11 SR74,375
West Sec - W7 & W8 75 0% 20-Jan-11 18-Apr-11 SR568,088
U7W010 Lvelling & Compaction Sta 0+044 to 0+000 5 0% 20-Jan-11 26-Jan-11 SR810
U7W020 10cm Plain Conc. Sta 0+044 to 0+000 1 0% 26-Jan-11 27-Jan-11 SR17,456
U7W030 Waterproofing above Blinding for W7 & W8 5 0% 27-Jan-11 02-Feb-11 SR20,366
U7W040 Reinf. for Side Ret-Wall Sta 0+044 to 0+000 20 0% 02-Feb-11 26-Feb-11 SR183,361
U7W050 Conc. for Ret-Wall Sta 0+044 to 0+000 1 0% 26-Feb-11 27-Feb-11 SR238,195
U7W060 Curing for Ret-Walls 7 0% 28-Feb-11 08-Mar-11 SR6,176
U7W070 W-proofing/Protection Board on Walls for (W7,W8) 13 0% 08-Mar-11 23-Mar-11 SR48,600
U7W080 Backfilling betw.Ret Wall & Shoring Wall (W7,W8) 22 0% 23-Mar-11 18-Apr-11 SR53,125
West Bridg
Bridge Section 122 0% 15-Dec-10 07-May-11 SR3,256,233
WBE010 Retaining Wall Corbel / BackWall 12 0% 15-Dec-10 29-Dec-10 SR317,460
WBE020 Transportation / Erection of Bridge U Beams 14 0% 28-Dec-10 13-Jan-11 SR360,750
WBE030 Post Tensioning / Grouting of Bridge U Beams 10 0% 08-Jan-11 19-Jan-11 SR288,600
WBE040 Installation of Precast Concrete Slab Panels 12 0% 19-Jan-11 02-Feb-11 SR216,450
WBE050 Reinforcement Steel for Cast-in-Stu Top Slab 12 0% 02-Feb-11 16-Feb-11 SR432,900
WBE060 Concrete Casting of Cast-in-Situ Top Slab 1 0% 16-Feb-11 17-Feb-11 SR216,450

Start Date 27-Aug-08 Data Date 08-Jul-10 Actual Work INTERSECTION OF PR. MAJID ST. WITH PR. MOHD BIN ABDUL AZIZ ST.  Date Revision Checked Approved
07-Oct-08 Baseline Schedule
Remaining Work TAHLIA) REVISION # 2 SCHEDULE
07-Apr-09 Revised Schedule
Finish Date 07-Sep-11 Must Finish Date 07-Sep11 Critical Remaining Work (FINAL DESIGN) PROJECT No. B4‐10047(555) 21-Apr-09 Resubmittal with cost correction
Milestone HUTA Hegerfeld Saudia Ltd 28-Jan-10 Time Extension Claim Schedule
(c) Primavera Systems, Inc. Page 5 of 15 08-Jul-10 As per Consultant (MTMM) Commepnts
Activity ID Activity Name Orig % Start Finish Budgeted Total 2009 2010 2011
Dur Comp CostS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

WBE070 Back Wall Construction for the Bridge portion 10 0% 17-Feb-11 01-Mar-11 SR216,450
WBE080 Approach Slab on Both Sides of Tunnel Deck 12 0% 01-Mar-11 15-Mar-11 SR216,450
WBE090 Water proofing Membrane for Deck Slab 4 0% 15-Mar-11 20-Mar-11 SR116,375
WBE100 New Jersy Concrete Barrier Single Face - Tunnel 4 0% 20-Mar-11 24-Mar-11 SR136,700
WBE110 Plain Concrete Curb for Walkway on Deck Slab 3 0% 23-Mar-11 27-Mar-11 SR29,925
WBE120 CurbstonesWalkway Tiles beside U/pass parapet... 14 0% 27-Mar-11 12-Apr-11 SR176,400
WBE130 CurbstonesWalkway Tiles beside U/pass parapet... 14 0% 02-Apr-11 18-Apr-11 SR176,400
WBE140 Asphalt wearing course on top of Ground Bridge 2 0% 16-Apr-11 18-Apr-11 SR25,425
WBE150 Walkway Plain Concrete fill 3 0% 18-Apr-11 21-Apr-11 SR19,950
WBE160 Precast Concrete Tiles (40X40X4 cm) 6 0% 21-Apr-11 28-Apr-11 SR308,700
WBE170 Patch Up Repair Asphalt beside the Underpass 7 0% 28-Apr-11 07-May-11 SR848
Underpass East Side 497 8.14% 25-Nov-09 A 16-Jul-11 SR30,324,258
Excavation for MERW 398 24.08% 25-Nov-09 A 22-Mar-11 SR6,456,170
UEE010 Exca. of Roads from Sta 0+378 to 0+634 (Layer 1) 40 62.5% 25-Nov-09 A 31-Jul-10 SR2,487,100
UEE020 Excavation from Sta 0+378 to 0+603 (Layer 2) 25 0% 28-Jul-10 26-Aug-10 SR1,309,000
UEE030 Excavation from Sta 0+378 to 0+520 (Layer 3) 14 0% 26-Aug-10 11-Sep-10 SR916,300
UEE040 Excavation from Sta 0+378 to 0+440 (Layer 4) 10 0% 11-Sep-10 23-Sep-10 SR654,500
UEE050 Excavation for Remaining Underpass 25 0% 25-Sep-10 23-Oct-10 SR392,700
UEE070 Excavation with Dewatering of the Underpass 200 0% 28-Jul-10 22-Mar-11 SR696,570
Construction of MERW
Constructi 185 11.4% 09-Mar-10 A 24-Oct-10 SR6,480,000
UEC010 Const. of MERW Sta 0+378 to 0+634 (Layer1) Nr... 25 40% 09-Mar-10 A 03-Aug-10 SR972,000
UEC020 Const. of MERW Sta 0+378 to 0+634 (Layer1) St... 25 36% 09-Mar-10 A 04-Aug-10 SR972,000
UEC030 Const. of MERW Sta 0+378 to 0+603 (Layer2) Nr... 20 0% 04-Aug-10 26-Aug-10 SR907,200
UEC040 Const. of MERW Sta 0+378 to 0+603 (Layer2) St... 20 0% 12-Aug-10 04-Sep-10 SR907,200
UEC050 Const. of MERW from Sta 0+378 to 0+520 (Layer3) 18 0% 29-Aug-10 20-Sep-10 SR842,400
UEC060 Const. of MERW from Sta 0+378 to 0+520 (Layer3) 18 0% 01-Sep-10 23-Sep-10 SR842,400
UEC070 Const. of MERW from Sta 0+378 to 0+440 (Layer4) 15 0% 16-Sep-10 03-Oct-10 SR421,200
UEC080 Const. of MERW from Sta 0+378 to 0+440 (Layer4) 15 0% 19-Sep-10 05-Oct-10 SR421,200
UEC090 Const. of MERW for Remaining U-pass 15 0% 07-Oct-10 24-Oct-10 SR194,400
Execution of Tension Piles 34 100% 27-Apr-10 A 30-May-10 A SR175,140
UET010 Ten-Piles Raft Found'n P12,P10,P8,P6,P4 &P2 14 100% 27-Apr-10 A 12-May-10 A SR34,020
UET020 Ten-Piles Raft Found'n P29,P27,P25,P23 & P21 14 100% 01-May-10 A 13-May-10 A SR28,224
UET030 Ten-Piles Raft Found'n P19,P17,P15,P13 & P11 14 100% 06-May-10 A 20-May-10 A SR28,224
UET040 Ten-Piles Raft Found'n P9,P7,P5,P3 & P1 14 100% 08-May-10 A 24-May-10 A SR28,224
UET050 Ten-Piles Raft Found'n P22,P20,P18,P16 & P14 14 100% 15-May-10 A 22-May-10 A SR28,224
UET060 Ten-Piles Raft Found'n P31,P30,P28,P26 & P24 14 100% 22-May-10 A 30-May-10 A SR28,224
Pile Trimming
Trimm 25 0% 25-Sep-10 23-Oct-10 SR108,180
UEP010 Exca. & P-Trimming P31,P30,P28,P26 & P24 10 0% 25-Sep-10 05-Oct-10 SR16,560
UEP020 Exca. & P-Trimming P29,P27,P25,P23 & P21 10 0% 26-Sep-10 06-Oct-10 SR16,560
UEP030 Exca. & P-Trimming P22,P20,P18,P16 & P14 10 0% 30-Sep-10 11-Oct-10 SR16,560
UEP040 Exca. & P-Trimming P19,P17,P15,P13 & P11 10 0% 05-Oct-10 16-Oct-10 SR16,560
UEP050 Exca. & P-Trimming P12,P10,P8,P6,P4 &P2 12 0% 10-Oct-10 23-Oct-10 SR25,380
UEP060 Exca. & P-Trimming P9,P7,P5,P3 & P1 7 0% 16-Oct-10 23-Oct-10 SR16,560
Underpass East Section 131 0% 03-Oct-10 05-Mar-11 SR2,218,205
UES010 Lvelling & Compaction Sta 0+378 to 0+420 East Se 5 0% 03-Oct-10 07-Oct-10 SR1,080
UES020 10cm Plain Conc. Sta 0+378 to 0+420 East Sec. 1 0% 09-Oct-10 09-Oct-10 SR64,838
UES030 Waterproofing above Blinding for East Sec. 7 0% 10-Oct-10 17-Oct-10 SR87,282
UES040 Raft Steel Reinf.Sta +378 to +420 East Face1 16 0% 18-Oct-10 04-Nov-10 SR216,450
UES050 Raft Steel Reinf.Sta +378 to +420 East Face2 16 0% 26-Oct-10 13-Nov-10 SR216,450

Start Date 27-Aug-08 Data Date 08-Jul-10 Actual Work INTERSECTION OF PR. MAJID ST. WITH PR. MOHD BIN ABDUL AZIZ ST.  Date Revision Checked Approved
07-Oct-08 Baseline Schedule
Remaining Work TAHLIA) REVISION # 2 SCHEDULE
07-Apr-09 Revised Schedule
Finish Date 07-Sep-11 Must Finish Date 07-Sep11 Critical Remaining Work (FINAL DESIGN) PROJECT No. B4‐10047(555) 21-Apr-09 Resubmittal with cost correction
Milestone HUTA Hegerfeld Saudia Ltd 28-Jan-10 Time Extension Claim Schedule
(c) Primavera Systems, Inc. Page 6 of 15 08-Jul-10 As per Consultant (MTMM) Commepnts
Activity ID Activity Name Orig % Start Finish Budgeted Total 2009 2010 2011
Dur Comp CostS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

UES060 Concrete for Found's Sta 0+378 to 0+420 East Sec 1 0% 14-Nov-10 14-Nov-10 SR360,750
UES070 Curing for Foundation 7 0% 16-Nov-10 23-Nov-10 SR6,494
UES080 Reinf. Ret-Wall Sta 0+378 to 0+420 East (North) 20 0% 16-Nov-10 08-Dec-10 SR238,223
UES090 Conc.for Ret-Wall Sta 0+378 to 0+420 East(North) 1 0% 09-Dec-10 09-Dec-10 SR231,008
UES100 Curing for Ret-Walls East Sec.(Nr-East) 7 0% 11-Dec-10 18-Dec-10 SR6,205
UES110 Reinf. Ret-Wall Sta 0+378 to 0+420 East (South) 20 0% 22-Nov-10 14-Dec-10 SR238,223
UES120 Conc.for Ret-Wall Sta 0+378 to 0+420 East(South) 1 0% 15-Dec-10 15-Dec-10 SR231,008
UES130 Curing for Ret-Walls East Sec.(St-East) 7 0% 16-Dec-10 23-Dec-10 SR6,205
UES140 W-proofing/Protection Board on Walls for East Se 20 0% 19-Dec-10 10-Jan-11 SR165,240
UES150 Backfill b/w Ret wall & Shoring wall Ht=6m 23 0% 11-Jan-11 06-Feb-11 SR74,375
UES160 Backfill b/w Ret wall & Shoring wall upt req lvl 23 0% 07-Feb-11 05-Mar-11 SR74,375
East Sec - E1 138 0% 05-Oct-10 15-Mar-11 SR2,216,640
U1E010 Lvelling & Compaction Sta 0+420 to 0+466 (E1) 5 0% 05-Oct-10 10-Oct-10 SR1,080
U1E020 10cm Plain Conc. Slab Sta 0+420 to 0+466 (E1) 1 0% 11-Oct-10 11-Oct-10 SR64,838
U1E030 Waterproofing above Blinding for E1 5 0% 12-Oct-10 17-Oct-10 SR87,282
U1E040 Protc'on Screed Conc & P-Head Treatment for E1 5 0% 18-Oct-10 23-Oct-10 SR127,544
U1E050 Raft Steel Reinf. Sta 0+420 to 0+466 (E1) Face1 17 0% 24-Oct-10 11-Nov-10 SR209,235
U1E060 Raft Steel Reinf. Sta 0+420 to 0+466 (E1) Face2 17 0% 01-Nov-10 21-Nov-10 SR209,235
U1E070 Concrete for Found's Sta 0+420 to 0+466 (E1) 1 0% 22-Nov-10 22-Nov-10 SR288,600
U1E080 Curing for Foundation 7 0% 23-Nov-10 30-Nov-10 SR6,494
U1E090 Reinf. Ret-Wall Sta 0+420 to 0+466 (Nr-East) E1 21 0% 23-Nov-10 16-Dec-10 SR226,679
U1E100 Conc. for Ret-Wall Sta 0+420 to 0+466-NE1 1 0% 18-Dec-10 18-Dec-10 SR231,008
U1E110 Curing for Ret-Walls - NE1 7 0% 19-Dec-10 26-Dec-10 SR6,205
U1E120 Reinf. Ret-Wall Sta 0+420 to 0+466 (St-East) E1 21 0% 01-Dec-10 25-Dec-10 SR226,679
U1E130 Conc. for Ret-Wall Sta 0+420 to 0+466 - SE1 1 0% 26-Dec-10 26-Dec-10 SR231,008
U1E140 Curing for Ret-Walls SE1 7 0% 27-Dec-10 03-Jan-11 SR6,205
U1E150 W-proofing/Protection Board on Walls for (E1) 20 0% 29-Dec-10 20-Jan-11 SR145,800
U1E160 Backfill b/w Ret wall & Shoring wall Ht=6m(E1) 23 0% 22-Jan-11 16-Feb-11 SR74,375
U1E170 Backfill b/w Ret wall & Shoring wall upt req lvl 23 0% 17-Feb-11 15-Mar-11 SR74,375
East Sec - E2 145 0% 18-Oct-10 05-Apr-11 SR2,257,564
U2E010 Lvelling & Compaction Sta 0+466 to 0+514 (E2) 5 0% 18-Oct-10 23-Oct-10 SR1,080
U2E020 10cm Plain Conc. Slab Sta 0+466 to 0+514 (E2) 1 0% 24-Oct-10 24-Oct-10 SR64,838
U2E030 Waterproofing above Blinding for E2 7 0% 25-Oct-10 01-Nov-10 SR87,281
U2E040 Protc'on Screed Conc & P-Head Treatment for E2 7 0% 02-Nov-10 09-Nov-10 SR139,181
U2E050 Raft Steel Reinf. Sta 0+466 to 0+514 (E2) Face1 18 0% 10-Nov-10 01-Dec-10 SR209,235
U2E060 Raft Steel Reinf. Sta 0+466 to 0+514 (E2) Face2 18 0% 20-Nov-10 09-Dec-10 SR209,235
U2E070 Concrete for Found's Sta 0+466 to 0+514 (E2) 1 0% 11-Dec-10 11-Dec-10 SR288,600
U2E080 Curing for Foundation 7 0% 12-Dec-10 19-Dec-10 SR5,772
U2E090 Reinf. Ret-Wall Sta 0+466 to 0+514 (Nr-East) E2 22 0% 12-Dec-10 05-Jan-11 SR226,679
U2E100 Conc. for Ret-Wall Sta 0+466 to 0+514 - NE2 1 0% 06-Jan-11 06-Jan-11 SR231,008
U2E110 Curing for Ret-Walls NE2 7 0% 08-Jan-11 15-Jan-11 SR6,176
U2E120 Reinf. Ret-Wall Sta 0+466 to 0+514 (St-East) E2 22 0% 19-Dec-10 12-Jan-11 SR226,679
U2E130 Conc. for Ret-Wall Sta 0+466 to 0+514 - SE2 1 0% 13-Jan-11 13-Jan-11 SR231,008
U2E140 Curing for Ret-Walls SE2 7 0% 15-Jan-11 22-Jan-11 SR6,176
U2E150 W-proofing/Protection Board on Walls for (E2) 20 0% 17-Jan-11 08-Feb-11 SR165,240
U2E160 Backfill b/w Ret wall & Shoring wall Ht=6m(E2) 24 0% 09-Feb-11 08-Mar-11 SR79,688
U2E170 Backfill b/w Ret wall & Shoring wall upt req lvl 24 0% 09-Mar-11 05-Apr-11 SR79,688
East Sec - E3 146 0% 02-Nov-10 21-Apr-11 SR2,082,042
U3E010 Lvelling & Compaction Sta 0+514 to 0+554 (E3) 5 0% 02-Nov-10 07-Nov-10 SR1,080

Start Date 27-Aug-08 Data Date 08-Jul-10 Actual Work INTERSECTION OF PR. MAJID ST. WITH PR. MOHD BIN ABDUL AZIZ ST.  Date Revision Checked Approved
07-Oct-08 Baseline Schedule
Remaining Work TAHLIA) REVISION # 2 SCHEDULE
07-Apr-09 Revised Schedule
Finish Date 07-Sep-11 Must Finish Date 07-Sep11 Critical Remaining Work (FINAL DESIGN) PROJECT No. B4‐10047(555) 21-Apr-09 Resubmittal with cost correction
Milestone HUTA Hegerfeld Saudia Ltd 28-Jan-10 Time Extension Claim Schedule
(c) Primavera Systems, Inc. Page 7 of 15 08-Jul-10 As per Consultant (MTMM) Commepnts
Activity ID Activity Name Orig % Start Finish Budgeted Total 2009 2010 2011
Dur Comp CostS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

U3E020 10cm Plain Conc. Slab Sta 0+514 to 0+554 (E3) 1 0% 08-Nov-10 08-Nov-10 SR64,838
U3E030 Waterproofing above Blinding for E3 7 0% 09-Nov-10 17-Nov-10 SR87,281
U3E040 Protc'on Screed Conc. E3 7 0% 18-Nov-10 25-Nov-10 SR87,281
U3E050 Raft Steel Reinf. Sta 0+514 to 0+554 (E3) Face1 15 0% 27-Nov-10 13-Dec-10 SR209,235
U3E060 Raft Steel Reinf. Sta 0+514 to 0+554 (E3) Face2 15 0% 05-Dec-10 21-Dec-10 SR209,235
U3E070 Concrete for Found's Sta 0+514 to 0+554 (E3) 1 0% 22-Dec-10 22-Dec-10 SR288,600
U3E080 Curing for Foundation 7 0% 23-Dec-10 30-Dec-10 SR5,772
U3E090 Reinf. Ret-Wall Sta 0+514 to 0+554 (Nr-East) E3 19 0% 23-Dec-10 13-Jan-11 SR194,933
U3E100 Conc. for Ret-Wall Sta 0+514 to 0+554 - NE3 1 0% 15-Jan-11 15-Jan-11 SR231,008
U3E110 Curing for Ret-Walls NE3 7 0% 16-Jan-11 23-Jan-11 SR6,176
U3E120 Reinf. Ret-Wall Sta 0+514 to 0+554 (St-East) E3 19 0% 16-Jan-11 06-Feb-11 SR194,933
U3E130 Conc. for Ret-Wall Sta 0+514 to 0+554 - SE3 1 0% 07-Feb-11 07-Feb-11 SR231,008
U3E140 Curing for Ret-Walls SE3 7 0% 08-Feb-11 15-Feb-11 SR6,176
U3E150 W-proofing/Protection Board on Walls for (E3) 20 0% 12-Feb-11 06-Mar-11 SR126,360
U3E160 Backfill b/w Ret wall & Shoring wall Ht=6m(E3) 20 0% 07-Mar-11 29-Mar-11 SR69,063
U3E170 Backfill b/w Ret wall & Shoring wall upt req lvl 20 0% 30-Mar-11 21-Apr-11 SR69,063
East Sec - E4 142 0% 18-Nov-10 02-May-11 SR1,982,332
U4E010 Lvelling & Compaction Sta 0+554 to 0+594 (E4) 5 0% 18-Nov-10 23-Nov-10 SR1,080
U4E020 10cm Plain Conc. Slab Sta 0+554 to 0+594 (E4) 1 0% 24-Nov-10 24-Nov-10 SR64,838
U4E030 Waterproofing above Blinding for E4 7 0% 25-Nov-10 02-Dec-10 SR87,281
U4E040 Protc'on Screed Conc. E4 7 0% 02-Dec-10 09-Dec-10 SR87,281
U4E050 Raft Steel Reinf. Sta 0+554 to 0+594 (E4) Face 1 15 0% 11-Dec-10 27-Dec-10 SR209,235
U4E060 Raft Steel Reinf. Sta 0+554 to 0+594 (E4) Face 2 15 0% 19-Dec-10 04-Jan-11 SR209,235
U4E070 Concrete for Found's Sta 0+554 to 0+594 (E4) 1 0% 05-Jan-11 05-Jan-11 SR216,450
U4E080 Curing for Foundation 7 0% 06-Jan-11 13-Jan-11 SR5,772
U4E090 Reinf. Ret-Wall Sta 0+554 to 0+594 (Nr-East) E4 19 0% 06-Jan-11 27-Jan-11 SR194,933
U4E100 Conc. for Ret-Wall Sta 0+554 to 0+594 - NE4 1 0% 29-Jan-11 29-Jan-11 SR227,401
U4E110 Curing for Ret-Walls NE4 7 0% 30-Jan-11 06-Feb-11 SR6,176
U4E120 Reinf. Ret-Wall Sta 0+554 to 0+594 (St-East) E4 19 0% 30-Jan-11 20-Feb-11 SR194,933
U4E130 Conc. for Ret-Wall Sta 0+554 to 0+594 - SE4 1 0% 21-Feb-11 21-Feb-11 SR227,401
U4E140 Curing for Ret-Walls SE4 7 0% 22-Feb-11 01-Mar-11 SR6,176
U4E150 W-proofing/Protection Board on Walls for (E4) 20 0% 24-Feb-11 19-Mar-11 SR116,640
U4E160 Backfill b/w Ret wall & Shoring wall Ht=6m(E4) 19 0% 20-Mar-11 10-Apr-11 SR63,750
U4E170 Backfill b/w Ret wall & Shoring wall upt req lvl 19 0% 11-Apr-11 02-May-11 SR63,750
East Sec - E5 144 0% 04-Dec-10 19-May-11 SR1,893,623
U5E010 Lvelling & Compaction Sta 0+594 to 0+634 (E5) 5 0% 04-Dec-10 08-Dec-10 SR1,080
U5E020 10cm Plain Conc. Slab Sta 0+594 to 0+634 (E5) 1 0% 09-Dec-10 09-Dec-10 SR64,838
U5E030 Waterproofing above Blinding for E5 7 0% 11-Dec-10 18-Dec-10 SR87,281
U5E040 Protc'on Screed Conc. for E5 7 0% 19-Dec-10 26-Dec-10 SR87,281
U5E050 Raft Steel Reinf. Sta 0+594 to 0+634 (E5) Face1 15 0% 27-Dec-10 12-Jan-11 SR209,235
U5E060 Raft Steel Reinf. Sta 0+594 to 0+634 (E5) Face2 15 0% 04-Jan-11 20-Jan-11 SR209,235
U5E070 Concrete for Found's Sta 0+594 to 0+634 (E5) 1 0% 22-Jan-11 22-Jan-11 SR216,450
U5E080 Curing for Foundation 7 0% 23-Jan-11 30-Jan-11 SR5,772
U5E090 Reinf. Ret-Wall Sta 0+594 to 0+634 (Nr-East) E5 19 0% 23-Jan-11 13-Feb-11 SR194,905
U5E100 Conc. for Ret-Wall Sta 0+594 to 0+634 - NE5 1 0% 14-Feb-11 14-Feb-11 SR223,765
U5E110 Curing for Ret-Walls NE5 7 0% 15-Feb-11 22-Feb-11 SR6,176
U5E120 Reinf. Ret-Wall Sta 0+594 to 0+634 (St-East) E5 19 0% 15-Feb-11 08-Mar-11 SR194,905
U5E130 Conc. for Ret-Wall Sta 0+594 to 0+634 - SE5 1 0% 09-Mar-11 09-Mar-11 SR223,765
U5E140 Curing for Ret-Walls SE5 7 0% 10-Mar-11 17-Mar-11 SR6,176

Start Date 27-Aug-08 Data Date 08-Jul-10 Actual Work INTERSECTION OF PR. MAJID ST. WITH PR. MOHD BIN ABDUL AZIZ ST.  Date Revision Checked Approved
07-Oct-08 Baseline Schedule
Remaining Work TAHLIA) REVISION # 2 SCHEDULE
07-Apr-09 Revised Schedule
Finish Date 07-Sep-11 Must Finish Date 07-Sep11 Critical Remaining Work (FINAL DESIGN) PROJECT No. B4‐10047(555) 21-Apr-09 Resubmittal with cost correction
Milestone HUTA Hegerfeld Saudia Ltd 28-Jan-10 Time Extension Claim Schedule
(c) Primavera Systems, Inc. Page 8 of 15 08-Jul-10 As per Consultant (MTMM) Commepnts
Activity ID Activity Name Orig % Start Finish Budgeted Total 2009 2010 2011
Dur Comp CostS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

U5E150 W-proofing/Protection Board on Walls for (E5) 20 0% 14-Mar-11 05-Apr-11 SR77,760


U5E160 Backfill b/w Ret wall & Shoring wall Ht=6m (E5) 19 0% 06-Apr-11 27-Apr-11 SR42,500
U5E170 Backfill b/w Ret wall & Shoring wall upt req lvl 19 0% 28-Apr-11 19-May-11 SR42,500
East Sec - E6 74 0% 02-Mar-11 26-May-11 SR630,042
U6E010 Lvelling & Compaction Sta 0+634 to 0+656 5 0% 02-Mar-11 07-Mar-11 SR810
U6E020 10cm Plain Conc. Sta 0+634 to 0+656 1 0% 08-Mar-11 08-Mar-11 SR17,456
U6E030 Waterproofing above Blinding for E6 5 0% 09-Mar-11 14-Mar-11 SR20,365
U6E040 Reinf. for Side Ret-Wall Sta 0+634 to 0+656 19 0% 15-Mar-11 05-Apr-11 SR194,905
U6E050 Conc. for Ret-Wall Sta 0+634 to 0+656 1 0% 06-Apr-11 06-Apr-11 SR238,195
U6E060 Curing for Ret-Walls 7 0% 07-Apr-11 14-Apr-11 SR6,176
U6E070 W-proofing/Protection Board on Walls for (E6) 14 0% 16-Apr-11 01-May-11 SR77,760
U6E080 Backfilling between Ret Wall & Shoring Wall (E6) 22 0% 02-May-11 26-May-11 SR74,375
East Sec - E7 & E8 75 0% 09-Mar-11 04-Jun-11 SR568,088
U7E010 Lvelling & Compaction Sta 0+656 to 0+700 5 0% 09-Mar-11 14-Mar-11 SR810
U7E020 10cm Plain Conc. Sta 0+656 to 0+700 1 0% 15-Mar-11 15-Mar-11 SR17,456
U7E030 Waterproofing above Blinding for E7 & E8 5 0% 16-Mar-11 21-Mar-11 SR20,366
U7E040 Reinf. for Side Ret-Wall Sta 0+656 to 0+700 20 0% 22-Mar-11 13-Apr-11 SR183,361
U7E050 Conc. for Ret-Wall Sta 0+656 to 0+700 1 0% 14-Apr-11 14-Apr-11 SR238,195
U7E060 Curing for Ret-Walls 7 0% 16-Apr-11 23-Apr-11 SR6,176
U7E070 W-proofing/Protection Board on Walls for (E7,E8) 14 0% 24-Apr-11 09-May-11 SR48,600
U7E080 Backfilling betw.Ret Wall & Shoring Wall (E7,E8) 22 0% 10-May-11 04-Jun-11 SR53,125
East Bridge
Bridg Section 113 0% 07-Mar-11 16-Jul-11 SR3,256,233
EBE010 Retaining Wall Corbel - Bridge Bearings/BackWall 12 0% 07-Mar-11 20-Mar-11 SR317,460
EBE020 Transportation / Erection of Bridge U Beams 14 0% 21-Mar-11 05-Apr-11 SR360,750
EBE030 Post Tensioning / Grouting of Bridge U Beams 10 0% 06-Apr-11 17-Apr-11 SR288,600
EBE040 Installation of Precast Concrete Slab Panels 12 0% 18-Apr-11 01-May-11 SR216,450
EBE050 Reinforcement Steel for Cast-in-Stu Top Slab 7 0% 02-May-11 09-May-11 SR432,900
EBE060 Concrete Casting of Cast-in-Situ Top Slab 2 0% 10-May-11 11-May-11 SR216,450
EBE070 Back Wall Construction for the Bridge portion 10 0% 12-May-11 23-May-11 SR216,450
EBE080 Approach Slab on Both Sides of Tunnel Deck 10 0% 24-May-11 04-Jun-11 SR216,450
EBE090 Water proofing Membrane for Deck Slab 4 0% 05-Jun-11 08-Jun-11 SR116,375
EBE100 New Jersy Concrete Barrier Single Face - Tunnel 4 0% 05-Jun-11 08-Jun-11 SR136,700
EBE110 Plain Concrete Curb for Walkway on Deck Slab 3 0% 09-Jun-11 12-Jun-11 SR29,925
EBE111 Curbstones/Walkway Tiles beside U/pass parape... 14 0% 06-Jun-11 21-Jun-11 SR176,400
EBE112 Curbstones/Walkway Tiles beside U/pass parape... 14 0% 12-Jun-11 27-Jun-11 SR176,400
EBE120 Asphalt wearing course on top of Ground Bridge 2 0% 26-Jun-11 27-Jun-11 SR25,425
EBE130 Walkway Plain Concrete fill 3 0% 28-Jun-11 30-Jun-11 SR19,950
EBE140 Precast Concrete Tiles (40X40X4 cm) 6 0% 02-Jul-11 07-Jul-11 SR308,700
EBE150 Patch Up Repair Asphalt beside the Underpass 7 0% 09-Jul-11 16-Jul-11 SR848
Utilities Crossing
Cro Underpass Ground Bridge 43 0% 16-Apr-11 05-Jun-11 SR9,458,350
UGB010 Rerouting design / drawings Approval from STC 0 0% 16-Apr-11 SR0
UGB020 Traffic Permission - Telephone Lines Rerouting 0 0% 16-Apr-11 SR0
UGB030 Rerouting of Telephone Lines 25 0% 16-Apr-11 15-May-11 SR263,450
UGB040 Rerouting design / drawings Approval from SCECO 0 0% 20-Apr-11 SR0
UGB050 Traffic Permission - Electrical Cables Rerouting 0 0% 20-Apr-11 SR0
UGB060 13.8kV Medium Voltage Cable Rerouting 36 0% 20-Apr-11 01-Jun-11 SR2,923,200
UGB070 Rerouting design / drawings Approval from WSDA 0 0% 21-Apr-11 SR0
UGB080 Traffic Permission - Water Lines Rerouting 0 0% 21-Apr-11 SR0
UGB090 160mm dia Water Line Rerouting Works 18 0% 21-Apr-11 12-May-11 SR838,150

Start Date 27-Aug-08 Data Date 08-Jul-10 Actual Work INTERSECTION OF PR. MAJID ST. WITH PR. MOHD BIN ABDUL AZIZ ST.  Date Revision Checked Approved
07-Oct-08 Baseline Schedule
Remaining Work TAHLIA) REVISION # 2 SCHEDULE
07-Apr-09 Revised Schedule
Finish Date 07-Sep-11 Must Finish Date 07-Sep11 Critical Remaining Work (FINAL DESIGN) PROJECT No. B4‐10047(555) 21-Apr-09 Resubmittal with cost correction
Milestone HUTA Hegerfeld Saudia Ltd 28-Jan-10 Time Extension Claim Schedule
(c) Primavera Systems, Inc. Page 9 of 15 08-Jul-10 As per Consultant (MTMM) Commepnts
Activity ID Activity Name Orig % Start Finish Budgeted Total 2009 2010 2011
Dur Comp CostS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

UGB100 300mm dia Water Line Rerouting Works 18 0% 24-Apr-11 15-May-11 SR765,050
UGB110 800mm dia Water Line Rerouting Works 30 0% 24-Apr-11 29-May-11 SR1,820,850
UGB120 1000mm dia Water Line Rerouting Works 36 0% 24-Apr-11 05-Jun-11 SR2,847,650
Bridge Structural
Stru Works 185 0% 12-Aug-10 19-Mar-11 SR13,440,681
North Deck 153 0% 12-Aug-10 09-Feb-11 SR6,720,341
Abutment Work 137 0% 12-Aug-10 22-Jan-11 SR3,349,534
BNA010 Excavation of Roads upto required pile levels 5 0% 12-Aug-10 17-Aug-10 SR196,350
BNA020 Execution of Piles for Abutment A1 12 0% 18-Aug-10 31-Aug-10 SR439,560
BNA030 Exca. upto required level & Pile Trimming 10 0% 01-Sep-10 12-Sep-10 SR14,400
BNA040 100mm Plain Concrete Slab Laying 1 0% 15-Sep-10 15-Sep-10 SR84,000
BNA050 Pile Head Treatments 18 0% 16-Sep-10 06-Oct-10 SR73,260
BNA060 Abutment works at Axis A1 20 0% 28-Sep-10 20-Oct-10 SR701,527
BNA070 Waterproofing Membrane/Coating upto Ground l... 7 0% 21-Oct-10 28-Oct-10 SR40,027
BNA080 Backfilling Above Foundation Abutment 12 0% 30-Oct-10 11-Nov-10 SR31,875
BNA090 Execution of Columns @ A1 14 0% 13-Nov-10 29-Nov-10 SR352,800
BNA100 Formwork for Cross Head Beams @A1 15 0% 30-Nov-10 16-Dec-10 SR138,353
BNA110 Steel Fixing for Cross Head Beam @ A1 15 0% 08-Dec-10 25-Dec-10 SR276,705
BNA120 PT Bars/Ducts & Accessories fixing A1 7 0% 20-Dec-10 27-Dec-10 SR419,580
BNA130 Closing Shutter & Concrete pouring @ A1 3 0% 26-Dec-10 28-Dec-10 SR230,587
BNA140 Side Formwork Removal & Cleaning 2 0% 29-Dec-10 30-Dec-10 SR23,059
BNA150 Initial Stressing- Cross Head Beams (PT+Tendons) 18 0% 29-Dec-10 18-Jan-11 SR104,895
BNA160 Pot Bearings Erection on Abutment 7 0% 15-Jan-11 22-Jan-11 SR222,557
Pier Columns
Colum Works 136 0% 01-Sep-10 09-Feb-11 SR3,370,807
BNP010 Excavation of Roads upto required pile levels 5 0% 01-Sep-10 06-Sep-10 SR196,350
BNP020 Execution of Piles for Pier P1 12 0% 07-Sep-10 22-Sep-10 SR439,560
BNP030 Exca. upto required level & Pile Trimming 10 0% 23-Sep-10 04-Oct-10 SR14,400
BNP040 100mm Plain Concrete Slab Laying 1 0% 05-Oct-10 05-Oct-10 SR84,000
BNP050 Pile Head Treatments 15 0% 06-Oct-10 23-Oct-10 SR73,260
BNP060 Foundations (Pile Caps) for Pier P1 15 0% 24-Oct-10 09-Nov-10 SR722,800
BNP070 Waterproofing Membrane/Coating upto Ground l... 7 0% 10-Nov-10 18-Nov-10 SR40,027
BNP080 Backfilling Above Foundation Abutment 12 0% 20-Nov-10 02-Dec-10 SR31,875
BNP090 Execution of Columns @ Pier P1 14 0% 04-Dec-10 19-Dec-10 SR352,800
BNP100 Formwork for Cross Head Beams P1 15 0% 20-Dec-10 05-Jan-11 SR138,353
BNP110 Steel Fixing for Cross Head Beam @ P1 15 0% 28-Dec-10 13-Jan-11 SR276,705
BNP120 PT Bars/Ducts & Accessories fixing - P1 7 0% 09-Jan-11 16-Jan-11 SR419,580
BNP130 Closing Shutter & Concrete pouring @ P1 3 0% 15-Jan-11 17-Jan-11 SR230,587
BNP140 Side Formwork Removal & Cleaning 2 0% 18-Jan-11 19-Jan-11 SR23,059
BNP150 Initial Stressing- Cross Head Beams (PT+Tendons) 18 0% 18-Jan-11 07-Feb-11 SR104,895
BNP160 Pot Bearings Erection on Pier 7 0% 02-Feb-11 09-Feb-11 SR222,557
South deck 151 0% 23-Sep-10 19-Mar-11 SR6,720,341
Abutment Work 151 0% 23-Sep-10 19-Mar-11 SR3,349,534
BSA010 Excavation of Roads upto required pile levels 5 0% 23-Sep-10 28-Sep-10 SR196,350
BSA020 Execution of Piles for Abutment A2 12 0% 29-Sep-10 12-Oct-10 SR439,560
BSA030 Exca. upto required level & Pile Trimming 10 0% 13-Oct-10 24-Oct-10 SR14,400
BSA040 100mm Plain Concrete Slab Laying 1 0% 25-Oct-10 25-Oct-10 SR84,000
BSA050 Pile Head Treatments 18 0% 26-Oct-10 16-Nov-10 SR73,260
BSA060 Abutment works at Axis A2 20 0% 17-Nov-10 09-Dec-10 SR701,527
BSA070 Waterproofing Membrane/Coating upto Ground l... 7 0% 11-Dec-10 18-Dec-10 SR40,027
BSA080 Backfilling Above Foundation Abutment 12 0% 19-Dec-10 01-Jan-11 SR31,875

Start Date 27-Aug-08 Data Date 08-Jul-10 Actual Work INTERSECTION OF PR. MAJID ST. WITH PR. MOHD BIN ABDUL AZIZ ST.  Date Revision Checked Approved
07-Oct-08 Baseline Schedule
Remaining Work TAHLIA) REVISION # 2 SCHEDULE
07-Apr-09 Revised Schedule
Finish Date 07-Sep-11 Must Finish Date 07-Sep11 Critical Remaining Work (FINAL DESIGN) PROJECT No. B4‐10047(555) 21-Apr-09 Resubmittal with cost correction
Milestone HUTA Hegerfeld Saudia Ltd 28-Jan-10 Time Extension Claim Schedule
(c) Primavera Systems, Inc. Page 10 of 15 08-Jul-10 As per Consultant (MTMM) Commepnts
Activity ID Activity Name Orig % Start Finish Budgeted Total 2009 2010 2011
Dur Comp CostS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

BSA090 Execution of Columns @ A2 14 0% 02-Jan-11 17-Jan-11 SR352,800


BSA100 Formwork for Cross Head Beams A2 15 0% 18-Jan-11 03-Feb-11 SR138,353
BSA110 Steel Fixing for Cross Head Beam @ A2 15 0% 26-Jan-11 12-Feb-11 SR276,705
BSA120 PT Bars/Ducts & Accessories fixing A2 7 0% 07-Feb-11 14-Feb-11 SR419,580
BSA130 Closing Shutter & Concrete pouring @ A2 3 0% 13-Feb-11 15-Feb-11 SR230,587
BSA140 Side Formwork Removal & Cleaning 2 0% 16-Feb-11 17-Feb-11 SR23,059
BSA150 Initial Stressing- Cross Head Beams (PT+Tendons) 18 0% 19-Feb-11 10-Mar-11 SR104,895
BSA160 Pot Bearings Erection on Abutment 7 0% 12-Mar-11 19-Mar-11 SR222,557
Pier Columns
Colum Works 132 0% 13-Oct-10 16-Mar-11 SR3,370,807
BSP010 Excavation of Roads upto required pile levels 5 0% 13-Oct-10 18-Oct-10 SR196,350
BSP020 Execution of Piles for Pier P4 12 0% 19-Oct-10 01-Nov-10 SR439,560
BSP030 Exca. upto required level & Pile Trimming 10 0% 02-Nov-10 13-Nov-10 SR14,400
BSP040 100mm Plain Concrete Slab Laying 1 0% 14-Nov-10 14-Nov-10 SR84,000
BSP050 Pile Head Treatments 10 0% 16-Nov-10 27-Nov-10 SR73,260
BSP060 Foundations (Pile Caps) for Pier P4 15 0% 28-Nov-10 14-Dec-10 SR722,800
BSP070 Waterproofing Membrane/Coating upto Ground l... 7 0% 15-Dec-10 22-Dec-10 SR40,027
BSP080 Backfilling Above Foundation Pier 12 0% 23-Dec-10 05-Jan-11 SR31,875
BSP090 Execution of Columns @ Pier P4 14 0% 06-Jan-11 22-Jan-11 SR352,800
BSP100 Formwork for Cross Head Beams Piers P4 15 0% 23-Jan-11 08-Feb-11 SR138,353
BSP110 Steel Fixing for Cross Head Beam @ P4 15 0% 31-Jan-11 16-Feb-11 SR276,705
BSP120 PT Bars/Ducts & Accessories fixing Piers P4 7 0% 12-Feb-11 19-Feb-11 SR419,580
BSP130 Closing Shutter & Concrete pouring @ P4 3 0% 17-Feb-11 20-Feb-11 SR230,587
BSP140 Side Formwork Removal & Cleaning 2 0% 20-Feb-11 21-Feb-11 SR23,059
BSP150 Initial Stressing- Cross Head Beams (PT+Tendons) 18 0% 22-Feb-11 14-Mar-11 SR104,895
BSP160 Pot Bearings Erection on Pier 7 0% 09-Mar-11 16-Mar-11 SR222,557
Earth Retaining
Retain Wall 159 0% 30-Nov-10 02-Jun-11 SR1,285,718
North Side R
Retaining Wall 106 0% 30-Nov-10 02-Apr-11 SR642,859
BNW010 Reinf. Earth Wall System NE Side for Ht=4m 25 0% 30-Nov-10 28-Dec-10 SR119,088
BNW015 Compacted Backfill in Layers 25 0% 06-Dec-10 03-Jan-11 SR0
BNW020 Reinf. Earth Wall System NE Side upto req lvl 20 0% 29-Dec-10 20-Jan-11 SR119,088
BNW030 Compacted Backfill in Layers 20 0% 04-Jan-11 26-Jan-11 SR36,000
BNW040 Reinf. Earth Wall System NW Side for Ht=4m 25 0% 29-Dec-10 26-Jan-11 SR119,088
BNW045 Compacted Backfill in Layers 25 0% 04-Jan-11 01-Feb-11 SR0
BNW050 Reinf. Earth Wall System NE Side upto req lvl 20 0% 27-Jan-11 19-Feb-11 SR119,088
BNW060 Compacted Backfill in Layers 20 0% 02-Feb-11 24-Feb-11 SR36,000
BNW070 Utilities - Lighting Conduits, Cables etc. 7 0% 24-Feb-11 03-Mar-11 SR67,169
BNW080 PC Parapet on Top of RE Walls NE side 20 0% 05-Mar-11 27-Mar-11 SR13,670
BNW090 PC Parapet on Top of RE Walls NW side 20 0% 10-Mar-11 02-Apr-11 SR13,670
South Side Retaining Wall 117 0% 18-Jan-11 02-Jun-11 SR642,859
BSW010 Reinf. Earth Wall System SE Side for Ht=4m 25 0% 18-Jan-11 15-Feb-11 SR119,088
BSW015 Compacted Backfill in Layers 25 0% 24-Jan-11 21-Feb-11 SR0
BSW020 Reinf. Earth Wall System NE Side upto req lvl 20 0% 16-Feb-11 10-Mar-11 SR119,088
BSW030 Compacted Backfill in Layers 20 0% 22-Feb-11 16-Mar-11 SR36,000
BSW040 Reinf. Earth Wall System SW Side for Ht=4m 25 0% 16-Feb-11 16-Mar-11 SR119,088
BSW050 Reinf. Earth Wall System NE Side upto req lvl 20 0% 17-Mar-11 09-Apr-11 SR119,088
BSW060 Compacted Backfill in Layers 30 0% 23-Mar-11 26-Apr-11 SR36,000
BSW070 Utilities - Lighting Conduits, Cables etc. 7 0% 27-Apr-11 04-May-11 SR67,169
BSW080 PC Parapet on Top of RE Walls SE Side 20 0% 05-May-11 28-May-11 SR13,670
BSW090 PC Parapet on Top of RE Walls SW Side 20 0% 11-May-11 02-Jun-11 SR13,670

Start Date 27-Aug-08 Data Date 08-Jul-10 Actual Work INTERSECTION OF PR. MAJID ST. WITH PR. MOHD BIN ABDUL AZIZ ST.  Date Revision Checked Approved
07-Oct-08 Baseline Schedule
Remaining Work TAHLIA) REVISION # 2 SCHEDULE
07-Apr-09 Revised Schedule
Finish Date 07-Sep-11 Must Finish Date 07-Sep11 Critical Remaining Work (FINAL DESIGN) PROJECT No. B4‐10047(555) 21-Apr-09 Resubmittal with cost correction
Milestone HUTA Hegerfeld Saudia Ltd 28-Jan-10 Time Extension Claim Schedule
(c) Primavera Systems, Inc. Page 11 of 15 08-Jul-10 As per Consultant (MTMM) Commepnts
Activity ID Activity Name Orig % Start Finish Budgeted Total 2009 2010 2011
Dur Comp CostS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

Center Port
Portion of Flyover Bridge & Underpass 274 0% 21-Oct-10 07-Sep-11 SR21,237,799
Underpass Center Portion 199 0% 17-Jan-11 07-Sep-11 SR7,107,813
Sub-Structure of Underpass
Sub-Struct 117 0% 17-Jan-11 02-Jun-11 SR4,105,188
UCP010 Exca. of Roads Sta 0+321 to 0+378 (Layer 1) 24 0% 17-Jan-11 14-Feb-11 SR785,400
UCP020 Const. of MERW from Sta 0+321 to 0+378 (Layer1) 24 0% 19-Jan-11 16-Feb-11 SR288,600
UCP030 Exca.with Dewatering Sta 0+321 to 0+378 (Layer2) 20 0% 08-Feb-11 03-Mar-11 SR398,040
UCP050 Const. of MERW from Sta 0+321 to 0+378 (Layer2) 20 0% 10-Feb-11 06-Mar-11 SR144,300
UCP060 Exca.with Dewatering Sta 0+321 to 0+378 (Layer3) 15 0% 26-Feb-11 15-Mar-11 SR497,550
UCP070 Const.of MERW from Sta 0+321 to 0+378 (Layer3) 15 0% 28-Feb-11 17-Mar-11 SR72,150
UCP080 Exca.with Dewatering Sta 0+321 to 0+378 (Layer4) 12 0% 12-Mar-11 26-Mar-11 SR497,550
UCP090 Const. of MERW from Sta 0+321 to 0+378 (Layer4) 12 0% 14-Mar-11 28-Mar-11 SR72,150
UCP100 100mm Plain Concrete Slab Laying 1 0% 28-Mar-11 29-Mar-11 SR19,200
UCP110 Waterproofing Membrane above Blinding Conc. 7 0% 28-Mar-11 05-Apr-11 SR46,550
UCP120 Protection Screed Concrete 1 0% 05-Apr-11 06-Apr-11 SR68,888
UCP130 Raft Foundation Reinforcements 14 0% 06-Apr-11 23-Apr-11 SR216,450
UCP140 Concrete for Raft Foundation 1 0% 24-Apr-11 25-Apr-11 SR216,450
UCP150 Steel Reinforcement for Side Retaining Walls 14 0% 25-Apr-11 11-May-11 SR360,750
UCP160 Concrete for Side Retaining Walls 1 0% 11-May-11 12-May-11 SR288,600
UCP170 Waterproofing Membrane/Protection Board on W... 5 0% 12-May-11 18-May-11 SR90,060
UCP180 Backfilling around Ret./Pump Stn Walls & Columns 15 0% 16-May-11 02-Jun-11 SR42,500
Super Structure
Stru of Underpas 95 0% 18-May-11 07-Sep-11 SR3,002,626
UCP190 Retaining Wall Corbel - and BackWall 12 0% 18-May-11 01-Jun-11 SR216,450
UCP200 Execution of Mortar bed for Bridge U beams 5 0% 28-May-11 02-Jun-11 SR148,371
UCP210 Transportation / Erection of Bridge U Beams 20 0% 01-Jun-11 25-Jun-11 SR216,450
UCP220 Post Tensioning / Grouting of Bridge U Beams 15 0% 12-Jun-11 29-Jun-11 SR216,450
UCP230 Installation of Precast Concrete Slab Panels 15 0% 15-Jun-11 03-Jul-11 SR288,600
UCP240 Reinforcement Steel for Cast-in-Stu Top Slab 15 0% 18-Jun-11 05-Jul-11 SR432,900
UCP250 Concrete Casting of Cast-in-Situ Top Slab 1 0% 05-Jul-11 06-Jul-11 SR360,750
UCP260 Stitching Concrete-Gr. Bridge Adjoining Old/New 3 0% 06-Jul-11 10-Jul-11 SR72,150
UCP270 Back Wall Construction for the Bridge portion 12 0% 09-Jul-11 23-Jul-11 SR144,300
UCP280 Approach Slab on Both Sides of Tunnel Deck 16 0% 19-Jul-11 07-Aug-11 SR144,300
UCP290 Water proofing Membrane for Bridge Top Slab 5 0% 06-Aug-11 11-Aug-11 SR150,100
UCP300 Plain Concrete Curb for Walkway on Deck Slab 7 0% 11-Aug-11 20-Aug-11 SR29,925
UCP310 Asphalt wearing course on top of Ground Bridge 2 0% 17-Aug-11 20-Aug-11 SR16,950
UCP320 Expansion Joint Treatment 12 0% 20-Aug-11 04-Sep-11 SR280,380
UCP330 Walkway Plain Concrete fill 5 0% 27-Aug-11 01-Sep-11 SR19,950
UCP340 Precast Concrete Tiles (40X40X4 cm) 6 0% 31-Aug-11 07-Sep-11 SR264,600
Flyover Bridge
Brid Centeral Portion 274 0% 21-Oct-10 07-Sep-11 SR10,344,291
UBC010 Piles Execution - Column(P2 & P3) Foundations 15 0% 21-Oct-10 07-Nov-10 SR879,120
UBC020 Excavation & Pile Trimming upto required level 10 0% 28-Oct-10 08-Nov-10 SR16,560
UBC030 100mm Plain Concrete under Column Foundations 1 0% 09-Nov-10 09-Nov-10 SR19,200
UBC040 Waterproofing Membrane above Blinding Conc. 4 0% 10-Nov-10 14-Nov-10 SR30,020
UBC050 Protection Screed Conc & Pile Head Treatment 1 0% 16-Nov-10 16-Nov-10 SR68,888
UBC060 Execution of Pile Cap Foundation for Pier P2 14 0% 17-Nov-10 02-Dec-10 SR176,400
UBC070 Execution of Pile Cap Foundation for Pier P3 14 0% 23-Nov-10 08-Dec-10 SR176,400
UBC080 Execution of Columns @ Pier P2 18 0% 04-Dec-10 23-Dec-10 SR418,950
UBC085 Execution of Columns @ Pier P3 18 0% 09-Dec-10 29-Dec-10 SR418,950
UBC100 Waterproofing Membrane/Protection Board -Colu... 7 0% 30-Dec-10 06-Jan-11 SR90,060
UBC110 Backfilling upto Ground Level 10 0% 08-Jan-11 18-Jan-11 SR31,875

Start Date 27-Aug-08 Data Date 08-Jul-10 Actual Work INTERSECTION OF PR. MAJID ST. WITH PR. MOHD BIN ABDUL AZIZ ST.  Date Revision Checked Approved
07-Oct-08 Baseline Schedule
Remaining Work TAHLIA) REVISION # 2 SCHEDULE
07-Apr-09 Revised Schedule
Finish Date 07-Sep-11 Must Finish Date 07-Sep11 Critical Remaining Work (FINAL DESIGN) PROJECT No. B4‐10047(555) 21-Apr-09 Resubmittal with cost correction
Milestone HUTA Hegerfeld Saudia Ltd 28-Jan-10 Time Extension Claim Schedule
(c) Primavera Systems, Inc. Page 12 of 15 08-Jul-10 As per Consultant (MTMM) Commepnts
Activity ID Activity Name Orig % Start Finish Budgeted Total 2009 2010 2011
Dur Comp CostS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

UBC120 Pot Bearings Erection on Piers P2 & P3 4 0% 19-Jan-11 23-Jan-11 SR445,113


UBC130 Formwork - Cross Heads incl Cantilevers P2 25 0% 24-Jan-11 21-Feb-11 SR138,353
UBC140 Steel Fixing/Forms Closing - Cross Heads P2 25 0% 26-Jan-11 23-Feb-11 SR276,705
UBC150 PT Bars/Ducts & Accessories fixing in CH @ P2 10 0% 19-Feb-11 01-Mar-11 SR419,580
UBC160 Closing Shutter & Concrete - Cross Head Beams... 5 0% 26-Feb-11 02-Mar-11 SR230,588
UBC170 Formwork - Cross Heads incl Cantilevers P3 25 0% 30-Jan-11 27-Feb-11 SR138,353
UBC171 Steel Fixing/Forms Closing - Cross Heads P3 25 0% 01-Feb-11 01-Mar-11 SR276,705
UBC172 PT Bars/Ducts & Accessories fixing in CH @ P3 10 0% 21-Feb-11 03-Mar-11 SR419,580
UBC173 Closing Shutter & Concrete - Cross Head Beams... 5 0% 28-Feb-11 05-Mar-11 SR230,588
UBC180 Side Formwork Removal & Cleaning 8 0% 06-Mar-11 14-Mar-11 SR46,118
UBC190 Initial Stressing- Cross Head Beams (PT+Tendons) 6 0% 12-Mar-11 17-Mar-11 SR209,790
UBC200 Erection of Precast U Beams 36 0% 17-Mar-11 27-Apr-11 SR276,705
UBC210 Stitching Concrete between U Beams / Cross He... 24 0% 04-Apr-11 01-May-11 SR92,235
UBC220 Initial Stressing of Complete Via Duct 8 0% 01-May-11 09-May-11 SR209,790
UBC230 Final Stressing / Grouting - Cross Head Beams 8 0% 09-May-11 17-May-11 SR419,580
UBC240 Final Stressing / Grouting of Complete Via Duct 5 0% 17-May-11 22-May-11 SR419,580
UBC250 Backwall on Abutment A1 15 0% 23-May-11 08-Jun-11 SR110,250
UBC260 Approach Slab near Abutment A1 Backwall 10 0% 07-Jun-11 18-Jun-11 SR132,300
UBC270 Backwall on Abutment A2 15 0% 30-May-11 15-Jun-11 SR110,250
UBC280 Approach Slab near Abutment A2 Backwall 10 0% 14-Jun-11 25-Jun-11 SR132,300
UBC290 Precast Slab Panels Installation above U Beams 25 0% 23-May-11 20-Jun-11 SR276,705
UBC300 Reinforcement Steel fixing for Top Slab 25 0% 08-Jun-11 06-Jul-11 SR461,175
UBC310 Concrete pouring of Top Slab 2 0% 07-Jul-11 09-Jul-11 SR368,940
UBC320 Side Formwork Removal & Area Cleaning 2 0% 10-Jul-11 11-Jul-11 SR46,118
UBC330 Static Load Test for the Bridge 7 0% 10-Jul-11 17-Jul-11 SR743,400
UBC340 Dynamic Load Test for the Bridge 7 0% 13-Jul-11 20-Jul-11 SR1,373,400
UBC350 Precast Parapet Barrier fixing on Edges 12 0% 24-Aug-11 07-Sep-11 SR13,670
Pump Station
Statio Works 211 0% 15-Dec-10 17-Aug-11 SR3,785,695
UPS010 Excavation for Pump Station 5 0% 15-Dec-10 20-Dec-10 SR10,080
UPS020 Dewatering & Deep Excavations for Pump Station 10 0% 21-Dec-10 01-Jan-11 SR696,570
UPS030 Execution of Pump Station Foundation 5 0% 02-Jan-11 06-Jan-11 SR2,520
UPS040 Execution of Shoring Wall for Pump Station 8 0% 08-Jan-11 16-Jan-11 SR144,300
UPS050 Stage 1 - Side Walls of Pumps Lift Pit 16 0% 17-Jan-11 03-Feb-11 SR72,150
UPS060 Backfilling upto the Pump room Middle Slab 7 0% 05-Feb-11 12-Feb-11 SR31,875
UPS070 Middle Slab of Lift Pit - Pump Station 12 0% 13-Feb-11 26-Feb-11 SR72,150
UPS080 Stage 2 - Pump Station Side Walls 18 0% 27-Feb-11 19-Mar-11 SR57,720
UPS090 Pump Station Top Slab 8 0% 20-Mar-11 28-Mar-11 SR230,880
UPS100 Waterproofing works for Pump Station Top Slab 5 0% 29-Mar-11 03-Apr-11 SR48,600
UPS110 Backfilling around Pump Stn upto Ground level 18 0% 04-Apr-11 24-Apr-11 SR21,250
UPS120 Inside Surface Treatment for Waterproofing 8 0% 16-Apr-11 24-Apr-11 SR48,600
UPS130 Installation of Pumping Pipeline with Valves etc 20 0% 25-Apr-11 17-May-11 SR176,175
UPS140 Installation of 3 ton Wench with the Roof Slab 8 0% 18-May-11 26-May-11 SR293,625
UPS150 Installation of 3 Submersible Pumps 24 0% 28-May-11 23-Jun-11 SR1,174,500
UPS160 Installation of Ladders, Covers etc. 25 0% 25-Jun-11 23-Jul-11 SR117,450
UPS170 Installation of Panel Board for the Pumps 12 0% 24-Jul-11 06-Aug-11 SR352,350
UPS180 Elect. Connection, Testing & Commissioning 10 0% 07-Aug-11 17-Aug-11 SR234,900
Utilities & R
Road Works 123 0% 16-Apr-11 06-Sep-11 SR14,186,545
Underpass 122 0% 16-Apr-11 06-Sep-11 SR9,738,346
Utilities Before
Be Road Works 61 0% 16-Apr-11 26-Jun-11 SR7,454,679

Start Date 27-Aug-08 Data Date 08-Jul-10 Actual Work INTERSECTION OF PR. MAJID ST. WITH PR. MOHD BIN ABDUL AZIZ ST.  Date Revision Checked Approved
07-Oct-08 Baseline Schedule
Remaining Work TAHLIA) REVISION # 2 SCHEDULE
07-Apr-09 Revised Schedule
Finish Date 07-Sep-11 Must Finish Date 07-Sep11 Critical Remaining Work (FINAL DESIGN) PROJECT No. B4‐10047(555) 21-Apr-09 Resubmittal with cost correction
Milestone HUTA Hegerfeld Saudia Ltd 28-Jan-10 Time Extension Claim Schedule
(c) Primavera Systems, Inc. Page 13 of 15 08-Jul-10 As per Consultant (MTMM) Commepnts
Activity ID Activity Name Orig % Start Finish Budgeted Total 2009 2010 2011
Dur Comp CostS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

Storm Water
Wa Utilities Works 49 0% 27-Apr-11 22-Jun-11 SR794,250
UUR010 Installation of Storm Water Pipe & Gutter Drains 30 0% 27-Apr-11 31-May-11 SR525,970
UUR020 Gutter Drains Interconnection/Pump Stn Pipeline 25 0% 04-May-11 01-Jun-11 SR20,460
UUR030 Gutter Drain Covers & Grating 30 0% 09-May-11 12-Jun-11 SR27,280
UUR040 Catch Basins with Connection to nearest Drain 30 0% 11-May-11 14-Jun-11 SR18,593
UUR050 Slow Down Chamber for Stormwater 7 0% 15-Jun-11 22-Jun-11 SR201,947
Electrical Utilities Works 61 0% 16-Apr-11 26-Jun-11 SR6,660,429
EUW010 Insta.of Lt Poles with Foundation 12Mt West side 14 0% 16-Apr-11 02-May-11 SR259,101
EUW020 Insta.of Lt Poles with Foundation 12Mt East side 14 0% 21-Apr-11 08-May-11 SR259,101
EUW030 High Mast LPs with Foundation/Insp Pits North 12 0% 24-Apr-11 08-May-11 SR264,742
EUW035 High Mast LPs with Foundation/Insp Pits North 12 0% 24-Apr-11 08-May-11 SR264,742
EUW040 Luminaire High Pressure Sodium 1000 Wt 12 0% 26-Apr-11 10-May-11 SR46,240
EUW050 Low Voltage Switch Board w/500kVA Transformer 12 0% 08-May-11 22-May-11 SR120,638
EUW060 Electrical SubStation 500kVA 12 0% 08-May-11 22-May-11 SR844,194
EUW070 Electrical Cable Trench Excavation West Side 14 0% 14-May-11 30-May-11 SR1,025,800
EUW080 Installation of Electrical Cables 10 0% 17-May-11 29-May-11 SR577,760
EUW090 Electrical Cable Trench Excavation East Side 14 0% 17-May-11 02-Jun-11 SR1,025,800
EUW100 Installation of Electrical Cables 10 0% 23-May-11 04-Jun-11 SR577,760
EUW110 Handholes / Earthing Pits / Inspection Chambers 10 0% 29-May-11 09-Jun-11 SR836,388
EUW120 Street Light Poles/Fixtures fixing 10 0% 04-Jun-11 15-Jun-11 SR222,086
EUW130 Underpass Amenity Lights inside the Tunnel 14 0% 09-Jun-11 26-Jun-11 SR304,086
EUW140 Supply & Install Distribution Board DB-SL 14 0% 09-Jun-11 26-Jun-11 SR31,991
Road Works 57 0% 21-Jun-11 28-Aug-11 SR895,300
UTRW010 Expansion joints Sealant Filler 15 0% 21-Jun-11 09-Jul-11 SR140,190
UTRW020 New Jersy Concrete Barrier Double Face - Tunnel 15 0% 27-Jun-11 14-Jul-11 SR273,400
UTRW030 Gravel & Sand Filling / Levelling in Underpass 12 0% 02-Jul-11 16-Jul-11 SR28,800
UTRW040 Subgrade Layer with compaction 15 0% 07-Jul-11 25-Jul-11 SR34,560
UTRW050 Aggregate Base Course (ABC) with compaction 15 0% 11-Jul-11 28-Jul-11 SR253,500
UTRW060 Prime Coat MC-1 for portion w/out Raft Slab 5 0% 25-Jul-11 31-Jul-11 SR2,000
UTRW070 70mm Bituminous Base Course w/out Raft Slab 12 0% 31-Jul-11 14-Aug-11 SR105,000
UTRW080 Tack Coat for Underpass Raft Slab 10 0% 09-Aug-11 21-Aug-11 SR5,000
UTRW090 Tack Coat for portion w/out Raft Slab 10 0% 13-Aug-11 25-Aug-11 SR2,000
UTRW100 50mm Asphalt Wearing Course for Underpass 12 0% 13-Aug-11 28-Aug-11 SR50,850
Misc. Work
Works After Road Works 15 0% 18-Aug-11 06-Sep-11 SR1,388,367
UUMW010 Ret.Thermoplastic Road Marking & Ceramic Studs 12 0% 18-Aug-11 03-Sep-11 SR106,050
UUMW020 Gantry Sign Support Footings, Instal & Lighting 12 0% 22-Aug-11 06-Sep-11 SR1,282,317
UUMW030 Snag List & Handing Over of Underpass works 14 0% 20-Aug-11 06-Sep-11 SR0
Flyover Bridge
Brid 110 0% 01-May-11 06-Sep-11 SR4,448,199
Utilities Before
Be Road Works 50 0% 01-May-11 27-Jun-11 SR1,113,136
Storm Water
Wa Utilities Works 36 0% 01-May-11 11-Jun-11 SR292,253
BUT010 Gully Drains / Drop Down to Ground Catch Basins 24 0% 01-May-11 28-May-11 SR120,216
BUT020 Storm Water Collecting Basins with Grating Cover 10 0% 19-May-11 30-May-11 SR132,984
BUT030 Catch Basins connected to Nearest Drain Manhol... 8 0% 28-May-11 05-Jun-11 SR18,593
BUT040 Gutter Drains for Bridge portion 12 0% 29-May-11 11-Jun-11 SR20,460
Electrical Utilities Works 48 0% 02-May-11 27-Jun-11 SR820,883
BUE010 Installation of Light Poles with Foundation 12Mt 20 0% 02-May-11 25-May-11 SR371,983
BUE020 Luminaire High Pressure Sodium 400 Wt 15 0% 10-May-11 28-May-11 SR144,814
BUE030 Installation of Street / Amenity Light Cables 20 0% 28-May-11 20-Jun-11 SR152,043
BUE040 Installation of Amenity Light Fixters 20 0% 31-May-11 23-Jun-11 SR76,022

Start Date 27-Aug-08 Data Date 08-Jul-10 Actual Work INTERSECTION OF PR. MAJID ST. WITH PR. MOHD BIN ABDUL AZIZ ST.  Date Revision Checked Approved
07-Oct-08 Baseline Schedule
Remaining Work TAHLIA) REVISION # 2 SCHEDULE
07-Apr-09 Revised Schedule
Finish Date 07-Sep-11 Must Finish Date 07-Sep11 Critical Remaining Work (FINAL DESIGN) PROJECT No. B4‐10047(555) 21-Apr-09 Resubmittal with cost correction
Milestone HUTA Hegerfeld Saudia Ltd 28-Jan-10 Time Extension Claim Schedule
(c) Primavera Systems, Inc. Page 14 of 15 08-Jul-10 As per Consultant (MTMM) Commepnts
Activity ID Activity Name Orig % Start Finish Budgeted Total 2009 2010 2011
Dur Comp CostS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

BUE050 Installation of Street Light Fixters 20 0% 04-Jun-11 27-Jun-11 SR76,022


Road Works 88 0% 17-May-11 28-Aug-11 SR1,510,475
BUR010 Precast Concrete Curbs on Edge & Middle 21 0% 17-May-11 09-Jun-11 SR415,800
BUR020 Levelling of Backfill in retaining wall areas 7 0% 14-Jun-11 21-Jun-11 SR14,400
BUR030 30cm Subgrade Layer with compaction 12 0% 22-Jun-11 05-Jul-11 SR66,240
BUR040 20cm Aggregate Base Course (ABC) with compa... 15 0% 26-Jun-11 12-Jul-11 SR253,500
BUR050 Prime Coat MC-1 for Ramps portion 4 0% 11-Jul-11 14-Jul-11 SR6,000
BUR060 70mm Bituminous Base Course for Ramps Portion 7 0% 14-Jul-11 21-Jul-11 SR105,000
BUR070 Tack Coat for Bridge Portion 4 0% 20-Jul-11 24-Jul-11 SR5,000
BUR080 50mm Asphalt Wearing Course for Complete Bri... 3 0% 23-Jul-11 25-Jul-11 SR49,155
BUR090 Expansion Joint Treatment 12 0% 23-Jul-11 04-Aug-11 SR280,380
BUR100 Sand fill in side & middle curb / walkways 15 0% 25-Jul-11 10-Aug-11 SR138,600
BUR110 Pavement Tiles 40 x 40 x 4 24 0% 31-Jul-11 28-Aug-11 SR176,400
Misc. Work
Works After Road Works 36 0% 26-Jul-11 06-Sep-11 SR1,824,589
BUM010 Ret.Thermoplastic Road Marking & Ceramic Studs 8 0% 26-Jul-11 03-Aug-11 SR106,050
BUM020 Gantry Sign Support Footings, Instal & Lighting 25 0% 31-Jul-11 29-Aug-11 SR1,282,317
BUM030 Highway Signs/Sign Boards & Sign Supports all Ty 25 0% 08-Aug-11 06-Sep-11 SR436,222
Demobilization & Hand Over
Demobilizat 11 0% 27-Aug-11 07-Sep-11 SR0
Demobilization
Demobilizat 11 0% 27-Aug-11 07-Sep-11 SR0
DMB010 Demobilization & finishing Touches 10 0% 27-Aug-11 06-Sep-11 SR0
DMB020 Handover of Complete Bridge & Underpass 2 0% 05-Sep-11 07-Sep-11 SR0

Start Date 27-Aug-08 Data Date 08-Jul-10 Actual Work INTERSECTION OF PR. MAJID ST. WITH PR. MOHD BIN ABDUL AZIZ ST.  Date Revision Checked Approved
07-Oct-08 Baseline Schedule
Remaining Work TAHLIA) REVISION # 2 SCHEDULE
07-Apr-09 Revised Schedule
Finish Date 07-Sep-11 Must Finish Date 07-Sep11 Critical Remaining Work (FINAL DESIGN) PROJECT No. B4‐10047(555) 21-Apr-09 Resubmittal with cost correction
Milestone HUTA Hegerfeld Saudia Ltd 28-Jan-10 Time Extension Claim Schedule
(c) Primavera Systems, Inc. Page 15 of 15 08-Jul-10 As per Consultant (MTMM) Commepnts