Appendix 5: Electrical Load Assessment Outline Development Control Plan

St James's Hospital Appendix 5


Electrical Load Assessment
for
Outline Development Control Plan ( Signed Off Scheme ) Electrical Load Assessment
Ref Description Area ( m2 ) Remarks

2
1.0 Existing Site: 113584.00 Total = 124704m
IBTS ( 11120 m2 ) - separate supply
Clinical Sciences Complex included
2.0 New Developments ( as in original brief ): - included in item 6 below
( from Phase 1A to Phase 4A inclusive )

3.0 Existing Buildings to be demolished: 31635.77 to be deleted

4.0 Existing Buildings/ Facilities to be relocated off site: 4042.00 to be deleted

5.0 Demolished Buildings to be re-provided: - included in item 6 below

6.0 Additional Buildings ( outside original brief ) 151462.70 Total = 163704.4


Private Hospital = 37800 ( sep supply )
Long Term Developments = 25558.3
New Total Area: 229368.93
say 230000 inc 25-28% circulation space/
communication and Plant areas

Ref Electrical Load Total Connected Diversified Load

1.0 Lighting ( 12W/m2 )


2760000
Apply diversity factor of 0.9 2484000

2.0 Small Power ( see also note 2 and 3 below )


Ward Areas
150000
Apply diversity factor of 0.8 120000
Offices and Departmental Areas
5250000
Apply diversity factor of 0.8 4200000

3.0 Mechanical Cooling


No diversity is applied 2820000
2820000

4.0 Mechanical Equipment and Ancillary Systems


( see note 4 below ) 1207500
No diversity is applied 1207500

Total 10831500

Allow space capacity of 25% for future expansion 13539375 W


13.54 MW
With a power factor of 0.95, Total Maximum Demand = 14.25 MVA
say 14.50 MVA

Existing capacity of CHP 1.003 MW


Power required from the ESB = 14.91 - 1.003 = 12.54 MW
or 13.20 MVA
say 13.50 MVA
Note:
1.0 The floor areas are based on:
Architect's Existing Accommodation Area Schedule dated 12May 2006 and
Summary Schedule of Accommodation P10 070125
2.0 Ignore power for cleaning sockets in the circulation space/ communication and Plant areas
3.0 Small power of 35 W/m2 includes medical electrical equipment
4.0 75% of the net departmental areas is served by mechanical cooling
5.0 Allow CoP = 3.5
6.0 The calculation above include Trinity College and Haughton Institute

March 2008 Page 349

Anshen+Allen Team