You are on page 1of 34

SYSTEM PROTECTION AND VOLTAGE STABILITY

A SPECIAL PUBLICATION OF THE


IEEE POWER SYSTEM RELAYING COMMITTEE

PREPARED BY

WORKING GROUP K12


PROTECTION AIDS TO VOLTAGE STABILITY

JUNE 1993
Abstracting is permitted with credit to the sour@. lnstructors are permitted to photocopy isolated
articles
for noncommercial classroom use without fee. For coping, reprint, or republication permission, write
to the
IEEE Copyrights Manager, IEEE Service Center, 445 Hoes Lane,P.O. Box 1331, piscataway,
NJ 0gg55-1gg1.
All rights reserved. Copyright O 1993 by The lnstitute of Electrical and Electronics Engineeri,
lnc.
IEEE Catalog Nunber: 93THO 596-7 pWR
ISBN Softbound: 0-7803-9981 -1

Additional copies are available from


IEEE Service Center
445 Hoes [*ane
Piscataway, NJ 08854-41 50
1-800-678-IEEE
SYSTEM PROTECTION AND VOLTAGE STABILIT1

Engineering Societv

TABLE OF CONTENTS

1.0 Introduction.............. """" 1

2.0 Voltage Stabiliry """""""' 1

2.1 Some Voltage Collapse tncidents.... """"""2


2.ZTheMechanism of Voltage Co1lapse..... """"""""""""' 3
2.3 Solutions to Vottage Stability Problems... """"""""""" 8
3.0 Undervoltage I.oad Shedding """""" 10
3.1 General """"""""' 10
3.2 Distributed Measuring Relays """""""""" 13
3.3 Centralized Measuring Relay(s) """"""""' t3
3.4 Comparison of Distributed and centralized schemes. ............'......'.' 14
3.5 Other Concepts """""""""""' 15

3.6 Actual, or Pianned Installations """"""""' 77


TVA........... ........"'..'......... 17
Ontario Hydro, """"""""" 18
BC Hydro... """""""""""' 18

WesternWashington """"'20
Consumers Power Co.............' """"""'21
Florida Power and Light... """""""""" 21
ELECTRABEL (Belgium) """""""""'23
4.0 Other Protection Items Related to Low Voltages. """"""""""23
4.1 Generator Backup Protection... """""""""'23
4.2 Generator Overeicitation and Rotor Overload Protection. ............. ......................24
4.3 Generator Auxiliaries Protection '....."....'... """""""""' 25
4.4 Backup Line Protection With I-ong Reach Settings """'25
4.5 Voltagi Controlled Overcurrent Protection... """""""""26
5.0 Conclusion. """"""""""27
REFERENCES............. """""27
APPENDIX

June, 1993
A Report lYepared by the Power System Relaying Committee of the mEE Power
Engineering Society

This special report was prepared by the


Protection Aids to Yoltage Stability Working
Group of the Substation Protection
Subcommittee. At the time the report was
submitted for approval, May, 1993, the Working
Group membership consisted of M. Begovic, D.
Fulton, M.R Gorzalez, J. Goossens, E-A. Guro,
R.W. ffaas, C.F. Henville, G. Manchur, G.L.
Mictrel, R.C. Pastore, J. Postforoosh, G.L-
Schmitt, J.B. Williams, K. Zimmerman.
Contributions from former Working Group
member A.A. Burzese are also acknowledged.
1.0 lntroduction 2.A Voltaoe Stabilitv

As transmission systems become more heavily Voltage stability is defined by the System
loaded, the risk of voltage instability increases. Dynamic Performance Subcommiuee of the IEEE
Protective relay operations play a signiflcant part Power System Engineering Committee [Reference
in system voltage collapses, and relay engineers 1, page 2l as being the ability of a system to
need to understand the increased threat to reliable maintain voltage so that when load admittance is
relay perfofinance. This paper discusses the increased, load power will increase, and so that
possibilities of voltage instability in power both power and voltage are controllable. The
systems and how this risk will affect protective same reference defines a voltage collapse as being
relaying. The problem and symptoms of voltage the process by which voltage instability leads to a
instability are described, including references to very low voltage profile in a significant part of the
actual incidents. system.

Power system engineers cooperate with relay and A voltage collapse may be caused by a variety of
communications engineers to develop new means single or multiple contingencies. These may be
to minimize the risk of voltage collapse by the sudden removal of real or reactive power
application of new automatic protection and generation or a transmission element (a
control schemes. One such automatic scheme, transformer or a transmission line), an increase of
undervoltage load shedding, is discussed with load witlout an adequate increase of reactive
regard to system voltage characteristics and power, or the slow clearing of a system fault'
relaying techniques. The importance of
coordinating schemes with existing equipment is An electric power system is a dynamic system.
discussed. In addition, the advantages and Changes in the system occur due to a variety of
disadvantages of distributed and centralized causes such as: changes in demand or generation,
relaying are investigated along with several line switching, surges and faults. Slow changes
schemes now existing or planned to be instalted. due to changing loads and generation schedules
Experience with actual installations is also are always occurring, and may be considered as
described. changes from one steady state to another. Rapid
changes which are largely complete within a few
Other protection items related to low voltage are cycles are usually classified as dynamic' They
also presented. Such items as generator backup include switching and lightning surges and
protection, excitation system overload protection, electromechanical transients of synchronous
auxiliaries protection, backup line protection and machine rotors. Both rapid and slow changes
voltage controlled overcurent relaying are directly affect system voltage and can sometimes
discussed. lead to voltage collapse. The voltage collapse is
often a slow event relative to the traditional power
It should be noted that undervoltage load shedding system machine instability problems' It can occur
and other protection schemes described here are over periods of seconG to minutes to hours
the results of the Working Group's investigation, starting with sudden or gradual decrease in system
and are not intended to be a recommendation. It is voltage. While machine angular stabiiity
the purpose of the working group to spur problems may be associated with voltage collapse,
discussion and encourage more information to be this report does not discuss angular stability
published on this subject. concerns.
Several recent voltage collapse incidents have 2.1 Some Voltage Collapse lncidents
heightened the awareness of utility planners and
operators to the possibilities of such events[2,3]. The following brief descriptions of some recent
The possibilities increase as transmission lines severe incidents are intended to illustrate the
become more heavily loaded in an attempt to variety of ways in which the problem can develop.
maximize the efftcient use of existing generation The indicated references give more complete
and transmission facilities. As the dependen@ otr descriptions of the incidents and their causes.
power transmitted from remote generation sources
increases, the reactive power losses associated The voltage collapse that affected the Tennessee
with such transmission require increased local Valley Authority in August 1987 t5l was caused
reactive power supplies to maintain voltage by the slow clearing of a fault, during which the
stabilify[4]. system voltage fell to a low value and could not
recover before transmission line protection relays
The voltage stability of a power system is greatly operated to further aggravate the problem. The
dependent upon the amount, location and type of voltage during the fault was low enough to cause
reactive power sources available. If the reactive motors to staIl, resulting in locked rotor
power support is far away, insufficient in size, or conditions. This added reactive loading caused
too dependent on shunt capacitors, a relatively the voltage to desease further. After the fault was
normal contingency (such as a line outage or a removed from the system by protective means, the
sudden increase in load) can trigger a large system added reactive loading from the stalled motors
voltage drop. This voltage drop occurs because of kept the system voltage from rising to its pre-fault
several factors: level.
. Real power demanded by the load may stay
coflstant During the voltage collapse that affected the
. var requirements of the load may increase Tokyo Electric Power Company on July 23,
o vars supplied by shunt capacitors drop 1987[Reference 1, pages 125-132], a very fast
o vars supplied by line charging capacitance drop increase of load (4O0 MWminute) caused a
o vars absorbed by transmission lines increase gradual decrease of voltage that could not be
controlled by the addition of reactive power in the
If the voltage drops to a point where some motors form ofcapacitor banks. This illustrates a voltage
stall, the reactive power requirement increases collapse by the rapid increase of load without the
quickly, and the rate of voltage decline increases addition of adequate reactive power. Losing
similarly. Many large motors may be tripped off transmission facilities can also result in the loss of
line by their contactors. Smaller motors without voltage.
contactors must depend upon thermal cutouts and
may thus draw locked rotor currents for tens of The Swedish network power failure of December
seconds. Stailed motors can accelerate a voltage 17, 1983 [Reference 1, pages 115-125] was
collapse catastrophically t5l. initiated by the loss of a substation. Transmission
lines were overloaded and a 220 kY line was
Heavily loaded mnsmission lines during low tripped by overload protection. The voltage in the
voltage conditions can result in operation of southern part of the country decreased and
protective relays causing other lines to trip in a automatic tap changing went into operation, which
cascading mode. started restoring load but lowering voltages in the
northern part of the country. As a result, north-
Voltage stability is a serious problem that power south lines were overloaded and tripped by
utilities must explore in the planning stage [4]. It A system split resulted wit}
protection relays.
is imperative that methods to protect the system load being shed in power deficient areas.
from a voltage collapse be investigated by taking Approximately 11,400 MW of toad was
into account all contingencies that will cause the intemrpted by this event.
system to lose voltage stability.
ln March of 1989, a disturbance in Hydro Quebec MW delivered to the load. One notation
was attributed to geomagnetic fluctuations caused convention that has been proposed is to define the
by ilcreased solar activity. Quasi dc nominal load as the amount of load connected,
geomagnetically induced currents caused half measured by the amount of MW it would consume
cycle overexcitation in some transfofiners' which at nominal conditions, i.e., 1.0 p.u. voltage and
in turn generated increased harmonics in the frequency. Ttte actual load, also measured in
system. The increased harmonics tripped all MW (what is seen by the disparcher), is the actual
SVCs on the HV network. These banks were used power consumed by the load. In general it is
for voltage control in long radial transmission important to recognize that the nominal load is the
lines linking large generation facilities in the north independent variable dictating system behavior,
with the load centers in the south. Without the not the acnral load, which is dependent on the
needed voltage support, the whole network voltage and frequency.
collapsed within seconds. This is an example of a
very fast collaPse. Consider the behavior of two different fypes of
load -
"resistive" and "motor" load. Figure 1
In Belgium, on 4 August 1982, a voltage collapse shows the relationship between load and voltage
was initiated by a trip of a nuclear generator. The for these two different types of loads using
generator was loaded at 700 MW450 Mvar and simplified models. For this example, the resistive
was connected to the 40O kV system during load is defined as 7 5Vo resistive, aIJLd 25Vo constant
commissioning tests. Although there was ample power, that is, given bY the formula:
spinning reserve (1,300 MW = 23Vo,844 Mvar =
337o) with respect to peak load, the reactive power P = 0.25 + 0.75Y2 (where P is the actual
transfer to the generators electrically closest to the power, and V is the voltage, both on a per unit
tripped unit resulted in some field limiter actions nominal power and voltage basis)
followed by overload protection trip of 5 more
units. For 4 ll2 minutes from the initial outage' The motor load is 75Vo cnnstant power and25Vo
the frequency remained stable but the voltage (as resistive, and is defined as:
recorded at one 150 kV power station bus) showed
the typical voltage collapse almost in proportion P=0.75 +O.25Y2
to the square of the percentage of total Mvar
generation lost. After one of the major 400 kV tie
lines tripped (through end zone distance
protection) power oscillations and frequency
decline started in the affected region. Thus the o.
-1
angular stability was lost only after loss of the tie F]
line, and total collaPse followed. 3
o
J

2.2 The Mechanism of Voltage D


E,
U
4
0s

Collapse

Effect of load type. 09 1 l2 t3


oJ oa 11
VOLTAGE (pu.)
The fact that loads are generally voltage dependent
is a criticalaspect of voltage security analysis. Fisure 1, Load Voltage Relationshi
The language used to describe loads, when their
voltage and frequency dependence are included is
For the resistive load, when there is a voltage dip'
not yet well standardized. A clear distinction limit the
the load current also decreases, tending to
must be made between the amount of load dip. But the load reduction
severity of the voltage
intended to be served ftom a bus, and the actual
for the motor is significanfly less, and in fact the 1l
load current increases, thereby exacerbating the 1

voltage dip. This detrimental effect is more 0s


pronounced if reactive (e) loads are invotved, o3
since they commonly have greater effect on - o-7

voltage Ievels in the system. In fact, the Ioss of 9or S tessed System -------)
reactive power provided by power factor
o
p{
d'05
correction capacitors that are usually connected to )ol
motor loads causes motors to absorb even more o3
reactive power during a voltage dip than before o2
the dip. 01"

0
The ability of a given transmission system to OJ 0-3 0,a 05 os o.7 08 0s 1
Act:aLibrrer b!.)
deliver power is also limited by the voltage at the
deUvery point. Consider a simple ,yite. ,s
shown in Figure 2a). 2b) PV Curves

X=.5 pu (nornnl) If the axes of the curves of Figure 1 are exchaoged


X=.6 pu (stressed system) with each other, the curves of Figure 1 can be
overlaid on those of Figure 2b) to show the
operahng point ofa system as in Figure 3.

It can be seen from Figure 3 that for the particular


system and loads considered, the "normal system"
can operate stably with both resistive and motor
loads at pornts where the load curves and system
curve intersect. However, when the system
becomes stressed, it can only operate stably with a
resistive load. There is no intersection of system
and load curves for the motor load; so there is no
Figure 2a) Simple System stable operating point.

L/

The relationship of acrual power delivered to


the 1:
load conductance (GVz) versus the voltage at
the
load bus is shown in Figure 2b). 1

1
Two curves are plotted, for the "normal system,, ;tr
the value of the system reactance (X) is 0.5 p.u., :0,
and for the "stressed system" the value of X is
0.6 ot
p.u. It can be seen how the actual power delivered
to the load increases as tlte nominal power (load o,
conductaoce) increases from .33 p.u. (resistive)
o
until t}te "nose', of the curve is .eaihed, at which 02 ol 06 oB 1 1' rl
A ctEl pq, s (p !.)
time the delivered power decreases as the nominal
power increases further. Due to the increased
system reactance, the stressed system is Figure 3 Stable and Unstatrle Systemlload
able to Characteristics
deliver less acfual power than the normal system.
The curves of Figure 2b) are known as pV
curves.
Effect of Load Dynamics ttrat less heating power provided by a heater
will cause the heater to stay on longer in its
Since voltage stability is a relatively slow controlled cycle to maintain the thermostat
dynamic characteristic of a power system, load reference temperature. If a particular load is
characteristics must be considered over a long made up of several heaters, their diverse "off'
term also. For instance, electric heating load times will be reduced during a voltage
could be considered to be proportional to the reduction. Over a period of some tens of
square ofthe supply voltage, and indeed it is' over minutes, heating load which was reduced by a
a short term. If system voltage is reduced, heating voltage drop will be completely restored to
load will immediately drop proportionately to the original levels due to loss of diversity.
square of the voltage reduction. However, two
time related phenomena crunteract the loss of Thus heating load, when considered in the time
resistive load due to voltage reduction. ftame of voltage stabilify, is not constant
virtually constant power
resistance load at all, but
1 Voltage supplied to most customers is load. This near constant power characteristic
regulated by transformer tap changers or (over a long time frame) of heating load may
voltage regulators. Within a minute or two of cause slowly evolving voltage collapse. Such
a voltage reduction, regulating devices will phenomena is particularly of concern in systems
start to increase the voitages supplied to the with winter peaking loads [6].
loads, and restore the lost load. Figure 4
shows how the load characteristic of a heating Effect of Reactive Power Supplies and
load moves further to the right (nearer the Deficiencies
unstable nose of the curve) after tap changer
action boosts the voltage supplied to the loads The magnitude of the reaciive power component
by t2%. of the load has an even larger effect on voltage
stability than the dependence of load on voltage
P-V Orrves magnitude. Figure 5a) shows a simple system
I.4 with a load with a variable power factor, and
Hesistive (rn legJdion Figure 5b) shows the PV curves for a load with
1.2
load f 'reraPcttme'f i three different power factors. Considerably less
power can be delivered to an inductive load than
I
to a resistive load. [f shunt capacitors are added,
j to make the load appear capacitive, (leading power
factor), even more power can be transferred over
o
s the given system.
E 0.6

0.4

o.2

0
o.2 0.4 0.6 0.t | 1.2
hwer (p.u.)
re 4. Effect of Load Dynamics

2 an a longer time base, thermostatic effects


load. Virtually all electric heaters
also restore Figure 5a) Simple System with
are thermostatically conftolled. This means
capacitors is that as the system voltage drops, they
generate fewer vars, and cause the power factor
of
the load to decrease.
OE

In addition to shunt capacitors, utilities also often


b-dibd(d4"S) ---->
;6 need to apply dynamic sources of reactive power,
g
such as static var compensators, syrrchronous
condensers or local generation to maintain voltage
02
stability near load centers. Untike shunt
capacitors, tIrc total amount
of available reactive
o support from these reactive power sources does
not drop as the voltage drops (as long as the
l*.e is operating within its control range).
Dynamis sources are able to provide a variable
amount of reactive power to maintain desired
An important reason for increasing concrn about voltage levels.
voltage stability in the 1gg0,s and 'gO's is the
increasing loading of transmission lines. At light While PV curves are helpfuI in understanding the
loads, fhe reactive power provided by the charging phenomena of voltage stability and collapse, they
capacitance of a transmission line more than are not usefrrl for determining the reactive power
compensates for the reactive power absorbed by support needed at various polnts in a power
the line inductance. However, when line loading system. A more usefrrl curve is the Ve curve
exceeds the surge impedance loading, the reactive which shows the reactive power margin available
power absorbed by the line increases above the in a system. Figure 6 shows a Ve curve for two
reactiye power supplied by the charging different load levels at a particular point in a
capacitance. power system. The e axis shows the reactive
power that needs to be added or removed ftom a
Two factors contribute to the high reactive power bus to maintain a given vottage at a given load.
demanG of heavily loaded lines. Firsfly, the
power absorbed by the line increases as the square
of the load current. Secondly, the increased
reactive power losses cause a voltage drop, and
reactive power supplied by the line charging
capacitance drops as the square of line voltage.

As Iines become more heavily loaded, utilities


apply shunt capacitors more widely in an attempt
to control voltages near the receiving ends of
transmission systems. As shown in Figure 5b),
the leading power factor resulting from the
application of shunt capacitors allows an increased
power transfer capabili ty. Reactive Power Needed

Shunt capacitors are a double edged sword. re 6 VQ Curve


Though they increase the voltage transfer
capability of a system, the approach to the point of pornt A on the light load curve, if the voltage
collapse is more precipitous, and the polnt of lt
decreases, there is an excess of reactive power at
collapse is higher, (nearer the normal operating the bus, which will raise the voltage again. If the
voltage). Another detrimental effect oi shunt voltage increases, there will be a deficiency in
reactive power, which will cause the voltage to condenser generates maximum reactive power
drop. Thus point A is a stable operating point. ln with the rotor current limiter activated are also
the case of the heavy load, the curve is above the shown.
G0 line, and stable operation is not possible.
Reactive power must be added to the bus until the When the output of the synchronous condenser is
curve crosses the reestablished Q = 0 line' Thus limited by the rotor current limiter, the maximum
VQ curves can be used to help determine the transmissible power is reduced to Pmaxl due to
amount of reactive support needed at various the fact that voltage is maintained farther away
locations within the system. Full discussion of ftom tlrc load (at bus I instead of at bus 2). If the
VQ curves is beyond the scope of this paper. loading starts ftom point A on the curve with the
Reference 1 provides a comprehensive description voltage regulated at bus 2 and continues to point
of the application of PV and VQ curves' B, one may be misled to believe that the
loadability margin is (Pmax2-PB) instead of
Effect of System Characteristics (Pmaxl-PB), which is much smaller. This may
happen if it is not realized when the synchronous
Another mechanism of voltage collapse [7] may condenser rotor curent limiter becomes activated.
develop in systems characterized by long radial Therefore, instead of continuing loading along the
transmission links. One such system is shown in rajectory BD, the system could be loaded along
Figure 7a): a constant power load is supplied from the line BC, with substantially reduced maximum
a remote generator G via a long transmission line loading point. In large power systems, the
whose capacity is enhanced by a synchronous loadability margin at the point of transition @B-
condenser S which maintains cotNtant voltage at Pmaxl) may be small (or even negative) so that
bus 2. the voltages practically collapse as soon as the
limiters are activated [8].
Busl Bus2 Bus3 The associated PV
diagram (Figure 7b) Operating Practices
shows the load voltage
vs. transferred power Some operating practices may further aggravate
when voltage is kePt tlre situations when rotor curent limiters are being
Figure 7a\ Simple constant at bus 2 activated. In an attempt to bring a geoerator tr
System (trajectory ABD). The synchronous condenser off var limits under low
maximum transmissible power is Pmax2. TfE voltage conditions, the initial reaction of the
operating characteristics when the synchronous operating personnel may be to reduce the
generator terminal voltage in an attempt to reduce
the generated reactive power. This further reduces
the load voltages. Over a period of time'
I tapchangers (if not blocked) will increase load
voltages and thermostats will restore loads, thus
0.8 again activating the rotor current limiters, which
i
j
may prompt yet another reduction in terminal
{ u.6
voltage, bringing the system to voltage collapse.

Combined Effect of Generated and Absorbed


0.,1
Reactive and Real Power

0.2
It is considerably easier to transmit real power
Pmaxl than reactive power along a transmission system,
0
0.5 1
especially at high loads. The following example
Pows (p.u) is intended to assist in the visualization of the
Figure 7b) PV Curves
relationship between reactive power generated at The slope of the curve AC is infinite (or vertical)
the source of the transmission system, and the real at polnt C, meaning that the rate of change of eg
and reactive power consumed by the load. with increasing load beyond point D is infinite.
Any attempt to increase the Ioad beyond point D
Consider a simple power system consisting of a on a line BD will result in voltage collapse. point
generator connected to a constant power load via a D represents a voltage stability boundary to the p,
Eansmission line. The 3-D curve representing the Q load that can be served by the given system.
reactive power (Qg) produce<l by a generator as a All lines similar to the line DC, which project
function of the loading parameters P and Q has a vertically from the P, Q plane to meet the shaded
form as shown in Figure 8. surface tangentially, represent voltage stability
limits for the given system. These lines cross the
PQ plane aloug the dotted curve GDH, and meet
the shaded surface at the dotted curve ECF. Thus
the curve GDH represents the limit to the amount
of constant P,Q load that can be served, and any
attempt to serve more load will result in an infinite
rate of change of Qg [8, 10].

Therefore, in the vicinity of voltage collapse


points, small changes of P andlor Q will have a
large impact on the magnitude of generated
reactive power. These conclusions can be shown
to hold for the power system of arbitrary size and
topology, resulting in infinite sensitivity (on a
steady state basis) of the total generated reactive
power with respect to load parameters near
voltage collapse [8]. Figure 8 demonstrates the
difficulty of dispatching reactive power to support
voltage at remote locations. Reactive power is
most effective in raising system voltages when it
is generated near the load supply polnts.

Figure 8 Generated Reactive power


2.3 Solutions to Vottage Stabitity
vs.
Problems
Parameters in the Sample System
Voltage instability is an operating problem as well
Consider two operating points on the p-e plane, as a planning problem. The proper studies
shown as B and D, which correspond to the load performed during planning can detect when
requirements (PB, agl and (pD, eO) systems are susceptible to voltage instability
respectively. Point A represents ttre generated during certain loading levels and contingencies.
reactive power (Qq) required to satisfy the load When the studies have identified certain scenarios
requirements (PB,-QB) via a given mnsmission where voltage stability is at risk, plans may be
line. Point C shows Ure Qs corresponding to the made to modify the system to eliminate the risk.
heavier load (PD, QO). lTre slope of the curve If modifications are impractical, or cannot be
AC at any potnt represents the sensitivity of the implemented soon enough, system operators then
generated reactive power with respect to the have to operate the system in a manner such as to
loading parameters P, Q. As the load increases minimize the chance of voltage collapse with the
from point B to point D, the slope of the curve AC system as it is.
increases.
Operating Solutions System Modifications

It is of utrnost importance that system operators The addidon of transmission reinforcement is a


learn to recognize conditions where voltage most effective means of ensuring voltage stability.
stability is at risk so that they can be ready to act However, this option is expensive. The cost of a
if voltage collapse begins. Therefore, proper 500 kV line can be more than $700,000 per mile.
training is very important. However, even frilly Acquiring right of way land has met with
fained operators need comprehensive guidelines increasing difficulty as the question of electric and
describing scenarios where an additional single magnetic frelds @MF) becomes more publicized.
contingency can cause voltage collapse.
Series capacitors have been applied for voltage
Operating guidetnes may limit supply to stability purposes as they are a means of
intemrptible load, or may requke less than increasing transmission capability without
optimum generation schedules to ensure voltage building new lines. As well as being expensive,
stability is maintained after an unexpected single this optioo may introduce protection problems
contingency. associated with series compensated lines.

As a general principle, under normal conditions Running generators near the load supply points is
operators try to operate dynamic var sources such a method of adding var generation, and reducing
as synchronous condensers, generators and static transmission requirements. This option can also
var compensators (SVCs) with no import or export be expensive.
of vars. This has two benefits:
The installation of shunt capaciiors is often among
. keeping an instantaneous source of reactive the most inexpensive means of adding reactive
power available to maintain voltages in the power supplies near the load centers. Many
event of a sudden contingency which causes a utilities add such banla in an attempt to serve
voltage drop. more load from existing transmission and
. minimizing the effect on system voltage if the generation facilities. As mentioned in Section 2.2
var source is lost. this option is effective within certain limits. Fixed
shunt capacitors have the uldesirable effect of
Operators may consider the following strategy in providing less vars at low voltages, when more
near voltage-unstable situations: vars are required. Switched shunt capacitors arc
also very effective provided they can be controlled
. use all available reactive support. in such a manner as to avoid excessive wear on the
. Increase loading on, or start generators near switches. TVA applies switched capacitors as
load supply points to reduce line loading, even described in Section 3.6. Reactors which are
if such generation is not economic. normally always in service may also be switched
. maintain system voltage as high as possible, out to contol voltage.
even if this means operating generators at
reactive capability limits. The installation of synchronous condensers or
. block tap changers for temporary load relief, SVCs is also a help in stabilizing voltages during
and even reduce the voltages in the disturbances. This option can also be high in
distribution network before attempting more capital cost, but provides conrollable reactive
radical remedial actions. power supply with relatively low operating cost.
. if the problems persist start load shedding. Many utilities apply a combination of fixed
capacitors and dynamic reactive sources to
maintain desired voltages during steady state
conditions and during disturbances.
Load Shedding apply their knowledge of duration and magnitude
of voltage depressions during transient conditions
When the above mentioned solutions are not caused by faults or other disturbances. Tfrc
practical, or cannot be implemented soon enough, system plarmers fhen assess the probability of
load shedding when voltage mUapse is imminent achieving voltage stability wirh load shedding
is sometimes considered as a solution [1]. Manual applied with settings that override other U.ensient
load shedding may be effective if fte voltage conditions which do not indicate the impending
collapse is slow enough, and if the operators onset of voltage collapse.
recognize the need for shedding soon enough. In
some cases, (e.9. the TVA, Swedish and Hydro System planners conduct numerous studies using
Quebec cases mentioned in Section Z.l) the VQ curves and other analytical methods tl,9 t;
system changes state to one of voltage instability I
determine the amount of load that neds to be shed
so quickly that manual load shedding would not to retain voltage stability under the envisaged
be fast enough. Therefore automatic load contingencies. Voltage collapse is most probable
shedding has been applied t9l. under heavy (near peak) load conditions; so the
amount ofload to be shed depends on system peak
Since it is never desirable to shed load for high load and generation sources. For instance, several
probability contingencies, load shedding may be utilities in the Seattte Tacoma area have selected
considered as a temporary or partiat solution to the l1Vo of peak load to be shed in three steps during
voltage collapse problem, or as backup action for an undervoltage condition.
extreme contingencies.
Selection of loads is based on various criteria.
Some of the following may be considered:

3.1 General 1. Consider the type of load to be shed, industrial,


commercial or residential. Industrial load is
Philosophy of Undervoltage Load Shedding often selected as a candidate ftr
underftequency load shedding because
industrial load is normally fairly constant at
Whenever there is a system disturbance and
near peak levels. This type ofload is relatively
voltage drops to a certain pre-selected level for a
stable compared to the high level of daily
certain pre-selected time period, then selected
flucfuation of residential and commercial load.
loads may be shed. (The selection of voltage However, residential and commercial load can
levels, time steps, and type of load is described in
be considered as dependable as industrial load
the following.) The intention is that when load is
for undervoltage shedding since such shedding
dropped from a disturbed system, the voltage
recovers to normal levels.
is most likely to be required near peak loads
when all types of loads are high. As discussed
earlier, constant power loads such as motor
Different Steps Involved in Load Shedding
loads are the most detrimental to voltage
stability, and these types of loads can be
1. Determination of the amount of load to be considered. When industrial motor loads are
shed.
being considered, the particular types of motors
2. Selection ofloads to be dropped.
are important. If the motor loads include
3. Determination of time steps of load shedding.
synchronous motors, the dynamic reactive
4. Deterrnination of
voltage level(s) at which power generation capability of such motors
shedding begins.
may be helpllrt to keep the voltage up.
Similarly industrial loads which also have their
Cooperation between protection engineers and
system planners is important, particularly in steps
own generation may also be helplul in
maintaining system voltage.
three and four. The protection engineers can

10
2. If lines are to be tripped, select the lines which according to an inverse time curve which could
are not required to maintain system integrity, result in fault clearing times even longer than 5
such as radial supply lines, or lines with heavy seconds. The time delay should also override
tapped loaG, and light through loads. System transient voltage dips which may not require load
tie lines help retain voltage stability by shedding. Such dips could be caused by a variety
providing line charging vars and by sharing of circumstances such as motor starting, generator
power flow (reducing the current through loss of field, and the dead time before successfi.tl
individual lines). The sharing of power flow reclose of a ransmission line. Undervoltage relay
reduces system var losses in transmission lines time delays should be set longer than the transient
since such losses are proportional to the square conditions which can depress the measured
of line currents. voltage to the operating level of the undervoltage
relays.
3. Select large load blocks to minimize the
amount of automatic systems needed to shed Appropriate voltage level selection is also
enough load to avoid voltage collapse. Of important. If the voltage drops to a level that
course, the blocks must be small enough to indicates the onset of voltage collapse, the
allow the principle of shedding in time steps to undervoltage load shedding must be started. As
be effective. can be seen from the PV curves in section 2.2,
voltage collapse can start at voltages very close to
4. Since absorbed reactive power depresses normal levels. It is also important to prevent
system voltages much more than real power, voltage depression to levels where motors begin to
shedding of loads with low power factor will sta1l, since voltage collapse is extremely fast after
be the most effective in maintaining system motors start to stall. The desired level at which
voltage. It should be noted however, that loads shedding should be started may be in the range of
which depend on power factor correction 0.85 to 0.97 p.u of lowest norrnal voltage (at the
capacitors to maintaio a high power factor, bus during peak system load). It should be noted
become low power factor loads at low voltages that the lowest normal voltage is not necessarily
when the capacitors supply less reactive power. the system nominal voltage. Many utiiities may
have a lowest norrnal voltage which is somewhat
5. It may be possible to set a rate structue that different from the nominal system voltage.
allows customers to pay a lower tariff if they
accept load shedding when voltage collapse is Insome cases it may not be possible to apply
imminent. appropriate settings to pure undervoltage load
shedding schemes. In such cases, the
Load shedding is often initiated in steps to avoid undervoltage relay sensing location may have to
over shedding [9]. The selection of appropriate be changed, or load shedding may have to be
time steps is an important factor in effective initiated by measurement of parameters other than
undervoltage load shedding. The proper time step simple voltage level.
depends on the system load characteristics,
generation source, and rate of change of voitage An inverse time undervoltage relay for which the
condition. Load shedding which is too slow can operating time depends on the degree of
fail to prevent voltage collapse problems. Load undervoltage may allow an effective application of
shedding which is too fast can create overvoltage appropriate delays at given voltage levels. This
conditions or undesirable mistripping of load type of reiay may be especiaity applicable where
under short circuit fault conditions or other an undervoltage load shedding scheme is required
transient voltage depressions. The time delay to coordinate with inverse time overcurrent short
should let the short circuit protection relays circuit protection relays.
(distance and overcurrent) clear faults. Distance
relays are set with delays which could range from When determining the required levels and time
0 - 5 seconds, and overcurrent relays may trip steps, system planners may consider simulations

11
such as those shown in Figure 9. The solid lines constant impedance (Z), constant current G) and
show the voltage fajectory at a particular bus. constant power (P) loads. The total pwer is
The broken lines in Figure 9a) show where three given by the expression Power = aYt + bV + c
level detectors pick up and start timers which time (where a = 0.56, b -- 0.27, c = 0.17 for puget
out before shedding load. The ends ofthe broken Sound area load). Such a composite Ioad is often
lines show when the load blocks are shed. It can referred to as a ZIP load model.
be seen from Figure 9a) that leyel detectors ftr
blocks I md 2 both pick up at 0.92 p.u., and that There is usually no unique "correct" relationship
block 1 is shed after 5 seconds, and block 2 after 8 between voltage levels and time steps in a staged
seconds. The level detector for block 3 picks up at load shedding scheme. The best relationship can
0.9 p.u., and sheds load after 5 seconds. The be quite difftcult to detennine, particularly if
second curve (figure 9b)) shows how the voltage multiple modes of voltage collapse are possible.
does not recover if only load blocks 1 and 2 are When regional collapses are driven by the
shed. transformer tap changes and thermostatic effects
discussed in Section 2.2, relatlvely minor trade
offs between voltage level and time delay can
BLOCK 2J
result in significanfly different system
ELOCK 5:
perforrnance [6].

The above mentioned considerations indicate that


secure and effective settings for undervoltage load
shedding schemes can only be acfueved ttrough
cooperation between system planners and system
protection engineers.

Indiscriminate Nature of Yoltage Magnitude

40 scom Voltage relays are non directional, and of


unlimited reach. They will sense voltage
!,o5
depressions due to short circuits and other
disturbances which are not necessarily related to
voltage collapse. Some techniques can be used to
l-o
improve the ability of undervoltage relays to
discriminate between conditions which require
\ load shedding and conditions that do not require
9 o.es
load shedding.
d

o.9
Firstly, the relay may measure alt ttuee phase
voltages, and require all three to be depressed
before initiating a shedding timer. With this
\ technique the relay is less likely to respond to
o 10 20 40 sEcoNDs unbalanced short circuits which may be cleared
b) TlYo BIrcKs SHED
somewhat more slowly than three phase short
circuits. Another similar approach is to have the
Figure 9 Voltage Collapse Studies With and relay measure only positive sequence voltage,
Without Adequate Load Sheddin which is depressed less for unbalanced short
circuits than for three phase faults.
The curves drawn in Figure 9 are based on a
composite load model which is a combination of Another usefi.rl technique is to have the relay

12
initiate the timer only if the measured voltages are be designed to detect undervoltage or rate of
within a window, below a certain (maximum) voltage change, and may have various time delays
level, and above another (minimum) level. The built in. The voltages which are measured must
maximum level (the shedding level) is selected by be unaffected by the operation of
load tap
system studies as described earlier in this section. changers and other local regulating devices.
The minimum level may be set somewhere in the
region of 0.5 to 0.7 p.u. This means that load will Unlike relays in centralized shedding schemes,
not be shed for accidental loss of signal to the these relays must detect voltage stability on the
undervoltage relay (due say to loss of primary basis of local conditions alone. Distributed relay
equipment supplying the signal, or due to schemes will not have shedding initiated directly
disconnection or short circuit of the vt secondary following the of loss of critical transmission
leads). It also means that load will not be shed fu system facilities whose failures have been
slowly cleared three phase faults which depress predicted to initiate voltage instability.
the system voltage to less than the minimum level.
The minimum level has to be chosen such that if The distributed model for undervoltage load
the system voltage is at that level for the duration shedding borrows heavily from distributed
of the load shedding delay, then the problems are underfrequency load shedding schemes which
so severe that load shedding will not be effective have been in place for manY Years.
in helping the system to recover.
3.3 Centralized Measuring Relay(s)
Naturally, in a time staged shedding sequence, it is
important to apply a voltage relay with high reset
Instad of distributing relays around the area of
ratio. This is required so that only a small concern, measurements may be taken at one tr
recovery in voltage level is required to stop flle
more key busses within the area, and trip signals
shedding sequence.
transmitted to shed load at various locations
within the area.
Whether or not shedding is staged, voltage relay
setpoints are close to normal operating voltage.
Since voltage instability may be recognized by
High accuracy relays are required, with low drift
in setpoinl The accuracy of the voltage low voltages across the region, the basis of
centralized measurement lies in the notion that if
transformers supplying the relay must also be
the voltage is low at certain key locations, it is
considered in assessing the overall accuracy of a
likely to be also low throughout the area. The key
scheme.
locations are the busses at the major transmission
receiving stations. It is likely that these busses
3.2 Distributed Measuring RelaYS will be at the highest subtransmission voltage in
the area, and will also have the highest fault level
A system of relays to detect voltage instability and (i.e., they will be very "stiff'). If there is more
shed load may be designed to be distributed than one key location, voltage level detectors at all
ttfoughout the area of concern. If the system is key locations should be evaluated before a load
implemented entirely on the distributed model, no shedding decision is made.
centralized equipment is required. Each protective
relay is closely coupled to a segment of load to be The use of "and" type logic could determine if
shed. As voltage conditions at a relay enter the voltages are low at all key locations before
region where collapse is predicted, load assigned allowing load to be shed. This would result in
to that relay is shed. good security, since all measuring elements would
have to indicate approaching voltage collapse.
In order to provide separate instability detection at However, unless redundant detectors utd
each load shedding location, lower-cost voltage communications are provided, there would be
measuring relays are installed. These relays may some sacrifice in dependability, since failure of

13
any single detector or communication benveen di stributed measuring scheme.
detectors could resultin failure of the sctrcme
when it is needed.

For better reliability, a voting scheme may be


3.4 Comparison of Distributed and
Centralized Schemes.
applied. In such a scheme, any two out of three
detectors could initiate load shedding. This type
Advantages of Distributed Versus Centralized
of scheme would provide better dependability than
Shedding
an "anded" scheme, and better security than a
scheme that depended on a single measurement.
1. The retiability of the distributed system is
increased by diversification. Failure of one
Other criteria than voltage level, such as status of
component of the distibuted system will not
major transmission lines or output of dynamic var
sources may also be used in deciding to shed load
direcfly or detrimentally affect the operation of
to avoid the danger of voltage collapse. Ttrese other components of the load shedding system.
criteria when combined with voltage level may The effects of failures will be localized. The
centralized system depends on the reliability of
provide a better and/or earlier indication of the
approach of voltage collapse than simple only a few relays, or one relay. Failure of the
centralized system results in complete failure of
measurement of voltage level. Whatever means
are taken to decide upon load the scheme, false operation of the centralized
shedding,
scheme results in large blocks of load being
communications requirements between level
unnecessarily shed.
detectors are minimized by selection of only a few
key measuring points, or existing SCADA
communications may be used [12].
2. ln a disfibuted system, load shedding is
concentrated and localizedto the areas where
The measuring scheme can easfly be designed to the effects of the instability are felt most
shed load at appropriate levels and times and in strongly. Load will not be shed prematurely
appropriate blocks to meet the requirements of tlrc before conditions indicating instability are
voltage stability plan. measured locally. With a centralized system,
load is shed when the centralized decision is
Although communications requirements between made, whether or not the voltage at the load
measuring devices at key locations are minimal, delivery point is low.
a
centralized measuring scheme depends heavily
upon communications to carry the load shedding 3. The distributed model does not depend on
decision to load supply points. communications facilities for its operation. If
Trrese
communications requirements can make a the local relays and breakers are operable, load
cenftalized scheme relafively expensive compared shedding will occur even if communications
to a distributed scheme, unless the facilities fail. The centralized scheme is heavity
communications facilities are already required fu dependent upon communications facilities,
other reasons. The load shedding communications both for making the shedding decision, and for
facilities themselves need to be carefirlly designed implementing it. This can make the scheme
to avoid compromising reliability built in to fhe more expensive than a distributed scheme,
load shedding decision scheme. For best especially if high speed communications are
reliability, the communications facilities should be required to make the load shedding scheme fast
radial fiom the decision point(s) so that failure enough to prevent voltage collapse. If
of communications are required anyway for load
one signal will not result in total failure of
the restoration by supervisory control, then this
scheme, and false trip of one signal will not result
in undesirable shedding of all load. In this way, advantage of the distributed scheme is not as
radial Ioad shedding signals can provide some prominent.
of
the reliability provided by the diversity of a

14
4. For multi-utility projects, coordination of
installation work is much simpler with a 5. Since measuring equipment is located at only a
distributed system than it would be for a few locations, more money can economically
centralized scheme. be used to increase the reliability of the
centralized decision scheme (e.9., by applying
Advantage of Centralized Versus Distributed redundant, or voting measuring schemes).
Shedding.
3.5 Other ConcePts
1. In a centralized system, the location of the
undervoltage measuring relay is not constrained Load shedding need not necessarily be initiated by
to be near a suitable load. The voltage(s) to be undervoltage relays. There are other indicators of
monitored may be selected puely on the basis the approach of voltage collapse. A discussion of
of being the most appropriate point on the some other load shedding con@pts follows.
system. Usually, the important supply busses Except for the rate of change of voltage relay
are monitored. The voltage level is tightly scheme, all other concepts involve some sort of
regulated under normal conditions @y virtue of system measurements. They are probably most
the high short circuit level(s) at the bus(ses) easily implemented as a centralized scheme ratlpr
being monitored). Small voltage depressions than a distributed scheme which may sometimes
can be used to indicate voltage instability more be implemented in a pure undervoltage scheme.
reliably than similar voltage depressions at a
less stiff bus where the voltage has a wider Rate of Change of Yoltage RelaYs
range of variation under normal conditions.
Rate of change of voltage relays can be more
Z.By means of communications between key effective than simple voltage magnitude detectors
locations, with a centralized system it can be for planned load shedding because voltage
established that low voltages exist tiroughout coilapse is direcfly related to rate of change of
the region before a decision is taken to shed voltage. Magnitude detectors cannot differentiate
load. This avoids load shedding due to voltage between faster or slower rates of change of
depressions caused by local disturbances not voltage.
associated with imminent regional voltage
collapse. It may be possible that in some cases rate of
change of voltage could discriminate between
3. A centralized system may use other indicators voltage reductions caused by the onset of voltage
from any part of the system (such as are instability, and voltage reductions caused by
described in Section 3.5) in addition to voltage system short circuits. However, application of
level to predict the approach of voltage this type of measurement is limited for two
instability. These indicators can be used to reasons. Firsfly a system short circuit may initiate
increase the reliability of the decision that a voltage collapse, especially where slow clearing
voltage collapse is imminent. is involved, as with the TVA problem described in
Section 2. i Secondly, the rate of change of
4. Shoft time delays associated with small voltage
voltage as voltage instability approaches is very
depressions are more likely to coordinate wiill difficult to calculate; so suitable settings for rate
fault clearing devices at stiffbusses than at less of change of relays are difficult to determine.
stiff busses. This is because the higher fault
level at a stiff busses means that more fault Loss of Lines
current is flowing for a given voltage
depression than at a less stiff bus. Thus it may
The loss of lines can cause many problems to
be easier to achieve useft:l and secure settings
system voltage stability. The problem severity
with centralized relays at centralized busses.
depends on the following factors:

15
1. The type of line. Transmission lines usually output (as mentioned in Section 2). If the output
have a larger effect on voltage stability than of important sources of dynamic vars can be
subtransmission lines since the former do not measured, then indication of high output, together
usually serve load directly, and their loss with low voltages may be taken as an indicator of
causes more reactive power losses in the possible voltage stability problems, and may be
system without any loss in load. As shown in used as a basis for a load shedding decision. This
Section 2.2, a more higily stressed is the basis of the BC Hydro scheme described in
is more likely to suffer
transmission system Section 3.6.
voltage collapse.
2. The type of load on the line (for the same Hybrid Scheme
reasons discussed in the selection ofloads to be
shed). In a hybrid relay scheme, the on-line conditions of
3. The network connections of the lines (which the system are monitored. Line loading and status
determine the effect to the network on loss of and/or output of important var sources may be
the line). combined with undervoltage relays to deterfirine
4. The amount of load on ttre line. the approach of voltage collapse. The Florida
5. The system flexibitty to shift load on to other Power and Light scheme described in Section 3.d
lines. uses a variety of parameters to deterrnine the need
6. The duration for which the line is lost. This is for load shedding. Such schemes can be useflrl
important since collapse may sometimes be when secure and effective settings for
avoided by restoration of the line within a few undervoltage relays cannot be achieved.
minutes.
State Estimation and State Measurement
If a line is a transmission line and it connects a
generating source to a system, tlren loss of the line
Energy management systems (EMS) receive
means loss of generation which can cause low
voltage problems in the system. Detennination of
information ftom the complete system
continuously. EMS may include facilities to
fte status of critical lines may be used to initiate estimate the state of the system and indicate the
load shedding if critical lines are lost. Tfie onset of voltage collapse. The state estimation
importance of lines vary constantly, according to process uses information on the magnitudes of bus
the system conditions; so load shedding initiated voltages, and real and reactive power flows in the
by loss of critical lines has to be constanfly lines to perform power flow calculations to try to
adjusted to match different system conditions. If
duplicate the state of the power system in a near
the line does not carry much load and the system real time fashion. The process of state estimation
is strong enough to shift load to other transmission however takes several minutes, and is usually not
lines, the loss will not create a serious problem for
able to give sufficienfly accurate information soon
the system. The need to reset load shedding enough to initiate automatic load shedding for
patterns according
to the importance of lines in effective maintenance of voltage stability.
certain system conditions means significant
demanG upon system operators, and may be The
impractical if system conditions change rapidly
technology to make system wide
synchronized phasor measuremenfs using global
and frequently.
positioning satellite time signals can be used to
transmit bus magnitude and angles to an EMS,
Totalized Output From Dynamic var Sources
and thus provide network state measurement
rather than state estimation. Direct state
Reactive power reserve can be a good indicator of
measurement provides information sooner ano
the ability of a system to withstand low voltages. more accurately than state estimation. Wherr
To ensure reserye capability, it is good operating
complete or partial state measurement techniques
practice to operate dynamic sources at near zero
are used, it may be possible to utilize some system

16
wide indicators of voltage stability such as: steps shed load at the various locations in
successive time intervats. This process continues
. The near singularity of the Jacobian matrix (a until the voltage recovers enough to let the sensing
matrix of partial derivatives of the load flow relays resel
equations with respect to state variables -
voltage magnitudes, and phase angles), [10]. The undervoltage sensing relay, will respond to
. Sensitivity of reactive power injections with system faults as well as low system voltage. It
respect to loading Parameters [8] must therefore be blocked from operating under
fault conditions. It is blocked for ground faults on
system state measurement may provide the most the 161 kV and 46 kV systems by a low set
effective control actions (including load shedding) instantaneous overvoltage relay connected to the
to maintain voltage stability. While the prospects 3Vo polarizing potential. It is blocked for phase
for state measurement to aid system voltage faults on the 46 kV system by an instantaneous
control are brighl the techniques are not widely overcurrent relay connected to see the total
applied at the time of printing this paper. The transformer current. Figure 10 shows the
confidence of the industry in direct state connections of a tYPical scheme.
measuements grows, supported by increasing
numbers of users, successful fleld testing, and 16't kv
efforts to standardize higttly accurate +
synchronizing techniques and data interchange
formats. Numerous implementations of advanced
control theory based on power system state
measurements are expected in the future.

3.6 Actual, or Planned lnstallations


TVA.

An undervoltage load shedding scheme was


installed at nine 161 kV substations in the area
south of the TVA West Point 500 kV substation.
This scheme was instailed because of unstable
voltage in that area resulting from the loss of the
West Point 500 kV transfonner. By shedding
some loads, usable voltage could be maintained on
Fisure 10 TVA Scheme
the others [11].

There is no practical way to block the sensing


The undervoltage sensing relay at each of the nine
relay for phase faults on the 161 kV system, but
locations is set aL 87Vo of normal operating
none is needed since load shedding must occur
voltage. The sensing relays are induction cup
during the time interval between the zone 2 and 3
relays, with high reset ratio. These relays operate
elements of the 161 kV line relays. Ttte zone 2
through timers to shed load by tripping and
elements must be permitted to operate for fault
locking out Eansformer breakers or breakers on
conditions before any load shedding can start, and
radial 161 kV or 46 kV lines.
the load shedding sequence must be completed
before any reversed zone 3 elements can operate
There are five steps of operation in the load
on overload conditions. The zone 2 elements are
shedding scheme with a time delay between each
set at 30 cycles, and any reversed zone 3 element
,step. The flrst step closes the 161 kV capacitor
that could operate on load after loss of the West
bank breaker at West Point. The remaining four

t7
Point 500 kV bank is set at 120 cycles. The five 1. Short-time automatic reclosure on the major
steps of load shedding action occur at 45, 60,75, 230 kV circuits supplying the Ottawa area,
90 and 105 cycles. The approximate amount of followed by
load shed in each step and the corresponding time 2. automatic load shedding
delay is listed below. 3. automatic capacitor switching
4. automatic load tap changer blocking
Time 45 60 75 90 105
in The fast auto reclosure (0.9 to 1.3 seconds) of the
Cvcles 230 kV circuits is used as a first measure to
,t maintain voltages prior to initiating load rejection.
MW 203 86 r22 154
of If reclosure is unsuccessfi:l, then depending on the
load depth and duration of the voltage drop, load may
shed be shed.

* West Point capacitor bank breaker closed. There are nine blocks of load which can be
individually selected for shedding via a two tiered
The scheme has operated as designed on four scheme: FAST and NORMAL. The FAST
occasions (all in 1987) due to loss of supply from component can be armed by operator action from
one of the West Point transfonners. In all cases, attended master stations and will trip if local
load shedding prevented complete collapse of the station voltage drops below a preset value for a
161 kV system. On one occasion, over shedding preset period (nominally 1.5 seconds). The
occurred and the voltage rose to 106 to lljVo of NORMAL component will always be armed,
normal, but this level was soon reduced as load except when FAST shedding has been setected
was restored. On another occasion, supply was and will trip at the same voltage level as FAST,
lost from one of the transformers at 3:12 am. Due but after a longer time delay (nominally 10
to the low load at that time, the voltage was not seconds). It is used to provide additionat
reduced low enough to cause load shedding. Later protection in the event of unforeseen
in the day, as ambient temperature rose, and load circumstances. Up to 750 MW of load can be
increased, one of the 161 kV lines sagged into a selected for shedding by this scheme, depending
tree, and was locked out. Upon loss of the line, on the load level.
the load shedding scheme operated to shed area
load. The scheme has never operated to shed load The load shedding scheme involves monitoring of
unnecessarily. the local 230 kV supply by accurate and stabte
single phase-voltage relays (in-house design) from
Ontario Hydro, main and alternate potential sources, with
automatic transfer for loss of the main source. For
Until sufficient reinforcement is provided via added security, the voltage relays are duplicated,
incorporation of 500 kV fransmission facilitjes, a and they must both operate in order to shed load.
portion of Ontario Hydro's system in the eastern AIso, there are separate duplicated voltage relays
part of the Province (Ofiawa area) is vulnerable to for FAST and NORMAL shedding modes. If both
voltage insfability under certain contingencies; the main and alternate potentjal sottrces are lost,
e.E. Ioss of a critical 230 kV circuit during Ioad shedding is blocked.
conditions of high power flows into the Ottawa
area fiom the west. To contain voltage declines in BC Hydro
the area under these conditions, which coutd
potentially lead to voltage collapse, a coord.inated BC Hydro plans to apply centralized undervoltage
undervoltage protection scheme is employed load shedding schemes in two regions. Load
consisling of the following: shedding is expected only during heavy winter
peak load conditions coincident with certain

18
double contingencies. The first scheme was
installed for the D9A93 winter peatq and the
second is planned to be installed a year later.

The first scheme will be on Vancouver Island


which is supplied as shown in the simplified
system diagram in Figure 11. The key locations
for voltage measurement will be the 230 kV
busses at DMR, SAT and VTf. These busses lie
along the backbone 230 kV transmission system
that supplies the Island's loads. The output of four
synchronous condensers (2X50 Mvar and 2X100 Figure 12 Logic Diagram of Vancouver Island
Mvar) located at VTT wiII also be measured and
used in the decision to shed load.

23OlV&d l3SLVLd&
Monitoring equipment was installed at the DMR,
SAT and VIT busses, and on the YTf synchronous
condenser outputs before the scheme was
implemented. Records from this equipment were
used to help decide upon settings of the measuring
devices. The settings selected were 97Vo of lowest
normal voltage for 10 seconds, before shedding
9rbotr the first block, with two second delays befse
Ciblekm shedding subsequent blocks.
M.bl.Dd.

The voltage relays are high accuracy, high reset


ratio digital relays, giving an ouFut only if the
measured voltage level on all three phases falls
within a certain window. The undervoltage relays
AC[H are supplied from 23O kV capacitor voltage
r- lV tE
transformers, with automatic changeover between
S0O

230 lv hlH
normal and alternate sources. The output of the
synchronous condensers is measured by a
138I: E
23O LV ld&
prograrnmable logic controller (PLC). The PLC
Figure 1.1. Simplified Diagram measures the output and status of all four
of Vancouver Island synchronous condensers, and gives an output if
the measured Mvar exceeds 95Vo of the total rated
The intent is to shed load if voltage is low at Mvar of all the in service synchronous condensers.
DMR and at either YTf or SAT and if at the same
[ime, the Vm synchronous condensers are The second scheme will be installed in the L.ower
producing nearly their full rated output. The logic Mainland region of British Columbia in the major
diagram of Figure 12 shows how the various load center of the utility. The voltages at three
measurements are used to implement the load major 230 kV busses in the region will be
shedding commands. Load shedding measured, as well as the output of 4X150 Mvar
communications facilities to the major load synchronous condensers supplying the load center.
cnters already exist to shed load in the event of The load shedding communications facilities will
overload of the 138 kV submarine cables from the have to be added to this region, making
mainland. Load will be shed in three blocks of implementation of the scheme considerably more
250 MW in tlree timed stages. difficult than for Vancouver Island.

19
Western Washington control.

Five utilities in the Puget Sound region of . The load shedding equipment is required to be
Washington State have implemented a distributed, in service only during the seasonal period of
automatic load shedding program to protect the high risk Some utitities will disable the
region against the effects of a possible winter equipment during low risk season.
voltage instability t9l. The risk of voltage
instability, is expected to be short lived, lasting . The program went into effect in November,
only until new var resources have been 1991. No voltage instability occurred during
constructed. The need for the load shedding the mild winter ot 199l-1992. There was no
program wiII be reviewed periodically after the undesirable shedding of load due to over
new var resources are available. sensitive relay settings.

The utilities are ted by Bonneville Power . AII utilities use oneor both of two types of
Administration, and include the following other undervoltage relays. Both types of relay are
utilities - Seattle city Light, puget sound power high accuracy, and high reset ratio relays
and Lighl Tacoma City Light and Snohomish measuring all three phases. Orre type of relay
County Public Utilify District. Common features is solid state analogue, and the other is digital.
of the program are:
Details of each implementation are described
. Automatically shed up to l5Vo of peak load. below.

. Shed load based on locally measured voltage Seattle City Light


as a percentage of Iowest normal voltage.
"Lrwest norrnal voltage" is interpreted fu Seattle has identified two 50 MW, 26 kV
each shedding location, based on historical residential load buses for each shedding group.
voltage during a time of previous system peak The six buses are located at four substations.
Each of these buses will be shed by an
. I-oad will be shed by three independent independent undervoltage relay. Undervoltage
sets of relays at different locations according to relay inputs are from wire wound potential
the following criteria: transformers. Automatic transfer of the relays to
alternate sources in the substation is provided to
Voltage Time Load permit operation during line maintenance.
Deoression Delav Shed Supervisory control is provided at each of the four
L0%o 3.5 sec 5Vo substations to permit seasonal enabling and
8Vo 5.0 sec 5Vo disabling of the schemes and to provide a local
8Vo 8.0 sec. 5Vo
indication of its enabled status. The SCADA
system also transmits alarms to the central power
Voltage is measured at an unregulated source dispatch center and provides for load restoration
at each shedding location by direct dispatcher command.

There is no common equipment and no real Puget Sound Power and Light
time inter-utility communication required to
operate the program. Each utiiity has Puget has identified eleven lines with tapped loads
separately borne the cost of its load sheddinp to be tripped for load shedding. To avoid fatse
equipment. The only coordination betweei tripping for loss of sensing supply, the
the utilities is their agreement on the undervoltage relays are set not to trip below 657o
protective relay settings and on the quantity of of lowest normal voltage.
Ioad to be put under automatic shedding

20
Tacoma City Light of nominal system voltage. The
set at 857o - 947o
time delay relays are set at 90 seconds. Where
Tacoma has identified a 115 kV tansmission line two lines at a substation have an undervoltage
feeding a residential unit substation for each scheme, the delay relays arc set at 90 and 120
shedding group. Under peak conditions, the lines seconds. These long time delays allow the scheme
carry loads of 70,40 and 30 MW respectively' to ride through system disturbances and only
operate for the peak load conditions for which it
Snohomish County Public Utility Dstrict was designed.

ll5 kV transmission
Snohomish has identifled a The scheme has operated conectly for several
line for each shedding goup. Load shedding situations and has not mis-operated for fault m
relays are applied at each end ofthese lines so that switching conditions. One system operated during
two relays must sense an undervoltage condition the summer of 1988 when loads hit and actually
to shed the tapped load. The relays are blocked exceeded the projections. The scheme operated
from tripping if there is a mmplete loss of due to the overloads causing low voltages.
potential on all three phases. Each breaker which Another scheme operated correctly when a looped
can be tripped to shed load has SCADA controls line was opened at one end for breaker
to provide alarms and for remote restoration. The maintenance. The line loads were higher than
undervoltage relays are disabled during sufirmer projected and distribution voltages got below the
by use of the SCADA system. setting causing the load to be dropped.

Consumens Power Co. Florida Power and Light

Consumers Power Company selectively applies a Florida Power and Light (FPL) has had in service
special protective scheme using undervoltage since 1985, a "Fast Acting Load Shedding"
relaying to alleviate local overload conditions (FAIJ) program to protect against severe system
which may cause damage to system components overloads not covered by the more conventional
or serve customers with an unacceptably low underfrequency load shedding system [12].
voltage. These schemes, which are a temporary
measure until appropriate system modifications System Planning studies had revealed that the
can be made, are applied to disconnect distribution addition of two 500 kV ties had strengthened
or sub-transmission lines ftom the CPCo system connections to neighboring utilities so much that
for identified outage condifioos. There are 23 system separation could not be assured under
such schemes installed on the CPCo system. certain double contingency losses of FPL
sixteen are installed at distribution substations generation. This meant that existing
with radial distribution lines, and seven are underftequency load shedding would not operate
installed at subtransmission substations with to kep the system stable under these double
looped lines. contingencies. Simultaneous loss of two or more
large generators (with more than 1200 MW total
The schemes consist of an undervoltage relay and output) could result in excessive power import
a time delay relay. The undervoltage relay is a into the state of Florida wilch could result in what
single phase solid state analogue relay, usually was called a "stable but overloaded" system
connected phase to neutral. Operation of the condition. That condition would leave the
undervoltage relay and the time delay relay will systems intact (without separation) but with severe
trip and block reclosing of the associated tlrermal and reactive overloads which could lead to
switching device. voltage collapse and uncontrolled system
separations after approximately 30 seconds.
The undervoltage relay settings are provided by
the system planning engineers, and are typically The FALS program runs in the system control

21
centre (SCC) computersin Miami, and uses state value and the alarm point setting.
wide SCADA communications to recognize a
"stable system overload" that results in lines At least one point in each row must be in the
operating above their ratings, low system voltages alarm condition to set a flag for that row. All six
at predetermined key substations, and heavy rows must have their respective flag set to initiate
reactive power demands upon generators. When a load shed signal with no intentional delay.
this condition is detected, FAI-S initiates a ftip Undelayed load shedding is expected to occur
signal to shed a predetermined amount of load by within 20 seconds of a disturbance which requires
tripping subtransmission lines at certain stations to shedding. A delayed load shed is initiated if four
prevent loss of bulk transmission lines and/u specific row flags are set and verified in the alarm
generators which could cause a blackout. condition for a specific time delay. The time
delay is to allow off line capacitor banks to switch
The program is based on a six by six matrix of in and mitigate those less severe overloads.
alarm conditions of individually telemetered
points as shown in Figure 13. Each matrix cell Each element in the matrix uses voltage or power
shows (in order) the monitored point, the present measurements already available in the computer.

TP #3 ST LUC 1 MARTIN 1 FPL-PCC FLA NET POIN-DUV+


INTERCHNG RICE-POIN

MW 670 MW 857 MW 593 -2550 -2962 2234


cHNG>-400 cHNG>-400 CHNG>-3OO MW>-3700 MW> 4400 MW>2900
TP #4 ST LUC 2 MARTIN 2 FPL-PCC FLA NET POIN-DUV+
INTERCHNG RICE-POIN

MW 672 MWO MW M2 -2550 -2962 223/.


cHNG>-400 CHNG>-4OO cHNG>-300 MW>3700 MW> 4400 MW>2900
DUVAL RICE POINSETT MARTIN ANDYTOWN LEVEE
5OO VOLT 5OOVOLT 5OO VOLT 5OO VOLT 5OO VOLT 5OO VOLT

508.9 5't4.7 s24.5 522.1 514.2 516.0


<465.0 <475.O <465.0 <470.0 <465.0 <465.0
DUVAL POINSETT RICE LEVEE ST LUC 1 ST LUC 2
5OO VOLT 5OO VOLT 5OO VOLT 5OO VOLT NET Mvar NET Mvar

508.9 524.5 514_7 516.0 85 0


<MO.O <MO.O <440.O <440.0 >470 >470
SEMINOLEl SEMINOLE2 MARTIN 1 MARTIN 2 TP #.I TP #2
NET Mvar NET Mvar NET Mvar NET Mvar NET Mvar NET Mvar
't30 135 68 69 il 53
>450 >450 >530 >530 >350 >350
FLA NET FPL.PCC POIN-DUV+ NOT USED NOT USED NOT USED
INTERCHNG RICE-POIN

-2962 -2550 22U


MW> 4700 MW>3900 MW>3100

Figure 13. FPL FALS Matrix

22
Only one phase is monitored for voltage the load reduction willat least give temporary

measurements, and two-and-a - half element watt load relief. The undervoltage relays reset at
transducers are used for the power measurements' 148 kV.

The program must shed a minimum of 800 MW, . Individual local blocking of the voltage raise
independent of the system load. Since fewer function of the oLTC is installed. on each
transmission lines need to be shed at high loads to load serving transformer there is an
reject the 80O MW, the FALS program bases the undervoltage relay measuring high side
number of lines to be shed on the current system voltage. Whenever this voltage goes under
load. 97Vo of lowest normal voltage, the tap changer
is blocked from raising the secondary voltage.
To improve the security of the scheme, the FALS The undervoltage relay resets at 997o of
trip signal received at each substation is lowest normal voltage. This measure is
supervised in a permissive mode by an intended to avoid local collapse induced by
underfte,quency re1ay. These relays are set at OLrc action which would tend to keep the
59.95 Hz, which will allow operation for most load constant with respect to primary voltage.
generation disturbances in the State. The
underftequency relays' outputs remain energized Automatic clearing.
for one minute to allow time for load shedding if
necessary. Whenever voltages on both sides of a distribution
transformer are less thanTjVo of nominal for more
The matrix parameters are revised as the system than 5 seconds, the fansformer is tripped locally.
changes so that the FAI-S program remains This can be considered as a sort of ultimate drastic
coordinated with the system response. undervoltage load shedding, but it is primarily
meant to facilitate overall system restoration
ELECTRABEL (Belgium) procedures.

Theoretical study of the possible effect of


automatic on load tap changer (OLTC) action with to Low Voltages.
respect to the voltage collapse risk showed that:
4.1 Generator Backup Protection
. OLTC's cao aggmvate the situation by
keeping load constant Impedance relays and voltage controlled cr
. OLTC's can even induce a local collapse at a restrained overcufrent relays used as system
substation primary bus by themselves. backup are typically connected to cts and v[s at the
generator. Impedance relays are more likely to be
Therefore, two different measures were taken found on unit connected machines for applications
that require coordination with step distance relays
. With respect to voltage behavior, a system can and timers. Voltage controlled or restrained
be looked upon as being composed of voltage overcurent relays are favored for use on much
coherent regions. Such regions have been smaller machines, much less than 100 MVA 1151.
defined for the Belgian system, and the
primary (150 kV) voltages have been
Under system peak load conditions and sagging
monitored by undervoltage relays in each of system voltage it would be expected that
them. Whenever the voltage at two points automatic voltage regulators (AVRs) and system
goes under 145 kV for more than 5 seconds, a
operators would operate machines at their
tegion-wide central order is sent to lower the maximum reactive capabiiity to provide reactive
set point of all OLTC'sby 5Vo, giving 57o less MVA support to the system. The reactive power
secondary voltage to the load. The idea is that exported ttrough unit transformer impedance

23
would keep generator terminal voltage several additional external protective relays, with the
percentage pornts higher than the system voltage. possible exception of an overexcitation relay
For larger generators with unit fransformers, (volts/hertz). The system protection engineer
voltages at the relays would therefore tend to be at should determine tllat there is adequate proteclion
or oyer IAOVo of generator rated voltage. of the generator, the step up transformer and the
Although generator terminal voltage may be near excitation system and that settings are appropriate.
normal, the reactive load will be unusually high. The manufachrers' individual machine application
and settings manual must be used. The volts/trertz
Since generators rarely operate in steady state at protection relay is usually required to protect the
the limits of their reactive capability, the backup generator step up transformer and unit connected
distarrce relays are not tested by long term station auxiliary transformer because their
to conditions near their operating
exposure overexcitation limits can be more restrictive than
boundaries. These devices have caused the generator.
unnecessary generator tripping during stessed
system conditions, thereby aggravating the stess Both to reduce the probability of overexcitation
to tlrc system [13]. The setting of distance type conditions, and to provide system voltage control,
relays on generators requires consideration of the it is of the utmost importance that the AVR be in
maximum reactive load under steady state service at all times while a machine is in
operation with subsequent system 3 phase fault operation. operating and maintenance practices
and the heavy reactive values added to it. Thus should encourage operation in only the AVR
these settiags require stability type studies ratlrer mode.
than the conventional short ckcuit studies.
Similarly to the case with the backup distance and
Low system voltages may be able to reduce the oyercurrent relays, the excitation system overload
terminal voltage of small generators to levels is rarely exposed to long
protection equipment
which may be lower than the minimum rated term operation of the equipment near its
operating voltage of the unit. This is especiaily capability. Overload protection and control
true if a step up tansformer has a relatively low systems have been found to be incorrectly set with
impedance such that the vars being generated by respect to the equipmeot capability, and have been
the generator cannot raise the terminal voltage known to cause uruEcessary limiting of reactive
significantly. Small generators may be protected power production, or tripping of the generator to
by voltage controlled or voltage restrained aggravate undesirable system conditions t131.
overcurrent relays. In such installations, care must The Belgian incident described in Section 2.1 is
be taken to ensure that the terminal voltage cannot an example of a case where there were very severe
drop low enough to allow the overcurent results ofundesirable tripping ofgenerators due to
protection to undesirably trip the generator. overexcitation.

4.2 Generator Overexcitation and Some utilities have engaged upon programs to test
their generators at the limits of their capabilities to
Rotor Overload Protection.
ensure the proper operation of overexcitation and
rotor overload protection and conftol systems[16,
Modern static excitation systems can respond to
system short circuit conditions in a matter of a few
171. For example, American Electric power
milliseconds. Generator field and stator ctrrents conducted an extensive survey of the reactive
power capability of their generators, and found
can be overloaded for a number of seconds, up to
about two minutes, when tlese currents must be
several cases where the expected reactive
returned to values within the steady state capability was not available. In a significant
capability of the equipment. Excitation systems number of cases they increased the available
incorporate protection features that are based on reactive capability by adjusting the generator
generator short time ratings and should not require overexcitation protection

24
4.3 Generator Auxiliaries Protection 4.4 Backup Line Protection with Long
Reach Settings
The reactive power generation and absorption
capability of generators is often limited by the Backup zone 3 and zone 4 distarrce relays are
need to maintain auxiliary voltage supply between sometimes applied for the clearing of faults
certain limits. These limits can be specially involving a breaker failure at a remote location, to
difficult to maintain at nuclear stations where avoid the necessity of a dedicated direct transfer
special undervoltage protecfion is applied' trip channel. In some cases, use of these relays
can even avoid the necessity for local breaker
There are two levels of undervoltage tripping at failure protection on the remote bus' The required
nuclear generating stations. The first level of reach of the backup elements is a function of the
undervoltage tripping may be set at approximately apparent impedance to the most remote point on
70Vo of nominal bus voltage with a time delay of the next line section, and consequently can be very
approximately one second. This level of large in comparison with typical zone 2 seffings'
protection is to detect a loss of offsite power and For coordination reasons. the time delay is
to transfer the bus voltage to another voltage generally somewhat longer than that for the zone 2
source. The first level ofundervoltage tripping is elements, with times up to a few seconds being
not primarily for equipment protection' Safety- typical.
related motors are shed and sequenced onto the
diesel generators once they are running. Motors During system low voltage conditions, the backup
not required for safe shutdown of the plant are not distance elements may become susceptible to
re-ener$znd. operation on load. While the ohmic characteristic
of a distarrce relay is independent of voltage, the
The second level of undervoltage may be set at load is not generally a constant impedance' The
approximate\ gAVo of nominal bus voltage. This apparent impedance presented to a distance relay
second level ofundervoltage tripping is to proted as the load voltage varies will depend on the
safety-related equipment ftom sustained degraded voltage characteristics of the load.
voltage. When the undervoltage relay operates' an
alarm is sent, and a timer is started. This may Figure 14 is an RX diagram that shows the
allow time for the operator to try to raise the approximate apparent impedance loci of three
voltage and minimizes the uruEcessary separaflon different types of radially supplied loads (curves a,
of the plant from offsite power. If after the time b and c). The impedances are shown as presented
delay expires, the voltage is still degraded, load is to a mho type distarrce relay at the source end of a
shed, offsite power is tripped, the diesel generator line of 1.0 p.u. impedance, with a reach (for
is started and safety-related load is sequenced onto example purposes) of 3.0 p.u' The three curves
the generator. If safety injection ha,s been show how the apparent impedances of the line
initiated, indicating a loss of cooling accident plus the load vary as the voltage at the relay varies
GOCA), the timer is byPassed' ftom 1.1 p.u. (the right hand ends of the curves) to
0.8 p.u (the left hand ends of the curves). A11
Although it may be specially difficult to maintain impedances are shown in per unit, with a base
proper voltage levels at nuclear stations, similar impedance of the line impedance. The nominal
difficulties exist at many fossil fueled generating load impedance of all three curves is about 2.6
stations. During the AEP reactive power audit p.u., which is a heavy load, corresponding to
[16], large gains in reactive power capability were abott l5OVo of the surge impedance load' The
obtained by carefi.rl review of generator auxiliary load impedance of 2.6 p.u. at 0'9 power factor
supply voltages. corresponds to a nominal real power load of 0'35
p.u. and reactive power load of 0.15 p.u. '

The three types of loads for which the curves arc

25
drawn, are described as follows: capacitor compensation become worse than that of
the simple motor load due to the decreasing
(a) A "motor" load similar to that described in effectiveness of the compensation at lower
Section 2.2 of thisreport, where voltages. As expected, the apparent impedance of
the resistive load does not change dramatically,
however, it must be remembered that highly
(b)A 0.9 power factor (P,Q) type motor load resistive loads are rare. As mentioned in section
which has been made a unity power factor 2.2, even a nominally constant impedance load
nominal load by the addition of shunt like heating becomes more like a constant power
capacitors, i.e., load over a loog term.
r- O.gs(.zs +.25Y2)
Q= - j0.15(( .7s+.2sv\-v2) The cause for coocern becomes apparent when the
where j is {(-r). circumstances for the low voltage situation are
considered. For example, if the low voltage
Appendix 1 shows how the points for curve (b) situation resulted from the loss of one or more
were calculated with the help of a personal transmission lines, or generating units, there may
computer based mathematical program. be a substantial change in the real and reactive
power flow through the line in question. The
(c) A 0.9 power factor "resistive" load similar to combination of low voltage and worsened phase
that described in Section 2.2 of this report, and angle may cause a long set relay to operate
like curve (b), also compensated to unity power undesirably, either on a steady state basis, or in
factor by the addition of shunt capacitors, response to recoverable swings related to the
where initiating event. Since the loss of an additional
transmission path at that time could result in a
complete system collapse, the time response of
Q= - j0. 1s(( .25*.7 5v21-y21
any automatic voltage control measures should be
Note that Curve (c) is drawn as a heavy line nearly coordinated with the response of the affected
superimposed on curve @) backup elements. If this is impractical, then
alternatives such as direct transfer trip for the
breaker tailure condition (in lieu of backup
3
protection), should be considered.

- 4.5 Voltage Controlled Overcurrent


o Protection
8 15
f;
U
U
d
1
( BC Hydro uses fault current limiting reactors at
05 most of its distribution feeder stations. These
o
reacttrs are usually on the source side of the
feeder circuit breaker, and allow the use of feeder
1
breakers with lower intemrpting ratings than
Rei#nc bu.) would otherwise be required for clearing close in
faults. The feeder bus overcurrent relays must
Figure 14 Apparent Impedance presented to a sense faults between the feeder reactor and the
Distance at Yarious Voltages. feeder circuit breaker. Due to the reduced fault
level on the load side of the reactor, the bus
Itcan be seen triat as voltage is reduced, the overcu-rrent relays cannot be set above maximum
apparent impedances of the motor loads become load currents, and still dependably detect faults
considerably smaller, and the power factors get beyond the reactor, especially under various single
worse. The power factors of the loads with shunt contingencies. At many stations, bus oyercurrent

26
relays have been set to start at levels near or below The time frame of voltage collapse is longer than
the maximum load they may have to carry, and that of transient stability. The exact speed of
starting of the relays is controlled by undervoltage collapse is on load and system
dependent
relays. These under voltage relays typically characteristics. Automatic load shedding
operate at about 87% of nominal system voltage. schemes have operating times varying from 60
cycles GVA) to 120 seconds (CPCo)' Automatic
It is possible that if the system voltage is low, the load shedding schemes are not always applicable'
undervoltage relays controlling the bus Some collapses (such as the Quebec Hydro
overcurrent relays may operate, and allow the collapse mentioned in Section 2.1) happen too
overcurrent relays to start on load curent. If the quickly for load shedding to be effective.
load is high, as may well be the case if the voltage
is depressed due to insufficient var support for the Operating experience of automatic load shedding
high load, the bus overcurrent relays could operate schemes so far is limited by the few years that
to shed the bus load. Such operation would be a many such schemes have been operational.
form of unintentional undervoltage load shedding. However, the limited experience has been good.
In such circumstances, the unintentional load
shedding would be very slow (in the region of Unexpected relay operations during system
several tens of seconds), since the load current overload and low voltages have affected collapse
would at the most, be a very low multiple of the in several incidents. While the unexpected
pickup setting of the overcurrent relays. Although operations are not always undesirable, it is
the load shedding would be unintentional, it important that relays operate in a foreseeable
would be beneflcial to the system, by removing manner under low system voltages. Therefore
some of the highest loads. Due to the long time protection engineers should consider the effect of
delays associated with the shedding, it is unlikely low voltages in the application, setting and testing
that over-shedding would occur. of relays.

5.0 Conclusion REFERENCES

As the threat of voltage instability increases, 1. IEEE Power SYstem Engineering


utilities implement new schemes to automatically Committee, System Dynamic performance
minimize the possibility of system wide voltage Subcommittee, "Voltage Stability of Power
collapse and blackout. Protection engineers Systems: Concepts, Analytical Tools, aod
shoutd learn the basic causes and effects of system Industry Experience". IEEE Publication
operation at low voltages to be better able to assist No. 90TH0358-2-PWR.
system planners in designing schemes which will
reliably operate as intnded. 2. G. Brownell and H. Clark, "Analysis and
Solutions for Bulk SYstem Voltage
Several types of automatic load shedding schemes Instability" IEEE Computer Applications in
are already in service, or planned to be in service Power, July 1989.
soon. Most of them use a direct measurement of
voltage as at least one parameter to be used in 3. NERC Interconnection Dynamics Task
ariving at a decision to shed load. The voltage at Force, Summary of "Survey of the Voltage
which action must be taken is very close to normal Collapse Phenomenon", NERC PubUcation
operating levels, being only 6 - l1%o'lower than dated August 1991.
minimum normal voltages. This means that care
is required to ensure the schemes do not mis- 4. C. Concordia, "Voltage tnstability",
operate for conditions other than true approach to Electrical Power & EnergY SYStems,
voltage instability. Some utilities use other Volume 13, No. 1, FebruarY, 1991.
pararneters as well as voltage, including var
generation and power flows.

27
5. G. C. Buftock" "Cascading Voltage Collapse 14. M. B. Awad, H. M. ZninBl-Din, and C. E.
in West Tennessee" proceedings, Western Graham, "Preventative Measures to Voltage
Protective Relay Conference, 1990, Spokane Collapse in Bulk Electricity Systems"
Washington. presented at the Conference on Bulk power
System Voltage Phenomena - Voltage
N.W. Miller, et al, "Voltage Stability of the Stability and Security, potosi, Missouri,
Puget Sound System Under Abnormally Sept. 19-24, 1988. EPRI Conference
Cold Weather Conditions", IEEE Proceedings, (EL-6 I 83).
Trarsactions paper No. 92 SM 534-g PWRS
presented at the 1992 pEs Summer power 15. IEEE Power System Relaying Committee
Meeting Working Group Report "A Suwey of
Generator Back-up Protection practices",
7. C. Barbier, J. P. Barret, "An Analysis of IEEE Trans. on Power Delivery, Vol. 5 No.
Phenomena of Voltage Collapse on a 2, Apnl1990, p.p. 575-584
Transmission System", Revue Generale
d'Electricitie, Special Issue July, 19g0, pp. l6 P. B. Johnson, et. al., "Maximizing the
3-21. Reactive Capability of AEp Generating
Stations", A paper presented to the
8. M. Begovic, A. G. phadke, ',Control of American Power Conference, Chicago,
Volrage Srability Using Sensirivity Illinois, April 1990.
Analysis", IEEE Trans. on power Systems,
Vol. 7, No. 1, February 1992,p.p.ll4-l13 17. N.E. Nilsson and J. Mercurio, ',synchronous
Generator Capability Curve Testing and
9. C. W. Taylor, "Concepts of Undervoltage Evaluation", IEEE Transactions paper,
Load Shedding For Vottage Stabitity" IEEE presented at PES 1993 Winter Meeting,
Trans. on Power Delivery, April, 1992, p.p. New York, paper No. 93 WM U2_2
48H88 PWRD.

10 M. Begovic, A. G. phadke, ,'Voltage


Stability Assessment Through Measurement
of a Reduced State Vector", IEEE Trans. on
Power Systems, Vol. 5, No. 1, February
1990, p.p. 198-203

l1 H. M. Shuh, J. R. Cowan, "Undervoltage


Irad Shedding, An Ultimate Application
Voltage Collapse',, proceedings, Georgia
for
Institute of Technology protective Relaying
Conference, April 29 - May l, lggz

t2 Nirenberg, S.A., Mclnnis, D.S. and Sparks,


K.D., "Fast Acting l.oad Shedding", IEEE
IIr^, on Power Systems, yol. 7, No. 2,
May 1992,p.p.873-817.

13. C. W. Taylor, "Generating plant Control


and Protection under Abnormally Low
Network Voltages,' l99l paper circulated in
NERC.

28
APPENDIX 1 (Mathcad (TM) file printout)

Derivation of Apparent lmpedances to a Distance Relay supplying Radial,


'voltage sensitive) Load
A singte phase system will be studied, as shown on the following figure:'

j,=ff
a:= 377

load =
PLt*
OL1 +
coMPt

Choose typical parameters for resistance, charging, and inductance of a


200 km. long 500 kV transmission line.

Rl := 200'.017 Xc:= x := zoo'[j'co'.902'to-] z := Rl+)o


8
j'0'200'1.2'10

Gonvert the tine impedance and charging susceptance to per unit values
(with the line impedance being equal to 1.0 p.u.). Split the line charging
susceptance into two hatves, one at each end of the line.
zpu,= lnl -*,-,_zw
zf,
XC := XC CH:= 1

ZPU z.XC

Define a variable voltage varying from 0.8 p.u. to 1.1 p.u. in 7 steps
:= I
r:= 16..22 Vt20

Create real and reactive power loads at a given power factor, and
capacitive shunt compensation which are equal to the reactive load at 1.0
p.u. voltage. For this example, choose a power factor of 0.9, and a
"motor" type load which is75o/o constant P,Q, and 25olo constant
impedance.
0 := acos(.9)

pL := cos[01.[.;s*.2s.[u,]'] eL, ,= -:.'io[e]'[.zs+.zs'[v,]'z] coMPt;=;'sin[t]'[t,]'

29
The impedance of the total (voltage dependent) load is given by:-

z.e'lv,f2
ztoad,"=
f-JQr-.*ir*J
By catculating in steps, the impedances of the various series and parallel
combinations of impedances and admittances, find the apparent impedance
at the relaying point at various voltages
I-
Admittancel, := Admittance2, := CH+ Admittancelt 7.ENDt '.- 7t +
Zload Admittance2
t

I
Admittance3t
'=
CTI* ZAPPt :=
Admittance3
ZFNDr

Plot the value of the apparent impedance on the R,X plane, and
tabulate the vatues for use on another plot showing the mho circle.

5*,

*{*,]

30

You might also like