Professional Documents
Culture Documents
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,051.29
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 94.62
Total Cost for 1.00 Nos. = Resource Cost + Overhead Cost 9,556.19
11257 9-1-2 Providing and laying of wire crates 3.00x1.50x1.50 in size with a 8 gauge BWG GI 10,962.30 Nos.
0 wire conforming to IS: 280 & IS:4826 in 150mm x 150mm mesh laid with stone
boulders weighing not less than 25 kg each.(As per PWD Uttarakhand Specification)
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,205.97
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 108.54
Total Cost for 1.00 Nos. = Resource Cost + Overhead Cost 10,962.30
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,051.29
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 94.62
Total Cost for 6.75 cu.m = Resource Cost + Overhead Cost 9,556.19
11257 9-2-2 Providing and laying of wire crates 3.00x1.50x1.50 in size with a 8 gauge BWG GI 1,624.00 cu.m
2 wire conforming to IS: 280 & IS:4826 in 150mm x 150mm mesh laid with stone
boulders weighing not less than 25 kg each.(As per PWD Uttarakhand Specification)
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.20 330.00 day 66.00
2 PL15 Beldar/mazdoor (unskilled) 3.60 300.00 day 1,080.00
3 PL16 Mazdoor (Semi skilled) 1.80 330.00 day 594.00
Material Group
1 PM2204 Galvanised steel wire crates of mesh size 150 22.50 213.41 sq.m 4,801.74
mm x 150 mm woven with 8 gauge bwg GI
wire in rolls of required size.
2 PM2206 Stone boulder of weight not less than 25 kgs to 6.75 460.15 cu.m 3,106.04
be used in wirecrates
Total Resource Amount 9,647.78
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,205.97
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 108.54
Total Cost for 6.75 cu.m = Resource Cost + Overhead Cost 10,962.30
Specification:
11257 10-1 Type - A, "W" : Metal Beam Crash Barrier 3,061.30 metre
6 Providing and erecting a "W" metal beam crash barrier comprising of 3 mm thick
corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC
series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 1.8 m
high, 1.1 m below ground/road level, all steel parts and fitments to be galvanised by
hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be
fixed on the vertical post with
a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per clause
810 (Vertical post fixed in M15 cement concrete filled in standard pit of size 1.20m
x 0.45m x 0.45m)
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL03 Blacksmith 1st class/Electrician 0.50 546.00 day 273.00
2 PL14 Mate 0.06 330.00 day 19.80
3 PL15 Beldar/mazdoor (unskilled) 1.00 300.00 day 300.00
Machine Group
1 PMC074 Tractor 0.10 476.10 hours 47.61
Material Group
1 PM0101 MS Flat / Structural Steel 146.01 41,364.68 M.T. 6,039.66
/kilogram
2 PM0105 Nuts, Bolts and Rivets 20.00 77,964.68 tonne/kilogra 1,559.29
m
Total Resource Amount 8,239.36
1 11-4-2-2 Nominal mix 1:2.5:5 (Hand mixing) 0.49 5,647.50 cu.m 2,744.69
Over Heads
59. Material for Riveting, Bolting and Welding Accessories 15% on (Material Group) 1,139.84
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,515.49
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 136.39
Total Cost for 4.50 metre = Sub Items Cost + Resource Cost + Overhead 13,775.77
Cost
Item Rate Per metre 3,061.28
11257 10-2 Type - B, "THRIE" : Metal Beam Crash Barrier 6,659.50 metre
7 Providing and erecting a "Thrie" metal beam crash barrier
comprising of- 01/05/2016
3 mm thick - corrugated sheet metal beam rail, 85 cm above
MISCELLANEOUS ITEMS - 2016-2017 Page 4 of 14 18/06/16 6:45
10 road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm
spaced 2 m centre to centre, 2 m high with 1.15 m below ground level, all steel parts
and fitments to be galvanised by hot dip process, all fittings to conform to IS:1367
and IS:1364, metal beam rail to be fixed on the vertical post with
a space of channel section 150 x 75 x 5 mm, 546 mm long
complete as per clause 810 (Vertical Post fixed in M15 Cement concrete filled in
standard pit of size 1.20m x 0.45m x 0.45m)
Rate Card Block 15 Gairsain (CHAMOLI) Effective Date 01/05/2016
1 11-4-2-2 Nominal mix 1:2.5:5 (Hand mixing) 0.49 5,647.50 cu.m 2,744.69
Over Heads
59. Material for Riveting, Bolting and Welding Accessories 15% on (Material Group) 2,998.57
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 3,296.76
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 296.71
Total Cost for 4.50 metre = Sub Items Cost + Resource Cost + Overhead 29,967.58
Cost
Item Rate Per metre 6,659.46
Specification:
11258 12-1 Tack coat using VG-10 grade bitumen @0.35kg/sqm,over normal bituminous 14.30 sq.m
3 surfaces
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 2,746.59
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 247.19
Total Cost for 1,750.00 sq.m = Resource Cost + Overhead Cost 24,966.52
11258 12-2 Tack coat using VG-10 grade bitumen @0.40 kg/sqm, over dry and hungry 16.00 sq.m
4 bituminous surfaces
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 3,088.91
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 278.00
Total Cost for 1,750.00 sq.m = Resource Cost + Overhead Cost 28,078.22
11258 12-3 Tack coat using VG-10 grade bitumen @ 0.40 kg/sqm, over granular surfaces 16.00 sq.m
5 treated with primer
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 3,088.91
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 278.00
Total Cost for 1,750.00 sq.m = Resource Cost + Overhead Cost 28,078.22
11258 12-4 Tack coat using VG-10 grade bitumen @0.45 kg/sqm, over cement concrete 17.80 sq.m
6 pavement
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 308.64
Total Cost for 1,750.00 sq.m = Resource Cost + Overhead Cost 31,172.15
Specification:
Chapter Name Premix Carpet (Including Tack Coat) as per PWD Specifications
Amount And Rate In (Rs)
Item Description Rate Unit
11258 13-1 Cleaning of the existing painted surface and laying 2 cm thick premix over a tack 228.10 sq.m
7 coat with graded approved grit and VG-30 grade bitumen including heating the
bitumen to the required temperature and mixing either in mixer or in hand drums,
including cartage of materials,maintenance of side patries, and watering them during
operation for proper completion of the work as directed by the engineer-in-charge.
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 3.00 330.00 day 990.00
2 PL15 Beldar/mazdoor (unskilled) 33.00 300.00 day 9,900.00
3 PL17 Mazdoor/Beldar (Skilled) 2.00 432.00 day 864.00
4 PL31 Coolie 10.00 300.00 day 3,000.00
Machine Group
1 PMC066 Smooth Wheeled Roller 8 tonne 3.00 648.60 hours 1,945.80
Material Group
1 PM0040 Bitumen VG-30 574.12 32,231.98 tonne/kilogra 18,505.09
m
2 PM0062 Crushed Stone chipping 13.2 mm nominal size 5.02 2,295.72 cu.m 11,517.61
3 PM0063 Crushed Stone Chipping 6.7 mm size 100% 2.51 2,295.72 cu.m 5,757.66
passing 11.2 mm and retained on 2.36 mm
4 PM0518 Fuel wood 590.84 527.81 Quintal/kilog 3,118.52
ram
5 PM1551 Sundries 200.00 1.70 Lumpsum 340.00
Total Resource Amount 55,938.67
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 6,992.33
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 629.31
Total Cost for 278.70 sq.m = Resource Cost + Overhead Cost 63,560.32
11258 13-2 Cleaning of the WBM surface and laying 2 cm thick premix carpet over a tack coat 244.50 sq.m
8 with graded approved grit and VG-30 grade bitumen including heating the bitumen
to the required temperature and mixing either in mixer or in hand drums, including
cartage of materials, maintenance of side patries, and watering them during
operation for proper completion of the work as directed by the engineer-in-charge.
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 3.00 330.00 day 990.00
2 PL15 Beldar/mazdoor (unskilled) 33.00 300.00 day 9,900.00
3 PL31 Coolie 10.00 300.00 day 3,000.00
4 PL44 Skilled torch operator for laying tack 2.00 546.00 day 1,092.00
Machine Group
1 PMC066 Smooth Wheeled Roller 8 tonne 3.00 648.60 hours 1,945.80
Material Group
1 PM0040 Bitumen VG-30 685.60 32,231.98 tonne/kilogra 22,098.31
m
2 PM0062 Crushed Stone chipping 13.2 mm nominal size 5.02 2,295.72 cu.m 11,516.69
3 PM0063 Crushed Stone Chipping 6.7 mm size 100% 2.51 2,295.72 cu.m 5,757.66
passing 11.2 mm and retained on 2.36 mm
4 PM0518 Fuel wood 6.30 527.81 Quintal 3,325.19
5 PM1551 Sundries 200.00 1.70 Lumpsum 340.00
Total Resource Amount 59,965.65
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 7,495.71
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 674.61
Total Cost for 278.70 sq.m = Resource Cost + Overhead Cost 68,135.96
11258 13-3 Cleaning of the existing painted surface and laying 2 cm thick premix carpet over a 225.90 sq.m
9 tack coat with graded approved grit and VG-10 grade bitumen including heating the
bitumen to the required temperature and mixing either in mixer or in hand drums,
including cartage of materials,maintenance of side patries, and watering them during
operation for proper completion of the work as directed by the engineer-in-charge.
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 3.00 330.00 day 990.00
2 PL15 Beldar/mazdoor (unskilled) 33.00 300.00 day 9,900.00
3 PL17 Mazdoor/Beldar (Skilled) 2.00 432.00 day 864.00
4 PL31 Coolie 10.00 300.00 day 3,000.00
Machine Group
1 PMC066 Smooth Wheeled Roller 8 tonne 3.00 648.60 hours 1,945.80
Material Group
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 6,925.31
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 623.28
Total Cost for 278.70 sq.m = Resource Cost + Overhead Cost 62,951.03
11259 13-4 Cleaning of the WBM surface and laying 2 cm thick premix carpet over a tack coat 240.90 sq.m
0 with graded approved grit and VG-10 grade bitumen including heating the bitumen
to the required temperature and mixing either in mixer or in hand drums, including
cartage of materials, maintenance of side patries, and watering them during
operation for proper completion of the work as directed by the engineer-in-charge.
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 3.00 330.00 day 990.00
2 PL15 Beldar/mazdoor (unskilled) 33.00 300.00 day 9,900.00
3 PL17 Mazdoor/Beldar (Skilled) 2.00 432.00 day 864.00
4 PL31 Coolie 10.00 300.00 day 3,000.00
Machine Group
1 PMC066 Smooth Wheeled Roller 8 tonne 3.00 648.60 hours 1,945.80
Material Group
1 PM0041 Bitumen VG-10 685.60 31,297.98 tonne/kilogra 21,457.96
m
2 PM0062 Crushed Stone chipping 13.2 mm nominal size 5.02 2,295.72 cu.m 11,516.69
3 PM0063 Crushed Stone Chipping 6.7 mm size 100% 2.51 2,295.72 cu.m 5,757.66
passing 11.2 mm and retained on 2.36 mm
4 PM0518 Fuel wood 6.30 527.81 Quintal 3,325.19
5 PM1551 Sundries 200.00 1.70 Lumpsum 340.00
Total Resource Amount 59,097.29
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 7,387.16
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 664.84
Total Cost for 278.70 sq.m = Resource Cost + Overhead Cost 67,149.30
Specification:
Chapter Name Providing and Laying of Mechanically Woven Double Twisted Hexagonal shaped Gabions size 3m x 1m x 1 m
Amount And Rate In (Rs)
Item Description Rate Unit
11259 12-1 Providing and Laying of Mechanically Woven Double Twisted Hexagonal shaped 7,207.00 Nos.
1 Gabions (Zinc plus PVC coated), of size 3mX1mX1m with two diaphragms at 1m
interval, having mesh opening 100mmx120 mm, mesh wire diameter 2.7mm/3.7mm,
edge/selvedge wire diameter 3.4/4.4 mm and lacing wire diameter 2.2/3.2 mm. (The
work includes filling boulders in the gabions).
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.20 330.00 day 66.00
2 PL15 Beldar/mazdoor (unskilled) 3.68 300.00 day 1,104.90
3 PL16 Mazdoor (Semi skilled) 1.88 330.00 day 621.39
Material Group
1 PM0136 Stone for Random Rubble Masonry 3.00 370.15 cu.m 1,110.46
2 PM2216 Mechanically Woven Double Twisted 16.00 215.00 sq.m 3,440.00
Hexagonal wiremesh of PVC coated
galvanized steel wire , having mesh opening
100mmx120mm and mesh wire diameter
2.7mm/3.7mm for gabions, rivet mattresses
and rockfall netting(including cost of
3.4/4.4mm dia edge/selvedge wire and
2.2/3.2mm dia lacing wire)
Total Resource Amount 6,342.75
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 792.84
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 71.36
Total Cost for 1.00 Nos. = Resource Cost + Overhead Cost 7,206.95
11259 12-2 Providing and Laying of Mechanically Woven Double Twisted Hexagonal shaped 7,388.80 Nos.
2 Gabions (Zinc plus PVC coated), of size 3mX1mX1m with two diaphragms at 1m
interval, having mesh opening 100mmx120 mm, mesh wire diameter 2.7mm/3.7mm,
edge/selvedge wire diameter 3.4/4.4 mm and lacing wire diameter 2.2/3.2 mm. (The
work includes filling boulders in the gabions).
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.20 330.00 day 66.00
2 PL15 Beldar/mazdoor (unskilled) 3.68 300.00 day 1,104.90
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 73.16
Total Cost for 1.00 Nos. = Resource Cost + Overhead Cost 7,388.75
Specification: