This article is about the selection of an access method in order to create an infrastructure for the
transport of ore, workers, and equipment in "underground mining projects".

Mine access is the method of which both people and equipment are able to get to and from an
underground orebody. The selection of a proper access method is crucial to the overall design of the
mine, since it is a long term decision that requires extensive time and capital. The two most common
methods of underground mine access to be compared are ramp and shaft access. A variety of
parameters must be understood and examined before proper access can be determined and designed,
these include: Depth of mining, orebody geometry, production rates and rock quality.

Contents
[hide]

1 Types of Mine Access

o 1.1 Shaft Access

1.1.1 Development Requirements

1.1.2 Costing

1.1.3 Advantages of Using a Shaft

1.1.4 Disadvantages of Using a Shaft

o 1.2 Ramp Access

1.2.1 Development Requirements

1.2.2 Costing

1.2.3 Advantages of Ramp Access


1.2.4 Disadvantages of Ramp Access

2 Decision Analysis

o 2.1 Summary of Factors

2.1.1 Shaft

2.1.2 Ramp

2.1.3 Other

3 References

Types of Mine Access


Shaft Access

Figure 1 - Underground shaft layout[1]

Shaft access utilizes a skip and hoisting system in order to transport workers and materials through a
vertical passage located near the orebody. Generally this system is best suited for deeper mines that will
require higher production rates. A general rule of thumb states that a mine that has the potential to go
deeper than 500m or plans to have production rates over 400000t/year will be best suited to a shaft [2].
Shaft access can also be utilized through an internal shaft, or a winze. This type of access is most
commonly utilized in the case of deep lenses that extend past the initial mine life. The top of the winze is
located underground and usually offset from the initial mode of access in order to get access to deeper
pockets of the orebody. The development of a winze can differ slightly from that of a conventional shaft
since raise bore technology can be used to ream the internal shaft.
Development Requirements

Figure 1 shows a general layout of what it required in a shaft access and handling system. In most cases
the task of shaft sinking is allocated to a contractor who can usually advance between 3 and 5 vertical
meters per day [3]. As can also be seen from this diagram, an ore pass exists which utilizes gravity to
transport material from each level down to the skip where it can be brought to surface. This is not a
requirement if ramp haulage is to be used. Production shafts are usually driven using traditional drilling
and blasting methods with the use of a shaft mucker that is lowered down the shaft to pull out blasted
materials.

Shafts are usually located along the centroid of the orebody, offset on the footwall side. It should be
located at a large enough distance away to ensure that once the orebody is mined out the integrity of the
shaft is not compromised. However, a large distance away from the orebody means higher operating
costs from extensive materials handling; so a balance must be considered.

Click here for more information on Shaft construction

Costing

Costs for shaft development are heavily dependent on the rock type that is being worked with as well as
the desired shape of the shaft. These prices are detailed from Cost Mine services in table 1 and 2 below.
As well included in table 3 is the costing structure for an internal raise bored winze.

Table 1 - Circular Shaft Costs[4]


Table 2 - Rectangular Shaft Costs[4]

Table 3 - Raisebore Shaft Costs[4]


Advantages of Using a Shaft

Higher production capabilities

More versatile with depth

Smaller excavation; requires less support


Disadvantages of Using a Shaft

Much longer to development

Higher upfront capital

Ramp Access
Figure 2 - Underground ramp layout[5]

Ramp access in a mine consists of driving a down-sloped heading with horizontal curves in order to
transport mobile rubber-tired equipment from surface to the orebody, as shown in Figure 3 below. Ramp
access is attractive for shallow orebodies, particularly where a decline portal can be sited within an
existing open pit [2]. Ramps can be driven at grades ranging up to 20%, but are usually restricted to no
[3]
more than 16% if they are to be used for truck transport of stope muck. The slope of a ramp is
determined by the capacity of vehicles to negotiate declines, with 15% grades being common, with 12%
[1]
in curves and 10% at level intersections The economic depth limit to which a single ramp access mine
can extend is governed by haulage costs, equipment selection, productivities, and ventilation
considerations. [3] I should be noted that ramps allow increased equipment mobility between levels when
compared to shafts. This allows the size of equipment fleets to be minimized, and utilization of equipment
to increase.
Development Requirements

In order to drive an access ramp, conventional drill and blast methods are usually employed (drill,blast,
scale, muck and bolt), with average advance rates being is as follows: 0.3-0.5 m/man shift for an
inexperienced crew; 0.7-0.8 m/man shift for competent crews; and 1.0-1.25 m/man shift for exceptionally
productive crews. [1] In designing a ramp, one must first consider the capabilities of the equipment that
will be travelling on the ramps. While one must consider equipment capabilities for the decline grade, as
noted above, physical dimensions of the equipment as well as ventilation requirements need to be
considered. It is common for the required turning radius for equipment to be 15m to 30m, but will vary
based on what is selected. [6] It is also important to consider ventilation requirements for the equipment
travelling on the ramp. A good rule of thumb is that 0.0633 m3/s of volumetric airflow will be required per
[1]
kilowatt of operating or installed diesel equipment. Also, air velocities in haulage and travelway ramps
should be between 0.5 m/s and 3 m/s [1] to ensure proper air circulation without creating difficult working
conditions. As such, it is common for ventilation requirements to have a significant influence on the face
area of access ramps.
Costing

Factors affecting the capital cost of driving a ramp include operating & maintenance cost of excavation
equipment, consumables (bits, steels, explosives, ground support material, etc.)and manpower [1]. A
summary table of standard costs per linear metre of advance is show below.

Operating costs for a ramp accessed mining operation will vary greatly between mining operations, but
contributing costs include: operating cost of trucks (fuel, oil, tires, etc.) $/hour of operation, maintenance
cost of trucks, $ / hour of operation, ventilation, grading and labour costs.

Table 4 - Ramping Costs[4]

Advantages of Ramp Access


Quicker advance rates in development stage allows faster access to ore

Generally lower capital cost to develop

Flexible production based on equipment selection

Increased equipment mobility between levels


Disadvantages of Ramp Access

Less productive than shaft access

High operating costs as depth increases

May require extensive ground support in poor rock conditions

Decision Analysis
Due to the higher capital costs associated with shaft access, the question of mine access decisions is
often asked in terms of at what depth is ramp access no longer the most economical option. In the past,
350m was a highly quoted number for the depth at which shaft access is superior, but with improvements
in diesel truck technology over the years, this figure may no longer be universally valid [2]. In fact,
McCarthy and Livingston determined the feasibility limits of ramp access to be around 800m and
1.2millon tons per annum (Mtpa), set by truck performance and ventilation. Other important conclusions
include that the optimum changeover depth from decline haulage to shaft hoisting becomes shallower as
the mine life increases, as well as also becoming shallower as required productivities increase [2].

Due to the non-universality of access selection it is important that steps are taken to optimize the
decision. After all, access can be the determining factor in a mines production rate, and thereby the
mining method. The result then trickles down creating differences in mining and milling costs due to
economies of scale and other factors. Moreover, equipment expenditures and working capital
requirements can also vary widely between the options. It is then necessary to build a case for each
option, in an attempt to optimize the decision from a financial basis; creating the highest possible return
for investors. When building a case for each of the options it is important to create a defensible cash flow
analysis for each. These cash flows should reflect the reality of operating conditions specific to the
access method selected. It should go beyond back-of-the-envelope type calculations and demonstrate
due diligence in researching, and substantiating estimations and projections.

The two flow charts shown below outline relevant factors in deciding between a ramp or shaft access
method:
Figure 3 - Mine Access Flowchart[1]

Summary of Factors
Shaft
Mining and Milling Constraints Method of Shaft Construction Cross Sectional Area Shaft Lining
Shaft Layout Hoisting System Cage for Transport of Men & Equipment Type & Number of Ore Skips
Headframe Construction Crushing Station Shaft Lining Collar Construction Loading Pockets
Sinking Rate

Ramp
Mining and Milling Constraints Cross Sectional Area Advance Rate Ramp Grade Ramp Lining &
Ground Support Transport of Men and Equipment Truck Size & Number Portal Construction Level
Interval & Layout Equipment Flexibility

Other
Discount Rate Level Stations Level Interval Geotechnical Competence
References

1. 1.0 1.1 1.2 1.3 1.4 1.5 1.6 DeSouza, E. (2010). Mine Access. 8-48. Kingston, Ontario, Canada

2. 2.0 2.1 2.2 2.3 McCarthy, P. L. (1993). Shaft or Decline? An Economic Comparison

3. 3.0 3.1 3.2 McIsaac, G. (2008). Mine 244 Underground Mining Course Notes. Course Notes .
Kingston, Ontario, Canada: Queen's University

4. 4.0 4.1 4.2 4.3 InfoMine USA, Inc. (2009). Mine Cost Service. Spokane Valley: Jennifer B. Leinart

5. Oriel Resources. (n.d.). VOSKHOD MINE DESIGN & DEVELOPMENT. Retrieved February
09, 2011, from Oriel Resources Web site: http://www.orielresources.com/voskhoddesign.asp

6. M Brazil, D. L. (n.d.). Optimisation in the design of underground mine access. Uncertainty and
Risk Management in Orebody Modelling and Strategic Mine Planning . Melbourne, Australia:
University of Melbourne