MasterSeries PowerPad - Project Title 349685418

UB 457X152X52 END PLATE

Beam to Beam End-Plated Connection to BS 5950

LOADING CASE 001

Basic Data
Applied Forces at End-plate Interface
Resultant Forces M, Fv, F 70.0 kNm, 110.0 kN, 0.0 kN

Load directions Top of Joint in Tension, Rafter moving Down.

Design to BS 5950-1: 2000 and the SCI Green Book:

Joints in Steel Construction : Moment Connections: SCI-P-207/95

Basic Dimensions
Beam-457x152UB52 [28] D=449.8, B=152.4, T=10.9, t=7.6, r=10.2, py=275

Bolts 20 mm in 22 mm holes Grade 8.8 Bolts

Plates S 275, Welds E 35

Rafter Capacities Mc, Fvc, Fc 301.4 kN.m, 564.0 kN, 1832.6 kN Mc = 301.4 kN.m OK
MasterSeries PowerPad - Project Title 349685418

Summary of Results (Unity Ratios)


Moment Capacity 175.7 kNm (for 3 rows of bolts) (Modified Applied Moment Mm=70.0 kNm) 0.40 OK

Moment Capacity 102.7 kNm (for the 1 rows of bolts required in the tension zone) 0.68 OK

Shear Capacity 0.18 OK

Flange Welds 0.45 0.45 OK

Web Welds 0.42, 0.16 0.42 OK

Step 1: Tension Zone


Basics
Beam bp, g, t, Sww, m, e, n 170.0, 90, 7.6, 8, 34.8, 40.0, 40.0

Bolt Capacity Pt' Table 2.1 and Appendix IV 137.2 kN

Prmode3=NbPt' 2137.2 274.4 kN Eq 2.3

Plastic distribution Limit

Tp< /1.9(Uf/Pyp) 20.0 < 20/1.9(785.0/265) 20.0>18.3 Elastic

Classification No Plastic Deformation occurs. Modify Plastic distribution Eq 2.5; 2.6

BOLT ROW 1

End Plate row 1 only

m, e, m2U, m2L, 34.8, 40.0, 52.7, 0.0, 5.7

Le modes i, ii, iii 218.7, 189.2, 198.7 193.9 mm T2.5: 3

Mp=Leftktk py/4 193.920.020.0265.0/4 5139.1 kN.mm

Prmode1=4Mp/m 45139.1/34.80 590.7 kN Eq 2.1

Prmode2=(2Mp+nNbPt')/(m+n) (25139.1 + 40.002137.2)/(34.80 + 40.00) 284.1 kN Eq 2.2

Pr=min(Prmode1,2,3) min(590.7, 284.1, 274.4) 274.4 kN

Beam Web Tension row 1 only

Lt=min(0.87g,L1)+min(0.87g,L2) min(0.8790, 59.1) + min(0.8790, 77.9) 137.0 mm fig 2.17

Ltenhanced=(LtLt+LsLs) (137.0137.0 + 228.0228.0) 266.0 mm fig 2.33

Pt=LttbPyb 266.07.6275 556.0 kN Eq 2.4

Potential resistance of Bolt Row 1 Pr1 274.4 kN Mode 3

BOLT ROW 2

End-Plate rows 1 to 2 combined


MasterSeries PowerPad - Project Title 349685418

Lef(Row 1)=Max(ii/2, iii/2) Max(189.2/2, 198.7/2) 99.3 mm

Lef(Row 2)=(ii / 2) 189.2/2 94.6 mm

Lef=Lef(Row 1)+P+Lef(Row 2) 99.3 + 105.0 + 94.6 298.9 mm

Mp=Leftktk py/4 298.920.020.0265.0/4 7921.6 kN.mm T2.6: 3 & 1

Prmode1=4Mp/m 47921.6/34.80 910.5 kN Eq 2.1

Prmode2=(2Mp+nNbPt')/(m+n) (27921.6 + 40.004137.2)/(34.80 + 40.00) 505.3 kN Eq 2.2

Pr=min(Prmode1,2,3) min(910.5, 505.3, 548.8) 505.3 kN

Pr net=Pr-Pr1,1 505.3 - 274.4 230.9 kN

Triangular limit Ptri= Pr1La/lamax 274.4269.4/374.4 197.4

Pr 2=Min(Pr 2+PrResid, Ptri) Min(230.9 & 0.0, 197.4) 197.4 kN modified

New Residual PrResid=Pr 2-Ptri 230.9 - 197.4 33.4 kN

BOLT ROW 3

End-Plate rows 1 to 3 combined

Lef(Row 1)=Max(ii/2, iii/2) Max(189.2/2, 198.7/2) 99.3 mm

Lef(Row 3)=(ii / 2) 189.2/2 94.6 mm

Lef=Lef(Row 1)+P+Lef(Row 3) 99.3 + 210.0 + 94.6 403.9 mm

Mp=Leftktk py/4 403.920.020.0265.0/4 10704.1 kN.mm T2.6: 3 & 1

Prmode1=4Mp/m 410704.1/34.80 1230.4 kN Eq 2.1

Prmode2=(2Mp+nNbPt')/(m+n) (210704.1 + 40.006137.2)/(34.80 + 40.00) 726.4 kN Eq 2.2

Pr=min(Prmode1,2,3) min(1230.4, 726.4, 823.2) 726.4 kN

Pr net=Pr-Pr2,1 726.4 - 471.8 254.6 kN

Triangular limit Ptri= Pr1La/lamax 274.4164.4/374.4 120.5

Pr 3=Min(Pr 3+PrResid, Ptri) Min(254.6 & 33.4, 120.5) 120.5 kN modified

New Residual PrResid=Pr 3-Ptri 254.6 - 120.5 134.1 kN

Potential Tension Capacity


Sigma Pri 274.4 + 197.4 + 120.5 kN 592.3 kN

Step 2: Compression Zone


Beam Compression

Beam Compression Zone Flange in Compression Utilising 40% OverStressing

Total Area Flange 152.410.9 16.6 cm


MasterSeries PowerPad - Project Title 349685418

Pcbeam 16.62751.40 639.5 kN Eq 2.9

Potential Compression Capacity


Pcmin 639.5 639.5 kN OK

Step 4: Moment Capacity


Fc=Min(Pri+N, Pc) min(592.3 + 0.0,639.5) 592.3 kN

Fri=Fc-Axial 592.3 - 0.0 592.3 kN

P=Pri -Fri 592.3 - 592.3 0.0 kN

Final Bolt Forces and Moment Capacities

Bolt row 3 Mc3=Pr3h3 120.5164.4 19.8 kN.m

Bolt row 2 Mc2=Pr2h2 197.4269.4 53.2 kN.m

Bolt row 1 Mc1=Pr1h1 274.4374.4 102.7 kN.m

Mc 175.7 kN.m

Mm=M 70.0 70.0 kN.m OK

Tension Bolts Only the first 1 rows are required to resist the applied moment

The remaining rows shall be considered to be part of the shear zone.

Mc' for 1 rows 102.7 102.7 kN.m

Ft for 1 rows 274.4 274.4 kN

Ftdesign=Ft Mapp/Mc' 274.470.0/102.7 187.0 kN

Step 5: Shear Bolts


Bolt Shear Capacity BSC=91.875, tg=40 91.9 kN

Bearing Capacity-End Plate pb=460, edge=85.0, =20, tk=20, kbs=1.00 184.0 kN

Bearing Capacity-Bolts pb=1000, =20, tk=20 400.0 kN

Pss=Min(bearing...,shear) Min(184.0, 400.0, 91.9) 91.9 kN

Pts Min(bearing...,0.4shear) Min(184.0, 400.0, 36.8) 36.8 kN

V=NsPss+NtPts 691.9 + 236.8 625 kN OK

Step 7: Welds
Flange Tension Weld
MasterSeries PowerPad - Project Title 349685418

Fapp=min(BTPy, Ftdesign) Min(152.410.9275, 187.0) 187.0 kN

FwCap=20.7tsLPyw 20.78(152.4 - 28)275 420.1 kN OK

Flange Compression Weld

Direct Bearing assumed. No check required

Web Welds in Tension Zone

Lwt=L-proj-T-root+1.73g/2 90 - 20 - 10.9 - 10.2 + 1.73 90/2 126.8 mm

Load per row

Row1=K1Fr1 (53/(35 + 53))274 165.3 kN

Total Load Ft 165.3 165.3 kN

FwCap=20.7tsLwtPyw 20.78126.8275 390.4 kN OK

Web Welds in Shear Zone

Lws=D-(Tt+Tb )-rt-rb-Lwt 449.8 - 21.8 - 10.2 - 10.2 - 127 280.9 mm

FwCap=20.7tsLwsPyw 20.78280.9220 692.0 kN OK


MasterSeries PowerPad - Project Title 349685418
MasterSeries PowerPad - Project Title 349685418