You are on page 1of 3

Environmental Impact Assessment (EIA)

Environment Impact Assessment or EIA can be defined as the


study to predict the effect of a proposed activity/project on
the environment.

Environmental Impact EIA systematically examines both beneficial and adverse


consequences of the project and ensures that these effects
Assessment (EIA) are taken into account during project design.

Ar. Sandeep Kumar


ar.sandeeptyagi@gmail.com What is Assessment ?

Purpose and objective of EIA Brief History of EIA


Purpose of EIA is to ensure the protection On 27 January 1994, the Union Ministry of
and conservation of the environment and Environment and Forests (MEF), Government of
natural resources against uncontrolled India, under the Environmental (Protection) Act
1986, promulgated an EIA notification making
development. Environmental Clearance (EC) mandatory for
expansion or modernisation of any activity or for
Long-term objective is to ensure a sustainable setting up new projects listed in Schedule 1 of the
economic development that meets present notification.
needs without compromising future Since then there have been 12 amendments made in
generations ability to meet their own needs. the EIA notification of 1994.
The new EIA notification was introduced by the
Ministry of Environment and Forests (MoEF) on
Currently practiced in more than 100 September 14, 2006.
countries.

EIA PROCESS IN BRIEF The EIA Procedure


The EIA process in India consists the following phases:

1. Project Proposal
2. Screening
3. Scoping and consideration of alternatives
4. Base line data collection
5. Impact prediction and Assessment of Alternatives
6. EIA Report
7. Public hearing
8. Decision-making
9. Monitoring the clearance conditions
The EIA Procedure The EIA Procedure (continued)
3. Scoping and consideration of alternatives
1. Project Proposal Scoping is a process of detailing the terms of reference of EIA. It
Any proponent embarking on any major development project has to be done by the consultant in consultation with the project
shall notify IAA (Impact Assessment Authority) in writing by proponent and guidance, if need be, from Impact Assessment
the submission of a project proposal. The project proposal Agency. The Ministry of Environment and Forests has published
shall include all relevant information available including a land- guidelines for different sectors which outlines the significant
use map in order for it to move to the next stage which is issues to be addressed in the EIA studies.
screening. The submission of a project proposal signifies the Quantifiable impacts are to be assessed on the basis of
commencement of the EIA process. magnitude, prevalence, frequency and duration and non-
quantifiable impacts (such as aesthetic or recreational value),
2. Screening significance is commonly determined through the socio-economic
Screening is done to see whether a project requires criteria. After the areas, where the project could have significant
environmental clearance as per the statutory notifications. At impact, are identified, the baseline status of these should be
this stage, the project proponent decides the type of project monitored and then the likely changes in these on account of the
and also about requirement of Environmental Clearance. If construction and operation of the proposed project should be
required, the proponent may consult IAA. predicted.

The EIA Procedure (continued) The EIA Procedure (continued)


4. Base line data collection 6. EIA Report
Base line data describes the existing environmental status of the An EIA report should provide clear information to the decision-maker on the
identified study area. The site-specific primary data should be monitored different environmental scenarios without the project, with the project and
for the identified parameters and supplemented by secondary data if with project alternatives. The proponent prepares detailed Project report
available. and provides information in logical and transparent manner. The IAA
5. Impact prediction and Assessment of Alternatives examines if procedures have been followed as per MoEF notifications.
Impact prediction is a way of mapping the environmental consequences 7. Public hearing
of the significant aspects of the project and its alternatives. For every After the completion of EIA report the law requires that the public must be
informed and consulted on a proposed development after the completion of
project, possible alternatives should be identified and environmental
EIA report. The State Pollution Control Boards will conduct the public
attributes compared. Alternatives should cover both project location and
hearing before the proposals are sent to MoEF for obtaining environmental
process technologies. Alternatives should then be ranked for selection of
clearance. Any one likely to be affected by the proposed project is entitled
the best environmental optimum economic benefits to the community at to have access to the Executive Summary of the EIA. The affected persons
large. Once alternatives have been reviewed, a mitigation plan should may include: a) Bonafide local residents; b) Local associations; c)
be drawn up for the selected option and is supplemented with an Environmental groups: active in the area; d) Any other person located at
Environmental Management Plan (EMP) to guide the proponent towards the project site / sites of displacement. They are to be given an opportunity
environmental improvements. The EMP is a crucial input to monitoring to make oral/written suggestions to the State Pollution Control Board as per
the clearance conditions and therefore details of monitoring should be Schedule IV.
included in the EMP.

The EIA Procedure (continued) Which project requires EIA?


8. Decision-making
Decision making process involve consultation between the project
proponent (assisted by a consultant) and the impact assessment authority
(assisted by an expert group if necessary). The decision on environmental
clearance is arrived at through a number of steps including evaluation of All new projects/activities listed in EIA
EIA and EMP.
Schedule;
9. Monitoring the clearance conditions
Monitoring has to be done during both construction and operation phases
of a project. It is done not just to ensure that the commitments made are
Expansion and/or modernization of
complied with but also to observe whether the predictions made in the EIA
reports are correct or not. Where the impacts exceed the predicted levels, existing projects /activities; and
corrective action should be taken. Monitoring also enables the regulatory
agency to review the validity of predictions and the conditions of Change in product mix
implementation of the Environmental Management Plan (EMP). The Project
Proponent, IAA and Pollution Control Boards should monitor the
implementation of conditions. The proponent is required to file once in six
months a report demonstrating the compliance to IA.
Limitations of EIA process in India Limitations of EIA process in India (contd.)
Limited involvement of public and No provision in place to cover landscape
government agencies in the initial phases. and visual impacts in the Indian EIA
regulations.
EIA screening for developmental projects
is based on investment criteria instead of Most reports are made in English and not in
impact potential. the local language.

Screening done on the basis of a defined Only the executive summary is translated
list. Threshold values on the size of the into local language.
project has been used to decide whether
the project will be cleared by the state
government or the central government.

Thank You..

You might also like