OBRA: EMPEDRADO AHOGADO EN MORTERO INICIO: 14/Nov/2014

EN LA CALLE MANANTIAL, LOCALIDAD DE TERMINO: 26/Dic/2014


PANALES, MUNICIPIO DE TOLIMAN, QUERETARO. PLAZO: 43 Dias Nat.
EN LA LOCALIDAD DE PANALES, MUNICIPIO DE TOLIMAN FECHA: 03/Nov/2014
CONCURSO NO. DEEAOP-MT-INV FED-36-2014
PROGRAMA DE MONTOS MENSUALES DE: MANO DE OBRA
Das 2014
Clave Descripcin Inicia Trab. Termina Total Nov Dic
MO-0001 PEON 14/Nov/2014 34d 26/Dic/2014 77,217.75 19,113.82 58,103.93

MO-0002 AYUDANTE 14/Nov/2014 14.5d 02/Dic/2014 2,314.30 2,206.09 108.21

MO-0003 CADENERO 14/Nov/2014 12d 28/Nov/2014 2,004.73 2,004.73

MO-0004 ALBAIL 14/Nov/2014 32d 24/Dic/2014 78,492.61 16,956.43 61,536.18

MO-0010 CHOFER 14/Nov/2014 11.5d 26/Dic/2014 2,437.06 2,219.37 217.69

MO-0015 CABO 14/Nov/2014 34d 26/Dic/2014 11,148.92 3,195.02 7,953.90

MO-0021 OPERADOR DE RETROEXCAVADORA


14/Nov/2014 14.5d 02/Dic/2014 3,599.95 3,431.63 168.32

MO-0022 OPERADOR VIBROCOMPACTADOR


21/Nov/2014 26.5d 24/Dic/2014 627.77 414.80 212.97

MO-0023 OPERADOR DE EQUIPO LIGERO 14/Nov/2014 26.5d 24/Dic/2014 4,853.77 959.23 3,894.54

TOTAL PARCIAL: 182,696.86 50,501.12 132,195.74


TOTAL ACUMULADO: 50,501.12 182,696.86

"ESTE PROGRAMA ES PUBLICO, AJENO A CUALQUIER PARTIDO POLITICO. QUEDA PROHIBIDO EL USO PARA ING. ALVARO UGALDE RIOS
FINES DISTINTOS AL DESARROLLO SOCIAL