You are on page 1of 4

that led to the attachment warranties, to prove that the loss subject

1. PILIPINAS BANK, petitioner, vs . COURT OF APPEALS, HON. of petitionerss claim is covered by the Policy.
ELOY R. BELLO, in his capacity as Presiding Judge, RTC-
Manila, Branch 15, and MERIDIAN ASSURANCE CORPORATION, When petitioner was about to present Mr. Tubianosa to testify, private
respondents respondent objected and argued that said witness testimony
G.R. No. 141060 regarding the negotiations on the terms and conditions of the policy
September 29, 2000 would be violative of the best evidence rule. Private respondent's
objection was overruled and Tubianosa was allowed to take the stand.
Doctrine: There is no ambiguity in the provisions of the Policy which Private respondent again objected to the questions regarding the
would necessitate the presentation of extrinsic evidence to clarify the negotiations on the terms and conditions on the policy, and the trial
meaning thereof. The petitioner failed to set forth in its Complaint a court sustained the objection in part and overruled it in part by
specific allegation that there is an intrinsic ambiguity in the insurance allowing petitioner to adduce evidence pertaining to the negotiations
policy which would warrant the presentation of further evidence to other than what appears in the insurance policy. The petitioner filed a
clarify the intent of the contracting parties. Motion to Recall Witness, praying that it be allowed to recall
Tubianosa to testify on the negotiations pertaining to the terms and
Facts: Petitioner obtained from private respondent Meridian conditions of the policy before its issuance to determine the intention
Assurance Corporation a Money Securities and Payroll Comprehensive of the parties regarding the said terms and conditions. Private
Policy. While the policy was in full force and effect, petitioner's respondent objected thereto, on the ground that the same would
armored vehicle bearing Plate No. NBT 379 was on its way to deliver violate the parol evidence rule. RTC issued an order denying
the payroll withdrawal of its client Luzon Development Bank ACLEM petitioners motion to recall Tubianosa to the witness stand, ruling that
Paper Mills, was robbed by two armed men wearing police uniforms. the same would violate the parol evidence rule.
The loss suffered by petitioner amounted to P545,301.40.
Petitioner filed a petition for certiorari with the Court of Appeals
Petitioner filed a formal notice of claim under its insurance policy with assailing the aforementioned Orders of the RTC. CA dismissed the
private respondent invoking Section II of the Policy which states: petition and held that there was no grave abuse of discretion on the
Section II-MONEY AND SECURITIES OUTSIDE PREMISES: The Company part of respondent judge. It held that there is no ambiguity in the
will subject to the Limits of this Section as hereinafter provided provisions of the Policy which would necessitate the presentation of
indemnify the insured against loss by any cause whatsoever occuring extrinsic evidence to clarify the meaning thereof. The Court of
(sic) outside the premises of Money and Securities in the personal Appeals also stated that petitioner failed to set forth in its Complaint
charge of a Messenger in transit on a Money Route x x x. and the a specific allegation that there is an intrinsic ambiguity in the
warranty/rider attached to the Policy which provides that- insurance policy which would warrant the presentation of further
WARRANTED that in respect of PILIPINAS BANK Head Office and all its evidence to clarify the intent of the contracting parties.
branches, pick-up and/or deposits and withdrawals without the use of
armored car, company car, or official's car shall be covered by this Issue: WON the provsions of the Policy are clear enough to warrant
policy. the presentation of extrinsic evidence

Private respondent denied petitioner's claim and averred that the Held: Yes. We find no cogent reason to disturb the findings of the
insurance does not cover the deliveries of the withdrawals to Court of Appeals. ThePetitioners Complaint merely alleged that under
petitioner's clients. Petitioner filed a complaint against private the provisions of the Policy, it was entitled to recover from private
respondent with RTC-Manila. Private respondent filed a motion to respondent the amount it lost during the heist. It did not allege
dismiss which was granted by the RTC. After the case was remanded therein that the Policys terms were ambiguous or failed to express the
to the RTC and the latter set the case for pre-trial, petitioner filed its true agreement between itself and private respondent. Such being
Pre-Trial Brief, stating among others, that it would present as one of the case, petitioner has no right to insist that it be allowed to present
its witnesses Mr. Cesar R. Tubianosa to testify on the existence and Tubianosas testimony to shed light on the alleged true agreement of
due execution of the insurance policy, particularly on the negotiations the parties, notwithstanding its statement in its Pre-Trial Brief that it
that were held prior to the execution thereof, including negotiations was presenting said witness for that purpose.
Section 9, Rule 130 of the Revised Rules of Court expressly requires
that for parol evidence to be admissible to vary the terms of the
written agreement, the mistake or imperfection thereof or its failure
to express the true agreement of the parties should be put in issue by
the pleadings.

As correctly noted by the appellate court, petitioner failed to raise the


issue of an intrinsic ambiguity, mistake or imperfection in the terms
of the Policy, or of the failure of said contract to express the true
intent and agreement of the parties thereto in its Complaint. There
was therefore no error on the part of the appellate court when it
affirmed the RTCs Order disallowing the recall of Tubianosa to the
witness stand, for such disallowance is in accord with the rule that
when the terms of an agreement have been reduced to writing, it is
considered as containing all the terms agreed upon and there can be,
between the parties and their successors-in-interest, no evidence of
such other terms other than the contents of the written agreement.

Under the general rule in Section 9 of Rule 130 of the Rules of Court,
when the terms of an agreement were reduced to writing, as in this
case, it is deemed to contain all the terms agreed upon and no
evidence of such terms can be admitted other than the contents
thereof.
7. LEIGHTON CONTRACTORS PHILIPPINES, INC., petitioner, vs. In a letter, respondent informed petitioner that, due to the revisions
CNP INDUSTRIES, INC., respondent in the designs of the roof ridge ventilation and crane beams, it
G.R. No. 160972 incurred "additional costs" amounting to P13,442,882. In its August
March 9, 2010 12, 1997 progress report, respondent reiterated that the roof ridge
ventilation and crane beams were not included in the scope of work
Doctrine: Respondent, presented the August 12, 1997 progress and were not part of the sub-contract price and presented the cost
report signed by Bennett. However, respondent knew that Bennett estimates in the progress report. Because respondent was unable to
was not authorized to order any changes in the scope of works or to meet the project schedule, petitioner took over the project on April
approve the cost thereof. Bennett did not sign the subcontract for and 27, 1998. At the time of the takeover, respondent had already
in behalf of respondent but only as a witness. Respondent was accomplished 86% of the project for which petitioner paid
therefore aware of Bennett's lack of authority. We find that the P42,008,343.69. Respondent asked petitioner to settle the
contract was never modified. "outstanding balance" of P12,364,993.94, asserting that the roof
ridge ventilation and crane beams were excluded from the project
Facts: Hardie Jardin, Inc. (HJI) awarded the contract for site cost. Petitioner refused to pay as the subcontract clearly stated that
preparation, building foundation and structural steel works of its fibre the sub-contract price was a fixed lump sum.
cement plant project in Barangay Tatalon in San Isidro, Cabuyao,
Laguna to petitioner Leighton Contractors Philippines, Inc. The parties submitted the matter to the Construction Industry
Respondent CNP Industries, Inc. submitted to petitioner a proposal to Arbitration Commission (CIAC) for arbitration. Respondent argued that
undertake, as subcontractor, the construction of the structural the proposal it submitted (accepted by petitioner) excluded the roof
steelworks of HJI's fibre cement plant project. It estimated the project ridge ventilation and crane beams as the fabrications drawings were
to require 885,009 kgs. of steel costing P44,223,909. petitioner "clouded" or had not been finalized when the subcontract was
accepted respondent's proposal specifying that the project cost was executed. Furthermore, petitioner approved the cost estimates when
for the fixed lump sum price of P44,223,909. Respondent agreed and Simon Bennett, petitioner's quantity surveyor, signed the August 12,
petitioner instructed it to commence work. Petitioner revised the 1997 progress report. This proved that the said portions were
fabrication drawings of several of the structure's columns "additional works" excluded from the fixed lump-sum price.
necessitating adjustments in the designs of roof ridge ventilation and Petitioner, on the other hand, asserted that the subcontract explicitly
crane beams. Petitioner communicated the said revisions to included the aforementioned works in the scope of work.
respondent and respondent estimated that the said revisions required Furthermore, it was not liable for the "additional costs" incurred by
an additional 8,132 kgs. of steel costing P13,442,882. However, it did respondent as the subcontract clearly provided that the project was
not re-negotiate the fixed lump-sum price with petitioner. for the fixed lump-sum price of P44,223,909. It likewise denied
approving respondent's additional cost estimates as Bennett signed
Petitioner and respondent signed a sub-contract providing: the August 12, 1997 progress report only to acknowledge its receipt.
(B) Subcontract works. To carry out complete structural steelworks The CIAC found that the subcontract was perfected when petitioner
outlined in the Sub-contract Lump Sum Price [of P44,223,909] in accepted respondent's proposal. Thus, because the fabrication
accordance with the Main Drawing and Technical Specifications and drawings for the roof ridge ventilation and crane beams had not yet
in accordance with the Main Contract, all of which are available on been finalized then, the same were deemed "additional works" not
Site. included in the lump-sum price.
(C) Special Conditions of the Sub-Contract. Notwithstanding the
provisions of Clause 11(4) of the General Conditions of the Sub- Petitioner assailed the CIAC decision via a petition for review in the
contract, this Sub-contract is on a Fixed Lump Sum basis and CA. the CA dismissed the petition and affirmed the CIAC decision in
is not subject to re-measurement. It is the responsibility of toto.
[respondent] to derive his own quantities for the purpose of the Lump
Sum Subcontract price. No additional payments will be made to Issue: WON the cost of the additional steel used for the roof ridge
[respondent] for any errors in quantities that may be revealed during ventilation and crane beams was included in the fixed lump-sum
the Sub-contract period. price.
Held: Yes. The scope of work was defined in the subcontract as the contract, petitioner was only liable to pay the stipulated subcontract
completion of the structural steel works according to the main price.
drawing, technical specifications and the main contract. Thus, to
determine whether the roof ridge ventilation and crane beams were IMPORTANT TOPIC BUT NOT EVID-RELATED - In contracts for a
included in the scope of work, reference to the main drawing, stipulated price like fixed lump-sum contracts, the recovery of
technical specifications and main contract is necessary. The main additional costs is governed by Article 1724 of the Civil Code. Settled
contract stated that the structural steel works included Drawing Nos. is the rule that a claim for the cost of additional work arising from
P302-6200-S-405 and P302-6200-S-402. This, according to petitioner changes in the scope of work can only be allowed upon the: (1)
and respondent, referred to the roof ridge ventilation and crane written authority from the developer or project owner ordering or
beams. Hence, the said works were clearly included in the sub- allowing the written changes in work and (2) written agreement of
contract works. parties with regard to the increase in price or cost due to the change
in work or design modification.
The parol evidence rule, embodied in Section 9, Rule 130 of the Rules The compliance with the two requisites of Article 1724, a specific
of Court holds that when the terms of an agreement have been provision governing additional works, is a condition precedent for the
reduced into writing, it is considered as containing all the terms recovery. The absence of one or the other condition bars the recovery
agreed upon and there can be, between the parties and their of additional costs. Neither the authority for the changes made nor
successors in interest, no evidence of such terms other than the the additional price to be paid therefor may be proved by any other
contents of the written agreement. It, however, admits of exceptions evidence.
such as when the parties subsequently modify the terms of their
original agreement.

Respondent contends that when Bennett signed the August 12, 1997
progress report, petitioner approved the additional cost estimates, in
effect modifying the original agreement in the subcontract.
Respondent therefore claims an exception to the parole evidence rule.
Respondent, in this instance, presented the August 12, 1997 progress
report signed by Bennett. However, respondent knew that Bennett
was not authorized to order any changes in the scope of works or to
approve the cost thereof. It addressed all correspondences relating to
the project to (petitioner's) project manager Michael Dent, not
Bennett. Moreover, Bennett did not sign the subcontract for and in
behalf of respondent but only as a witness. Respondent was therefore
aware of Bennett's lack of authority. We find that the contract was
never modified.

In a fixed lump-sum contract, the project owner agrees to pay the


contractor a specified amount for completing a scope of work
involving a variety of unspecified items of work without requiring a
cost breakdown. By entering into a fixed lump-sum contract,
respondent undertook the risk of incurring a loss due to errors in
measurement. The sub-contract explicitly stated that the stipulated
price was not subject to remeasurement. Since the roof ridge
ventilation and crane beams were included in the scope of work,
respondent was presumed to have estimated the quantity of steel
(the minimum and maximum amount) needed on the said portions
when it made its formal offer. By the very nature of a fixed lump-sum

You might also like