You are on page 1of 11

Proceedings of the Institution of

Civil Engineers
Geotechnical Engineering 159
July 2006 Issue GE3
Pages 207217

Paper 14381
Received 17/08/2005
Accepted 03/04/2006

Keywords: Chris Haberfield Ben Collingwood


foundations/piles & piling Golder Associates Pty Ltd, Wagstaff Piling Pty Ltd,
Australia Melbourne, Australia

Rock-socketed pile design and construction: a better way?


C. Haberfield BE, BSc, PhD, FIE(Aust) and B. Collingwood BE, PhD

Piles socketed into rock are often used to support heavy The performance of rock-socketed piles at serviceability loads
loads from buildings and infrastructure. Piles typically of is dependent predominantly on the shear resistance developed
up to 1.8 m diameter carrying safe working loads of up at the interface between the concrete shaft and the surrounding
to 40 MN are utilised in Australia. Their design has rock. The resistance developed depends on many factors
traditionally been based on conservative, empirical rules. including the shaft diameter, the type, stiffness and strength of
GARSP (Golder Associates Rocket field Socket the rock, and construction effects such as socket roughness, the
Procedure) is a recent design innovation that provides a thickness of smear zone or residual drilling fluid coating the
serviceability approach to design, and allows socket socket walls, and the pressure imposed onto the socket rock
lengths to be optimised during the drilling process, often due to fluid concrete placement. 13 Shaft resistance is very
resulting in significant savings. It also provides better sensitive to several of these parameters, and, as a result, socket
control of the risks associated with unexpected ground performance can vary significantly from one site to another,
conditions and with construction of the pile. GARSP has even in the same rock type.
been used in collaboration with Wagstaff Piling on
several large-scale socketed pile projects in Melbourne, Over the last 30 years numerous studies have been made on the
Australia, including the second hotel for Crown Casino, performance and design of piles in rock. 2,424 In many of these
the new grandstand at the Melbourne Cricket Ground, studies the importance of construction effects such as
the redevelopment of Spencer Street Station, and roughness and drilling fluid residue and smear on the capacity
several residential towers. The adoption of this approach of drilled shafts has been emphasised. Overall, these studies
for these projects in conjunction with best practice have greatly improved the knowledge of socketed pile
construction techniques has resulted in significant cost behaviour and the ability to predict their performance.
savings in terms both of materials and of construction
time. This paper briefly describes the traditional design The significant increase in knowledge of rock-socketed pile
approaches and the basic components of GARSP, and performance has led to the development of quite sophisticated
then presents some recent projects where it has been computer programs to calculate the loaddeformation
used. performance of socketed piles. 20,2527 Each of these programs
has its relative merits and shortcomings. Major shortcomings of
1. INTRODUCTION most of the programs are that they rely on properties that are
Multi-storey buildings, bridges and elevated freeways, facilities not normally measured as part of a standard site investigation,
for industrial production and offshore oil and gas platforms are and they are unable to account for variations in construction
all large structures that require stable foundations to ensure methods (e.g. type of drilling tool, cleanliness and roughness of
safe working conditions with minimal maintenance. In many the socket, use of drilling fluids), which may have an impact
cases the surface soils are not of adequate strength to provide on socket performance. ROCKET97 20,28 is a computer program
stable foundations, and instead the large loads imposed by that addresses these issues. It provides a fundamental and
these structures must be carried to stronger rock at depth. One rational approach to the analysis of rock-socketed piles, which
common engineering solution to this problem is to use large- relies on basic and commonly measured rock properties and
diameter concrete piles drilled or socketed into the rock. These can account for the effects of construction.
rock-socket piles are constructed by drilling through the softer,
near-surface soil deposits into the founding rock stratum, Although our knowledge of rock-socketed pile performance
placing steel reinforcement into the borehole or socket so and our ability to drill larger and deeper sockets have
formed, and then casting concrete into the socket. Loads are improved, our design methods still rely largely on simple
subsequently transferred through the column of the concrete empirical rules and a load-based approach. The inherent
pile and into the surrounding rock. The socket must be conservatism of this approach often results in unnecessarily
designed to carry the imposed loads safely and limit long sockets and extra cost.
settlements to an acceptable level. Pile lengths in excess of
70 m, diameters up to 3 m and serviceability loads in excess of The first-named author, with assistance from some colleagues,
50 MN are possible. has recently developed GARSP (Golder Associates Rocket field

Geotechnical Engineering 159 Issue GE3 Rock-socketed pile design and construction: a better way? Haberfield Collingwood 207
Socket Procedure), a system for the design of socketed piles, realised, recommendations were site specific, and unrelated to
which allows socket lengths to be optimised during the drilling any design philosophy that would allow these results to be
process using visual observation of the drilling cuttings. In extrapolated to other sites and conditions.
addition, this system provides better control of the risks
associated with unexpected ground conditions and with Since the mid 1970s there have been numerous attempts to
construction of the pile. It is a serviceability-based approach relate pile shaft resistance to the rock strength. The values of
that often results in reduction in socket lengths and significant shaft resistance initially adopted were extrapolated from the
cost savings. results of field pile tests in clay. Typically, allowable shaft
resistance values were limited to 5% of the rock strength in
This new system has been used on more than ten large-scale uniaxial compression. 10,12,33 Numerous investigators have
socketed pile projects in Melbourne, including the new demonstrated the conservatism of such recommendations,
grandstand at the Melbourne Cricket Ground, the especially for soft rocks, but the 5% value is still in common
redevelopment of Spencer Street Station, and several use.
residential towers. The adoption of this approach for these
projects has resulted in significant savings to the client in By the early 1980s field load testing of pile shafts in rock was
terms both of materials and of construction time. possible, and valuable data on shaft resistance became
available. Several researchers presented empirical correlations
The primary analysis tool used in GARSP is the computer between shaft resistance and the unconfined compressive
software ROCKET97. 20,28 ROCKET97 can account for rock strength qu of the rock. Fig. 1 shows correlations presented by
properties, drilling technique and construction processes, and is Rowe and Armitage. 14 The adhesion factor is the ratio of
based on analysis methods that have been confirmed through ultimate shaft resistance to qu . Kulhawy and Phoon 18 later
extensive large-scale laboratory direct shear testing of presented a more comprehensive database. Fig. 1 shows that
concreterock interfaces and field testing of side only, base there is almost an order of magnitude variation in back-
only and complete piles in siltstone. The methods have also calculated adhesion factors, confirming that factors other than
been found to be appropriate for other rock types, with rock strength also play an important role in defining the shaft
assessed performance in weathered granite, basalt, sandstone, capacity of rock-socketed piles.
conglomerate and calcarenite showing close agreement with
field test results. Socket roughness was identified as one of these factors. In
particular, through the analysis of field load tests in rock, the
This paper briefly describes current methods of rock socket pile capacity of rough shafts was demonstrated to be several times
design and analysis. The basis of the new system is then greater than that of smooth shafts in the same material.
described, and several recent projects where it has been used Existing correlations with qu were modified to reflect the
are presented. influence of roughness. Recommendations followed to roughen
sockets artificially as a standard construction practice. Williams
2. A BRIEF HISTORY OF SOCKETED PILE ANALYSIS and Pells2 observed that discontinuities present within the rock
AND DESIGN mass reduced shaft resistance, and suggested a reduction factor
The design philosophy for piles socketed into rock has a be applied to account for the influence of rock mass stiffness.
relatively short history. Initially the tendency was (and still is
in some parts of the world) to design these piles allowing for During the 1970s several researchers presented analytical and
base resistance only. Presumably it was thought that ultimate finite element solutions for piles in an elastic medium. 3539
pile resistance, at least for short sockets, was dominated by end
bearing, and that base cleanliness was not considered to be a
significant problem. It has since been established that the total 10
05
response of a pile to axial load is dependent on the 045qu

development of both side and base resistance, with side


043
resistance generally dominating at serviceability loads, 04qu

especially for long sockets. This is because shaft resistance in


pile sockets is mobilised at much smaller displacements than
Adhesion factor, q

05 2 3
02qu 3
base resistance. 29,30 Typically, peak shaft resistance mobilises 2
2
at displacements of around 0.51% of pile diameter, whereas
05
03qu 2
01 044qu
064
displacements of around 1020% of pile diameter may be Legend
Mudstone, shale
required to approach ultimate base resistance. 31 In developing Sandstone
the shaft resistance, the pilerock system initially acts Indicates test not to failure
Shaded symbol denotes a tension (Pull-out) socket
monolithically, and deformations may be considered to be
Correlation from:
entirely elastic. However, with increased load, additional Linear regression13
Horvath 34et al.
relative displacement or slip occurs at the pilerock interface, Horvath
gradually leading to more load being taken by the base. Williams et al.11

001
Specific allowance for shaft resistance in rock sockets started to 02 10 10 40
Unconfined compressive strength, qu: MPa
appear in the mid 1960s. Values of allowable shaft resistance
between 100 kPa and 1000 kPa were quoted for different Fig. 1. Empirical corrections with Rowe and Armitage 14
rocks. 32 Although the importance of shaft resistance was

208 Geotechnical Engineering 159 Issue GE3 Rock-socketed pile design and construction: a better way? Haberfield Collingwood
These solutions gave engineers a theoretically based method of empirical factors must usually be established. For example,
estimating pile settlements. They also provided a rational Carter and Ooi 26 describe a hardening and softening model
method for estimating the relative contributions made by shaft (HANSOM) for monotonic loadings of sockets in sandstone that
and base resistance. However, as the elastic solutions assume requires 13 input parameters, seven of which are empirically
no-slip behaviour at the pilerock interface they cannot be derived from direct shear tests under a range of stress
used to predict ultimate pile performance, and therefore must conditions and uniaxial compression tests. Such empirical
rely on the empirical correlations with qu , such as shown in factors may have to be re-established for other rock strengths,
Fig. 1, to estimate capacity. or rock types, or even for other surfaces, if the characterisation
of surface roughness is limited.
Williams et al. 11 used elastic solutions as a starting point for
their analyses, but then relaxed side and base resistance There appear to have been only two attempts to reduce the
according to empirical relationships developed from a reliance on empirical factors by modelling the micro-
comprehensive range of field tests to predict the observed non- mechanics of the interface directly. Hassan 27 developed an
linear characteristics of pile behaviour. Important outcomes elasto-plastic finite element model into which simplistic
from this research were the significance of socket roughness, interface roughness geometries can be input. An alternative
rock stiffness and the dilation of the socket during axial approach was adopted by researchers at Monash
displacement. The work-hardening aspects of socket behaviour University. 4650 Their approach has been to study the
were explained and demonstrated by the development of micromechanics of interface behaviour carefully through
constant normal stiffness direct shear testing. extensive laboratory testing, and to model the observed
behaviour using simplified models based on rock mechanics
Improved elasto-plastic theoretical solutions 14,37,40 that principles. The research has resulted in a theoretical model
accounted for pile slip have been developed. The elasto-plastic capable of predicting the full loaddisplacement behaviour of
analyses require a failure criterion and a flow rule to model the pilerock interface based only on a knowledge of the
plastic deformation or slip and dilation at the interface. Rowe interface roughness, the relevant boundary conditions (initial
and Armitage 14 incorporated strain-softening and a variable normal stress and normal stiffness), and basic rock and
dilation angle, which they claimed resulted in significantly concrete properties. These models have been incorporated into
improved solutions. Nevertheless, they conceded that the use of a computer program called ROCKET97. 21 Comparisons between
empirical correlations would be more appropriate given that model predictions and the results of laboratory direct shear
the model predictions depend heavily on input parameters that tests on concreterock (siltstone, sandstone, limestone and
are difficult to obtain with sufficient reliability. basalt) joints show excellent agreement. This fundamental
research has also investigated construction effects such as
Carter and Kulhawy 41 developed approximate analytical smear, drilling fluid residue, elevated concrete pressures and
solutions for the loadsettlement behaviour of side-only and socket roughness. 21,22,24
combined side and base resistance piles. The solutions assume
elastic perfectly plastic behaviour and can accommodate a pile 3. AVAILABLE DESIGN METHODS
response that is purely elastic or has undergone full slip. Partial Of the analysis methods described above, relatively few appear
slip is not accounted for. Average peak shaft resistance is to be commonly used for design (at least in Australia). Pells 23
determined from empirical correlations and is assumed to groups the available design methods into three categories:
include the effect of rock strength and interface dilation. elastic design, 12,41 design for side-slip 14,40 and non-linear
Pells 23 reported that the solutions provided by Carter and analysis. 11,50
Kulhawy were in close agreement with the finite element
solutions of Rowe and Armitage. 14 3.1. Elastic design
Various approaches have been devised in order to translate the
Since the 1980s researchers have been attempting to improve elastic solutions into simple design rules. Pells and Turner 36
the ability to predict the performance of pile sockets by presented a series of elastic solutions for shaft-only, base-only
conceptualising the pilerock interface as a form of rock joint. and combined shaft and base resistance piles determined from
The research has generally been directed at establishing numerical integration of Mindlins equations and finite element
appropriate constitutive laws based on the results of laboratory analyses. Two methods were proposed to account for the
testing of interface samples. 25,26,42 This work is closely allied to combined effect of shaft and base resistance. Both methods
the work of researchers in the field of rock mechanics, who make use of simple estimates of limiting shaft adhesion and
have established similar relationships for natural rock base resistance (i.e. 0.05 qu and 0.5 qu respectively for the
joints. 4345 Sydney Sandstone for which the method was specifically
developed). Both values are predicated on a criterion of
Most of these finite-element-based rock joint models do not limiting settlements to 1% of diameter.
explicitly model the kinematics of the pilerock interface, but
instead treat the interface as a black box and rely on In the first method, for a given load requirement and pile
empirically deprived parameters such as strength, dilation, and diameter, the developed end-bearing at a displacement of 1%
shear and normal stiffness of the interface to make predictions. of shaft diameter is assumed to be fully available. Any deficit
Such parameters are usually established through laboratory in capacity is assumed to be carried by the shaft, and the
testing programmes and are used incrementally to relate shear required shaft length is then determined from the shaft
and normal displacements to shear and normal stresses. In circumference and the allowable shaft adhesion. It is assumed
order to capture the necessary characteristics, numerous that the shaft resistance is plastic (i.e. is constant after

Geotechnical Engineering 159 Issue GE3 Rock-socketed pile design and construction: a better way? Haberfield Collingwood 209
reaching initial peak), resulting in no transfer of load to the the bottom rather than the bottom to the top) is then carried
base, and therefore guaranteeing settlements of less than 1% of out to sum the contributions of each sublayer and of the base.
pile diameter. This method is not rigorous, because the strain The base response is assumed to be elastic perfectly plastic or
fields from the assumed shaft and end-bearing components will hyperbolic, with the ultimate base resistance being input by the
not necessarily be compatible, and in practice the compatibility user. Base debris and enlarged (or smaller) bases can also be
requirement will force some redistribution of resistance. accounted for. The output is in the form of the pile head load
displacement response.
In the second method the socket length is iteratively designed
from charts provided for combined shaft and base resistance, As with all theoretical techniques, the solutions obtained are
thus taking into account elastic compatibility considerations. dependent on the input parameters. The following parameters
This second method results in longer pile sockets. This is are required to determine the z curve for each sublayer
essentially the same method as proposed by Horvath et al. 13
(a) pile properties: shaft radius, initial normal stress
Pells 23 adapted the second method to the limit state format and (b) rock properties: peak intact rock strength parameters:
provided recommendations with regard to strength reduction cohesion c9 and friction angle, 9; residual friction angle
factors. He also altered the determination of limiting shaft r : rock mass Youngs modulus E and Poissons ratio, 
resistance from 0.05qu to include estimates from existing (c) interface roughness properties: mean asperity height hav
correlations with qu (e.g. Fig. 1). and chord length .

The input parameters required to carry out an elastic analysis As almost all of these parameters can have a significant
include the Youngs modulus of the rock mass around and influence on shaft resistance (the exception being Poissons
below the pile, the average peak shaft resistance, and the ratio), it is imperative that the designer understands the
ultimate base resistance of the pile. influence that each has on the development of shaft resistance.
It is beyond the scope of this paper to describe in detail the
3.2. Design for side-slip impact of these parameters. The reader is referred to Seidel and
Rowe and Armitage, 14 building on the work of Rowe and Haberfield 48,49 and Haberfield and Seidel 50 for a full
Pells, 40 presented design charts for piles including slip. The description of the models on which the program is based.
method is similar to, and requires the same input parameters
as, the elastic method described above. The analytical solutions 4. DESIGN CONSIDERATIONS
developed by Carter and Kulhawy 41 can be used directly to The analyses and design methods described in Section 3 above
estimate the loaddisplacement behaviour of the pile. Input provide a rational basis for design of rock sockets. However, all
parameters are similar to that required for elastic analysis. the methods other than ROCKET97 rely on empirical
correlations between shaft resistance and rock uniaxial
3.3. Non-linear design strength (such as that shown in Fig. 1) to assess pile ultimate
Williams et al. 11 developed a non-linear design method by capacity. The wide scatter in such correlations forces the
combining empirically measured pile loaddisplacement designer to adopt a conservative approach (e.g. ultimate shaft
response curves with elastic solutions. By implementing a resistance 3 value of 0.05qu ).
simple iterative procedure they were able to develop load
displacement predictions for both side-only and complete (side As has been intimated earlier, the scatter in Fig. 1 can be
and base) piles. At the time, the resulting design method explained by considering the impact of pile diameter, rock type
provided a significant improvement in design rationale over properties and characteristics (e.g. fracturing), construction
existing methods, and was quickly accepted by local practices, socket roughness and the relative contributions of
practitioners for the design of sockets in the Melbourne base and shaft resistance to pile performance.
siltstone. Although still in use, the method has been largely
superseded by more recent research work and the development ROCKET97 provides a rational approach for assessing the
of ROCKET97. impact of all of these parameters. For example, the influence of
socket diameter, roughness and initial normal stress on the
The rock joint model developed by Seidel and Haberfield 49 loaddisplacement response of a pile socketed into highly to
forms the basis of a pile analysis program called ROCKET97. 21 moderately weathered siltstone is illustrated in Fig. 2.
The program allows the designer to divide the socket and
overburden into sublayers that might represent different rock The siltstone adopted for these analyses has a uniaxial
and soil types or different weathering conditions within the compressive strength of approximately 3 MPa, and the
same rock type. For each sublayer several fundamental input following properties: Youngs modulus 360 MPa, Poissons
parameters are required. From this input, a z (shear stress ratio 0.3, drained peak cohesion 0.75 MPa, drained peak
against displacement) curve for each layer is calculated. These friction angle 368 and residual friction angle 24.58. The
curves represent the behaviour of the concreterock interface reference case adopts a socket diameter of 0.9 m, an initial
for each sublayer. To determine the overall pile response, the normal stress of 0.1 MPa, and an absolute mean roughness
elastic shortening of the pile shaft and the vertical elastic angle of 108 at a chord length of 30 mm. For simplicity, only
deformations of the rock mass need to be considered. The the results of the predictions at this chord length have been
elastic deformations of the rock mass are determined using the included. In each of the analyses described below only the
solution determined by Randolph and Wroth. 35 A reverse Coyle relevant parameter (i.e. socket diameter, mean absolute
and Reese 51 analysis (i.e. working from the top of the pile to roughness angle, or initial normal stress) has been varied. All

210 Geotechnical Engineering 159 Issue GE3 Rock-socketed pile design and construction: a better way? Haberfield Collingwood
It is unlikely that designers
1000
800 Annotations denote mean absolute
and piling contractors will
035 asperity angle in degrees
Shaft resistance: kPa 800 routinely measure socket

Shaft resistance: kPa


600 150 175 roughness. For this reason,
125
06
600 100 Seidel and Haberfield 20 have
400 09 published recommended
15 75
400
20 50
upper and lower values of
200 roughness parameters for as-
200 25
Annotations denote diameter drilled sockets (i.e. not
of shaft in (m)
0 0 grooved) as a function of
0 5 10 15 0 5 10 15 rock strength. These are
Shaft displacement: mm Shaft displacement: mm
reproduced here in terms of
(a) (b)
roughness height in Fig. 3.
The values correspond to a
2000
50 mm chord length, which
1200 should give a reasonable
1500 estimate of ultimate
Shaft resistance: kPa

900 resistance and a conservative


estimate of displacement.
1000 600 Also shown in Fig. 3 are
estimates of socket roughness
300 back-estimated from pile load
500 100 tests using ROCKET97 and
30
Annotations denote initial normal recommendations for upper
stress in kPa and lower roughness limits
0
0 5 10 15 proposed by Collingwood. 24
Shaft displacement: mm It is interesting to note that
(c)
the maximum roughness
occurs in rocks with a qu of
Fig. 2. Predicted influence of (a) socket diameter, (b) socket roughness and (c) initial normal
stress on performance between 2 MPa and 10 MPa,
perhaps reflecting the
weathering and jointing
condition of these rocks. The
other parameters have been kept constant at the reference case greater roughness in these materials is also observed in
values. The range of parameters considered are reasonably practice.
typical of drilled sockets constructed in the siltstone bedrock
that underlies much of Melbourne, Australia. Collingwood 24 has developed a system for characterisation of
roughness that allows designers to assess their sockets visually
It should be emphasised that the ensuing discussion is relevant for roughness parameters. It is beyond the scope of this paper
only for the parameters stated, and would not necessarily be to describe roughness in further detail. The reader is referred to
appropriate for other cases involving different parameters. Seidel and Haberfield 54 and Haberfield and Seidel 50 for a more
complete description of roughness.

4.1. Influence of socket diameter


The influence of varying only socket diameter is shown in Fig.
2(a). An increase in socket diameter results in a decrease in Williams and Ervin52 extremely jointed rock
unit shaft resistance and initial stiffness. The decrease becomes 50
Pilesshaft resistance fully mobilised
less pronounced as the socket becomes larger. The dependence Pilesfull shaft resistance not mobilised
Effective roughness height: mm

40 Anchors (D , 450 mm)


on socket diameter is due to the constant normal stiffness Sockets known to contain sidewall smear
Seidel el al.,53proposed roughness bounds
condition: 1 as socket diameter increases, normal stiffness Proposed upper and lower bound roughness guidelines
decreases, resulting in a smaller increase in normal stress with 30
socket dilation, and lower shaft resistance.
20

4.2. Influence of socket roughness


10
Figure 2(b) shows that socket roughness is critical to socket
performance. Relatively smooth sockets display a much lower
capacity and lower stiffness than relatively rough sockets. 0

Artificial roughening of sockets has a beneficial effect on shaft 2 3 4 5


1 2 3 4 5
10 2 3 4 5
100 2 3

capacity. Fig. 2(b), however, also suggests that there is an Unconfined compressive strength: MPa
upper limit to socket roughness beyond which very little
increase in shaft capacity can be obtained by artificial Fig. 3. Variation of socket roughness with rock strength
roughening.

Geotechnical Engineering 159 Issue GE3 Rock-socketed pile design and construction: a better way? Haberfield Collingwood 211
4.3. Influence of initial normal stress pile tests to obtain such correlations is prohibitive, and well
The influence of initial normal stress on shaft capacity is beyond the scope of most projects. As a result, designers using
shown in Fig. 2(c). For the range of initial normal stresses that these methods will continue to produce overly conservative
would normally be expected to be encountered in drilled (and perhaps in some cases, unconservative) designs.
sockets due to the weight of wet concrete (which ranges from
about 75 kPa to 245 kPa), only minor differences in peak Design by elastic or limited slip methods also relies on an
resistance are predicted. However, the initial stiffness of the appropriate estimate of Youngs modulus for the rock. The
response increases as the initial normal stress is increased. As a value of Youngs modulus is best achieved through back-
result, although a poor estimate of initial normal stress is likely calculation of existing field pile tests or pressuremeter tests,
to have only a minor influence on the predicted shaft capacity, but more commonly through representative values learned
it may have a major influence on the predicted displacements through experience. Of interest is that in most cases the largest
at serviceability loads. component of settlement at the pile head results from elastic
compression of the pile shaft contained within the overburden.
Figure 2(c) also shows that substantial improvements in pre- For reasonably long sockets this compression can account for
peak shaft performance can be obtained by artificially more than 90% of the pile settlement at serviceability loads. It
generating high initial normal stresses. Such stresses can be is perhaps not surprising, then, that settlement estimates based
generated using expansive cements. Field investigations 55 have on elastic and limited slip methods coupled with conservative
been carried out to see whether this improved performance estimates of shaft capacity result in overestimates of
could be realised in practice. For relatively smooth sockets, settlement.
significant increases in shaft resistance were achieved
(threefold in some cases). However, for very rough sockets, The main advantage of theoretical non-linear methods is that
little, if any, increase in socket resistance was observed. In through such methods there is potential to make the pile work
general, initial stiffness increased with initial normal stress harder and/or to optimise design. By using such methods the
level. designer can assess the likely benefits to be gained by
changing pile diameter and length, socket roughening and
4.4. Influence of bonding, smear and drilling fluid residue socket cleaning. The loss of shaft resistance due to residual
During excavation of rock sockets it is likely that some drilling fluids can also be investigated. The sensitivity of the
contamination of the socket wall will occur, either through pile design to variation in rock properties can be easily
smearing of the rock while cutting (in dry sockets) or by assessed.
coating of the socket walls with drilling fluid residue (polymer
or bentonite filter cake). Cleaning of the socket wall may All of the above provide designers with greater confidence in
remove most of this contamination, but it is likely that some their designs, and provide potential for cost savings and
smear or drilling fluid residue will remainenough to prevent a reduction of risk for their clients.
significant cementitious bond occurring. Cheng 22 investigated
the effect of smear and drilling fluid residue on the
performance of concretesiltstone interfaces tested in direct 6. FROM DESIGN TO CONSTRUCTION
shear in the laboratory. He found that polymer drilling fluids ROCKET97 has been adopted as the analysis tool used with
effectively precluded bonding, but otherwise did not GARSP. GARSP provides a framework that allows the improved
significantly affect the performance of the interface. However, understanding of socket performance and construction
performance significantly reduced with increasing thickness of techniques to be more fully utilised, and which, coupled with
smear and bentonite filter cake. Theoretical models 22 of observations during pile installation, can reduce the risk and
performance for contaminated concreterock interfaces were costs associated with the installation of rock-socketed piles.
subsequently developed. These models are yet to be validated
for rock sockets, and have therefore not been incorporated into GARSP is a three-stage process comprising (a) geotechnical
ROCKET97. However, the program input parameters can be investigation, (b) analysis and design and (c) pile installation.
manipulated to approximate the effect of contamination. The All three stages are essential parts of the process.
effects of smear and bentonite filter cake for a 600 mm
diameter socket in moderately to slightly weathered siltstone
are shown in Fig. 4. The importance of good construction 6.1. Geotechnical investigation
practice and socket cleaning is clearly illustrated. The geotechnical investigation should comprise sufficient
boreholes to assess variation of the rock conditions across the
5. ADVANTAGES OF A MORE RATIONAL DESIGN site and with depth over the volume of rock affected by the
APPROACH piles. Sufficient field and laboratory tests should be carried out
All but one of the design methods presented earlier in the for basic strength and deformation properties to be accurately
paper rely on an empirically based determination of shaft quantified. In Melbourne, an extensive database of the
resistance. As has been demonstrated, there are several factors properties of the Melbourne siltstone, which forms the bedrock
that have a significant influence on shaft resistance. These for much of Melbourne and its surrounds, has been developed.
factors all interact in a very complex way, and, as a result, This database allows a reasonably accurate assessment of the
empirical correlations for shaft capacity that include only one strength and deformation properties of the rock from
parameter (e.g. qu ) will always exhibit a very large scatter. correlations with the saturated water content of the rock. As a
Although site-specific derived correlations may reduce the result, field and laboratory testing for piles in Melbourne
scatter to some degree, the cost of carrying out numerous field siltstone would normally comprise:

212 Geotechnical Engineering 159 Issue GE3 Rock-socketed pile design and construction: a better way? Haberfield Collingwood
value in assessing the peak
1400 1400
Annotations denote bentonite thickness strength parameters of the
1200 Clean socket 1200
Shaft resistance: kPa

Shaft resistance: kPa


2 mm rock. This may be useful in
1000 1000 Clean socket
4 mm harder rocks, where the
800 800 2 mm
6 mm strength of the concrete (pile)
600 600 4 mm
8 mm 6 mm is less than the rock, and is
400 400 therefore of more
10 mm 8 mm
200 200 10 mm significance with respect to
Annotations denote smear thickness
0 0 the performance of the pile.
0 5 10 15 0 5 10 15
Displacement: mm Displacement: mm
(a) 6.2. Analysis and design (b)
The data from the
Fig. 4. Predicted influence of socket wall contamination on socket performance: (a) rock smear; geotechnical investigation are
(b) bentonite filter cake interpreted to provide design
profiles of rock quality (or
weathering condition),
(a) saturated water content measurements on core samples at strength and deformation parameters with depth. An example
1 m intervals of the test data and assumed design profiles for a site in
(b) pressuremeter tests at 23 m intervals Melbourne is shown in Fig. 5.
(c) unconfined compressive strength tests on core samples at
pressuremeter test locations. On the basis of the UCS data, Fig. 3 is used to assess
appropriate (and prudent) roughness parameters for each layer
The purpose of the pressuremeter and unconfined compressive in the design profile. In choosing roughness parameters,
strength tests is to provide a check on the deformation and consideration is given to the type of drilling equipment and the
intact strength properties assessed from the correlations with experience of the drilling contractor. In general, a lower
water content, and to assess the impact of jointing (especially quartile value of roughness is adopted and insistence that all
on rock mass modulus). Peak strength parameters (friction sockets be artificially roughened using a roughening tool (e.g.
angle and cohesion) of the intact rock can be assessed using a tooth fitted to a bucket auger).
the Hoek and Brown failure criterion.
ROCKET97 is then used to assess socket performance for the
The above tests provide data that allow a site-specific range of pile diameters to be used at the site. A factor of safety
assessment of Youngs modulus and peak (intact) strength on settlement is applied to the results of these analyses to
parameters of the rock to be made, together with their produce an initial assessment of socket length, as shown in Fig.
variation across the site and with depth. The residual friction 6. This chart can be provided to the client for the purposes of
angle of the rock is usually assessed on the basis of previous preliminary cost estimation. The choice of factor of safety for
experience. For rocks where few data are available, direct shear serviceability depends on the extent of the site investigation
tests on smooth interfaces should be carried out to assess and the knowledge of the rock behaviour and properties. If a
residual friction angle. A Poissons ratio of about 0.3 can be comprehensive site investigation (as set out earlier) is carried
adopted for most rocks. out, a factor of safety on settlement of 1.5 is usually adopted.
A factor of safety of 2 applies for sites where the investigation
It should be noted that point load strength index is of little has been less extensive or where the knowledge of the rock

Moisture content: % Initial Youngs modulus, Ei: MPa Uniaxial compressive strength: MPa
0 10 20 30 0 1000 2000 3000 4000 0 5 10 15
0 0 0
Upstream end
2 2 2 design line
Downstream
4 4 4 end design line
Depth below top of siltstone: m

Depth below top of siltstone: m

Depth below top of siltstone: m

6 6 6

8 8 8

10 10 10

12 12 12

14 14 14

16 16 16

18 18 18

Fig. 5. Example of data and resulting design profile adopted for a site in Melbourne

Geotechnical Engineering 159 Issue GE3 Rock-socketed pile design and construction: a better way? Haberfield Collingwood 213
(a) It allows socket lengths to be optimised on the basis of the
50 For estimating purposes only. Actual
socket lengths to be assessed rock actually encountered in the socket.
45 based on ground conditions at pile (b) It confirms design assumptions by observing rock quality,
40 locations Socket diameter and ensuring that roughening and cleaning of sockets are
Allowable socket load: MN

5 18 m
35 Downstream end carried out in an appropriate manner.
30 Upstream end 15 m (c) It allows unexpected and variable ground conditions (e.g.
12 m
25 09 m dykes) to be identified, and immediate and appropriate
18 m
20 15 m
action to be taken (e.g. by lengthening or increasing
diameter of the socket) so that the constructed pile satisfies
15 12 m
the design requirements.
10
09 m (d) Piling installation techniques (i.e. contractor performance)
5
can be monitored.
0
0 2 4 6 8 10 12 14 16 (e) Drill cuttings can be collected for further assessment and
Socket length: m confirmation of socket logging procedures (for internal QA
requirements).
Fig. 6. Example of preliminary socket lengths for estimation
purposes The logging sheets compiled in the field by the field engineer
are reviewed for internal QA requirements, and a pile report
setting out the field observations and final socket design is
properties is not as extensive. The choice of factor of safety can completed, reviewed and sent to the client. ROCKET97 analyses
have a significant effect on the calculated length of the socket. are also carried out on some sockets to verify the field
The extra cost of a comprehensive site investigation is usually calculation procedures.
more than recovered in cost savings arising from reduced
socket lengths. 7. CASE STUDIES
GARSP has been used by Golder Associates in association with
In assessing the values in Fig. 6, the socket lengths assessed Wagstaff Piling on several major construction projects in
from the analysis are increased by 10% to allow for Melbourne. The ground conditions for these buildings have
unexpected ground conditions (e.g. dykes or other softer varied from 30 m of overburden over variably weathered
inclusions). It should be noted that these socket lengths are siltstone, to variably weathered siltstone from the surface, to
only preliminary, and final socket length is assessed in the field sites comprising weathered basalt overlying clays and sands
during socket drilling. overlying siltstone. The following project summaries illustrate
the use of this new system to advantage on some recent piling
The results of the analyses are also used to develop site-specific projects.
rock socket design sheets, which are subsequently used by field
engineers during socket drilling to assess the final length of the 7.1. Melbourne Central
sockets. Melbourne Central is a commercial tower in Melbourne that is
currently undergoing refurbishment. As part of this
refurbishment, additional loads were to be placed on the rock-
6.3. Construction socketed piles supporting the tower structure. An assessment
During construction, an appropriately trained and experienced was carried out to determine whether or not strengthening of
field engineer is on site to observe the pile installation process the foundations was required. On the basis of the information
and to assess final socket lengths. During drilling of the socket, provided, analyses using ROCKET97 indicated that the
the field engineer observes the drill cuttings and drill performance of the pile sockets would be satisfactory under the
penetration rate, and assesses the variation in quality and action of the new loads, and hence the recommendation was
weathering condition of the rock with depth. The rock socket made that no strengthening of the foundations was required.
design sheets are used to assess the variation in shaft resistance
along the socket as the depth of socket increases. This 7.2. Royal Domain Tower
calculation is based on the assessed mobilised displacement Royal Domain Tower is a residential tower development of
along the socket, which depends on the target settlement for about 40 levels currently under construction in Melbourne. The
the top of the socket. The target settlement is calculated by subsurface stratigraphy is variable, and comprises extremely
applying a factor of safety of either 1.5 or 2 (as adopted for the weathered to moderately weathered siltstone (unconfined
project) to the design serviceability requirement. When the compressive strength (UCS) values of about 0.75 MPa) from
depth of the socket is such that the target settlement criterion the surface. Several dykes were encountered during the site
is met, the ultimate capacity of the socket is checked to ensure investigation. The strength of the dykes varied from clay to
that ultimate limit state requirements (with appropriate factors relatively fresh rock, and the occurrence of dykes was difficult
of safety) are also satisfied. Drilling then stops, and socket to predict. The dykes therefore posed a significant risk to
roughening (to obtain minimum roughness levels) and cleaning foundation design. The tower is supported on approximately 85
(to remove smear and residual drilling fluids) are then carried piles, ranging in diameter from 0.75 m to 1.5 m. Serviceability
out. loads ranged between 5 MN and 15 MN, and design pile head
settlement is 1% of diameter. A detailed ground investigation
The presence of a field engineer on site achieves several was carried out, and GARSP was used to establish pile lengths.
purposes. The cost of the additional soil and rock testing was about

214 Geotechnical Engineering 159 Issue GE3 Rock-socketed pile design and construction: a better way? Haberfield Collingwood
A$10 000. The application of GARSP to this project resulted in Because of the limited site investigation and the
reduction in socket lengths of up to 13 m when compared with unconventional programming of the works, it was essential
traditional design approaches. Installed socket lengths varied that pile design could be adjusted on site by the geotechnical
generally between about 5 m and 11 m depending on observed engineer as the piles were drilled. The fixed occupation times
ground conditions and load. Total savings of around 950 m of and the high cost of mobilising piling equipment to poorly
socket length, 900 m3 of concrete, 1400 m3 reduction in spoil accessible locations made GARSP an essential tool on this
and several weeks in construction time were achieved as a project. The design efficiencies and flexibility delivered by this
result of the use of this design approach. approach were an invaluable tool in successful delivery of the
piling works, and provided savings estimated to be in the order
7.3. Melbourne Cricket Ground, Northern Stand of hundreds of thousands of dollars and tens of weeks in
Redevelopment duration.
This project involved design and installation of over 300 load-
bearing foundation and retention piles of 6001800 mm The first project summary set out above illustrates the use of
diameter, up to around 25 m depth. Pile loadings varied recent advances in rock socket pile analysis to preclude the
significantly, with up to 30 MN axial loading, and required need for a costly and difficult foundation upgrade for an
socketing into siltstone bedrock, which was found at depths existing development. The subsequent three project summaries
ranging from ground level to 20 m. illustrate the following key advantages of an efficient and
flexible design approach provided by GARSP
Limited geotechnical investigation could be carried out prior to
the commencement the works because of the presence of an (a) less conservative design outcome than conventional
existing grandstand across much of the site. The existing stand approaches
was progressively demolished, with piling works following (b) cost-effectiveness
close behind. As a result, the piling works became an ongoing (c) time saving
site investigation, with the geotechnical conditions encountered (d) real-time pile design
sometimes differing significantly from those found in the (e) on-site design adjustment.
nearest borehole. Execution of the works was complicated by
the presence of numerous badly decomposed and unpredictable This design approach, coupled with best practice construction
igneous dykes and an ancient riverbed alignment bisecting the practices and management, made a significant contribution to
site. overcoming the challenges faced during these three projects
and ensuring their success.
Preliminary geotechnical design of rock-socketed piles was
carried out based on the available geotechnical data, but all 8. SUMMARY AND CONCLUSIONS
sockets were logged and final design lengths assessed using This paper briefly provides an overview of analysis and design
GARSP. The flexibility of this design approach enabled socket methods for piles socketed into rock. It demonstrates the
design to be adjusted on site, based on the conditions weaknesses in the traditional methods of analysis and design,
encountered, and allowed socket lengths to be optimised and introduces a new design system called GARSP. This new
during the course of drilling. Despite the lack of preliminary system couples state-of-the-art analysis techniques with careful
site investigation, significant cost and time savings were able field observations and logging during construction to provide
to be delivered. significant improvements in pile design, in respect both to
optimisation of socket lengths and to reduction of risk. Four
7.4. Spencer Street Station Redevelopment case histories, where this new technology has been used, are
This project involved the installation of over 250 bored piles of presented. In three of these, the adopted design system
6001500 mm diameter across an extremely large site (around provided significant savings to the client in terms both of
75 000 m2 ) with ground conditions comprising variably material quantities and of construction time. In the first case
weathered basalt rock of unpredictable thickness overlying study, analyses of pre-existing piles using new analysis
around 1015 m of clays and sands, which were in turn techniques provided confidence that the existing building
underlain by siltstone rock. The piled foundations were foundations were able to carry the additional loads due to
required to carry the supports for the elaborate steel-framed refurbishment of the building, and no strengthening of
roof structure, which necessitated a stringent differential foundations was required, again providing considerable savings
settlement criterion. Piles were able to be founded in the basalt to the client.
rock, provided sufficient thickness and quality of rock were
available. In the event that this was not the case, the piles were 9. ACKNOWLEDGEMENTS
founded in the sands at around 20 m depth, or in some cases The authors gratefully acknowledge Foundation QA Pty Ltd for
drilled to siltstone at around 30 m depth. allowing the use of the program ROCKET97.

The construction site is an operational train station, in which REFERENCES


platforms were progressively closed and occupied for fixed 1. JOHNSTON I. W. Rock-socketing down under. Contract
durations for the construction works. Because of the difficulty Journal, 1977, 279, 5053.
of accessing the works areas prior to platform occupations, the 2. WILLIAMS A. F. and PELLS P. J. N. Side resistance rock
geotechnical site investigation was again limited. Occupation sockets in sandstone, mudstone and shale. Canadian
durations varied from months to as little as 12 days, and Geotechnical Journal, 1981, 18, No. 4, 502513.
much of the work was completed on weekends and night shifts. 3. ONEILL M. W. and HASSAN K. M. Drilled shafts: effects of

Geotechnical Engineering 159 Issue GE3 Rock-socketed pile design and construction: a better way? Haberfield Collingwood 215
construction on performance and design criteria. Christchurch, 1992, pp. 157162.
Proceedings of the International Conference on Design and 20. SEIDEL J. P. and HABERFIELD C. M. The axial capacity of pile
Construction of Deep Foundations, Orlando, FL, 1994, pp. sockets in rocks and hard soils. Ground Engineering, 1995,
137187. 28, No. 2, 3838.
4. FREEMAN C. F., KLAJNERMAN D. and PRASAD G. D. Design of 21. BAYCAN S. Improving the Capacity of Bored Piles and
deep socketed caissons into shale bedrock. Canadian Ground Anchors Using Expansive Concretes. PhD thesis,
Geotechnical Journal, 1972, 9, No. 11, 105114. Department of Civil Engineering, Monash University,
5. TOMLINSON M. J. Pile Design and Construction Practice. Australia, 1997.
Viewpoint Publications, Cement and Concrete Association, 22. CHENG F. K. K. A Laboratory Study of the Influence of Wall
London, 1977. Smear and Residual Drilling Fluids on Rock Socketed Pile
6. ROSENBERG P. and JOURNEAUX N. L. Friction and end- Performance. PhD thesis, Department of Civil Engineering,
bearing tests on bedrock for high capacity socket Monash University, Australia, 1997.
design. Canadian Geotechnical Journal, 1976, 13, No. 3, 23. PELLS P. J. N. State of practice for the design of socketed
324333. piles in rock. In Proceedings of the 8th ANZ Conference on
7. THORNE C. P. The allowable loadings of foundations on shale Geomechanics, Hobart, 1999, vol. 1, pp. 307328.
and sandstone in the Sydney region. Part 3: Field test 24. COLLINGWOOD B. The Effect of Construction Practices on the
results. Paper presented to Sydney Group of Australian Performance of Rock Socketed Piles. PhD thesis,
Geomechanics Society, Institution of Engineers of Department of Civil Engineering, Monash University,
Australia, 1977 (unpublished report). Australia, 2000.
8. HORVATH R. G. Field Load Test Data on Concrete-to-Rock 25. PEASE K. A. and KULHAWY F. H. 1984. Behaviour of rock
Bond Strength for Drilled Pier Foundations. University of anchors and sockets. In Proceedings of the 25th US
Toronto, Department of Civil Engineering, 1978, Symposium on Rock Mechanics, Evanston. Society of
Publication 78-07. Mining Engineers of AIME, New York, 1984, pp. 883890.
9. HORVATH R. G. and KENNY T. C. Shaft resistance of rock- 26. CARTER J. P. and OOI L. H. Application of a joint model to
socketed drilled piers. Presented at ASCE Annual concretesandstone interfaces. In Proceedings of the 6th
Convention, Atlanta, GA, 979, Preprint No. 3698. International Conference on Numerical Methods in
10. POULOS H. G. and DAVIS E. H. Pile Foundation Analysis and Geomechanics, Innsbruck. Balkema, Rotterdam, 1988,
Design. John Wiley & Sons, New York, 1980. pp. 889893.
11. WILLIAMS A. F., JOHNSTON I. W. and DONALD I. B. The design 27. HASSAN K. M. Analysis and Design of Drilled Shafts
of socketed piles in weak rock. In Proceedings of the Socketed into Soft Rock. PhD thesis, Department of Civil
International Conference on Structural Foundations on and Environmental Engineering, University of Houston,
Rock, Sydney. Balkema, Rotterdam, 1980, pp. 327347. 1994.
12. PELLS P. J. N., ROWE R. K. and TURNER R. M. An 28. SEIDEL J. P. ROCKET97 Help Manual. Department of Civil
experimental investigation into side shear for socketed Engineering, Monash University, 2000.
piles in sandstone. In Proceedings of the International 29. GILL S. A. 1980. Design and construction of rock caissons.
Conference on Structural Foundations on Rock, Sydney. In Proceedings of the International Conference on
Balkema, Rotterdam, 1980, pp. 291302. Structural Foundations on Rock, Sydney. Balkema,
13. HORVATH R. G., KENNY T. C and KOZICKI P. Methods for Rotterdam, 1980, pp. 241252.
improving the performance of drilled piers in weak rock. 30. WHITAKER T. The Design of Piled Foundations, 2nd edn.
Canadian Geotechnical Journal, 1983, 20, No. 4, 758772. Pergamon Press, Oxford, 1976.
14. ROWE R. K. and ARMITAGE H. H. 1984. The Design of Piles 31. WHITAKER T. and COOKE R. W. An investigation of the shaft
Socketed into Weak Rock. University of Western Ontario, and base resistances of large bored piles in London Clay.
Canada, 1984, Report GEOT-11-84. In Proceedings of the Symposium on Large Bored Piles. ICE,
15. JOHNSTON I. W., LAM T. S. K. and WILLIAMS A. F. Constant London, 1966, pp. 749.
normal stiffness direct shear testing for socketed pile 32. THORNBURN S. 1966. Large diameter piles founded in
design in weak rock. Geotechnique, 1987, 37, No. 1, bedrock. In Proceedings of the Symposium on Large Bored
8389. Piles. ICE, London, 1966, pp. 95103.
16. JOHNSTON I. W. and HABERFIELD C. M. Side resistance of 33. DAY H. B. Rock socketed piles: MMBW Highways Division
piles in weak rock. In Piling: European Practice and practice. In Proceedings of the Symposium on Rock
Worldwide Trends, (SANDS M. (ed.)). Thomas Telford, Socketed Piles. Australian Geomechanics Society, Victoria
London, 1992, pp. 5258. Group, 1974.
17. MCVAY M. C., TOWNSEND F. C. and WILLIAMS R. C. Design of 34. HORVATH R. G. Behaviour of Rock-socketed Drilled Pier
socketed drilled shafts in limestone. Journal of Geotech- Foundations. PhD thesis, University of Toronto, 1982.
nical Engineering, ASCE, 1992, 118, No. 10, 16261637. 35. RANDOLPH M. F. and WROTH C. O. A simple approach to pile
18. KULHAWY F. H. and PHOON K. K. Drilled shaft side resistance design and the evaluation of pile tests. In Behaviour of
in clay soil to rock. Proceedings of the Conference on Deep Foundations (LUNDGREN R. (ed.)). American Society for
Design and Performance of Deep foundations: Piles and Testing and Materials, West Conshohocken, PA, 1978,
Piers in Soil and Soft Rock. ASCE, 1993, Geotechnical ASTM STP 670, pp. 484499.
Special Publication No. 38, pp. 172183. 36. PELLS P. J. N. and TURNER R. M. Elastic solutions for the
19. KODIKARA J. K., JOHNSTON I. W. and HABERFIELD C. M. design and analysis of rock socketed piles. Canadian
Analytical predictions for side resistance of piles in rock. Geotechnical Journal, 1979, 16, No. 4, 481487.
Proceedings of the 6th ANZ Conference on Geomechanics, 37. DONALD I. B., CHIU H. K. and SLOAN S. W. 1980. Theoretical

216 Geotechnical Engineering 159 Issue GE3 Rock-socketed pile design and construction: a better way? Haberfield Collingwood
analyses of rock socketed piles. Proceedings of the based model for rough rock joints. International Journal of
International Conference on Structural Foundations on Rock Mechanics, Mining Science and Geomechanics
Rock, Sydney. Balkema, Rotterdam, 1980, pp. 303316. Abstracts, 1994, 31, No. 4, 279292.
38. POULOS H. G. and DAVIS E. H. Elastic Solutions for Soil and 48. SEIDEL J. P. and HABERFIELD C. M. A theoretical model for
Rock Mechanics. John Wiley & Sons, New York, 1974. rock joints subjected to constant normal stiffness direct
39. OSTERBERG J. O. and GILL S. A. Load transfer mechanism for shear. International Journal of Rock Mechanics and Mining
piers socketed in hard soils or rock. In Proceedings of the Sciences, 2002, 39, No. 5, 539554.
9th Canadian Rock Mechanics Symposium, Montreal. 49. SEIDEL J. P. and HABERFIELD C. M. Laboratory testing of
Department of Energy, Mines and Resources, Mine Branch, concrete-rock joints in constant normal stiffness direct
Quebec, 1973, pp. 235261. shear. Geotechnical Testing Journal, ASTM, 2002, 25,
40. ROWE R. K. and PELLS P. J. N. A theoretical study of pile No. 4, 391404.
rock socket behaviour. In Proceedings of the International 50. HABERFIELD C. M. and SEIDEL J. P. The role of theoretical
Conference on Structural Foundations on Rock, Sydney. models in the analysis and design of rock socketed
Balkema, Rotterdam, 1980, pp. 253264. piles. In Proceedings of the John Booker Memorial
41. CARTER J. P. and KULHAWY F. H. Analysis and Design of Symposium (SMITH D. W. and CARTER J. P. (eds)). Balkema,
Drilled Shaft Foundations Socketed into Rock. Electric Rotterdam, 2000, pp. 465488.
Power Research Institute, Palo Alto, CA, 1987, Report 51. COYLE H. M. and REESE L. C. Load transfer for axially
1493-4. loaded piles in clay. Journal of the Soil Mechanics and
42. LEONG E. C. and RANDOLPH M. F. Modelling of sliding Foundation Engineering Division, ASCE, 1966, 92, No.
behaviour at rock interfaces. In Proceedings of the 7th SM2, 126.
International Conference on Computer Methods and 52. WILLIAMS A. F. and ERVIN M. C. The design and
Advances in Geomechanics, Cairns, Australia. Balkema, performance of cast-in-situ piles in extremely jointed
Rotterdam, 1991, vol. 1, pp. 365369. silurian mudstone. In Proceedings of the 3rd ANZ
43. HEUZE F. E. and BARBOUR T. G. New models for rock joints Conference on Geomechanics, Wellington, New Zealand.
and interfaces. Journal of the Geotechnical Engineering New Zealand Institution of Engineers, Wellington, 1980,
Division, ASCE, 1982, 108, No. 5, 757776. vol. 1, pp. 115121.
44. LIEICHNITZ Q. Mechanical properties of rock joints. 53. SEIDEL J. P., GU X. F. and HABERFIELD C. M. A new factor
International Journal of Rock Mechanics, Mining Science for improved prediction of the resistance of pile shafts in
and Geomechanics Abstracts, 1985, 22, No. 5, 313321. rock. In Proceedings of the 7th ANZ Conference on
45. PLESHA M. E. Constitutive models for rock discontinuities Geomechanics, Adelaide, Australia. Institution of Engineers
with dilatancy and surface degradation. International Australia, Canberra, 1996, pp. 693697.
Journal for Numerical and Analytical Methods in 54. SEIDEL J. P and HABERFIELD C. M. Towards an understanding
Geomechanics, 1987, 11, No. 4, 345362. of joint roughness. International Journal of Rock
46. JOHNSTON I. W. and LAM T. S. K. Shear behaviour of regular Mechanics and Rock Engineering, 1995, 28, No. 2, 6992.
triangular concrete/rock joints: analysis. Journal of the 55. HABERFIELD C. M., BAYCAN S. and SEIDEL J. P. Field testing
Geotechnical Engineering Division, ASCE, 1989, 115, of bored piles in weak rock. In Proceedings of the 6th ANZ
No. 5, 711727. Conference on Geomechanics, Adelaide. Institution of
47. HABERFIELD C. M. and JOHNSTON I. W. A mechanistically Engineers Australia, Canberra, 1996, pp. 885890.

What do you think?


To comment on this paper, please email up to 500 words to the editor at journals@ice.org.uk
Proceedings journals rely entirely on contributions sent in by civil engineers and related professionals, academics and students. Papers
should be 20005000 words long, with adequate illustrations and references. Please visit www.thomastelford.com/journals for author
guidelines and further details.

Geotechnical Engineering 159 Issue GE3 Rock-socketed pile design and construction: a better way? Haberfield Collingwood 217

You might also like