You are on page 1of 24

Resolving Capital

Project Disputes:
Adopting a business
case approach

September 2014

At a glance
Plan for project
disruptions from the
start, and be prepared
to resolve conflicts
before they end up in
arbitration or litigation.

Employ a business case


approach to assess
chances for success,
potential liability,
and pros and cons
of various dispute
resolution approaches.

Know that disputes are


increasingly likely in
emerging markets due
to the growing number
of large, complex
infrastructure projects.
Introduction

At a glance Project disputes are an unfortunate fact of life in


Project owners and contractors most infrastructure developments. But they need not
should plan for disruptions along balloon into major conflicts that result in expensive,
the way and be prepared to resolve
brewing disputes before they time-consuming arbitration or litigation. The key is
spiral out of control and end up to spot disputes in their early stages and be prepared,
in arbitration or litigation.
through advance planning and proper controls and
A business case approach can help
assess the chances for success and the oversight, to resolve them as quickly as possible.
potential liability, as well as estimate
the duration, costs, and other risks of With disruptions and disputes increasingly likely to develop
various dispute resolution options.
on large, complex capital projects in fast-growing emerging
One of the greatest challenges in
disputes is collecting evidence to back markets, it is more important than ever to be prepared to
up claims, so its critical to keep records deal with them as expeditiously as possible. This report
updated and capture information from
project participants throughout the will help guide you through challenging disputes so as to
planning and construction phases. reduce costs, delays, and potential reputation damage.
The mediation or conciliation process
is a less costly, speedier way to We explain how to try to defuse problems before they become
resolve disputes than arbitration or
litigation. But when mediation fails, full-blown disputes and how to assess the situation like a
arbitration is usually more popular
than litigation in transnational
business case to determine the preferred approach should
disputes in the construction industry. informal negotiations fail. We also point out some of the
Disputes are increasingly likely in pitfalls to avoid, such as poor record keeping, and the pros
fast-growing emerging markets
where the number of large, complex
and cons of the various dispute resolution mechanisms.
infrastructure projects is expected
to surge over the next decade and Perhaps the best, most succinct advice comes from one
where there is limited experience
with international business
of PwCs capital projects partners: Resolve claims when
dispute resolution techniques. theyre big enough to see and small enough to solve.

| Resolving Capital Project Disputes: Adopting a business case approach


Planning for problems and defusing disputes

When capital projects veer off course, For instance, they will document the
they need not result in a contentious, cases where an owner is asking them
costly dispute. Ideally, problems are to do something different from what
identified early, communications lines was originally planned, as well as
remain open, and projects get back on any delays they experience in getting
track through informal negotiations. responses to requests for information.
The more effort companies put in at Then they will claim they were
the outset to create proper governance disrupted and the owner owes them
and control processes, the more likely money for delays and increased costs.
projects will remain on course.
Owners can mitigate such risks by
Find out more: But the reality is that even the best- establishing oversight including:
run projects experience disruptions.
Its about psychology to some appointing their own staff
extent, says John Wilkinson, PwC or an independent project
Middle East Regional Deals Leader. adviser to provide oversight;
The parties approach projects on
the basis that everything is going looking out for signs that the
to go well, whereas empirical contractor may be trying to develop
experience would tell you that things a disruption claim that could
are always going to go wrong. evolve later into a major dispute.

and implementing an assurance


Identifying risks early
process including:
Owners shouldnt mistakenly believe
they can avoid disputes because they designating an internal
have written a contract that they contract compliance or audit
Correcting the course of capital
believe shifts all of the risks for cost group or outside advisers
projects. http://www.pwc.com/gx/en/
capital-projects-infrastructure/pdf/ overruns and delays to the contractor. to provide assurance;
pwc-correcting-the-course-of-capital- Contractors will typically try to figure
projects-v3-pdf.pdf out how they can increase their profits making sure that all parties comply
within the constraints of the contract. with their respective obligations;

identifying early potential


challenges and risks and
managing those issues.

By envisaging potential problems


Its about psychology to some extent, says John at the start, you can be more agile
and respond to challenges along the
Wilkinson, PwC Middle East Regional Deals Leader. way, says Colm Tonge, PwC South
The parties approach projects on the basis that Africa Forensic Services Partner.
everything is going to go well, whereas empirical
experience would tell you that things are always
going to go wrong.

PwC | 1
More disputes
expected, especially Construction disputes in the Middle East
in emerging markets After the financial crisis of 2008, the number of disputes in the
Middle East began to rise as developers tried harder to keep project
Looking ahead, PwC expects
costs under control. During the boom times before the crisis,
more disputesand more high-
the focus was more on getting projects completedeven if they
stakes conflictsespecially in
went over budgetand then moving on to the next ones.
developing markets, as more large-
scale projects are built there. Several years ago, people might have been able to say, Well fine, well
take a hit on this one, but well get another project down the line and
Its likely that the number of disputes
make our money back on that one, says Jonathan Roe, PwC Middle
will continue to grow because the
East Capital Projects Director. Theres less willingness to do that now.
infrastructure market is expected
People are keen to settle if they can, but the clients Ive spoken to will
to surge in emerging economies.
only settle in situations where they consider the settlement to be fair.
PwC, in conjunction with Oxford
Economics, has developed a Disputes in the Middle East tend to be more complex than in other
detailed forecast of infrastructure regions partly because the projects often involve a host of contractors
development activity that shows the and sub-contractors. Government officials often seek the lowest
shift from developed countries to price and hire a number of different parties rather than assign
emerging markets, especially in Asia, multiple parts of a project to a contractor or sub-contractor.
accelerating over the next 10 years.
They think theyre saving themselves money by going for the lowest
Disputes tend to be difficult to resolve price, but all theyre doing is making the project more complex and taking
in developing markets because they on more of the risks themselves, says James Hanson, PwC Middle East
have less experience with major Capital Projects Partner. When they go with multiple contractors or sub-
projects and dispute resolution. contractors, theyve got different terms with each of them. Consequently, any
Construction disputes in Asia took the dispute situation will be more complex and potentially more costly, he adds.
longest to resolve in 201314 months
on averagefollowed closely by the
Middle East at 13.9 months, according
to an annual study of disputes by
ARCADIS and its EC Harris built asset
consultancy.1 Asia and the Middle East
also had the highest average dispute
value of any region in the study
US$41.9 million and US$40.9million,
respectively (see Table 1).

Table 1: Construction project dispute values and durations in emerging markets

Region Dispute values (US$ millions) Length of dispute (months)


2010 2011 2012 2013 2010 2011 2012 2013

Middle East 56.3 112.5 65.0 40.9 8.3 9.0 14.6 13.9
Asia 64.5 53.1 39.7 41.9 11.4 12.4 14.3 14.0
US 64.5 10.5 9.0 34.3 11.4 14.4 11.9 13.7
UK 7.5 10.2 27.0 27.9 6.8 8.7 12.9 7.9
Continental Europe 33.3 35.1 25.0 27.5 10.0 11.7 6.0 6.5
Global average 35.1 32.2 31.7 32.1 9.1 10.6 12.8 11.8
Source: ARCADIS Global Construction Disputes 2014: Getting the basics right.

1 ARCADIS, Global Construction Disputes 2014: Getting the basics right.

2 | Resolving Capital Project Disputes: Adopting a business case approach


Realising theres a The owner also didnt let issues
serious dispute accumulate into a big claim but Early warning signs
rather hit every small issue head There are usually early signs
Before owners and contractors can
on as it arose. A project database that a dispute is likely to erupt,
start to deal with a dispute, they have
was established early on to track which should be a signal to
to know theyre in one. While it should
all potential changes, be they early preemptively consult with
be obvious when they reach that
warnings notices, requests for experts and legal advisers.
stage, parties are generally in dispute
information, or compensation issues. Some typical warning signs:
way before they think they are,
In addition, a correspondence database
says Daryl Walcroft, PwC US Capital
helped ensure prompt responses to deadlines are missed,
Projects & Infrastructure Principal.
all communications. Regular project
control meetings were also held to the number of change
Sometimes what starts off as an
review all outstanding issues and orders increases,
informal negotiation gradually
correspondence and clearly state the
becomes more contentious. The tensions develop at the project
project managers decision within
tone of communication changes, site creating an unhappy
the required time to all matters not
going from a spirit of co-operation work environment,
resolved by mutual agreement.
to keep the project moving along
to a more serious discussion of why requests for information are not
Unfortunately, many owners play
its in trouble and whos to blame. answered in a timely manner,
the wait-and-see game, says Tony
Caletka, PwC US Capital Projects &
A project is clearly in dispute when project changes arent
Infrastructure Principal. They say
the owner stops paying the contractor. dealt with promptly,
maybe the job will be finished on time,
Owners experienced in the dispute
maybe the contractor wont claim for relationships between the
process often have a more aggressive
every mistake that the owners design project owner, contractor and
mentality, disallowing some costs and
team made. They play this theoretical sub-contractor become strained,
redlining items they are not going to
game that the claim might go away.
pay on the invoice. They know theyre
The fact is they get bigger, not smaller people start enforcing the
inviting a dispute, but arent afraid
over time. Caletkas advice: Resolve contract to the letter.
of it when they know theyre right.
claims when theyre big enough to
For a UK sports stadium project, the see and small enough to solve.
sports league signed a maximum
guaranteed price contract for
100million and didnt pay a penny
over that. The owner properly
denied payment and even told
the contractor that it should start
adjudication procedures if it felt the
owner was wrong. But the contractor Parties are generally in dispute way
never did because the contract was before they think they are, says Daryl
administered correctly and fairly.
Walcroft, PwC US Capital Projects &
Infrastructure Principal.

PwC | 3
Resolve claims when theyre big enough
to see and small enough to solve,
advises Tony Caletka, PwC US Capital
Projects & Infrastructure Principal.

4 | Resolving Capital Project Disputes: Adopting a business case approach


Find out more: Determining the cause 2. Cumulative impact
of the dispute Typically, the cause of disputes is a
Most disputes arise because projects combination of issues. The project
go well over budget and run far owner may request a number of
behind schedule. Poor estimates changes that add cost and time;
during project planning and missed the contractor may experience
deadlines are the largest contributors several risk events, such as
to project failure, according to Insights flooding or a labour strike; and the
and Trends, PwCs 2012 global survey contractor or sub-contractor may
of project management leaders. have performance problems.
Furthermore, fewer than half (46.5%)
Its very often a huge number of
of survey respondents say that an
relatively minor things which have
effective, formal process is in place to
just built up and built up and divided
manage changes to baseline plans.
the parties quite significantly,
Disputes come out of change, where says Richard Foley, head of the
Insights and Trends: Current Portfolio, people have differences of opinion construction advisory and disputes
Programme, and Project Management about the impact of the change on group at the international law firm
Practices. http://www.pwc.com/en_US/ the project, says Anthony Morgan, Pinsent Masons, who has many years
us/public-sector/assets/pwc-global- of experience with project disputes
PwC UK Capital Projects Dispute
project-management-report-2012.pdf in Western Europe and Asia.
Resolution Leader. There can be
differences in the interpretation of
The dispute gets even more
requirements or just a pure mistake
complicated when its difficult to
around the interpretation.
separate one contributing factor
1. Regional differences from another. For example, the
contractor may attribute performance
The ARCADIS study found that there
deficiencies to a combination
are five main causes, but the causes
of the owners design changes,
of disputes vary by region (see Table
weather and ground conditions.
2). Errors and/or omissions in the
contract proved to be the leading When a Spanish contractor was
cause in the US in 2013, while failure terminated for delays and lack
to make interim awards on extensions of performance on a highway
of time and compensation was the refurbishment project in southern
main issue in Asia. Failure to properly Trinidad, an analysis of competing
administer the contract was the major delaying events was conducted.
reason for disputes in the Middle East. Among the issues in the dispute was
In the UK, the top cause proved to be variation to the stone specifications
employer/contractor/sub-contractor because of an insufficient supply of
failing to understand and/or comply the needed materials on the island.
with contractual obligations, and in The expert report separated out
continental Europe, the chief cause competing delaying events and took
was differing site conditions. into account the effects of seasonal
weather and related production,
among other things. Ultimately, the
dispute was resolved by negotiation.

PwC | 5
Table 2: Most common dispute causes by region
2013 Rank Cause 2012 Rank

USA
1 Errors and/or omissions in the contract document 2
2 Failure to make interim awards on extensions of time and compensation 5
3 Differing site conditions 4
4 Incomplete design information or employer requirements (for D&B/D&C)
5 Failure to properly administer the contract

Asia
1 Failure to make interim awards on extensions of time and compensation 2
2 Failure to properly administer the contract 5
3 A biased project manager or engineer
4 An unrealistic contract completion date being defined at tender stage
5 Employer imposed change

Middle East
1 Failure to properly administer the contract 1
2 Employer imposed change 3
3 Employer/contractor/sub-contractor failing to understand and/or comply with its contractual
obligations
4 Errors and/or omissions in the contract document
5 An unrealistic contract completion date being defined at tender stage

UK
1 Employer/contractor/sub-contractor failing to understand and/or comply with its contractual 1
obligations
2 Failure to properly administer the contract 3
3 Incomplete design information or employer requirements (for D&B/D&C)
4 Poorly drafted or incomplete and unsubstantiated claims
5 Employer imposed change

Continental Europe
1 Differing site conditions
2 Third party or Force Majeure events 5
3 Employer/contractor/sub-contractor failing to understand and/or comply with its contractual 1
obligations
4 Employer imposed change
5 Failure to properly administer the contract
Source: ARCADIS Global Construction Disputes 2014: Getting the basics right.

6 | Resolving Capital Project Disputes: Adopting a business case approach


Find out more: Megaprojects and multiple stakeholders
Most disputes involve project owners, contractors, and sub-contractors,
but megaprojects could potentially include a wider variety of
stakeholders. Airports exemplify such vulnerability. Airports are
very complex structures. Unlike other infrastructure, you have a huge
number of operational stakeholders, says Michael Burns, PwC UK
Airports Advisory Leader. So that gives you a much more difficult
stakeholder environment in the case of delay or failure in a project.

When an airport expands, it affects the operations and revenues of the


airlines flying into that facility, operators of the parking lots and garages,
retail shops in the terminals, nearby hotels and train lines to the airport.

For example, the new airport in Berlin, Germany, has faced many
construction problems that have forced it to postpone its opening several
times. The delays have had major financial repercussions for such companies
When airport projects fly off course. as Air Berlin, which intends to make the airport a major hub operation. Air
http://www.pwc.com/en_GX/gx/capital- Berlin sued the airport operator, seeking compensation for the financial
projects-infrastructure/pdf/the_new_ damage caused by the repeated delays in opening the new facility.2
normal_for_airport_investment_-_02_
when_airport_projects_fly_off_course. If an airport is delayed, every airline will be in a position to sue, Burns adds.
pdf

3. Political pressures Sometimes one wonders whether


Projects can also end up in dispute the original timeframes for many
because the publicly announced projects were realistic or whether
completion date was arbitrary due to it was politically expedient to make
political pressure to meet an unrealistic promises of delivery within fairly
timeframe. A government official, for short timeframes, knowing that three
example, may promise his constituency or four years later they were going
a project on a certain date without to have to face the music about the
the necessary planning and scoping of project coming in at twice the budget
the project. In some cases, there may and twice as long a timeframe,
be urgency to reassure the electorate says Jonathan Cawood, PwC South
that the government has everything Africa Capital Projects Leader. Weve
under control and will quickly seen that on a few projects in Africa,
resolve, say, a power or water crisis. and we think maybe everybody
actually knew that upfront.

2 Deutsche Welle, Trial starts over Air Berlin damage claim against delayed BER
airport, http://www.dw.de/trial-starts-over-air-berlin-damage-claim-against-
delayed-ber-airport/a-17362076, accessed August 29, 2014.

PwC | 7
Disputes and emerging company, says Michael Burns,
economies PwC UK Airport Advisory Leader.
Consequently, its advisable for
With infrastructure and other
contractors to set expectations that
construction projects being
there will be change and put strong
built increasingly in emerging
communication mechanisms in place.
economies, its important to be
aware of differences that could Disputes are often more complicated
come into play in a dispute. if the local government owns the
project. In Africa, for example, some
Going in, contractors need to
Disputes are understand the political and regulatory
governments dont have the same
understanding of risk transfer or the
increasingly likely environment and choose local
private sectors level of control as
to flare up in fast- partners well. Finding a partner with
international investors do. That may
good in-country relationships with
growing emerging major clients is a good step to take,
give rise to misunderstanding and
frustration when projects go over
markets where says Charles Lloyd, PwC UK Capital
budget and get behind schedule. In
Projects Finance Partner. Youre
the number of more likely to reach resolution if
such countries as China and Vietnam,
large, complex its an Iraqi-to-Iraqi discussion or a
large cost overruns on government
projects simply arent discussed
infrastructure Qatari-to-Qatari discussion than if its
because of bureaucratic obstacles.
a foreign contractor negotiating.
projects is expected
If theres a change in elected
to surge over the next Cultural differences often come
government officials, that can add
into play in the dispute process.
decade, according to Construction dispute experts find that
further complications because a
project spans two administrations.
PwC analysis. in some Asian and Middle Eastern
Theres lack of continuity; the
countries, there is reluctance to
people who made the original
be confrontational and challenge
decisions are no longer accountable.
others, especially the project owner.
Find out more: Such political change can lead to
questioning and cancelling contracts,
Theres a need to suppress the
potentially provoking disputes.
bad news so you dont put egg
on peoples faces, says Mark
Government involvement can also
Rathbone, PwC Asia-Pacific Capital
create political dynamics that affect the
Projects Leader. The problems
dispute resolution process. Challenging
build until there are significant cost
the government could endanger
overruns and delays that, if not
visa renewals and participation in
resolved amicably in private, can
future projects in that country.
become a messy, public dispute.
Another risk in emerging economies
Project changes may not be viewed
is the potential for bribery and
as a normal part of the construction
corruption. For example, there could
process in some inexperienced,
be fraud in the certification of steel
emerging markets. As a result,
that wasnt completed to the proper
Capital project and infrastructure they may not build change control
standard, resulting in delays while
spending. http://www.pwc.com/gx/ procedures into contracts, leading to
en/capital-projects-infrastructure/ the work is redone with the proper
disputes that cant be resolved easily.
publications/cpi-outlook/index.jhtml materials. Bribery, corruption, and
political connections can also result in
There also seems to be less acceptance
people being appointed to jobs theyre
that there will be change in the project.
not ready to do, Colm Tonge, South
Then, when change is required,
Africa Forensic Services Partner says.
their expectation is thats part of
Then that becomes very expensive
the obligation of the construction
if it leads to delays down the track.

8 | Resolving Capital Project Disputes: Adopting a business case approach


Assessing disputes like a business case

Disputes often end up in arbitration The bottom line question to ask:


or litigation simply because neither What is the most desirable outcome
side is willing to admit it was at fault. of this dispute? Is it about resolving
Personalities and emotions may the dispute quickly to keep the
take over, making communication project moving forward and costs
strained and less productive. down? Or is it because one has a solid
case and chooses to fight no matter
how long or how much it takes?

The bottom line question to ask: What is the Considering the full
most desirable outcome of this dispute? Is it monetary picture
about resolving the dispute quickly or fighting
An important consideration before
no matter how long it takes? going into a long dispute resolution
process isnt only the potential
settlement amount, but also the
To take emotion and personal monetary interest that might
relationships out of the mix, owners accumulate. A good example of that
and contractors should consider issue was a project to build a womens
doing a business case analysis on the and childrens hospital in the U.S.
costs and benefits of an expeditious The contractor claimed millions in
resolution versus more protracted extra costs because it argued that
arbitration or litigation. They need to the owner and construction manager
take a rigorous, disciplined approach delayed it from carrying out its work.
to assess the chances for success and The owner disagreed and blamed
the potential liability, and to estimate the contractor for the late opening.
the duration, costs and other risks of
various dispute resolution approaches. The dispute went into litigation and
dragged on for years. Ultimately,
The elements of risk will vary from the contractor prevailed, with the
dispute to dispute, depending on judge awarding delay damages for
the nature and scale of the project, the entire 87 weeks in the claim
the contract, the specific problems and all of the 41,000 claimed hours
and the strength of the legal team. for disruption. The contractor did
And there are different cost and even better than expected because
risk profiles for various forms the owner not only had to pay the
of dispute resolution, whether settlement, but interest on it as well.
mediation, arbitration, or litigation.
So, there are angles to these claims
that I dont think people recognise,
says Caletka, who was retained by
the contractor in the hospital case
to provide his scheduling expertise.
The interest on settlements is one of
the factors that goes into the strategy
for how you pursue and settle and
which court you take the claim to.

PwC | 9
Protecting business Conducting a business
reputation case analysis
The value of business reputation Often, it takes an outside advisor,
and relationships will also affect whether an expert witness, consultant,
a partys willingness to resolve or lawyer, to be the voice of reason
disputes quickly and amicably rather and encourage a business case
than take an aggressive approach. analysis early in the dispute process.
For example, contractors are often The analysis can be done relatively
concerned about their reputation, quicklyoften in a month or so.
both in the marketplace and with The result is a much clearer view
the owner involved in the dispute. of the preferred way to proceed
rather than an impulsive reaction
Some companies say we have a to jump into expensive and time-
reputation we have to uphold and if consuming arbitration or litigation.
anyone tries to mess with us, were
going to litigate every time and we will For example, the owner and operator
never give up, says Erik Skramstad, of a sports stadium in the UK retained
PwC US Forensic Services Leader. PwC in 2006 to do a detailed analysis
Other clients say, No, no, we dont when the Australian contractor made
want to litigate. Lets just resolve this a claim for additional compensation
in a good manner. We want to have because it blamed project delays
a reputation as being reasonable. on design changes by the owner.

WNSL received claims for individual


changes, as well as a significant claim
for misrepresentation. PwC carried
out an as built delay analysis,
assessing its clients liability for more
than 80 changes and reviewing the
The value of business reputation and impact of such factors as delays to
relationships will affect a partys the structural steelwork. The analysis
willingness to resolve disputes helped WNSL reach a negotiated
settlement with the developer. The
quickly and amicably rather than stadium was finally completed in 2007.
take an aggressive approach.
Similar past cases that lawyers or
consultants have handled can provide
guidance in the business case analysis.
But its always hard to know just how
difficult the opposing party will be in
terms of dragging out the resolution
process and driving up the costs.

10 | Resolving Capital Project Disputes: Adopting a business case approach


Using quantitative 70% of a claim, and a contractor with A third-party adviser can sometimes
risk analysis an appetite for risk might decide to even help the client avoid arbitration
litigate. But it might settle if an offer or litigation. When a new airport was
The owner or contractor can also
is on the table for 50% of the claim. being built in China, for example,
perform a quantitative risk analysis
it turned out that the specifications
to assess dispute claims and the Getting a rational for the terminals roof tiles were
potential costs involved in different
assessment from extremely tight, causing problems
resolution scenarios. The cost of
independent advisers with the construction tolerances and
litigation, experts, lawyers, internal
requiring reworking. That resulted in
resources and business interruption A third-party independent assessment
a disruption claim against the owner
would be factored in, as well as of ones position can be quite valuable
in which the contractor retained
intangibles such as reputation damage. because it focuses on the facts of the
an adviser to conduct an extensive
case to make a rational assessment of
analysis to quantify the impact of the
To assess the likelihood of winning the causes of delays and cost overruns.
tight tolerance on productivity and
and by what order of magnitude, a Independent advisers can help their
costs and presented those findings to a
quantitative risk model would take into clients deal with such recurring issues
mediator for settlement of the claim.
account the contractual agreement in disputes as proving linkage between
and which side has the better cause and effect and determining
documentation and strongest legal whether there were concurrent causes
arguments for each claim. For example, of delay that both the employer and
there might be a 50% chance of getting contractor were responsible for.

PwC | 11
When contractor claims go unchallenged
Because they have so much project experience, many contractors realise
that disputes are simply part of the project life cycle and are often better
at documentation than owners. They may leave a document trail for
lawyers and consultants to use in a dispute and swing an arbitration
panel in their favour. For example, in a monthly report, a contractor
might document an event that occurred and blame the owner. If the
owner fails to challenge that contention in a letter, the contractors
claim may be accepted at face value. Owners are sometimes nave
because they havent experienced many projects and disputes.

Keeping good
documentation to
support claims
Information is power when it comes
to disputes, which is why meticulous
and extensive record keeping is so
important. A complete document
trail is needed to demonstrate why
certain actions were taken. It can
mean the difference between winning
and losing. Theres only so much
you can do when youve got bad
documentation, Lechner says. You
can be right and you can still lose.

Throughout the planning and the


construction process, owners and
contractors should keep records up
to date and capture information from
people working on the project
especially since most people leave
projects and may not be available
if and when a dispute arises later.

When an international engineering


contractor ran four months late
in completing the retrofitting of a
gas compression facility on a live
North Sea gas platform, it made a
claim to cover its additional costs.
Fortunately, information could be
retrieved from archival materials
and hundreds of time sheets were
entered into a database to analyse
productivity and inefficiency, thus
helping the parties resolve the
dispute through negotiation.

12 | Resolving Capital Project Disputes: Adopting a business case approach


Its important not only to keep Perhaps surprisingly, previous
records of delays but also to note the documentation lapses can resurface Email as evidence?
causes and impact in the document and affect a current dispute. On a These days, emails often pose a
trail. That will help prove linkage campus-style office building project, major problem because they arent
of cause and effect. Owners and for example, the owner was pressured organised and classified properly.
contractors also need to understand to settle because of a damning internal You may have long email chains
how accurate the data are. audit document from the past that and the title may not relate to
the opposing party found. The audit the project, so now youve got
Often, project schedules are designed report was highly critical of the to search your systems to see
to show the dates people want to owners project management team when people were talking to each
see rather than a realistic timeline. and lack of controls over document other, and often thats the biggest
That means they cant be relied on flows and responses to requests for challengeto put that factual
from an evidentiary perspective. In information. Even though the owner history together, says Colin
such cases, outside experts have to corrected all of the issues, no one ever Tonge, PwC South Africa Forensic
build a schedule that reflects what closed out the documentation trail Services Partner. That issue may
actually happened from other data with a record of the corrections. be exacerbated when people leave
sources, such as project reports and the project along the way. Its
progress data, and interviews with You have to make sure that your a normal corporate practice to
the people involved in the project. documentation is clear, and when back up somebodys email and
you identify issues, they have to be directories, but its not necessarily
At a time when big projects can closed out, Lechner says. You need a a practice to ensure that all
generate such a massive trove of document showing that you proactively project-related correspondence is
documents, digital technology addressed the issues. Otherwise, filed to the project, says Tonge.
is helping with record retention youre risking documentation So if you have a time lapse of
and document management. For that will adversely affect you in a two or three years between the
example, software can enable people dispute even though it may not have person going and realising that
to categorise documents and group a lot of relevance or accuracy. you need everything theyve got
them into potential claim issue
to demonstrate what happened
files, making for faster recovery
at a point in time, thats where a
in case a dispute develops.
lot of organisations fall down.

Theres only so much you can do when youve got


bad documentation, says Steve Lechner, PwC US
Capital Projects & Infrastructure Principal.
You can be right and you can still lose.

PwC | 13
Engaging in the dispute resolution process

Starting the dispute


resolution process Bring in the CEOs law firm Pinsent Masons, and an
Once the business case analysis is opposing counsel brought the two
In some cases, involving to
complete, dispute resolution planning CEOs involved together, and each
the CEOs of the companies in
begins. The parties will want to lawyer presented a summary of his
dispute can raise the discussion
assemble a team of lawyers and arguments. We had essentially
to a more productive level. The
experts. Select teams based on the treated the CEOs like they were
project teams closely involved
experiences of the individuals and the tribunal, Foley says. They
in the day-to-day construction
not the reputation of the companies had been contracting together for
may have clashed, and their
they work for. After all, people, decades, and the last thing they
feelings toward one another could
not companies, deliver results. wanted was to get into any formal
complicate the resolution process.
dispute. We got a deal that both
In a dispute over an energy CEOs were comfortable with, and
project, Richard Foley, head of theyre still contracting on other
the construction advisory and projects around the world.
disputes group at international

CEOs and high level executives are main decision makers of litigation
In your organisation,
and arbitration proceedings who makes the ultimate decision
whether to initiate ligitation or arbitration proceedings?

Other General Counsel/


15% Head of Legal
25%

6% Corporate Counsel
in charge of matter

54%

Board of Directors/
Senior Executive/
CEO

Source: PwC and Queen Mary University of London


2013 International Arbitration Survey

14 | Resolving Capital Project Disputes: Adopting a business case approach


Weighing dispute 1. Mediation and conciliation Proponents of mediation or
resolution options Its frequently specified in contracts conciliation point out that the
that mediation be tried before going to process is less costly and usually
Owners and contractors need to
arbitration. In the conciliation form of much speedier than arbitration or
consider the pros and cons of the
mediation, the mediator or conciliator litigation. Moreover, mediation is
various dispute resolution processes
makes recommendations regarding the often less confrontational and helps
in light of their particular case and
outcome of the process. Conciliation maintain business relationships.
the jurisdiction in which it would
can be more effective than other types The potential downside is that time
be arbitrated or litigated. Would
of mediation in bringing the case to and money are lost if mediation
the dispute be handled where
a close because of the opinion that is fails and the dispute must move
the project is being built or in the
issued, Caletka says. The weight of into arbitration or litigation.
contractors home country? That
will help determine the preferred the conciliator is heavy because its
Foley and his firm recommend to
dispute resolution mechanism. usually a retired judge or respected
clients that they include a tiered
arbitrator. That person is basically
resolution provision in their contracts.
On one end of the spectrum is saying that if he were the arbitrator or
The first step might be a 30-day
informal negotiation that leads to a judge, this is what he would decide.
period where senior management
settlement. Thats the most preferred
Other mediation approaches can must try to resolve the dispute. If
and most common course of action
simply be a testing ground in that fails, I would always advocate
because the parties keep control of
which the parties just want to know trying mediation or conciliation before
the process and its usually the least
how solid the other sides case defaulting to arbitration, Foley says.
expensive and fastest approach.
might be. You have to approach
At the other end of the spectrum is that kind of mediation with some
litigation that leads to a binding scepticism, adds Caletka.
decision. But if the parties spend
a lot of time and money on legal
processes, experts and so forth,
then their expectations rise
and they set out to recover the London calling
maximum amount possible. London has emerged as one of the most popular venues for international
clients to bring their disputes for a variety of reasons, including cost
In between are mediation or
issues, English law, and the availability of infrastructure expertise.
conciliation, dispute review or dispute
adjudication boards, and arbitration. Costs tend to be lower in the UK than in other parts of Europe, and
unlike in some jurisdictions, the successful party will normally recover
its costs, Walker says. Furthermore, he adds, English law respects
the parties freedom of contract, and the doctrine of precedent means
English law usually provides predictable outcomes. London also
offers parties a wide choice of experienced arbitrators, advocates,
translators and expert witnesses to help resolve disputes efficiently.

PwC | 15
I think its a pity that the dispute review boards
and their like are not used more often, says Richard
Foley, head of the construction advisory and disputes
group at Pinsent Masons, an international law firm.
Theyre kind of keeping parties honest, but also
enabling matters to be resolved as they come up.

2. Dispute review and dispute Foley believes more owners and


adjudication boards contractors should use dispute review
Some projects use dispute review boards or dispute adjudication
boards, which include three members boards as soon as a problem surfaces.
who evaluate disputes as they arise and I think its a pity that the dispute
make settlement recommendations review boards and their like are
that are not binding. There are also not used more often, he says.
dispute adjudication boards, which Theyre kind of keeping parties
deal with disputes as they come up honest, but also enabling matters
and make decisions that are binding to be resolved as they come up.
unless one of the parties issues a notice
The boards arent used more often
of dissatisfaction. If a notice is issued,
partly because theyre seen as
the parties are expected to try to reach
adversarialdrawing up battle
an amicable settlement, and if that
lines, as Foley puts it. Whereas
fails, the dispute moves to arbitration.
it should be seen as a sensible
Another option in the UK is HGCRA proactive step to try to resolve what
statutory adjudication, which aims is a genuine disagreement while its
to settle disputes over monetary all fresh in everybodys minds, he
issues in construction projects in a says. Then, we can all move ahead
relatively short amount of time. on the basis of some certainty.

16 | Resolving Capital Project Disputes: Adopting a business case approach


Rank the following perceived benefits of arbitration in order of importance for disputes
in your
Chartindustry sector perceived benefits of arbitration
1: Most important

%
Expertise of
19 28 10 6
decision maker

Neutrality 28 15 3 7

Confidentiality 21 16 10 13

Enforceability 20 15 17 11

Flexibility of
13 13 9 10
procedure

Speed 6 15 23 14

Cost 2 24 35

1 (Most important) 2 3 4 5 6 7 (Least important)

Source: PwC and Queen Mary University of London 2013 International Arbitration Survey

3. Arbitration Arbitration is a more expensive and Find out more:


In arbitration, disputes are normally longer process than mediation. In fact,
heard and decided by a three-person arbitration may even last longer and
panel. Each of the opposing parties be more expensive than litigation. In
chooses one arbitrator, and those litigation, the parties dont pay the
two arbitrators select an independent judge or jury for their hours on the
third member of the panel to provide case. But in arbitration, they must pay
some neutrality in the case. the arbitration panel for their time and
expenses, as well as their own lawyers,
As Chart 1 shows, the benefits of experts and others. In addition,
arbitration include the ability to choose judges dont typically let court cases Corporate choices in International
the arbitrators rather than be assigned stretch on and on, whereas arbitration Arbitration: http://www.pwc.com/gx/
to a judge in a court case; the ability may continue for several years. en/arbitration-dispute-resolution/
to set ones own timetable and rules; index.jhtml
and the privacy it affords, compared But arbitration is nonetheless
with a public litigation process. In a popular choice over litigation
fact, maintaining confidentiality is for transnational disputes in the
perhaps the biggest attraction of construction industry, according to
arbitration for many companies. the 2013 International Arbitration
Survey, which was conducted by the
School of International Arbitration
at Queen Mary University of
London and sponsored by PwC.

PwC | 17
If a dispute ends up in arbitration, project owners or contractors need to
put their money and management time fully behind the case. Its risky to
start off half-heartedly in the expectation that the other party will settle.

Rank the following dispute resolution mechanisms in Rank the following dispute resolution mechanisms in
order of preference order of preference for your industry sector
Chart 2: Companies preferred dispute resolution mechanisms

Overall results % Energy %

Arbitration 52 29 13 6 Arbitration 56 28 16

Court litigation 28 28 22 22 Court litigation 22 33 28 17

Adjudication/Expert 5 21 Adjudication/Expert
33 41 17 24 35 24
determination determination

Mediation 18 20 31 31 Mediation 5 11 16 68

1 (Most preferred) Financial Services %


2
3 Arbitration 23 38 31 8
4 (Least preferred)

Source: PwC and Queen Mary University of London


Court litigation 82 9 9
2013 International Arbitration Survey
Adjudication/Expert
20 7 20 53
determination

Mediation 9 36 37 18

Construction %

Arbitration 68 21 11

Court litigation 11 26 26 37

Adjudication/Expert
44 28 28
determination

Mediation 22 11 45 22

1 (Most preferred)
2
3
4 (Least preferred)

Source: PwC and Queen Mary University of London


2013 International Arbitration Survey

18 | Resolving Capital Project Disputes: Adopting a business case approach


In deciding whether or not to initiate arbitration proceedings rank the following in order
Chartof
3: significance
Most important factors in deciding whether or not to initiate arbitration proceedings

%
Strength of legal
40 26 7 2
position and arguments

Strength of evidence 15 36 10 8

Likely recoverable
18 15 12 4
damages
Ease of enforcement of
award/solvency 15 9 24 15
of respondents
Likely legal costs 9 12 23 24
Gaining an advantage
in subsequent settlement 8 5 22 46
negotiations with the
other side (terminating
the proceedings being 1 (Most important) 2 3 4 5 6 7 (Least important)
used as a bargaining chip)

Source: PwC and Queen Mary University of London 2013 International Arbitration Survey

About two-thirds (68%) of respondents To prevail in arbitration, Foley


in the construction industry listed also recommends identifying the The New York
arbitration as their preferred dispute pinch points in the arbitration Convention on the
resolution mechanism, compared process when youre most likely Recognition and
with 56% in the energy industry and to get a deal and working to get Enforcement of
23% in financial services. Courtroom yourself into the best possible Arbitral Awards
litigation was preferred by 82% position at each of those points.
Arbitrations popularity can also be
of financial services respondents.
The most important pinch points attributed to the growing number
(The other choices in the survey
usually present themselves: of countries149 as of 2013
were mediation and adjudication/
that have agreed to the New York
expert determination. See Chart 2).
at the very beginning when the Convention for recognising and
When asked which factors are notice of arbitration is served enforcing foreign arbitration
most important in deciding to and gets everyones attention; awards. The Convention on the
pursue arbitration, respondents Recognition and Enforcement
across all three industries cited after both parties have made of Foreign Arbitral Awards was
strength of their companys legal their first round of pleadings adopted in New York in 1958
position and arguments as most and each side can better assess and signed by 10 countries at the
important, followed by strength of the risks of going forward; time. In my view, the principal
the evidence and the value of likely reason why contracting parties
after the evidentiary process which from different nation states choose
recoverable damages (see Chart 3).
shows how costly the arbitration arbitration is that an arbitration
is getting and how strong the award offers better prospects of
evidence on both sides is; enforcement than the judgment
of a national court would because
a week before the scheduled start of so many countries have adopted
hearings and cross examinations. the New York Convention in
their domestic law, says Steven
Walker QC, a senior barrister at
Atkin Chambers in London.

PwC | 19
If a dispute goes to arbitration, its Thats what a developer and a Arbitration in
important to set a specific monetary construction company in the UAE emerging markets
target and develop a clear strategy decided last year. They announced
Legal experts usually recommend
that addresses the key issues plans to hold amicable discussions
arbitration over litigation in
necessary to succeed. Project owners to try to resolve a long-running
emerging markets where there is less
or contractors also need to put their multibillion-dirham dispute over
experience with disputes and fewer
money and management time fully construction of leisure facilities
legal precedents, creating even more
behind the case. Its risky to start off in Dubai. Both parties agreed
than the usual uncertainty. There
half-heartedly in the expectation to withdraw their case from the
could also be a lack of impartiality
that the other party will settle. Dubai International Arbitration
with a local court, but even when
Centre after realizing there wasnt
However, some companies do return that isnt a concern, its unlikely
sufficient progress in the dispute
to negotiations when arbitration drags in a less developed market that a
after several years of arbitration.
on too long without a resolution. judge with expertise in construction
So, despite the popularity of disputes will preside over the case.
arbitration, in many situations, When youre in arbitration, you
settlement is preferable to arbitration are picking specialists who have
when the terms of settlement are fair dealt with these sorts of projects
and acceptable to the disputing parties. and issues many, many times,
Foley says. And youre getting
the benefit of that experience.

Taking legal action can also raise


questions about which nations
laws apply if the contractors,
operators, or financing entities
Legal experts usually recommend are based outside the country
where the project is being built.
arbitration over litigation in
emerging markets where there is less The legal system in some regions
experience with disputes and fewer isnt conducive to some types of
dispute resolution. For example,
legal precedents, creating even more its difficult to enforce arbitration
than the usual uncertainty. awards in Africa. The tendency in
Africa is to refer arbitration to such
cities as Zurich, Paris, or London.
South Africa probably has the
required professional skills and
machinery to resolve disputes,
but it doesnt have a user-friendly
legal system to enforce arbitration
awards, Tonge says. Should a US
company get into difficulty in Malawi
with the government over a project,
for instance, South Africa would be
a logical place to come if the legal
system was more supportive of
international arbitration awards.

20 | Resolving Capital Project Disputes: Adopting a business case approach


Conclusion

While the goal of any project As more major projects are being
owner or contractor should be to built in emerging economies, owners
resolve small problems before they and contractors should also consider
mushroom into major disputes, the cultural differences that will affect how
parties also need to be realistic and problems are handled, as well as the
enter into contracts fully aware that legal environment for settling disputes.
disputes are an unfortunate but
inevitable fact of capital project life. But whatever the location, project
owners and contractors can make
When disputes do develop, owners and dispute resolution part of the planning
contractors should take a business case process upfront and establish the
approach to assess their positions and proper controls and oversight to
determine the preferred approach to manage and document issues as they
resolving the conflict. A quantitative occur. Not only will that reduce the
risk analysis can be a valuable way to chances of a major dispute developing,
assess the best resolution strategies. but it also will help them prevail should
Of course, much will depend on they end up in arbitration or litigation.
the quality of documentation.

Its also helpful to involve people in the


resolution process who arent closely
involved in the day-to-day project
work and have less of an emotional
stake in the outcome. They also bring
a fresh view of the challenges and
the uncertainties to be managed.

PwC | 21
www.pwc.com/capitalprojectsandinfrastructure

For a deeper discussion about Capital Project Disputes, contact:

Global Europe Additional contributors


to this publication
Richard Abadie UK
Global Leader Capital Projects & Neil Broadhead Michael Burns
Infrastructure (CP&I) UK & EMEA CP&I Leader Global Airports Advisory Leader
t: +44(0) 20 7213 3225 t: +44 (20) 780 45814
e: richard.abadie@uk.pwc.com James Hanson
e: neil.broadhead@uk.pwc.com
Middle East Capital
Americas Czech Republic Projects Team Partner
US Sirshar Qureshi
CEE CP&I Leader Stephen Lechner
Peter Raymond
t: (420) 251 151 235 US CP&I, Partner
US and Americas CP&I Leader
t: +1 703 918 1580 e: sirshar.qureshi@cz.pwc.com
Charles Lloyd
e: peter.d.raymond@us.pwc.com
Middle East UK Capital Project Finance, Partner
Africa Steve Anderson Jonathan Roe
Jonathan Cawood Middle East CP&I Leader Middle East Capital Projects, Director
Africa CP&I Leader t: +974 4419 2850
t: +27 11 797 5049 e: stephen.j.anderson@us.pwc.com Erik Skramstad
e: jonathan.w.cawood@za.pwc.com US Forensic Services Leader

Asia Capital project dispute Colm Tonge


Singapore resolution leaders South Africa Forensic Services, Partner
Mark Rathbone UK Daryl Walcroft
Asia Pacific CP&I Leader Anthony Morgan US CP&I, Principal
t: +65 6236 4190 t: +44(0) 20 7213 4178
e: mark.rathbone@sg.pwc.com e: anthony.j.morgan@uk.pwc.com John Wilkinson
Middle East Regional Deals Leader
US
Anthony Caletka
t: +1 713 356 587
e: anthony.caletka@us.pwc.com

2014 PwC. All rights reserved. PwC refers to the PwC network and/or one or more of its member firms, each of which is a separate legal entity. Please see http://
www.pwc.com/structure for further details. This content is for general information purposes only, and should not be used as a substitute for consultation with
professional advisors.
MW-15-0018 JP

You might also like