1) The minimum water content at which soil is still in liquid state
2) In pert the optimistic time is
3) Dengue weather is best controlled in which whether
4) Discharge is 80,000 cusecs and area is 1000 acres then duty will be
5) Odour of water is removed by
6) Free board is actually
7) Gantt charts are used for
8) Meandering depends on
9) Relation between G, S and e is
10) To check the strength of sub grade
11) Formula of uniformity coefficient
12) Flexible pavements are designed by
13) The maximum water content at which no reduction in volume
14) Irrigation used to lift water by gravity
15) Irrigation used in Pakistan
16) The main purpose of irrigation in Pakistan is to
17) Water courses emerge from
18) The purpose of side slope in embankment is to
19) Time consumed by activity in cpm is called
20) Marshall test method is used for
21) The purpose of grader in road construction
22) ECP in Project management is used for
23) If 28 days required concrete strength is 100 MPA then its strength after 7 d
ays will be
24) Minimum strength for Prestressed concrete is
25) BOD stands for
26) Slump Test is used to measure
27) The consumptive use of irrigation is calculated by
28) Best formula used for the design of lined canals is
29) True meridian is actually
30) Error in leveling may be due to
31) Losses in water supply are usually
32) Most expensive part during water supply is
33) Yield capacity of well increases with
34) Ratio between long chord of curve to tangent length
35) Four wheel drive is actually
36) The formula which also gives relation about hydraulic radius
37) Bore hole diameter is .the diameter of well
38) N value in SPT gives information about
39) In flexible pavement load is transferred ultimately to
40) Minimum cover for steel against corrosion
41) A rectangular channel is said to be wide if
42) Self cleansing velocity is maintained in sewer by
43) The roller used for A-6 soil is
44) How can we increase workability of concrete without using moisture content
45) A channel which neither silts nor scours is in
46) The best soil to be used for sub grade is
47) During concrete production in hot weather more than 33 C what will we do
48) Coefficient of creep length
49) Inverted filter should be how many times to that of depth of sheet pile ..
50) If there is hydraulic jump then we will check for its
51) Shrouding material normally used is
52) Deck slab, girder and pier are the part of
53) Mangla and Tarbela are
54) Concrete gravity dam is
55) The irrigation system of Pakistan was established in
56) Concrete to be transferred under water level
57) A soil which has equal porosity in all directions is
58) The foundation to be used in water when there is pressure from soil debris,
flowing water
59) Lacey silt factor to be used in Upar Bari Doab
60) A well has 30% porosity then its yield will be
61) The sewer which transferred sewage to ultimate disposal point or for treatme
nt is
62) The curve used to change from straight to circular curve is
63) Irrigated water should have PH between
64) If the canal is above the natural drainage then cross drainage structure pro
vided is
65) Effective span of simply supported beam is actually
66) Soil passing will be coarse if the passing and retained respectively is
67) Ratio of lateral strain to linear strain is
68) Inundation canals can be converted to perennial canal by
69) A motorway is
70) To minimize absorption losses canal should irrigate on
71) An eccentric load will induce ..
72) Cement used when there is enormous heat of hydration .
73) If wetted perimeter is large, more will be
74) Isohyets are
75) The yield of well will be decreased if
76) Yield of well increase with
77) The presence of which make the sulphate attack resistance limited in cement
78) Best Canal linning material in THAR DESERT is
79) Question about depth of T-beam
80) Question about unit hydrograph
81) Question about coordinates required during road construction
82) Question about bottom of well