You are on page 1of 6

Daily Report

www.GQIS.co.uk

Project: Hinkley Jetty Design


Customer: Egden Murray
Finalisation
Sub-Vendor: Zhejiang Chankong Steel
Vendor: ESC Group
Pipe CO.,LTD
Sub-Vendor Address: Tianning, Jiashan,
Vendor Address: Putuo, Shanghai,China
Zhejiang
Vendor Reference: Sub-Vendor Reference:

GQIS Assignment No: Customer Reference:

Purchase Order No: 3568 Report No: 010

8PM 1st, September


Date of Visit: -8AM
2nd,September,2016
MATERIAL INSPECTED THIS VISIT
Item No. Quantity Description Tag No., Batch No., Serial No., Cast,
Heat No.
3568-DC- 1 Raw plate material inspection Detail data refer to below
041-010 table.

SUMMARY / AREAS OF CONCERN

GUI-036-00 (Revision 0) Flash Report Dated: 22nd March 2016


Daily Report
www.GQIS.com
Customer: Egden Murray Purchase Order 3568
No.:

1. SMMARY / AREAS OF CONCERN:


1.1 Raw plate material inspection
As per ITP step 09(Incoming raw material quality control and assurance-Raw material inspection, including
material identification, appearance and dimension inspection), GQIS inspector carride out inpection for raw
plate material, the detail inspection scope as below table, all inspection data found in conformity with ITP &
specification and traceability, the surface hasnt found any indication of damage. The result is satisfactory.
Serial No. Material Size Heat No. Delivering Specification
Grade Condition
1610559080101 S355J2 35X1778X 1610559 Hot Rolled EN 10025-2 2004: S355J2
2771

1.2 Witness impact testing


As per ITP step 08(Incoming raw material quality control and assurance-steel plate and coil material
properties retest), GQIS inspector witness impact testing, before testing, GQIS inspector reviewed impact test
equipment calibration certificate and valid time and confirmed that are satisfactory, inspection the sampling
dimension and confirm that are satisfactory and traceable, confirm the impact test process in accordance with
EN ISO 100045-1, the test result in conformity with standard of BS EN10025-2 and BS EN10025-4.
Heat No. Material Valve 1(Mpa) Valve 2(Mpa) Valve 3(Mpa) Result
16303198 S420M 314 322 310 OK
16303197 S420M 246 296 293 OK
16103255A S355J2 269 312 305 OK
16203249A S355J2 315 316 337 OK

1.3 Witness chemical composition analysis


As per ITP step 08(Incoming raw material quality control and assurance-steel plate and coil material
properties retest), GQIS inspector witness chemical composition analysis, before testing, GQIS inspector
reviewed chemical composition analysis equipment calibration certificate and valid time and confirmed that
are satisfactory, inspection the sampling dimension and confirm that are satisfactory and traceable, confirm
the chemical composition analysis process in accordance with EN ISO 14284-1996, the test result in
conformity with standard of BS EN10025-2 and BS EN10025-4.

1.4 Inspection ancillary installation for pile 3568-C05-068


As per ITP step 15(production and installation of ancillary), on 30th August, 2016 GQIS inspector witness
hydrostatic testing for flexible hose, the result is acceptable. But when assebling the flexible hose the factory
welding socket with pile first, after threaded flexible hose with socket again, in this case need perform
hydrostatic test again, also that fabrication process is not in line with drawing requirement(drawing require
fixible hose end fitting to be threaded into full socket prior to welding to plate/pile shell), after consult with
factory they state they would manufacturing strictly according to the drawing and specification in the future.
After threaded flexible hose with socket found the hose more longer than drawing requrient, the extre length
about 240mm, this maybe affect the medium fluid speed, factory state they will send this batch of hose to
vendor to modified the flexible hose according to drawing.

Picture

007 (Revision 0) Daily Report Dated: 29nd August 2016


Daily Report
www.GQIS.com
Customer: Egden Murray Purchase Order 3568
No.:

Raw plate material inspection

Raw plate material inspection

007 (Revision 0) Daily Report Dated: 29nd August 2016


Daily Report
www.GQIS.com
Customer: Egden Murray Purchase Order 3568
No.:

Witness impact testing

Witness impact testing

007 (Revision 0) Daily Report Dated: 29nd August 2016


Daily Report
www.GQIS.com
Customer: Egden Murray Purchase Order 3568
No.:

Witness chemical composition analysis

Inspection ancillary installation for pile 3568-C05-068

007 (Revision 0) Daily Report Dated: 29nd August 2016


Daily Report
www.GQIS.com
Customer: Egden Murray Purchase Order 3568
No.:

After threaded flexible hose with socket in the bottom side found the hose more longer than drawing requrient,
the extre length about 240mm.
Accepted Yes Non-Compliant No

Technical Specialist: Su Jinlong Operations Coordinator:

Date: 8PM 1st, September -8AM Date:


2nd,September,2016

007 (Revision 0) Daily Report Dated: 29nd August 2016