Professional Documents
Culture Documents
2
History of the Company
Ed Zublin AG
21 km Singapore
4
History of the Company
Completed Projects in Singapore
6
History of the Project
Transmission Pipeline Across West Jurong Channel
CONVENTIONAL METHOD
(Trenching + Pipelaying + Backfilling)
VS
Reference Projects
Service Duct, Kieler Frde, Germany
Reception shaft
Jacking shaft
Technical Data:
Length: 1,368m
Internal Diameter: 4.10m
External Diameter: 5.00m
Slope: max 10%
Depth under Water level: max 37.46m
8
Reference Projects
Gautami Godavari River Crossing, India
Technical Data:
Reference Projects
Southern Seawater Desalination Plant, Australia
NORTHERN INTAKE
TUNNEL
LAUNCHING
RECEIVING PITS
SHAFT
OUTFALL TUNNEL
SOUTHERN INTAKE
TUNNEL
Technical Data:
Max. Drive Length: 950m
Total Length: 2,670m
Internal Diameter: 2.00m/2.40m
External Diameter: 2.45m/2.86m
Slope: max 4.8%
Depth: max 35.2m
10
HISTORY OF THE PROJECT
WORKING SHAFTS
MODIFICATION OF TBM
JACKING PIPE
CONSTRUCTION TECHNIQUES
PROBLEMS FACED
SAFETY
PROGRESS & RECORDS
11
Working Shafts
Shafts Design: D-Wall
12
Working Shafts
Jacking Shaft
2 JACKING PIPES
INSTALLATION 7.0 M
PLAN
~ 9.2 M
SHAFT DIAMETER REQUIRED FOR GAS PIPELINE INSTALLATION 13.5 M
13
Working Shafts
Receiving Shaft
14
Working Shafts
Good Subcontractor: Bachy Soletanche
15
Working Shafts
Praying Ceremony Good Praying!
16
HISTORY OF THE PROJECT
WORKING SHAFTS
MODIFICATION OF TBM
JACKING PIPE
CONSTRUCTION TECHNIQUES
PROBLEMS FACED
SAFETY
PROGRESS & RECORDS
17
Modification of TBM
Dual Mode Pipe Jacking Machine M-1182M
8 9 11 12 13
5 6 7
1 3 24
15 10
14
1 Cutting Wheel 6 Screw Conveyor 11 Power Pack
2 Drive Motor 7 Stone Crusher 12 Jacking Station
3 Steering Cylinder 8 Gate Valve 13 Winch
4 Articulation Joint 9 Belt Conveyor 14 Flushing Box
5 Gyro Target 10 Compressed Air Lock 15 Bypass
18
Modification of TBM
Fire Box (Stone Crusher)
19
Modification of TBM
High Voltage System
On-ground
20
Modification of TBM
Stand Alone Power Pack for IJS
21
22
Jacking Pipe
Pipe Factory in Thailand
23
Jacking Pipe
Production Line
24
HISTORY OF THE PROJECT
WORKING SHAFTS
MODIFICATION OF TBM
JACKING PIPE
CONSTRUCTION TECHNIQUES
PROBLEMS FACED
SAFETY
PROGRESS & RECORDS
25
Construction Techniques
Geology
CHART DATUM
SAND GRAVEL
CLAY CLAY
SAND
SILT
SILT
SAND
SAND
MUDSTONE
LEGENDS:
26
Construction Techniques
High Water Pressures in Rock
27
Construction Techniques
Universal Navigation System
28
Construction Techniques
Control Survey
Final Result
H = 153mm
V = 28mm
29
Construction Techniques
Intermediate Jacking Station (IJS)
Main Jacks
30
Construction Techniques
Intermediate Jacking Station (IJS)
300 344 345 346 347 348 349 396 397 398 399 400 448 449 450 451 452 511 512 513
141 142 143 189 190 191 192 193 240 241 242 243 244 245 246 293 294 295 296 297 298 299
31
Construction Techniques
3 Points Lubrication System
Compressed
e Hoses
Bentonit
Cables
Control
Stand Alone
TBM
TBM
12m
12m
32
HISTORY OF THE PROJECT
WORKING SHAFTS
MODIFICATION OF TBM
JACKING PIPE
CONSTRUCTION TECHNIQUES
DANGERS, TROUBLES AND PROBLEMS FACED
SAFETY
PROGRESS & RECORDS
33
34
Problems Faced During Operation
Surveyors Fault!
35
36
Safety
Safety Records
Monthly Accident Frequency Rates
Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11
No. of Manhours 3,300 10,070 11,860 14,215 17,289 15,714 16,204 19,208 18,084 22,200 24,192
Accident Frequency
- - - - - - - - - - -
Rate A
Accident Frequency
- - - - - - - - - - -
Rate B
Minor Accidents - - - - - - - - - - -
Major Accidents - - - - - - - - - - -
Manhours 3,300 13,370 25,230 39,445 56,734 72,448 88,652 107,860 125,944 148,144 173,272
Accident Frequency
- - - - - - - - - - -
Rate A
Accident Frequency
- - - - - - - - - - -
Rate B
37
Safety
Safety Drill / Training
38
HISTORY OF THE PROJECT
WORKING SHAFTS
MODIFICATION OF TBM
JACKING PIPE
CONSTRUCTION TECHNIQUES
DANGERS, TROUBLES AND PROBLEMS FACED
SAFETY
PROGRESS & RECORDS
39
40
Progress and Records
Breakthrough 18.12.2011
41
42
Progress and Records
Records Around the World
43