Professional Documents
Culture Documents
OR
Dark Art
Black Box
1
Contents
Introduction
Available Ground Treatment Techniques
Benefits and Application to Tunnelling
Case studies
2
Grout delivery techniques
Compaction grouting
3
Fissure grouting
4
Imperative that correct grout used for ground
condition
5
USE OF HIGH PRESSURE JETS TO REPLACE
SOIL WITH GROUT
6
JGP - Sludge return
7
DSM/JMM/Rasjet/WSM etc
4000
2500 Average
qu (kPa)
2000
2090 kPa
1500
Design line
1000
500
900 kPa
0
9-11
9-13
9-22
9-24
9-52
9-61
9-63
9-32
9-34
9-42
9-71
9-73
Sample no.
700
500
E50 (MPa)
400
Average
300
280 MPa
200
100
Design line
0 90 MPa
9- 9- 9- 9- 9- 9- 9- 9- 9- 9- 9- 9- 9- 9- 9- 9- 9- 9- 9- 9- 9- 9- 9-
11 12 13 21 22 23 24 51 52 53 61 62 63 31 32 33 34 41 42 43 71 72 73
Sample No.
8
Ground Freezing Alternative option
Break in/outs
Cross passage/ sumps
Head interventions
Settlement control of structures
Settlement control of tunnel
Stabilise ground for mined tunnel excavation
Reduce permeability to control water flow
9
Sinkholes on NEL
10
Typical Break out grouting arrangement
11
Grouting to ensure top heading stability
22m 28m
18m
14m
12
Challenging Ground conditions
13
TAM Grouting - Second Phase
Result
14
PVD Drains & surcharge to improve underconsolidated Marine Clay
vacuu
m
pump
PVD Fabric
replaced with
HDPE to
prevent water
ingress from
F1 material
15
Settlements induced by Surcharge
-400
-900
Settlemnt (mm)
-1400
-1900
-2900
-3400
Tim e
16
Grouting for Sump Construction
Ground Conditions
17
Controlling the works- Monitoring
A-5 B-5 C-5 D-5 E-5 F-5 G-5 H-5 I-5 J-5 K-5 L-5 M-5
Level
0.00 m.
0.20 m.
0.40 m.
0.60 m.
0.80 m.
1.00 m.
1.20 m.
1.40 m.
1.60 m.
1.80 m. 1.8m
2.00 m.
2.20 m.
2.40 m.
2.60 m.
2.80 m.
3.00 m. 3.0m
3.20 m.
3.40 m.
3.60 m.
3.80 m.
4.00 m.
4.20 m.
4.40 m.
4.60 m.
C828
Chemical Grouting
Drilling Profile Sump Pit 2 - Outer Bound
5.40 m.
5.60 m.
5.80 m. 5.7m
5.5m
5.4m 5.4m
5.5m
A-5 B-5 C-5 D-5 E-5 F-5 G-5 H-5 I-5 J-5 K-5 L-5 M-5 N-5 O-5 P-5 Q-5 R-5 S-5 6.00 m. 6.1m 6.0m
Level
0.00 m.
0.20 m.
0.40 m. = Soil & JGP
0.60 m.
0.80 m.
1.00 m. = Jet grouting (JGP)
1.20 m.
1.40 m.
1.60 m.
1.80 m. 1.8m = Sand
2.00 m.
2.20 m.
2.40 m.
2.60 m.
2.80 m.
3.00 m. 3.0m
3.20 m.
3.40 m.
3.60 m.
3.80 m. 3.7m
4.00 m.
4.20 m.
4.40 m.
4.60 m.
4.80 m. 4.7m
5.00 m.
5.20 m. 5.3m
5.40 m. 5.4m 5.4m
5.60 m. 5.5m 5.5m
5.80 m. 5.7m 5.7m
6.00 m. 6.1m 6.0m 6.0m 6.1m
= Sand
18
Trying to avoid this
Ground
treatment
to control
settlement
19
JLEP Waterloo station
Grouting arrangement
20
Cross section
21
Movement of Big Ben Clock Tower in London during Jubilee Line
Construction
7.0 35
6.0 30
4.0 20
3.0 15
2.0 10
0.0 0
01/01/1995 11/04/1995 20/07/1995 28/10/1995 05/02/1996 15/05/1996 23/08/1996 01/12/1996 11/03/1997 19/06/1997 27/09/1997 05/01/1998 15/04/1998
Date
To Conclude
22