7 Working at height (Scaffold Fall from height Injury to Choose an alternative work method for Work site
Platform) Falling material workers, site height work (If possible) supervisor/
Scaffold erection, dismantling Slip/ Trip staff Inspect the workplace before starting work safety officer
and use Collapse Visitors to ensure that it safe
Ladder Access/ Egress Public Competent Scaffolders (third party
Improper use of scaffold Damage to certified) should erect the scaffolding
equipment & with proper supervision. No Supervision no
Action /
Step Who or what may
Hazard Control Measures / Recovery Measures Responsible
No. Sequence of activities be harmed?
Party
Unauthorised access property scaffold work.
Adverse weather conditions Competent Inspector inspects & sign the
Uneven ground Tag
Unsafe work equipment Scaffolding to be inspected and signed
Missing scaffold every 7 days, after modification or adverse
components weather.
Housekeping Scaffold Tag System should be used (Red &
Green)
Manual lift (Scaffold
materials) Provide Proper Warning Signages.
Damage PPE Barrier to be erected using tape & warning
signs around the work area.
Provide guardrail & Edge protection
Platform secures with clamp
Horizontal and/or vertical, diagonal bracing
should be erect to prevent rack of the
scaffold structure
The Defective & damaged scaffold material
will be removed from the site.
Make sure that all people are well trained
to use properly harness and conduct
training
Do inspection harness daily before starting
the job.
Ensure that appropriate access to the work
platform is provided
Conduct a toolbox talk before starting the
work to advise the work group on the
associated hazards to avoid falls and
minimise injury
Conduct good housekeeping on daily basis
Do not stack any materials on working
platform
Tool tie shall be used to prevent tools fall.
Ensure the Work area to be left in a safe
hazard free condition at the end of each
work period
Provide adequate Personal Fall Protection
( Full body harness) to minimise the effect
of a fall
100% tie off will be followed
Approved rescue plan will being in place to
manage if any emergencies
Action /
Step Who or what may
Hazard Control Measures / Recovery Measures Responsible
No. Sequence of activities be harmed?
Party
Stop all work in the event of adverse
weather conditions.
Secure all tools and materials, or store in a
suitable container
All Ladders to be inspected and color
coded prior to use.
Maintain three points of contact with
ladder at all times.
Ladders must extend at least 1.05mt
length above stepping of point.
Do not carry tools or equipment while
stepping the ladder.
A stand by man will be provided to hold
the ladder firmly.
No work to be carried out off ladder
(excemptional
Ensure that adequate first aid treatment
and emergency transportation facilities are
available at the work site
Suitable & Sufficient PPE should be worn
8 Use of Hand tools Damage, & fabricated hand Injury to Damage/Fabricated hand tools Work site
tools workers, site (Homemade tools) will not be permitted on supervisor/
Improper tool staff all job sites. safety officer
Splashes Visitors Tools will be tested & tagged by
Hand injury Public Competent person before use
Damage to Use the right tools for each task.
equipment & Skilled workers to be carry out the work.
property Conduct a daily tool box talk prior to the
start of work
Ensure appropriate PPE always provided
and used, for example, wide vision goggles
or safety spectacles and a face shield, ear
plugs or muffs
9 Heat Exposure Heat stroke/Heat Cramps/ Injury to No work during hottest part of the day. Work site
Working in hot /Cold weather Heat exhaust workers, site Avoid dehydration: rest and drink lot of supervisor/
condition Dehydration staff water frequently safety officer
Poor ventilation Visitors Avoid sun exposure: proper clothing and
Hypothermia Public sunscreen
Damage to Frequent breaks will be provided
equipment & Avoid alcohol, caffeinated drinks, and
property heavy meals.
Action /
Step Who or what may
Hazard Control Measures / Recovery Measures Responsible
No. Sequence of activities be harmed?
Party
Avoid hypothermia conditions: stay dry,
wear suitable clothing specially winter.
Wear clothing suitable to the conditions
and the work
Rest and warm yourself frequently
Mechanical ventilation will be provided, if
area is closed by walls or heavy fencing
sheets (standby fan and air coolers).
If any symptoms are observed the person
will be transferred to a suitable place and
we will call immediately to control room for
further action. on Tel No. 135
10 Ergonomic Muscle pains Injury to personnel, Adequate number of workers to be Work site
Site Operatives assigned, Job rotation will be in place. supervisor/
No overworking for the installers by having safety officer
reserve workers
Proper platforms, tools, welfare facility to
be provided and ensure all are in place
before commencement of work.
11 Waste management Contamination. Site Operatives Adequate disposal methods shall in Work site
Biological. compliance with QP supervisor/
Disease. Store the minimum amount, if possible safety officer
12 Welfare facilities Contamination. Site Operatives Adequate welfare facilities shall in Work site
Biological. compliance with QP/ ATC Policy supervisor/
Disease., Illness. Ensure daily cleaning by regular safety officer
inspection
13 Emergency response. Failure of warning system. Site Operatives QP Emergency Number posted all over the Work site
Visitors (if any) sit 135 supervisor/
Site Emergency Contact numbers & safety officer
Evacuation chart posted.
14 Returning site to good condition Proper housekeeping to be maintained. Work site
All access shall be free from any supervisor/
obstructions safety officer