Figure X.X: The Gantt chart on the production of xylose from oil palm empty fruit bunch
Based on figure X.X, the project started with Project Briefing that lasted for 3
days. The following task is Selection of Title that lasted for 4 days. Followed by
Literature review (4 days), Market Overview (1 day), Proposal preparation and
submission (3 days), Introduction (4 days), Market Needs and Rate of Production
Determination (7 days), Reaction and Kinetics (10 days), Process Flow Diagram and
Material and Energy Balance (32 days) and Final Report and Presentation preparation
(2 days).