Gantt Chart

2-Feb 22-Feb 14-Mar 3-Apr 23-Apr 13-May 2-Jun

Project Briefing

Selection of Title

Literature Review

Market Overview

Proposal

Chapter 1: Introduction

Chapter 2: Market Needs and Rate of Production Determination

Chapter 3: Reaction and Kinetics

Chapter 4: Process Flow Diagram and Material and Energy Balance

Final Report and Presentation

Figure X.X: The Gantt chart on the production of xylose from oil palm empty fruit bunch

Based on figure X.X, the project started with Project Briefing that lasted for 3
days. The following task is Selection of Title that lasted for 4 days. Followed by
Literature review (4 days), Market Overview (1 day), Proposal preparation and
submission (3 days), Introduction (4 days), Market Needs and Rate of Production
Determination (7 days), Reaction and Kinetics (10 days), Process Flow Diagram and
Material and Energy Balance (32 days) and Final Report and Presentation preparation
(2 days).