The following items for your follow up today, kindly fill in as per the responsibilities:
3 Unichem Unichem Mishal - Check the status of the - Mishaal - Mr. Ali
Factory things delaying the project discussed
for tiles and other things. with
- Check the status for the fire Arshad
water tank has to be sorted - Mishaal - Under
out today with Capital. review with
( Mishaal to take action) - Yasar & Ben
- Follow up with Yasar for the Mishaal - Monday
pending payment for 30% April 25 to
for the MEP work and 20% finish
for mechanical work
advanced payment.
4 Milaha Adearest/G Mishaal and - Status for manpower we - Fahdi - Ready &
project ea Athif have to ensure availability waiting
of people. date cnfm
- Get a quotation for 10
helpers for 2 month from
different suppliers plus one - Mishaal
welder and one pipe
fabricator. - Fahdi /
- Anchor bolts size and Athif
anchor bolts supply.
- Job schedule has to be
- Fahdi
prepared by Fahdi
- Ensure that all the required
- Athif
tools and belts for the lifting
- Yaser
on Sunday is ready.
- Follow up with Mr Hisham prepared,
- Yasar to to open
about receiving of the
prepare USD A/C
advanced payment ( Yasar
invoices But will
to prepare invoice for
advanced payment and wiat Mr.
send it to GEA Mr Hisham Khaled
signature
and Mr. Purgaric today). - Due time -Ready waiting to
- Request from Zubair India 1 constrain, cfm
instrument technician, 4 doing
cable fabricator and cable locally
pullers and one electrical
engineer. For two month - Athif &
contract. Mishaal -Prepared 25000
- Check with Athif and incl. consumables
Mishaal the list of
equipment and tools
required for the job and the
approximate cost.
5 - - -
6 Festival Nisthar - What is the status? - Finished - ongoing
City 150 sqm
shaft
- Installing
duct of 2nd
shaft on
April 30
7 Drake and SS duct Nisthar - What is the status? - 2 teams - Ongoing
Scull DSI welding Yesterday they were working
complaining that no welders zone 3c,
attended to site from PGCC 3133 Mr Omar
please check the status. linear mt requested QR
- Status of completion of till 26th of 1500 for the
steel structure job with DSI. April missing beams
( Athif)
8 Payment Yasar - List of all our collectables - Done - Follow up
follow up has to be prepared from
Yasar as I requested from
him yesterday including all
our contractor list should
include the following data
- Contract amount, previous
receivables, remaining
amount, retention value
date of each invoice due - Ongoing - Follow up
date. but still no
- Follow up the LC payment answer
from DSI till yesterday is not from DSI
transferred to our account.
9 New copy ZeroX and Fahdi - Follow up with Canon for - Fahdi - To be
machine Canon the new machine finalized
max this
week
1 - - -