Professional Documents
Culture Documents
Globally, oil wells produce about 220 million BWPD (barrels of water per day)roughly three
barrels of water for every barrel of oil. In older fields, the water "cut," or ratio-of-water-to-oil,
can be 95% or higher. (Hallburton). From literature and published data the data for computations
were obtained for the design. See table below
In designing three-phase separators, it is a good idea to examine both vertical and horizontal
configurations for the specific case, and decide on the one that meets the physical requirements,
stream specifications, and economic attractiveness. (Economides, 2009).Also the available plot
space (foot print) may be a factor in the choice of separator (Wayne D. Monnery and William Y.
Svrcek).
PARAMETERS
Qg 1.8 MMscf/ Gas rate
d
Qo 6000 bbl/d Oil rate
Qw 14000 bbl/d Water rate
o
'o 30 API Oil density
o 0.876 Oil specific gravity
o 20 cP Oil viscosity
w 1 cP Water viscosity
w 1.073 Water specific gravity
g 0.75 Gas specific gravity
Z 0.94 Gas compressibility
P 218 Psia Operating pressure
o
T' 70 F Operating temperature
o
T 530 R Operating temperature
tw 20 minutes Water retention time
to 20 minutes Oil retention time
g 0.015 cP Gas viscosity
dm,w 500 Micron Smallest water droplet size to be removed
dm,o 100 Micron Smallest oil droplet size to be removed
3
g 0.886 lb/ft Gas operating density
3
54.66 lb/ft Oil operating density
o
2
66.95 lb/ft3 Water operating density
w
5
Design
This section involves the designing and Sizing of horizontal and vertical three phase Separators.
Three Design approaches that are acceptable in Industry are considered
Three Phase (Gas - Oil - Water) Horizontal /Vertical Separator: As per "Petroleum and
Gas Field Processing -Hussein K. Abdel-Aal, Mohamed Aggour, M. A. Fahim"
Three Phase (Gas Oil-Water) Horizontal/ Vertical Separator: As per API 12J
Three Phase (Gas Oil-Water) Horizontal/ Vertical separators as per Monnery and
Svrcek Separator Design
Three Phase (Gas - Oil - Water) Horizontal /Vertical Separator: As per "Petroleum and
Gas Field Processing -Hussein K. Abdel-Aal, Mohamed Aggour, M. A. Fahim"
This approach considers the gas capacity constraint and the liquid retention time constraint
results in developing two equations; each relates the vessel diameter to its length. Analysis of the
two equations determines the equation that governs the design and that should be used to
determine possible combinations of diameters and lengths. For three-phase horizontal separators,
consideration of the settling of water droplets in oil results in a third equation that determines the
maximum diameter of the separator. Therefore, in determining the vessels diameterlength
combinations, the diameters selected must be equal to or less than the determined maximum
diameter. (H. K. Abdel-Aal and Mohamed Aggour and M. A. Fahim , 2003)
Three Phase (Gas - Oil - Water) Horizontal Separator: As per "Petroleum and Gas Field
Processing -Hussein K. Abdel-Aal, Mohamed Aggour, M. A. Fahim"
Step 1
Determine Aw/A
Aw 0.5Q w t w 0.5 14000 20
= = =0.35
A Qo t o +Qw t w 6000 ( 20 ) +14000(20)
5. If no match is obtained, use the calculated value of Cd and repeat steps 24 until convergence
is obtained.
For this design assumed Cd = 0.34,
U Re Cd %
Approximate
error a
0.3400 100
1.589 45.989 1.3040 73.9
0.8119 23.168 1.9991 34.8
0.656 18.986 2.2926 12.8
0.6123 17.723 2.4069 4.7
0.5976 17.296 2.4489 1.7
0.5924 17.146 2.4643 0.62
0.5906 17.094 2.4697 0.22
The table above shows results from the iteration with percentage approximate error
computations.
Hence we use Cd= 2.4697
Determine the gas capacity constraints, dm = 100 m
54.6620.886
0.886 2.4697
=34.85 inft
100()0.5
0.5
TZ Q g g Cd
DL=420
P( )(
d m ( o g )
=420
)530 0.94 1.8
218 ( )
Determine the combinations of D and L that satisfy the gas capacity constraint. Select diameters
smaller than the determined maximum diameter and determine the corresponding effective
length. The result is shown below.
Table 4 D and L Combinations that Satisfy Gas Constraint
Investigation of the results however, shows that for any selected diameter, the effective length is
too small (not realistic). Therefore, the gas capacity does not govern the design but rather liquid
capacity governs the design.
Determine the liquid capacity (retention time) constraint
D 2 L=1.429 ( Q o t o +Q w t w ) =1.429 ( 6000 20+14000 20 ) =571600 2 ft
Determine the combinations of D and L that satisfy the liquid capacity constraint. Select
diameters smaller than the determined maximum diameter and determine the corresponding
effective length.
The most common slenderness ratio (SR) for horizontal separators: 3 SR 5 . Also As per
GPSA, typical horizontal L/D ratios are normally in the range of: 2.5 SR 5 .
Suitable separators are those with diameters between 126 D 144 . Therefore, the
recommended separator size can be either 126 in. by 48 ft, or 132 in. by 44ft or 138 in. by 40 ft
or 144 in by 36 ft.
Normally, smaller diameter and longer separators are less expensive than the larger diameter and
shorter separators. The choice of the diameter of separator is based on cost and availability.
We would go in for 126 in by 48 ft. The selected separator gas capacity is calculated by
substituting the values of D and L and calculating the value of Qg in the gas capacity constraint
equation. For a 126-in. by 48-ft separator, the gas capacity,
Three Phase (Gas - Oil - Water) Vertical Separator: As per "Petroleum and Gas Field
Processing - Hussein K. Abdel-Aal, Mohamed Aggour, M. A. Fahim"
Gas capacity is use to determine minimum diameter of the vessel
Liquid retention time constraints is used to determine the height of the vessel
Step 1
The minimum diameter that satisfies the water droplets settling constraint is determined
6686 6000 20
( w o )d2m= 2
=16290.76 2
(1.0730.876)500
6686 Q o o
D2min =
Dmin =127.64
The minimum diameter that satisfies the gas capacity constraint is determine as
0.5 0.5
g C
2
D =5058 Qg
min
TZ
P ( )( d
o g d m ) =5058 ( 1.8 ) ( 530 0.94
218 )( 0.886
54.6620.886
2.4697
100 ) =419.70 2
D min =20.49
The larger of the two minimum diameters determined above is then considered as the minimum
allowable vessel diameter.
Table 6 Comparison between Minimum Diameters due to gas and Liquid Constraint
Parameter Dmin/in
Minimum diameter due 20.49
to gas capacity
constraint
Minimum diameter due 127.64
to retention time
constraint
The minimum diameter due to the water droplets settling constraint is the larger. Hence liquid
capacity governs the design
Dmin =127.64
For various values of diameter larger than the minimum allowable vessel diameter, combinations
of diameters and liquid heights are determined as
( H o + H w ) D2=8.576 ( Q o t o +Q w tw ) =8.576 ( 6000 20+14000 20 )=3430400 3
( H o + H w ) D2=3430400 3
We find combinations of liquid height and Diameter that satisfy the above liquid capacity. For
1
diameters greater than 36, Seam to Seam length is determine by Ls= 12 (H o + H w +40)
Table 7 Results for Combinations D, Ls, and Hw + Ho that satisfy Liquid Capacity Constraints
Slenderness ratio (SR) for vertical separators: 1.5 SR 3 . Also as per GPSA, typical vertical
Three Phase (Gas Oil-Water) Horizontal/ Vertical Separator: As per API 12J
This approach involve the determination of gas capacityGas capacities of separators by modified
Stokes Law. When using Stokes Law. The capacity is based on the principle of the minimum
droplet size that will settle out of a moving gas stream at a given velocity. The maximum
allowable superficial velocity of the gas at operating conditions is determined.
Table 8 K factor values for the Souder Brown's Equation (Plisga, 2005)
K= 0.34
Step 1
The maximum gas superficial velocity is determined by
o g 0.5 54.6620.886 0.5
V a=k [ ] =0.34 [ ] =2.649 ft /s
g 0.886
Q g 1.348
Minimum gas flow area = =0.5089 ft 2
V a 2.649
1440 2 1
w= 0.7854 D NLL H
20 144 5.615
Using t = 20 min Normal liquid level (NLL)
Maximum liquid load expected = 6000 + 14000 +60(extra for contingency) = 20060 bbl/d
2 20060 56150
D NLL H= =286826.8398
3927
We use generate different combination of separator diameter, normal liquid level and height to
find a suitable separator.
The table below shows the different combinations of D and L using half full (NLL =0.5)
Slenderness ratio (SR) for Horizontal separators: 3 SR 5 .From the table above the
From the table it can be seen that all the recommended separators have their gas capacity to be
greater than the expected.
Using 1/4 full criterion NLL= 0.25, the results is show below
Table 10 D and L combinations for One Quarter Full Criterion
Based on same reason as above the recommended separators are those with diameters:
144 D 162 .
Based on same reason as above the recommended separators are those with diameters:
132 D 150
Based on same reason as above the recommended separators are those with diameters:
108 D 120
Based on same reason as above the recommended separators are those with diameters:
102 D 114
Based on same reason as above the recommended separators are those with diameters:
96 D 108
1.194 3
Qg = = =1.348 ft / s
Gas flow rate n ft3/s g 0.886
Q g 1.348
Minimum gas flow area = =0.5089 ft 2
V a 2.649
1440 2 1
w= D NLL H
20 144 5.615
Using t = 20 min Normal liquid level (NLL)
Maximum liquid load expected = 6000 + 14000 +600(extra for contingency) = 20600 bbl/d
20600 56150
D 2 NLL H= =294545.001
3927
We generate different combination of separator diameter, normal liquid level and height to find a
suitable separator. The table below shows the different combinations of D and L using half full
(NLL =0.5)
Monnery and Svrcek (1994) suggested that for horizontal separators, different devices can be
used to control the interface level such as a boot, a weir, or the combination of a bucket and weir.
A boot is used when the volume of heavy liquid is <1520 wt%, while a weir is used when the
volume is much greater. The bucket and weir type design is used when the interface level control
may be difficult, such as heavy oil, or when large amounts of emulsions or paraffins are present
(Arnold and Stewart, 1986).
This section looks at the design of three phase separators using procedures introduced by
Monnery and Svrcek (1994).
Symbol Nomenclature
A Vertical vessel cross-sectional area, ft2
AD Downcomer cross-sectional area, ft2
AL Equals A - AD
D Vessel diameter, ft or in
H Height, ft
HA Liquid Level above Baffle, in or ft
HBN Liquid height from above to feed nozzle, ft
HD Disengagement Height, ft
HH Holdup Height, ft
HL Height from Liquid interface to light nozzle, ft
HR Height from liquid nozzle to baffle, ft
HS Surge Height, ft
HT Total Vertical Separator Height, ft
WD Downcomer chord width, in
K= 0.34 refer to table 8 LL = Light Liquid (Oil) HL = Heavy Liquid V= Vapour (Gas)
Step 1
Determine terminal velocity
V T =k O
g
g
=0.34
55.6620.886
0.886
=2.649
ft
s
For conservative design
ft
V V =0.75V T =0.7 2.649=1.987
s
Determine the mass flowrate of the fluids (W)
bbl 622.4 lb
6000 5.615
Oil mass flowrate W = d ft lb
=76730
24 hours h
bbl lb
14000 62.4 5.615
Water mass flowrate W HL= d ft
=204390 lb/h
24
Step 2
Determine the density of the liquid mixture of oil and water at the separator operating conditions
by
W W HL 76730 204390
L= O + w =54.662 + 66.955 =63.600lb/ft 3
W +W HL W +W HL 76730+204390 76730+204390
Step 3
The vapour volumetric flowrate is determined by
WV 66450
Qg = = =20.833 ft 3 /s
3600 g 3600 0.886
Step 4
Calculate the vessel internal diameter, Di
4 Q g 0.5 4 20.833 0.5
D i=( ) =( ) =13.349 ft
VV 1.987
With mist eliminator, add 3 to 6in to Di to accommodate a support ring. For this design 5in
(0.416 ft) was added.
D=13.349+0.416=13.765 ft
Step 5
The settling velocities are determined, from table Ks = 0.163
66.95554.662
V HL =k s HL =0.163 =4.02 min
0.5
HL 66.95554.662
V =k s =0.163 =2.004 min
HL 1
Step 6
Calculate light/heavy liquid volumetric flow rate
W 76730
Q = = =23.395 ft 3 /min
60 60 66.955
W HL 204390
QHL = = =50.877 ft 3 /min
60 HL 60 66.955
Step 7
Calculate the settling times (ts)
HL and HH are taken to be 1ft (minimum values)
12 H L 12 1
t s , HL= = =2.985 min
V HL 4.02
12 H H 12 1
s ,= = =5.988 min
V 2.004
t
Step 8
Calculate the baffle plate Area, AL
The vertical vessel cross-sectional Area is determined as follows
2
D2 (14)
A= = =153.938 ft 2
4 4
Calculate the downcomer cross-Sectional area, AD
Q + QHL
A D=7.48 60
G
G = Baffle liquid load(gallons per hour per square feet gph/ft2 )and High liquid level above the interface
HL+HR
Minimum value of HR =1 ft = 9 in, HL = 1 ft =12 in
Hence HL+HR = 12 +12 =24 in
Using the above values G is obtained from the graph below
Figure 3Obtain G from the Downcomer Allowable Flow (Monnery and Svrcek, 1994) (Economides, 2009)
Step 9
Calculate the residence time tr
H A 1 150.537
r ,= L L = =6.435 min
Q 23.395
t
H L A 1 153.938
t r , HL= = =3.025 min
Q HL 50.877
s , ,the liquid separation is controlling the design .The diameter neeed
r ,<t s , HL t r , HL <t be increasedthen
If t
The procedure must be repeated from step 7
Table 23 Comparison of Settling Times and Residence Times for Light and Heavy Component
HL 2.993 3.025
LL 5.988 6.35
Step 11
Calculate volumetric flowrate of mixture( gas, oil and water)
Q +Q 23.395+50.877
Qm=Q g + HL =20.833+ =22.071 ft 3 /s
60 60
The mixture density is also determined
23.395+50.877
= =0.056
74.272+20.833 60
m= L + V ( 1 )=63.600 ( 0.056 ) +0.886 ( 10.056 )=4.398
Step 12
The minimum value of HA is assumed to be 6 in (0.5 ft)
HBN = 0.5dN + greater of (2 ft or Hs + 0.5 ft). Here dN is the inlet or outlet vapor/liquid nozzle
diameter in ft and can be calculated by
1 0.5
4 Qm
dN (60 ) (
m 2 =
4 22.071
60 )
4.398 =0.991 ft=11.892 .
dN is taken to be 2 ft dN = 2 ft
HBN = 0.5dN + greater of (2 ft or Hs + 0.5 ft)
H BN =0.5 d N + greater of ( H s+ 0.5 )=0.5 (2 )+1 greater than ( 2.412+ 0.5 )=4.412 ft=4.5 ft
Figure 4 Three-phase horizontal separator with a weir (Monnery and Svrcek, 1994) (Economides, 2009)
Symbol Nomenclature
Dv Vessel diameter, ft or in
dN Inlet or outlet nozzle diameter, ft or in
H Height, ft
HD Disengagement height, ft
HH Holdup height, ft
HLIN HLL to inlet nozzle centerline height, ft
HLLL Low liquid Level
HLL High Liquid Level
HS Surge height, ft
HT Total vertical height, ft
NLL Normal liquid level
Table 25 Low Liquid Level (LLL) for Different Vessel Diameters and Operating Conditions (Economides, 2009)
4 25 6 9
6 25 6 10
8 15 6 11
10 6 6 12
12 6 6 13
16 6 6 15
Table 26 Liquid Holdup and Surge Times (Wayne D. Monnery and William Y. Svrcek)
K= 0.34 refer to table 8 LL = Light Liquid (Oil) HL = Heavy Liquid V= Vapour (Gas)
V T =k O
g
g
=0.34
55.6620.886
0.886
=2.649
ft
s
For conservative design
ft
V V =0.75V T =0.7 2.649=1.987
s
bbl 622.4 lb
6000 5.615
Oil mass flowrate W = d ft lb
=76730
24 hours h
bbl lb
14000 62.4 5.615
Water mass flowrate W HL= d ft
=204390 lb/h
24
We determine the density of the liquid mixture of oil and water at the separator operating
conditions by
W W HL 76730 204390
L= O + w =54.662 + 66.955 =63.600lb/ft 3
W +W HL W +W HL 76730+204390 76730+204390
The vapour volumetric flowrate is determined by
WV 66450
Qg = = =20.833 ft 3 /s
3600 g 3600 0.886
V S =t S Q =60 3 23.395=4211.1 ft 3
Obtain L/D from table below
L/D Ratio Guidelines (Monnery and Svrcek, 1994)
Table 27 L/D ratios for different Separator Operating Conditions (Economides, 2009)
L/D = 3
The diameter of the vessel is determined
S
V H +V
1
3
16 (7018.5+4211.1) 13
16( 0.6 ( L ) ) =( ) =31.67 ft
D 0.6 3
D=
The total crossectional area is determined
2
D 2 ( 31.67 )
AT = = =787.75 ft
4 4
The vapour space height HV is set to the larger of 0.2D or 2ft (1 ft if there is no mist eliminator).
H V =0.2 ( 31.67 )=6.334 ft
H V 6.334
x= = =0.2
D 31.67
Determine y
a+cx + e x2 + g x 3+ i x 4
y=
1+bx+ d x 2 + f x 3 +h x 4
a= 4.755930103
b= 3.924091
c= 0.174875
d= 6.358805
e= 5.668973
f= 4.018448
g= 4.916411
h= 1.801705
i= 0.145348.
Calculate minimum length of liht liquid compartment to accommodate the light liquid hold up
/surge
V H +V S 7018.5+4211.1
L2 = = =16.98 ft
A T A V A LLL 787.75109.8116.532
Set interface at height Hw/2
H 25.336
H HL =H = W = =12.668 ft
2 2
Calculate crossectional area of heavy liquid by
H HL 12.668
x= = =0.4 and solving for y = 0.370818
D 31.67
2
A HL= y AT =0.370818 787.75=292.112ft
Crossectional area of light liquid
A =A T AV A HL=787.75109.81292.112=385.828 ft 2
Step 10
Calculate the rising velocity of oil droplets from water (VLH) and that of water droplet from oil
(VHL)
66.95554.662
V HL =k s HL =0.163 =4.02 min
0.5
HL 66.95554.662
V LH =k s =0.163 =2.004 min
HL 1
Calculate the settling times
12 H 12 12.668
t s , HL= = =37.81 min
V HL 4.02
12 H HL 1212.668
s ,= = =75.86 min
V 2.004
t
Determine L1
t S , Q t S , HL Q
HL
,
A HL A
L1=MAX
t S , Q 75.86 50.877 t Q 37.81 23.395
HL
= =13.21 ft > S , HL = =2.29 ft
A HL 292.112 A 385.828
Hence L1 = 13.21 ft = 13.5 ft
Paraffin
Coalescing plates in the liquid section and mesh pad mist extractors in the gas section are
particularly prone to clogging by accumulations of paraffin waxes. Manways, hand-holes, and
nozzles should be provided to allow steam, solvent, or other types of cleaning of the separator
internals. Also, the bulk temperature of the liquid should always be kept above the cloud point of
the crude oil to prevent paraffin wax formation in the separators (Saeid Mokhatab, 2006).
Foam
Foaming crudes offer a special problem in sizing separators. Foam is a mixture of gas dispersed
in a liquid and having a density less than the liquid but greater than the gas. Greater interface
area and longer retention time are needed to remove the gas from the liquid. Horizontal
separators normally give the largest interface area. Retention times of as high as 15 minutes may
be necessary. However, a retention time of 2 to 5 minutes is sufficient in most cases for the
separators to handle foaming crudes. ( American Petroleum Institute , 1989). Foam depressants
will often be effective in increasing the capacity of a given separator. Foam can be reduced by
(1) using a defoaming pack, (2) using defoaming chemicals, and (3) utilizing heat to break it
down. (Saeid Mokhatab, 2006)
Sand
Sand can be very troublesome in separators by causing cutout of valve trim, plugging of
separator internals, and accumulation in the bottom of the separator, thus leading to level control
problems. Traditionally, sand has only been removed once it has collected in the main production
separators. However, removal of sand upstream of these separators reduces sand problems to a
minimum, giving substantial operational benefits. To meet these needs, the Mozley Wellspin
desander has been developed to remove sand effectively in simple, compact systems based on
solid/liquid hydrocyclones, which remove the sand before it enters the separator (NATCO,
2002b). It should be noted that sand problems may be solved by using a filter or desanding
cyclone before the separator; however, filters will quickly block in sandy service and are not
often used.
Sloshing
More and more separators are installed on floaters and other installations subject to motion, e.g.
Tension Leg Platforms. The performance of these separators can be adversely affected by the
motion imposed by waves and wind. The accompanying sloshing will compromise liquid
handling capacity, separation efficiency and the functioning of level instrumentation. A common
way to mitigate the negative impact of sloshing is to install perforated baffles to limit the liquid
motion and damp the waves. However, the layout of these baffles and the selection of the net free
area is critical for their success. With decreasing Net Free Area (NFA) the damping will become
more effective, but in the case of oil/water mixtures the increasing fluid velocity through the
holes may lead to redispersion. (Shell, 2007)
Liquid carryover occurs when free liquid escapes with the gas phase and can indicate high liquid
level, damage to vessel internals, foam, improper design, plugged liquid outlets, or a flow rate
that exceeds the design rate of the vessel. Gas blowby occurs when free gas escapes with the
liquid phase and can be an indication of low liquid level, vortexing, or level control failure.
Emulsions
Scales
Since water injection is being done, there is a likelihood of scale formation. If injected fluids are
not compatible with formation water, scales could results. In this case the field is characterize by
high water cut with high concentration of Barite ion.
Mixing of two incompatible waters usually due to water flooding processes, most commonly
formation water rich in cations such as barium, calcium and/or strontium, mixing with sulfate
rich seawater, goes to the precipitation of sulfate scale which are deposited in the wellbore,
production facilities(Separators) and near wellbore. This mechanism is referred to as
incompatible mixing. Below is the chemical equation for the process. (Yassin, Study of Scale
Formation in Oil Reservoir During Water injection-A review, 2007)
Ba2+ (aq) (Sr2+ or Ca2+) + SO42-(aq) BaSO4(S) (SrSO4 or CaSO4)
Hence there is a need to make provisions for scale control and scale removal
Bader gave a detailed possible locations of scale deposits throughout the flow path of water. The
Figure below depicts the possible locations.
Figure 5 Possible Locations for Scale Deposition (J. Moghadasi, 2007)
Case 1: At the surface water injection facility where incompatible sources of water are
mixed prior to injection.
Case 2: In injection wells where the injected water starts to mix with the reservoir
formation water.
Case 3: Downhole in the reservoir where the injected water displaces reservoir formation
water.
Case 4: Downhole in the reservoir where the mixed injected water and formation water
are about to reach the range of producing wells.
Case 5: Downhole in the reservoir where the mixed (injected and formation) waters are
within the range of producing wells.
Case 6: At the connection of a branched zone where each branch produces different
water.
Case 7: At the manifold of a producing zone where water is produced from different
blocks within the same producing zone.
Case 8: At topside facility where produced fluids are mixed from different production
zones to separate oil and gas from produced waters, or in pipelines that transport
produced fluids to on-shore processing facilities.
Case 9: At disposal wells where produced water is injected for final disposal (Bader,
2006) (J. Moghadasi, 2007)
Problems caused by scale
One major problem caused by scales is corrosion to both downhole and surface equipment. One
important condition for corrosion is that materials surface must be dampened by an electrolyte,
which is a water solution that can conduct an electric current. Naturally occurring reservoir water
contains dissolve salt which makes it a good electrolyte. Some salts do dissolve with a decrease
in temperature and pressure rather than the general principle of precipitations with increasing
temperature and pressure hence creating a good electrolyte. Other factors contributing to
corrosion are pH, salt concentration, and oxygen concentration, along with the velocity of the
flowing medium. Also as a result of turbulence flow of fluid during production, scale deposits or
fragments that are carried in the flowing medium tend to scratch and erode the surfaces of
tubulars and equipment, causing a reduction in the corrosion resistance ability of materials
(Catherine Houska,CSI, TMR Consulting) (Mona El-Said, 2008).
Scales also cause equipment damage including coating and damaging downhole completions
equipment, surface valves and causing restriction to flow in flow conduits by reducing the
internal radius of tubulars due to the growth or the increase of scale thickness. Once scales are
formed, if not treated will continue to grow thicker. Calcium carbonate scale in production tubing
can grow and obstruct over 40% of the flowing area of the tubular whiles restricting access to
lower sections for workovers.
Formation damage around wellbores of both injection and producing wells is caused by scale
formation. Scales can develop around wellbore and cause a reduction in near wellbore porosity
and permeability and even block perforations (Mike Crabtree). Injection water at the wellhead is
usually of lower temperature as compared to reservoir temperature and when this water travels
along the injection pathway and well string the water cools the surrounding formations whiles
gaining heat (temperature) and pressure increment. If the water is saturated at surface conditions
with salts whose solubility decreases with increasing temperatures (e.g. anhydrite), scale may
form along the well-string. Also scale precipitation from the injection water may happen behind
the mixing zone resulting from pressure and temperature changes. This is particularly true of
waters containing salts whose solubility decreases with increasing temperature and decreasing
pressure (Yassin, Study of Scale Formation in Oil Reservoir During Water injection-A review,
2007).
Scale removal techniques must be quick, non-damaging to the separator and effective at
preventing re-precipitation. Best scale removal techniques depends on a knowledge of the type of
and quantity of scale and its physical composition and texture. A poor choice of scale removal
method can results in the promotion of rapid re-occurrence of scale or complex problems such as
formation of other precipitate as a result of the fluids used for treatment. In tubulars and surface
facilities, scale strength and texture play significant roles in the choice of removal technique.
Strengths and textures vary from delicate, brittle whiskers or crystals with high micro-porosity,
to rock-like, low-permeability, low-porosity layers. Scale purity affects its resistance to removal
methods. Scale may occur as single-mineral phases, but is more commonly a mixture of similar,
compatible compounds. For example, pure barium sulphate is hard and of low porosity and thus
not permitting penetration of treatment chemicals.. Mixtures of barium sulfate, often with
strontium sulfate, calcium sulfate or even calcium carbonate, will frequently yield to a variety of
removal methods, both chemical and mechanical. (Mike Crabtree, David Eslinger, Phil Fletcher
Matt Miller, Ashley Johnson, George King, 1999).
Chemical techniques
The first and often used approach to scale removal is chemical technique, especially when scale
is not easily accessible or exists where conventional mechanical removal methods are ineffective
or expensive to deploy.
Unlike salts of carbonate which are acid soluble, sulfate compounds of Barium, Strontium, or
Calcium are acid insoluble (example calcium Carbonate is soluble in Hydrochloric acid). A
major ionic component of seawater is sulfate ion (SO42-) which reacts with the following ions
(Ba2+, Sr2+ and Ca2+) which are naturally found in formation water depending on the fields
geological history. The above mention scales are sparingly soluble in water and as a result can
precipitate out and form deposits (Sulaiman, 2014).Therefore acid treatment cannot be use to
remedy barium scale deposit in separators.
Insoluble scale can be removed by the use of different scale dissolver chemicals. These are
chelate agents such as ethylene-diamine-tetra-acetic acid (EDTA) or diethylene-triamine-penta-
acetic acid (DTPA). A chelating agent is a complex molecule which breaks up the scale by
isolating and tying up the metallic ions in the scale. The application of these dissolvers is time
consuming and is dependent on high temperatures and circulation for optimum effect.
Calcium sulfates are soluble in many chelate dissolvers and is therefore the easiest sulfate scale
to handle. In contrast, barium sulfate is more difficult to handle, being very hard. (Tungesvik,
2013). Variations in the chemical structure of EDTA can also be used to remove non-carbonate
scale such as calcium sulphate and calcium/barium sulphate. Examples:
EDTA U105: used to dissolve CaCO3, iron carbonate and or iron oxide.
EDTA U104; used to dissolve wide variety of scale such as CaSO4 and even mixed scale
that is hard. (M.D. Garba, 2014)
Figure 7 EDTA compound structure (M.D. Garba, 2014)
This technique offers a wide range of tools, applicable depending on the areas of the scale
deposits, but also provides some limitation of ranges applicability. Therefore, selecting the good
method depends on the well position and the scale deposition. Mechanical methods are among
the successful methods in scale removal in tubular and surface facilities. Earlier, explosives
(Shock (e.g. String Shot) 1 to a maximum of 4 strands of 90 grain RDX) were used to rattle
pipe and break the brittle scale, but can easily cause damage to tubular, internal structures of
surface facilities. Very hard scale cannot be removed by explosive or penetrate by chemicals.
Thus, conventional is the next alternative option, this is most used by engineering tools and
machines. Conventional mechanical Method
Thick scales, especially those in tubulars, are often too strong for safe explosive removal and
have too little porosity for effective chemical treatments in a reasonable time frame. For these
deposits, removal usually requires techniques developed for drilling rock and milling steel.
Impact bits and milling technology have been developed to run on coiled tubing inside tubulars
using a variety of chipping bits and milling configurations. The downhole power source is
typically a hydraulic motor or a hammer-type impact tool. Motors are fluid-powered, stator and
rotor combinations that turn the bit. Because scale is rarely deposited evenly on the tubing wall,
milling power requirements vary enormously. When motors cannot supply the power needed for
the bit to cut the scale, the motor stalls and the milling process stops. As a result, scale-removal
rates vary with the type of scale and application, but generally range from about 5 to over 30
linear feet [1.5 to over 9 m] of scale removed from the tubular per hour of milling. The variation
in milling speed depends on the match between the type of deposit and the combination of motor
and mill.
Jetting with Solid Beads (e.g. abrasives) damage potential is moderate to high.
Abrasive slurries; Adding a small concentration of solids, 1% to 5% by weight, to a water jet can
drastically improve its ability to cut through scale. Water jets using abrasive sand are widely used
in the construction and demolition industries for cutting reinforced concrete, and even in
demilitarization for cutting live ammunitions without generating heat or an ignition source.
This technique also shows superior cutting performance in calcium carbonate scale over water
jetting alone
.
Unfortunately, using abrasives such as sand can damage steel tubulars. When scale is completely
removed from tubing, the abrasive jet erodes the steel as efficiently as it does the scale. Should
the jetting tool stall, there is a significant risk of the abrasive jet perforating the steel tubing.
An abrasive jet that cuts scale without damaging tubing must exploit the difference in hardness
between wellbore scale and the underlying steel. One of the key differences between wellbore
scale and tubular steel is that while scale is brittle, steel is prone to ductile failure. A sharp sand
particle will erode the surface of ductile material by a cutting and plowing action. On the other
hand, a hard round particle will bounce off the surface, removing only a small volume of steel
and leaving an impact crater. Scale exhibits brittle failure, so the impact of a hard particle
fractures the scale and ultimately causes substrate disintegration. Scale breakdown is
independent of particle shape. Choosing round rather than sharp, angular particles promotes scale
erosion while reducing damage to steel tubulars. (M.D. Garba, 2014) (Mike Crabtree, David
Eslinger, Phil Fletcher Matt Miller, Ashley Johnson, George King, 1999) (King, 2009)
Removing hard scale
The Blaster Services system features three scale removal techniques that can be applied to a
wide range of scale problems.
The Scale Blasting technique combines the use of Sterling beads abrasive with new
jetting tool for hard-scale removals.
The Bridge Blasting technique uses a powered milling head and abrasive jetting, when
scale completely plugs the tubular.
The Jet Blasting technique uses the new jetting tool with nonabrasive fluids for soft scale
removal.
For hard scales like iron, strontium and barium sulfate, nonabrasive fluid jetting and chemical
treatments are inadequate. The controlled-erosive action of the Sterling Beads abrasive has been
successful in removing every type of scale in tubing, including the most difficult barium sulfate
scales, at rates up to 100 ft/hr [30 m/hr] or more.
The Scale Blasting technique is a particularly good option when the scale encountered in the well
is insoluble, unknown or of variable hardness. The system also provides a safe method to remove
scale from downhole completion equipment. Rate of penetration (ROP) is controlled using a drift
ring that ensures full tubing-diameter cleaning with minimum damage to the steel surface. (Mike
Crabtree, David Eslinger, Phil Fletcher Matt Miller, Ashley Johnson, George King, 1999)
Scale Inhibition
The cost of removing scale is very high and non-profitable and can be as high as 2.5 million
Dollars, while the cost of differed production is even higher. In most cases prevention of scale
formation is preferable through chemical inhibitions to maintain good production. This can range
from basic dilution method to more advanced methods of threshold inhibitions.
Threshold inhibitors
Threshold inhibitors reacts chemically with the scale crystal nucleation side thereby reducing the
crystal growth. Threshold inhibitors are very effective, inhibiting scale mineral formation at
concentrations of 100 time less than balance stoichiometric ratio which significantly reduces cost
of treatment. Most of these compounds are of phosphate components. Examples:
Inorganic polyphosphate compounds
Organic Phosphate esters
Organic Phosphonates
Organic Aminophosphatees
Organic Polymers
These compound minimize scale deposition. They do so by combination of crystal dispersion
and stabilization of scale. (M.D. Garba, 2014) (Mike Crabtree, David Eslinger, Phil Fletcher
Matt Miller, Ashley Johnson, George King, 1999)
For Effective Scale Removal in Separators and Surface Facilities, all internals shall be removable
and installable through the manways and handways provided without welding.
Separator Internal Design
As per API standard and NORSOK standard, the following guidelines are followed when
installing and making choices for separator internal designs
All internals shall be removable and installable through the manways without welding.
Increased internal pressure drop caused by fouling shall be considered for all relevant
scenarios, including, but not necessarily limited to drain pipes (from gas outlet
arrangement).
On floating installations motion/wave-dampening internals shall be installed.
The separator shall operate such that undesired channelling,non-plug flow or short circuit
flows do not occur in both liquid and gas phase. For each project, a Computational Fluid
Dynamics (CFD) analysis for the entire separator shall be carried out to visualize
undesired flow patterns.
Inlet arrangement
The inlet arrangement shall have a documented design, and have a documented high
efficiency towards prevention of foam and emulsion and minimize generation of small
droplets.
The inlet arrangement shall be able to handle slug flow, if expected.
A flow straightening device should be located downstream, the inlet device shall cover
the full sectional area. Care should be taken to avoid plugging due to fouling (scale,
solids and asphaltenes).
Gas outlet nozzles shall be provided with demister arrangements. Pressure tappings
should be installed upstream and downstream gas outlet device, for continuous
measurement of differential pressure to detect clogging.
The liquid collected by the gas outlet device are collected and drained by a drain pipe to
the bottom of the separator. The pipe must be submerged below the Level Alarm Low
Low (trip level) (LALL). Sufficient drainage head must be assured, so that liquid carry-
over through the drain pipe does not occur under any circumstances. The drainage is
normally internal, into the vessel bottom, but should be routed externally in case of
insufficient drainage height. The total differential pressure over the demisting section,
measured in liquid height, shall not be more than 50% of the available drainage height
related to LAHH.
Solids removal
All separators shall, as a minimum, have nozzles for sand removal installed.
When solid production is likely the following requirements apply:
All separators shall have sand pans.
Internal jet water headers shall have nozzles for high volume / low driving pressure with
a fan spray pattern which is overlapping between each nozzle
The headers shall be spaced sufficiently for efficient sand removal by unidirectional jets
towards the sand pan.
Sand removal shall be based upon sand fluidisation rather than sand displacement.
Consideration shall be given towards efficient sand removal along the entire length of the
separator.
Nozzles to be protected against damage or misalignment by human activity during
normal vessel inspection/maintenance.
Nozzles
Manways shall be minimum 24 and installed to prevent trapped volumes when the separator is
drained.
Instrument nozzles shall be located outside the sand accumulation area.
Gas nozzles to flare shall be located such that liquid carry-over is avoided.
Separator inlet and outlet process nozzles (gas, oil, water) shall be sized a minimum of one
standard dimension larger than the connected pipe work. (NORSOK Standard, 2001)
Relief Devices
All separators, regardless of size or pressure, shall be provided with pressure protective devices
and set in accordance with ASME Code requirements. Multiple pressure relieving devices such
as a pressure relief valve in conjunction with a rupture disk may be used to provide the necessary
relieving capacity. The relief valve is normally set at the MAWP. The rupture disk is normally
selected to relieve above the set pressure of the relief valve. The pressure relief devices need not
be provided by the separator manufacturer, but over-pressure protection shall be provided prior
to placing the separator in service. The purchaser should determine who has the responsibility to
furnish relief devices
Corrosion Guidelines
The following guidelines are recommended for determining corrosion considerations for an
applicable vessel.
Well streams that contain water as a liquid and any or all of the following gases are considered to
be corrosive and are due consideration under these specifications:
Oxygen (O2)
Carbon dioxide (CO2)
Hydrogen sulfide (H2S).
The following guidelines are not mandatory but may be used to judge the extent of the corrosive
environment, with respect to carbon steels.
Oxygen:
less than 0.005 ppm in natural brine - non-corrosive
from 0.005 ppm to 0.025 ppm requires - consideration
Greater than 0.025 ppm in natural brine - corrosive.
Carbon dioxide:
less than 600 ppm in natural brine - non-corrosive
from 600 ppm to 1200 ppm requires consideration
Greater than 1200 ppm in natural brine - corrosive.
Hydrogen sulfide.
No lower limit of hydrogen sulfide has been identified as being non-corrosive. With
hydrogen sulfide presence, the environment should be considered corrosive.
NACE MR 0175 (latest edition) should be used for all cases of hydrogen sulfide content
for judgment of the possibility of sulfide stress cracking (SSC) and is extracted as
follows: Systems operating below 65 psia total pressure or below 0.05 psi H2S partial
pressure are outside the scope of this standard.
Should alloy steel or stainless steel be used, other forms of corrosion should be
considered such as, but not limited to, chloride stress cracking.
Some of the other factors that influence corrosion in a given vessel include: temperature,
pressure, fluid velocities, metal stress and heat treatment, vessel surface condition, and
time
Either sacrificial or impressed current anodes may be used, providing that the area of the
corrosion attack can physically be protected by use of these anodes.
Corrosion effects may be controlled with holiday-free internal coatings on all exposed metal
surfaces. NACE RP 0181 and NACE RP 0178 present guidelines and procedures for coating
vessels such as oil and gas separators.
Corrosion effects may be disregarded provided they can be shown to a negligible or entirely
absent on a historical basis. However, the system should be monitored periodically for possible
new corrosion.
Corrosion effects may be reasonably controlled with chemical inhibitor treatments.
Post weld heat treatment is recommended for carbon steel vessels for use in acid gas (containing
hydrogen sulfide and/or carbon dioxide) service. Post weld heat treatment may be required by
ASME Code regardless of corrosion considerations. (American Petroleum Institute, 2009)
( American Petroleum Institute , 1989)
In summary for reasons stated above the following Internal devices are recommended for
installation in the chosen separators.
Diverter plate
Half pipe
Inlet Vane distributor
Inlet Cyclone
Slotted tee distributor
Tangential inlet with annular ring
Deflector baffle
All the above separator design makes provisions and allowances for installation of the above
devices. The dimensions in terms of thickness is specified in the detailed design above. Monnery
and Svrcek 1994 makes room for installation of the above internal device.
Water Handling
Water production presents serious operating, economic, and environmental problems. Production
of water with the crude oil or natural gas reduces the productivity of the well due to the increased
pressure losses throughout the production system. Production of water containing high
concentrations of ions (barium) also results in serious corrosion problems, which add to the cost
of the operation. In most situations, the produced water has no value and should be disposed of.
In other situations, the produced water may be used for water flooding or reservoir pressure
maintenance. The produced water, collected from the separation, emulsion treatment, and
desalting systems, contains hydrocarbon concentrations that are too high for environmentally
safe disposal and hence needed to be treated which brings added operational cost of both
treatment and disposal. The produced water can be treated to meet environmental specifications
before disposal. Filters, precipitators, skim tanks and vessels, plate coalescers, serpentine pipe
packs and other technologies including chemical additions are used for treating produced water
to specification before disposal. (H. K. Abdel-Aal and Mohamed Aggour and M. A. Fahim ,
2003)