You are on page 1of 13

ctbuh.

org/papers

Title: Case Study: CCTV Building - Headquarters & Cultural Center

Authors: Chris Carroll, Arup


Craig Gibbons, Arup
Goman Wai-Ming Ho, Arup
Michael Kwok, Arup
Paul Cross, Arup
Xiaonian Duan, Arup
Alexis Lee, Arup
Ronald Li, Arup
Andrew Luong, Arup
Rory McGowan, Arup
Chas Pope, Arup

Subjects: Architectural/Design
Building Case Study
Structural Engineering

Keywords: Construction
Design Process
Form
Foundation
Performance Based Design
Structure

Publication Date: 2008

Original Publication: CTBUH Journal, 2008 Issue III

Paper Type: 1. Book chapter/Part chapter


2. Journal paper
3. Conference proceeding
4. Unpublished conference paper
5. Magazine article
6. Unpublished

Council on Tall Buildings and Urban Habitat / Chris Carroll; Craig Gibbons; Goman Wai-Ming Ho; Michael
Kwok; Paul Cross; Xiaonian Duan; Alexis Lee; Ronald Li; Andrew Luong; Rory McGowan; Chas Pope
Case Study: CCTV Building - Headquarters & Cultural Center

Authors
Chris Carroll, Paul Cross, Xiaonian Duan, Craig
Gibbons, Goman Ho, Michael Kwok, Richard
Lawson, Alexis Lee, Ronald Li, Andrew Luong,
Rory McGowan, Chas Pope
Arup

Arup is a global firm of designers, engineers,


planners and business consultants providing a
diverse range of professional services to clients
around the world. The firm has over 10 000 staff
working in more than 90 offices in 37 countries.

Arup has three main global business areas


buildings, infrastructure and consulting although
their multi-disciplinary approach means that any
given project may involve people from any or all of
the sectors or regions in which they operate. Arup
has extensive experience in the field of tall
buildings, having provided core multidisciplinary Figure 1. Architects impression of the building
design services for such notable projects as 30 St.
Mary Axe in London, the International Commerce
Center (ICC) in Hong Kong, and the I.Q. Tower in
Doha, Qatar. The new headquarters of China Central Television contains the entire television-making process
within a single building. The 234m tall tower redefines the form of the skyscraper, with the
primary system comprised of a continuous structural tube of columns, beams and braces
Arup
13 Fitzroy Street
around the entire skin of the building. In order to gain structural approval an Expert Panel
London process was necessary, for which a performance-based analysis was carried out to justify the
W1T 4BQ design. This made extensive use of finite element analysis and advanced non-linear elasto-
t: (+44) 020 7636 1531 plastic time history to evaluate the structural behaviour and ensure the building safety under
www.arup.com different levels of seismic event. The leaning form and varied programme, including the need to
accommodate large studio spaces, posed additional challenges for the gravity structure, and
resulted in the introduction of a large number of transfer trusses throughout the tower. Erecting
and connecting the two massive towers presented the structural engineers and contractors
with further design and construction challenges.

Introduction Architectural Concept


This article describes the structural design and China Central Television (CCTV), the countrys
construction of the CCTV Building in Beijing, state broadcaster, plans to expand from 18
including development of the structural con- to 200 channels and compete globally in the
cept, performance-based seismic design and coming years. To accommodate this expan-
Expert Panel Review process. sion, they organized an international design
competition early in 2002 to design a new
Prior to connection, the two Towers would headquarters building. This was won by OMA
(Office of Metropolitan Architecture) and Arup,
move independently of each other due to which subsequently allied with the East China

environmental conditions, in particular wind and Design Institute (ECADI) to act as the essential
local design institute (LDI) for both architecture

thermal expansion and contraction. As soon as and engineering.


The unusual brief, in television terms, was that
they were joined, therefore, the elements at the all the functions for production, management,

link would have to be able to resist the stresses


and administration would be contained on the
chosen site in the new Beijing Central Business

caused by these movements. District (CBD), but not necessarily in one build-

14 | CCTV Building CTBUH Journal | 2008 Issue III


Figure 2. Uniform bracing pattern Figure 3. Unfolded view of final bracing pattern

ing. In their architectural response, however, Development of the structural form two-storey module (see Figure 2). This was
OMA decided that by doing just this, it should From the outset, it was determined that the chosen to coincide with the location of several
be possible to break down the ghettoes that only way to deliver the desired architectural double-height studios within the Towers. A
tend to form in a complex and compartmen- form of the CCTV building was to engage the stiff floor plate diaphragm is therefore only
talized process like making TV programmes, entire faade structure, creating in essence an guaranteed on alternate storeys, hence lateral
and create a building whose layout in three external continuous tube system. This would loads from intermediate levels are transferred
dimensions would force all those involved to give the structure the largest available dimen- back to the principal diaphragm levels via the
mix and produce a better end-product more sions to resist the huge bending forces gener- internal core and the columns.
efficiently. ated by the cranked, leaning form as well as
loads from wind and extreme earthquakes.
However, results of the preliminary analysis
The winning design for the 473,000m, showed that the forces in the braces varied
234m tall, CCTV building (see Figure 1) thus The tube is formed by fully bracing all sides of considerably around the structure, with
combines administration and offices, news the faade. The planes of bracing are continu- particular concentrations near the roof of the
and broadcasting, programme production ous through the building volume in order to Overhang and at the connection to the Base.
and services the entire TV-making process reinforce and stiffen the corners. The system This led to an optimization process in which
in a single loop of interconnected activities is ideally suited to deal with the nature and the brace pattern was modified by adding or
around the four elements of the building: the intensity of permanent and temporary loading removing diagonals (i.e. doubling or halving
nine-storey Base, the two leaning Towers that on the building, and is a versatile, efficient the pattern), depending on the strength and
slope at 6 in each direction, and the nine to structure which can bridge in bending and stiffness requirements of the design, based on
13-storey Overhang, suspended 36 storeys in torsion between the Towers, provide enough a Level 1 earthquake analysis. This also enabled
the air. strength and stiffness in the Towers to deliver a degree of standardization of the brace ele-
loads to the ground, and stiffen up the Base ment section sizes (see Figure 3).
to reinforce the lower Tower levels and deliver
The public facilities are in a second building, loads to the foundations in the most favour-
the Television Cultural Centre (TVCC), and both able possible distribution, given the geometry. This was an extremely iterative process due
are serviced from a third Service Building that to the high indeterminacy of the structure,
houses major plant as well as security. The with each changing of the pattern altering the
whole development will provide 599,000m The tube was originally envisaged as a regular dynamic behaviour of the structure and hence
gross floor area and covers 187,000m, includ- pattern of perimeter steel or steel-reinforced the seismic forces that are attracted by each
ing a landscaped media park with external concrete (SRC) columns, perimeter beams, element. It was carried out in close
features. and diagonal steel braces set out on a typically

CTBUH Journal | 2008 Issue III CCTV Building | 15


collaboration with the architect, since the pat- design engineers who are relieved of any legal Seismic Fortifi- Level 1 Level 2 Level 3
tern of visually expressed diagonals was a key responsibilities by virtue of compliance. The cation Level
aesthetic aspect of the cladding system. Chinese code for seismic design of buildings Description Minor Moderate Severe
(GB50011 2001), sets out its own scope of
Peak ground 0.07g 0.20g 0.40g
applicability, limiting the height of various acceleration
The braced tube structure gives the leaning systems and the degree of plan and vertical
Towers ample stiffness during construction, Average Return 1 in 50 1 in 475 1 in 2475
irregularities. Design of buildings exceeding Period years years years
allowing them to be built safely within tight the code must go through a project-specific
tolerances before they are connected and Probability of 63% in 50 10% in 50 2% in 50
seismic design expert panel review (EPR) and exceedance years years years
propped off each other. The tube system also approval process as set out by the Ministry of
suits the construction of the Overhang, allow- Fortification No Repair- No col-
Construction. Criteria damage able lapse
ing its two halves to cantilever temporarily (remain damage
from the Towers. elastic)
Although the 234m height of the CCTV build- Table1. Seismic performance objectives
ing is within the codes height limit of 260m
The continuous tube has a high degree of for steel tubular structural systems (framed-
inherent robustness and redundancy, and of- tube, tube-in-tube, truss-tube, etc) in Beijing, Elastic superstructure design
fers the potential for adopting alternative load its geometry is noncompliant. The Seismic A full set of linear elastic verification analyses
paths in the unlikely event that key elements Administration Office of the Beijing Municipal were performed, covering all loading com-
are removed. Government appointed an expert panel of 12 binations including Level 1 seismic loading,
eminent Chinese engineers and academics to for which modal response spectrum analy-
closely examine the structural design, focusing ses were used. All individual elements were
Gravity loads are also carried by vertical
on its seismic resistance, seismic structural extensively checked and the buildings global
columns around the buildings central service
damage control, and life safety aspects. In performance verified. Selected elements were
cores, whilst a number of steel transfer trusses
order to engage the expert panel early in the also assessed under a Level 2 earthquake by
are introduced to support the floors in the
design process, three informal meetings were elastic analysis, thus ensuring key elements
Overhang, at high levels in the sloping towers,
held to solicit feedback and gain trust before such as columns remained elastic.
and over large studios in the Podium area.
the final formal presentation and approval in
January 2004.
The elastic analysis and design was principally
Each tower sits on a piled raft foundation. The
performed using SAP2000, a computer-based
rafts vary in thickness up to 7metres, and ex-
As the seismic design lay outside the scope nonlinear structural analysis program, and a
tend beyond the footprint of the Towers to act
of the prescriptive Chinese codes of practice, custom-written Chinese steelwork code post-
as a toe, distributing forces more favourably
Arup proposed a performance-based design processor in Excel. This automatically took the
into the ground. The foundation system is ar-
approach from the outset, adopting first individual load cases applied to the building
ranged so that the centre of the raft is close to
principles and state-of-the-art methods and and combined them for the limit state design.
the centre of load at the bottom of each tower,
guidelines to achieve set performance targets Capacity ratios were then visually displayed, al-
and no permanent tension is allowed in the
at different levels of seismic event. Explicit and lowing detailed inspection of the critical cases
33m long piles. Limited tensions in some piles
quantitative design checks using appropriate for each member. Due to the vast number of
are only permitted in major seismic events.
linear and non-linear seismic analysis were elements in the model (10,060 primary ele-
made to verify the performance for all three ments) and the multitude of load cases, four
Performance-based design approach levels of design earthquake. post-processors were run in parallel for each of
The legal framework in China governing build- the four types of element in the external tube
ing design practice is similar to those of Japan (steel columns, SRC columns, steel braces, and
The criteria for this performance-based design steel edge beams respectively).
and some continental European countries
are beyond those usually applied to such
where the design codes are legal documents
buildings in China, and were set by the design
published and enforced by the state govern-
team in consultation with the expert panel to The post-processor provided a revised element
ment. Design engineers must comply with
reflect the importance of the building both to list which was imported back into SAP2000,
the codes when designing buildings and
the client and to the Chinese Government. The and the analysis and post-processing repeated
structures covered by their scope, but equally
basic qualitative performance objectives were until all the design criteria were met. As the
the codes provide legal protection to the
as follows: structure is highly indeterminate and the load

16 | CCTV Building CTBUH Journal | 2008 Issue III


...structure CCTV

Maybe we could best describe it as a tube


folded in space All the outer surfaces are
covered in a diagonal steel mesh and this mesh is
folded and allows the weight to flow around the
building until it finds the ideal path to the
ground.

Ole Scheeren, Partner at the Office for Metropolitan Architecture, and
architect of the CCTV Building discusses the buildings unique
structural system. From CCTV, the new state television headquarters,
will broadcast Chinas rise, The Times, August 9th, 2008. Figure 4. Foundation settlement analysis

paths are heavily influenced by stiffness, each Inelastic deformation acceptance limits for the tory analysis method were used to determine
small change in element property moves load key structural brace members in the con- the seismic deformation demands in terms of
around locally. Optimizing the elements only tinuous tube were determined by non-linear the maximum inelastic inter-storey drifts and
for capacity would result in the entire load numerical simulation of the post-buckling be- the maximum inelastic member deformation.
gradually being attracted to the inside corner haviour. LS-DYNA, commonly used to simulate These deformation demands were compared
columns, making them prohibitively large, so car crash behaviour, was used for this work. against the structures deformation capacities
careful control had to be made of when an The braces are critical to both the lateral as storey-by-storey and member-by-member to
elements section size could be reduced and well as the gravity systems of the building and verify the seismic performance of the entire
when there was a minimum size required to are also the primary sources of ductility and building. All global and local seismic deforma-
maintain the stiffness of the tube at the back seismic energy dissipation. Non-linear numeri- tion demands were shown to be within their
face. cal simulation of the braces was needed to respective acceptance limits.
establish the post-buckling axial force/axial de-
formation degradation relationship to be used
To further validate the multi-directional modal in the global 3-D non-linear simulation model. Foundation design
response spectrum analyses, Level 1 time- It was also used to determine the inelastic de- The design of the foundations required that
history checks were also made using real and formation (axial shortening) acceptance limit the applied superstructure loads be redistribut-
artificially-generated seismic records. in relation to the stated performance criteria. ed across the raft so as to engage enough piles
Post-buckling inelastic degradation relation- to provide adequate strength and stiffness. To
ship curves illustrate the strength degradation validate the load spread to the pile group, an
Non-linear superstructure seismic design iterative analysis process was used adopting a
as the axial shortening increases under cyclic
For the performance-based design, a set of non-linear soil model coupled with a discrete
axial displacement time history loading. The
project-specific design rules were proposed by model of the piled raft system (see Figure 4).
acceptable inelastic deformation was then
the design team and reviewed and approved Several hundred directional load case com-
determined from the strength degradation
by the expert panel, for example allowable binations were automated in a spreadsheet
backbone curve to ensure that there was suf-
post-yield strains in each type of element. controlling the GSRaft soil-structure interaction
ficient residual strength to support the gravity
Appropriate linear and non-linear seismic solver.
loads after a severe earthquake event.
response simulation methods were selected
to verify the performance of the building
under all three levels of design earthquake. Having established the inelastic global The analysis iteratively modelled the redistri-
Seismic force and deformation demands were structure and local member deformation bution of load between piles when their safe
compared with the acceptance limits estab- acceptance limits, the next step was to carry working load was reached. The analysis was
lished earlier to rigorously demonstrate that all out non-linear numerical seismic response repeated for each load case until the results
three qualitative performance objectives were simulation of the entire 3-D building subjected converged and all piles were within the allow-
achieved. to Level 2 and Level 3 design earthquakes. able capacities. Finally, the envelope of these
Both the non-linear static pushover analysis analyses was then used to design the raft
method and the non-linear dynamic time his- reinforcement.

CTBUH Journal | 2008 Issue III CCTV Building | 17


Figure 5. Connection analysis Figure 6. Transfer trusses

Connection Design before the braces buckle or yield - assuming columns, spanning between the internal
The force from the braces and edge-beams the maximum probable material properties - core and the external tube structure. They
must be transferred through and into the to evaluate the stress magnitude and degree are typically two storeys deep and located in
column sections with minimal disruption to of stress concentration in the joints. The shape plant floors so as to be hidden from view and
the stresses already present in the column. The of the butterfly plate was then adjusted by to minimize the impact on floor planning. The
connection is formed by replacing the flanges smoothing out corners and notches until po- sizes of the transfer trusses mean that they
of the steel column with large butterfly plates, tential regions of yielding were minimized and could potentially act as outriggers linking
which pass through the face of the column the degree of stress concentration reduced to the external tube to the internal steel cores -
and then connect with the braces and the levels typically permitted in civil and me- undesirable as this would introduce seismic
edge-beams. No connection is made to the chanical engineering practice. CAD files of the forces into the relatively slender internal cores.
web of the column to simplify the detailing resulting geometry of the joints were exported The transfer trusses are thus connected to the
and construction. from the finite element models and used for internal cores and the external columns at
further drawing production. singular pin-joint locations only.

The joints are required to behave with the


braces, beams, and columns as strong joint/ Gravity Structure and Transfer Trusses Further transfer trusses are introduced to sup-
weak component. The connections must Whilst the external tube structure slopes port internal columns within the Overhang,
resist the maximum probable load delivered to give the unique geometry, the internal and to support floors above the large studios
to them from the braces with minimal yielding steel columns and cores are kept straight for in the Base (see Figure 6). As with the butterfly
and a relatively low degree of stress concentra- functional layout and to house lift and services plates, forces in the truss diagonals are carried
tion. High stress concentrations could lead to shafts. This resulted in a different configuration only by the flanges at connections, with the
brittle fracture at the welds under cyclic seis- for every floor - the spans from core to faade, webs stopping short of the chords to simplify
mic loading, a common cause of failure in con- and internal column to faade, change on construction.
nections observed after the 1994 Northridge each level.
earthquake in Los Angeles. Two connections,
representing the typical and the largest cases, Physical Testing
were modelled using powerful finite element Sloping cores were considered, to allow As part of the expert panel approval process,
analysis software such as MSC/NASTRAN (see consistency of floor plate layout, but ruled there was a requirement for three physical
Figure 5). out due to constraints on the procurement of tests to be carried out, in order to verify the
the lift systems. Therefore, additional columns analytical calculations:
are needed on upper storeys where the floor 1. Joint Test (butterfly plate): Beijings
The models were analyzed, subjected to the spans increase significantly on one side of the Tsinghua University tested a 1:5 scale
full range of forces that can be developed core. Transfer trusses support these additional model of the column-brace joint to confirm

18 | CCTV Building CTBUH Journal | 2008 Issue III


its performance under cyclical loading, in the 150mm thick composite floor slabs. In all The PTS outlined specific measures to address
particular the requirement that failure takes cases, the physical tests correlated closely with key issues in the construction of the building
place by yielding of the element rather the analysis. including:
than at the connection. 1. Construction sequencing and its effect
2. Composite column: Tongji University in Handover and Tender on the final stress in the structural elements
Shanghai tested 1:5 scale models of the In August 2004, after receiving approval for the 2. Ensuring the building and elements are
projects non-standard steel reinforced col- structural design from the Chinese Ministry of constructed to the designed setting out
umns. These tests resulted from concerns Construction, Arup handed over the extended and positions, within allowed construction
that the high structural steel ratio might preliminary design (EPD) documents to ECADI, tolerance
lead to reduced ductility. which then began to produce the Con- 3. Construction and linking of the overhang
3. Shaking table test: A 7m tall 1:35 scale struction Documents (CDs). Arup, however,
model of the entire building was con- maintained an extensive involvement on
structed to test the structural performance completion of the EPD design phase, includ- Further requirements were contained in
under several seismic events including a ing production of tender documentation for separate Construction Stages and Movement
severe Level 3 earthquake. The tests were the main structure and interaction with the reports, complementary to the PTS.
undertaken by the China Academy of Build- tenderers for the works, as well as being part of
ing Research (CABR) in Beijing, using the the tender review process. Together with the
largest shaking table outside America or architects OMA, Arup also had a continuous Some of the detailed issues identified in the
Japan (see Figure 7). site presence during construction, working PTS included:
with the contractor in implementing the 1. Weight audits placing the onus on the
design. contractor to convey the weight added to
This large-scale shaking table test was of
the building at stages during the construc-
particular interest. In China it is the norm for
tion. The contractor would then use this
buildings that fall outside the code to be thus Particular Technical Specification
information in the prediction of deforma-
studied, and the CCTV model was the largest One of the key tender documents was the
tion and movements, which would then
and most complex tested to date. The nature Particular Technical Specification (PTS), which
enable calibration and presetting of the
of the testing required the primary structural placed several requirements on the contractor
building during construction.
elements to be made from copper (to replicate that were specific to the design of CCTV.
as much as possible in a scale sense the ductil- 2. Specific monitoring of the tower defor-
ity of steel). The model also included concrete mation.
floors (approximately 8mm thick) to represent 3. Specific monitoring of deformations of
the foundations.
4. Presetting of the structure.
5. Monitoring of daily variation in the dif-
ference between the position of connec-
tion points as the Overhang construction
advanced prior to linking.
6. The requirement to connect when the
relative movement between the connec-
tion points of the Overhang would be
manageable.
7. A means of showing that the extent of
connection was commensurate with the
daily movement measurement, so as to
prevent the connection ripping apart once
it had been firmly made.
8. A requirement for post-installing certain
key structural elements.

Figure 7. Shake table test model

CTBUH Journal | 2008 Issue III CCTV Building | 19


Figure 8. Alternative methods of constructing the Overhang

Construction sequencing the lower part of the Overhang at ground level sis and is one of Chinas foremost universities.
The final stresses in the building are linked and strand jack the assembly into position; The independent site supervisor was Yuanda
to its construction sequence. In addition to and constructing incremental cantilevers from International.
regular gravity and lateral forces acting on the each Tower until the two met and connected
structure, there are significant additional con- at the centre of the Overhang (see Figure 8).
struction stage forces due to the fact that the The latter approach was as described in Arups Excavation and foundations
building comprises two separate leaning Tow- documentation, though any construction The ground-breaking ceremony took place
ers with cantilever up until the point at which approach was deemed acceptable provided it on 22 September 2004, and the excavation of
they are joined to become one structure. The could satisfy the locked-in stress limits defined 870 000m3 of earth began the following
additional bending and overturning stresses in the Particular Specification. month under an advance contract. Strict
that get locked into the Towers and founda- construction regulations in Beijing meant
tions prior to joining depend on the amount that spoil could only be removed at night:
of structure and faade completed at the time China State Construction Engineering Corpo- nonetheless, up to 12 000m3 of soil was re-
of connection. ration (CSCEC) was awarded the main contract moved each day, the entire excavation taking
in April 2005. CSCEC tendered on this third 190 days. Dewatering wells were also installed,
approach. since the groundwater level was above the
In essence, the greater the construction load maximum excavation depth of 27.4m below
applied to the building prior to connecting existing ground level.
the two Towers, the more this would manifest Construction team
itself as increased locked-in base moments in CSCEC, a state-owned enterprise under the
the Towers. After the connection was made, administration of the central government, The two Towers are supported on separate
any added weight would result in a thrust was established in 1982 and is Chinas largest piled raft foundations with up to 370 rein-
between the two Towers via the Overhang. construction and engineering group. CSCEC forced concrete bored piles beneath each,
now enjoys an international reputation, having typically 33m long and up to 1.2m in diameter.
completed an increasing number of projects In total, 1242 piles were installed during the
As part of the Particular Specification, the abroad including the Middle East, South spring and summer of 2005.
Construction Sequence report defined an America and Africa. The steelwork fabricators
upper and lower bound range of permissible were Grand Tower, part of the Bao Steel group
locked-in stress, allowing the contractor some based in Shanghai (Chinas largest steel manu- The Tower rafts were constructed over Christ-
flexibility in choosing his final construction facturer), and Jiangsu Huning Steel, based in mas 2005. The 7m thick reinforced concrete
sequence. Jixing, Jiangsu Province. slabs each contain up to 39 000m of concrete
and 5000 tonnes of reinforcement. Each raft
was constructed in a single continuous pour
A number of construction methods were Other members of the team were Turner Con- lasting up to 54 hours. At one stage, 720m3
proposed for the Overhang. These included struction (USA), providing support to CSCEC of concrete was being delivered every hour,
constructing of a temporary tower the full on construction logistics, China Academy of using a relay of 160 concrete trucks from three
162m height to the underside of the Over- Building Research (CABR), one of the major suppliers. Chilled water pipes were embed-
hang, providing a working platform to build design institutes in Beijing, and Tsinghua Uni- ded inside the pour and temperatures were
the Overhang connection in situ; constructing versity, which carried out the presetting analy- monitored for more than two weeks to ensure

20 | CCTV Building CTBUH Journal | 2008 Issue III


Figure 10. Typical baseplate

that the concrete did not experience too high The elements were lifted into place by two being lifted a short distance off the ground,
a temperature gradient during curing. The two tower cranes working inside each Tower, using a chain block. This simplified the erec-
rafts, poured within days of each other, were including M1280D cranes imported from tion process at height.
the largest single continuous concrete pours Australia the largest ever used in Chinas
ever undertaken by Chinas building industry. building industry.
In total, 133 343m of concrete went into the The vertical core structure was generally
foundations of the Towers and podium. erected three storeys ahead of the perimeter
Each crane not only had to be raised up to frame. This meant that the perimeter columns
14 times during construction, but also skewed could be initially bolted in place and braced to
The seismic analysis indicated that some col- sideways up to four times when it reached the core columns with temporary stays, then
umns and their foundation piles could experi- the upper levels, to maintain position relative released from the tower crane before final
ence tension during a severe design earth- to the edges of the progressively shifting surveying and positioning. The welders could
quake. Some of the perimeter columns and floorplate. then start the full-penetration butt welds re-
their baseplates were therefore embedded 6m quired at every connection: a time-consuming
into the rafts to enhance their anchorage (see task requiring shift work to achieve a continu-
Figure 9). Certain piles were also designed for Due to the 6 slope of the Towers, the perim- ous 24-hour process.
tension. eter elements needed to be adjusted to ap-
proximately the correct installation angle after
The maximum plate thickness of the columns
Steelwork construction is 110mm and the volume of weld sometimes
The first column element was placed on reaches as much as 15% of the total con-
13 February 2006. In total, 41 882 steel ele- nection weight. At the extreme case, a few
ments with a combined weight of 125 000 connection plates near the base of the Tower
tonnes, including connections, were erected required a 15m long site splice of 100mm thick
over the next 26 months, at a peak rate of 8000 plate, each taking a week to complete. The
tonnes per month. plate thickness of some elements exceeded
the maximum assumed in design, which had
been determined by likely steel availability.
During the design it was thought that some Onerous material specifications were laid
high-grade steel elements would need to be out for thick sections to ensure satisfactory
imported, but in the end all the steel came performance.
from China, reflecting the rapid advances of
the countrys steelwork industry. Steel sections
were fabricated at the yards of Grand Tower The geometrical complexity made construc-
in Shanghai and Huning in Jiangsu, and then tion slower than for other steel-framed build-
delivered to site by road (see Figure 10), with ings. Although the rate of erection increased
a size limit of either the tower crane capacity as the contractor became more familiar with
(80 tonnes) or the maximum physical dimen- the process, CCTV has no typical floors.
sions that could be transported (18m length). Nevertheless, up to six storeys per month
Figure 9. Column embedded in raft
was achieved for the relatively uniform

CTBUH Journal | 2008 Issue III CCTV Building | 21


(a) Tower deflects under its own (b) Preset upwards and backwards. (c) Resultant: no deflection under
weight. self-weight.

Figure 11. Basic concept of presetting

levels at Tower mid-height. Concreting the The presetting process was further com- The contractor commissioned CABR to
composite columns and floor slabs took plicated by the fact that when completed, carry out the movement monitoring, while
place several storeys behind steel erection, off almost all the columns have different stresses, Tsinghua University performed the building
the critical path. depending on the ratio of gravity to seismic movement prediction and presetting analysis
loads, unlike in a conventional building as required by the Arup specification. This
where all perimeter elements will be similarly required a more detailed time history analysis
Movements and presets stressed. As a result, different presets were of the final construction sequence, dividing
Arups calculations included a construction required on different sides of the Towers, the process into 53 assumed stages based
time history analysis to take account of the the exact values also depending on the final on estimated progress for the perimeter
effects of the predicted construction method construction sequence. In practical terms, tube, core, slab concreting, faade, services,
and sequence on the completed buildings this meant fabricating the columns longer on and interior fit-out. This was compared with
deflections and built-in forces. This indicated one side of each Tower, so that they would the results of the movement monitoring,
that the corner of the Overhang would move eventually shorten to the correct geometry and checks and adjustments were made as
downwards by approximately 300mm under under load. necessary.
the buildings dead weight. For there to be no
overall downward deflection under this load
case, the whole structure needed to be pre- Presetting was in two stages: at the fabrica- The studies found that the movements
set upwards and backwards to compensate tion yard, based on the results of the ana- during Overhang construction would be
(see Figure 11). The contractor continuously lytical modelling, and then at installation, if far more significant than those at the earlier
monitored construction to ensure that the required, to suit the actual building deforma- stages caused by the Towers lean only. Due
actual movements corresponded to analysis tion as monitored during the course of con- to the large number of variables needed for
assumptions and predictions. struction. Progress of floor plate concreting the presetting calculation (variable axial stiff-
(a) Tower deflects under its own weight was also controlled to suit the assumptions ness, final construction sequence, foundation
made in the presetting estimation. settlement, thermal movements, etc), the
(b) Preset upward and backward main focus of the analysis was on the critical
(c) Resultant: no deflection under self-weight Overhang construction stage. By the time

...safety vs. cost

It does not take a NIST report or a rocket scientist to figure out that requiring additional exit stairs
will improve overall occupant evacuation times The bigger question that needs to be answered is at
what economic cost to society?

David Frable, a General Services Administration fire safety engineer, asks the International Code Council to repeal stronger safety requirements for new
skyscrapers that were added to the countrys most widely used building code last year, arguing that they would be too expensive to meet. From
Agency Fights Building Code Born of 9/11, The New York Times, September 7th, 2008.

22 | CCTV Building CTBUH Journal | 2008 Issue III


Figure 12. The Overhang before connection Figure 13. The seven initial connection elements

Overhang erection commenced, there was al- Fabrication accuracy was therefore crucial so that final adjustments could be made to the
ready much movement data from the Tower for this part of the structure, with erection length of the linking elements while they were
construction that could be used to calibrate being carried out piece-by-piece 160m above still on the ground prior to installation.
the analysis. ground level. Trial assembly of these trusses
at the fabrication yard prior to delivery was
essential to ensure that minimal adjustment The contractor chose to connect seven link
Overhang construction would be needed at height. elements at the inside corner of the Over-
Construction of the Overhang began after the hang during this initial connection phase (see
steelwork for the two Towers was completed Figure 13). These were lifted into place to
to roof level. Tower 2 Overhang began first, in Prior to connection, the two Towers would less than 10mm tolerance and temporarily
August 2007, and the structure was cantile- move independently of each other due to en- fixed with pins in the space of a few minutes
vered out piece-by-piece from each Tower vironmental conditions, in particular wind and at 9.00am on 8 December 2007, before the
over the course of the next five months (see thermal expansion and contraction. As soon Towers started to move relative to each other
Figure 12). This was the most critical construc- as they were joined, therefore, the elements (see Figure 14). The pins allowed them to carry
tion stage, not only in terms of temporary at the link would have to be able to resist the the thermal loads while the joints were fully
stability but also because its presence and the stresses caused by these movements. As a welded over the following 48 hours.
way it was built would change the behaviour result, the connection strategy required a delay
of those parts of the Tower already construct- joint that could allow a sufficient number of
ed. The forces from the two halves of the partly elements to be loosely connected between The specification originally called for the
constructed Overhang would be concentrated the Towers, then locked off quickly to allow connection to take place while ambient
in the Towers until such time as the two halves them all to carry these forces safely before any temperatures were between 12-28C (i.e. close
were sufficiently linked and the building relative movement took place. to the standard room temperature assumed
became a single continuous form, when the in analysis). Since the connection took place
Arup specified that this should take place early during winter, the temperature at the time was
loads would start being shared between all of in the morning on a windless day, when the
the permanent structure. around 0C, so further analysis of the structure
two Towers would be at a uniform tempera- was carried out by the design team to check
ture and the movements at a minimum. the impact of the increased design thermal
The bottom two levels of the Overhang range.
contain 15 transfer trusses that support the in- In the lead-up to connection, Arups specifi-
ternal columns and transfer their loads into the cation required one week of monitoring of
external tube. In the corner of the Overhang, Once the initial connection was made, the
global and relative movements so that the remainder of the Overhang steelwork was
these trusses are two-way, resulting in some correct dimensions of the linking elements
complex 3-D nodes with up to 13 connecting progressively installed. With the building now
could be predicted. The relative movements acting as one entity, the Overhang was prop-
elements, weighing approximately 33 tonnes of the Towers during the day were found to be
each. ping and stabilising the two Towers, and con-
around 10mm. The contractor made the final tinued to attract locked-in stresses as further
measurements of the gap exactly 24 hours be- weight was applied. In addition to the primary
forehand (i.e. at identical ambient conditions) steelwork elements, a continuous steel

CTBUH Journal | 2008 Issue III CCTV Building | 23


Figure 14. Installation of first connection element Figure 15. The completed tower

plate deck up to 20mm thick was laid down Key elements at the intersection of the The performance-based design approach
on the lowest floors of the Overhang to resist Towers and podium were also post-fixed pioneered on CCTV has since been used suc-
the high in-plane forces that were part of this for similar reasons. In addition, this process cessfully for many other projects in China. The
propping action. The concrete floor slabs were enabled the architectural size of the elements structure of the CCTV building was complet-
only added once the entire primary structure to be controlled, while giving the contractor ed in May 2008, with the faade finished by
had been completed, so as to reduce the additional flexibility to deal with construction the start of the Beijing Olympic Games.
loads during the partially-constructed stage. movements.
Again, the construction stage analysis needed
to take account of this sequencing. That the contractor could construct such a
Delay joints were introduced between the vast and complex building with few delays
Towers and the Base to allow for differential was a credit to the design team and to
A topping-out ceremony on 27 March 2008, settlement between the two structures CSCEC, in particular the attention paid to de-
on a specially-constructed platform at the foundations. It should be noted that over half vising a feasible construction sequence from
corner of the Overhang, marked the comple- the predicted settlements were expected to an early stage, and the careful thought about
tion of the steelwork installation. take place after the Towers were constructed the buildability of the primary structural ele-
to their full height, due to the disproportion- ments and connections.
ate effect of the Overhang on the forces in
Post-installation of key elements certain columns. These were fully closed after
Arups early analysis showed that the corner completion of the main structure. Further References
columns on the inside faces of the Towers late-cast strips were also provided at several (1) CARROLL, C, et al. CCTV Headquarters, Beijing, China:
Structural engineering design and approvals. The Arup
would attract a huge amount of dead load locations around the basement to control Journal, 40(2), pp3-9, 2/2005
from the Overhang, and thus have little spare shrinkage. (2) CARROLL, C, et al. CCTV Headquarters, Beijing, China:
capacity for resisting seismic loads. Increas- Building the structure. The Arup Journal, 43(2), pp40-51,
ing the column sizes was rejected since they 2/2008
would become stiffer and hence attract even CONCLUSIONS
higher loads. Instead, the corner column and The project demonstrated that a building Credits
brace elements directly below the Overhang with many complex technical challenges Client: China Central Television
were left out until the end of construction, could be delivered successfully within a Architect: OMA Stedebouw BV, Ole Scheeren and Rem
forcing the dead loads to travel via the diago- tight programme. An international team Koolhaas
nals down adjacent columns and enabling was mobilized to make best use of the firms Engineer: Arup

the full capacity of the corner elements to be experience and knowledge, which required Local Design Institute: East China Architectural Design and

available for wind and seismic loads in the seamless co-ordination between a number of Research Institute Co Ltd (ECADI)

as-built condition. locations and cultures.


Illustrations
All Arup except Figure 1 ( OMA), Figure 13 ( CSCEC)

24 | CCTV Building CTBUH Journal | 2008 Issue III

You might also like