Professional Documents
Culture Documents
2
3
Instructor
Zahidul Islam
4
Aim 5
Introduction
Company Overview
Problems Identification
and Suggestion
Conclusions
Recommendation
Introduction 7
Established in 2003.
Development Ltd.
Handed Over Projects:
After the site survey Nirapad Real Estate & Development Ltd.
employed a designer and architect, from:
Talukder Designer & Consultant.
House# 11, Road# 08, Sector# 09, Uttara, Dhaka.
Structural Designer:
Eng. Kawser Talukder
B.Sc. Engg. (BUET)
Architect:
Mahmud-Ul-Aziz
DIT Plan
16
17
Use of Materials 18
Reinforcement
Stone
Cement
Brick
Sand
Sylhet sand (F.M. 1.8-2.5)
Fine sand (F.M. 1.1-1.4)
Plumbing and Sanitary Fittings and
Fixtures
Electrical Fittings and Fixtures
Tiles
Paint
Estimate 19
Bottom layer:
Binding for bottom layer
reinforcement, mainly use two
categories.
First one is short direction
reinforcement.
Second one is long direction
reinforcement.
Crank bar :
Crank bar should be used in both way of slab.
Brick Work
Working procedure of brick
wall:
1st lift brick work was, for 5" wall 4' and 10" wall 5'.
Lintel Work
Working procedure of lintel:
After completed 7' height brick wall,
lintel mainly made above the door and
window.
background:
At first clean the masonry and
RCC surface properly.
High part
If any part of the walls so
high, then cut the high part.
If required plaster thickness more than 1". Did the plaster in 2 coats
(scratch and finish coat).
Finished the surface with Gauging trowel, Wooden float and Floating rule.
34
Sewerage pit
waste water
pit
Figure: GI pipe
Problems Identification & Suggestion 38
I have supervised slab work, brick work, plaster work, sanitary & plumbing
work etc.