DEFECT REPORT IBH

A B C
1 ROOM VIESTA (ELECTRICAL) VEISTA (AIRCOND)
2 1st Floor
3 101
4 102
5 103
6 104 Leaking (Pipe Bath) Warm
7 105
8 106 Leaking (Pipe Sprinkler)
9 107 Lighting LED yellow (R&L)
10 108
11 109 DB-ROOM (Noisy)
12 110
13 111
14 112

15 Riser Between Room 113-114


113 Leaking Pipe Aircond
16 114
17 115 Leaking (Pipe Bath)
18 116
19 2nd Floor
20 201 Warm
21 202
22 203
23 204
24 205 Ligthing Bath (Malap)
25 206
26 207
27 208 Warm
28 209
29 210
30 211
31 212
32 213
33 214

34 Ligthing Bath (Not Functional)


215 Slot Card Beeping
35 216 DB-ROOM (Noisy)
36 3rd Floor
37 301
38 302 Leaking (Pipe Bath) Warm
39 303
40 304
41 305 Warm
42 306
43 307
44 308 Warm
45 309 Warm
DEFECT REPORT IBH

A B C
46 310 Warm
47 311
48 312
49 313 Leaking (Bath)
50 314
51 315
52 316 Warm
DEFECT REPORT IBH

A B C
53 ROOM VIESTA (ELECTRICAL) VEISTA (AIRCOND)
54 4th Floor
55 401
56 402 Digital Door Lock
57 403
58 404 Warm
59 405 Lighting (Bath) Warm
60 Riser Between Room 405-406 Riser Between Room 405-406
406 Leaking Pipe Bath Leaking Pipe Aircond
61 407 Warm
62 408 Leaking
409 Ligthing LED(R) Not Functional Riser Between Room 409-410
DB-ROOM (Noisy) Leaking Pipe Aircond
63 Riser Between Room 409-410
Leaking Pipe Bath

64 410
65 411 Ceiling Sprinkler (Need Plastering)
66 412
67 413
68 414
69 415 Leaking (Pipe Bath) Warm
70 416
71 5th Floor

72 501

73 502
74 503
75 504
76 505
77 506

78 507 warm

79 508 warm
80 509
81 510

82
511
83 512
84 513 Lighting LED (R)

85 514
86 515
DEFECT REPORT IBH

A B C

87 516 Warm
DEFECT REPORT IBH

D E F
1 FURNITURE YUDAH PAINTING
2
3
4
5
6 Almari Wall
7 Leaking (Silicon Window) Ceiling Bath
8
9
10
11 Wall
12 Wall
13 Ceiling & Wall
14

15
Leaking (Wall)
16
17
18 Ceiling (Need Compound)
19
20 Wall
21
22
23
24
25
26
27
28
29 Leaking Wall
30
31 Wall
32 Leaking Wall
33 Compound Ceiling

34

35
36
37
38 Door Frame Compound
39
40 Wall
41 Hair Dryer (Not Functional)
42 Wall
43
44
45
DEFECT REPORT IBH

D E F
46 Wall
47
48
49
50 Ceiling Crack
51
52
DEFECT REPORT IBH

D E F
53 FURNITURE YUDAH PAINTING
54
55 Door Frame Compound
56 Wall Corridor Leaking
57 Door Frame Compound Wall
58 Ceiling Compound Wall
59
60

61 Silicon Window
62

63

Wall
64 Leaking Wall (Critical)
65 Door Frame Compound
66 Touch Up Ceiling Wall
67
68 Door Stopper
69
70 Ceiling Need Plastering
71
Leaking Wall
72 Riser Between Room 501 -Room Wall
502 (Paitung)
73 Compound Bath Door
74 Wall
75
76
77 Incoming Water Supply to Flush
Pipe Tank
Riser Between Room 507 -Room
78
508(Paitung)
79 Wall
80 Leaking Wall
81 Leaking Wall

82 Incoming Water Supply to Flush


Pipe Tank
83
84 Riser Between Room 513 -Room
514 (Paitung) Wall
85 Leaking Window Wall
86 Leaking Wall Wall
DEFECT REPORT IBH

D E F

87 Riser Between Room 513 -Room Wall


514 (Paitung) Up & Down
Leaking Wall