Ensuring a Comfortable Hotel Stay

PROJECT NAME
High-end Hotel
Chiller Replacement

PROJECT LOCATION
Atlanta, Georgia

PROJECT TEAM
Owner: International
Hotel Company
Contractor: McKenneys, Inc.

MARKETS
Hospitality

M
cKenneys installed two machineswith new isolation and control magnetic-bearing chiller. An air-cooled tem-
new high-end chillers for a valveswithout any disruptions for guests. porary chiller maintained temperatures during
prominent hotel in Atlanta. the renovation along with the existing chiller
THE SOLUTION during phase one. Phase two included the
THE CHALLENGE The McKenneys team conducted a campus install of an interim air cooled chiller working
A popular flagship hotel wanted to replace tour to ensure hotel leadership that it could with the magnetic bearing chiller.
both of its 30-year-old centrifugal chillers. manage electrical services, piping, rigging,
With 90-percent occupancy during a typically insulation, automation upgrades and general THE RESULTS
hot Atlanta summer, the hotel couldnt risk contracting. Following detailed planning, the The new chillers were installed on time, within
downtime. McKenneys had to remove the team used a series of pipe freezes to shut down budget and helped the customer realize close
old chillers and install two new chilled water the chiller plant in preparation for the new to $40k in Georgia Power rebate incentives.

404-622-5000 704-357-1200
info@mckenneys.com info@mckenneys.com
1056 Moreland Industrial Boulevard 3601 Performance Road
Atlanta, Georgia 30316 www.mckenneys.com Charlotte, North Carolina 28214
2017 McKenneys, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A.
McKenneys, Inc. and the McKenneys, Inc. logo are registered trademarks of McKenneys, Inc. All other trademarks are the property of their respective owners.
The content of this document is not intended as an endorsement.

You might also like