Professional Documents
Culture Documents
Measurement Book
Sub-Contractor Jaganath Site
Period 26-May-16 25-Jun-16 Shift
Sno Description
Fixing of scaffolding and Unit No L B/H H
dismantling / shifting of
1 scaffolding to the next slab
including fixing of walers, H-Beams
Column
and Plywood. Cum 16 1.525 1.525 4.8
RKP STATION
Day/ Night
178.61 35 6,251
40.00 20 800
47,791
L&T-SUCG JV CC-27 DMRC Project Delhi
Daily Labour Report
SSK
Date USK OT
Sup OT Painter OT Carp
89 264.5 - ###
- -
SSK
Date USK OT Khalas
Sup OT Plmb OT
i
80 282
SSK
SSK
Date USK OT
Sup OT Fitt OT Carp
Shift Day
Site RKP
SKL SSK
### - 27 75
27 75
oject Delhi
t
Shift Day/Night
Site RKP
SKL
- - 19 48 26 93
282 45 141
oject Delhi
t
Shift Day/Night
Site RKP
SKL
93 - - ### - 50 125
307 50 125
oject Delhi
t
Shift Day/Night
Site RKP
SKL
OT Mas OT Rig OT Wel OT
12 59
12 59
L&T-SUCG JV CC-27 DMRC Project Delhi
Measurement Book
Sub-Contractor Amba Construction
Period 26-May-16 25-Jun-16
32752 0 12096
MD
OT 12167 0 8344
14347
OT 35673 15736
Site : RKP
Shift: Day/Night
Total
44848
20511
65359
2242
67,601
Delhi
Site : RKP
Shift: Day/Night
Total
145824
65756
211580
0
211,580
Delhi
Site : RKP
Shift: Day/Night
Total
121629
53950
175579
6081
181,661
Total
0
0
0
0
0
Delhi
Site : RKP
Shift: Day/Night
Total
80080
38545
118625
4004
122,629
Amba Construction
Sno. Activities Sub-Activities Unit
Wooden Lagging Shifting No
Wooden scrap shifting No
1 L/C for Internal carting of material Doka Shifting No
TMT scrap & offcut shifting No
Misc No
Ancillary Building m2
2 Dressing/Base Preparation
Misc m2
RS m2
3 L/C for Surface Preparation for Screed/ Waterproofing CS m2
PS m2
4 L/C for road washing m2
Waterproofing m3
5 L/C for Backfilling ES05 Soldier pile backfilling m3
Misc m3
Cleaning Nos
6 Barrication boards Shifting(100m)/ Dismantling Nos
Shifting(200-250m) Nos
Entry m3
7 L/C for PCC/ Concreting
Misc m3
RS m3
8 L/C for Screed CS/PS m3
BS m3
Entry m2
Ancillary Building m2
9 Labour charges for curing
Column m2
Misc m2
Lintel & Mullion m2
CJ m2
10 L/C for chipping
Column Hacking m2
CS & Undercroft Hacking m2
PS m2
CS m2
BS/PS m2
Ground Level m2
Fabrication Yard m2
11 L/C for Housekeeping
Misc- Wheel wash, office m2
Entry 03, 04 m2
Entry 02,01 m2
CC RS m2
CC Ground Level m2
12 L/C for repairing RM
13 L/C for Dewatering m2
14 L/C for welding works MT
15 L/C for giving direction to crane operator for lifting material(Rigger) No
16 L/C for scrap segregation/Rebar Shifting MT
17 L/C for loading & unloading of material MT
18 L/C for plaster work m2
19 Cleaning Of Spilled Concrete m2
20 L/C for dismantling Wooden Battens m2
21 Fixing of timber lagging m2
22 Dismantling of Brick Work m3
23 Compaction of soil for PCC m2
24 DWall cleaning m2
25 Hand Railing Fixing Rm
26 Toe Guard m3
Brickwork
27 Other m3
Kalayan Sah
Sno. Activities Sub-Activities Unit
Wooden Lagging Shifting No
Wooden scrap shifting No
1 L/C for Internal carting of material Doka Shifting No
TMT scrap & offcut shifting No
Misc No
Entry m2
2 Dressing/Base Preparation
Misc m2
RS m2
3 L/C for Surface Preparation for Screed/ Waterproofing CS m2
Entry m2
4 L/C for road washing m2
Waterproofing m3
5 L/C for Backfilling CC SP & wall gap filling m3
Misc m3
Cleaning Nos
6 Barrication boards Shifting(100-150m)/ Fixing Nos
Shifting(150-200m) Nos
Station m3
7 L/C for PCC/ Concreting
Misc m3
RS m3
8 L/C for Concrete Manually CS m3
BS m3
Station m2
PS m2
9 Labour charges for curing
Column m2
Misc
Station/Entry m2
CJ&Entry wall m2
10 L/C for chipping
Column Hacking m2
CS/Undercroft Hacking m2
PS m2
CS m2
BS m2
Ground Level m2
Fabrication Yard m2
11 L/C for Housekeeping
Misc- Wheel wash, office, m2
Entry 03, 04 m2
CC BS m2
CC RS m2
CC Ground Level m2
12 L/C for repairing RM
13 L/C for Dewatering m2
14 L/C for welding works MT
15 L/C for giving direction to crane operator for lifting material(Rigger) No
16 L/C for scrap segregation/Rebar Shifting MT
17 L/C for loading & unloading of material MT
18 L/C for plaster work m2
19 Cleaning Of Spilled Concrete m2
20 L/C for dismantling Wooden Battens m2
21 Fixing of timber lagging m2
22 Dismantling of Brick Work m3
23 Compaction of soil for PCC m2
24 DWall cleaning m2
25 Hand Railing Fixing Rm
26 Dismantling of civil str Station area m3
27 Other m3
Varsha Enterprises
Sno. Activities Sub-Activities Unit
Wooden Lagging Shifting No
Wooden scrap shifting No
1 L/C for Internal carting of material Doka Shifting No
TMT scrap & offcut shifting No
Misc No
Station, Entry m2
2 Dressing/Base Preparation
Misc m2
RS m2
3 L/C for Surface Preparation for Screed/ Waterproofing CS m2
BS m2
4 L/C for road washing m2
Waterproofing m3
5 L/C for Backfilling CC SP & wall gap filling m3
Misc m3
Cleaning Nos
6 Barrication boards Shifting(100m) Nos
Shifting(200-250m)
Station, Entry m3
7 L/C for PCC/ Concreting
Misc m3
Station, Entry m2
Ancillary Building m2
9 Labour charges for curing
Column m2
Misc
Station, Entry m2
CJ m2
10 L/C for chipping
Column Hacking m2
Undercroft Hacking m2
RS m2
CS m2
BS m2
Ground Level m2
Fabrication Yard m2
11 L/C for Housekeeping
Misc- Wheel wash, office, m2
Entry 02,03, 04,05 m2
CC BS m2
CC RS m2
CC Ground Level m2
12 L/C for repairing RM
13 L/C for Dewatering m2
14 L/C for welding works MT
15 L/C for giving direction to crane operator for lifting material(Rigger) No
16 L/C for scrap segregation/Rebar Shifting MT
17 L/C for loading & unloading of material MT
18 L/C for plaster work m2
19 Cleaning Of Spilled Concrete m2
20 L/C for dismantling Wooden Battens m2
21 Fixing of timber lagging m2
22 Dismantling of Brick Work m3
23 Compaction of soil for PCC m2
24 DWall cleaning m2
25 Hand Railing Fixing Rm
26 Toe Guard m3
Brickwork
27 Other m3
28 Dismantling of civil str Station area m3
Krishna Enterprises
Sno. Activities Sub-Activities Unit
Wooden Lagging Shifting No
Wooden scrap shifting No
1 L/C for Internal carting of material Doka Shifting No
TMT scrap & offcut shifting No
Misc No
Station, Entry m2
2 Dressing/Base Preparation
Misc m2
RS m2
3 L/C for Surface Preparation for Screed/ Waterproofing CS m2
BS m2
4 L/C for road washing m2
Waterproofing m3
5 L/C for Backfilling CC SP & wall gap filling m3
Misc m3
Cleaning Nos
6 Barrication boards Shifting(100m)/Fixing Nos
Shifting(200-250m) Nos
Station, Entry m3
7 L/C for PCC/ Concreting
Misc m3
Station, Entry m2
Ancillary Building m2
9 Labour charges for curing
Column m2
Cut & Cover m2
10 Station, Entry m2
CJ m2
L/C for chipping
Column Hacking m2
Undercroft Hacking m2
RS m2
CS m2
BS m2
Ground Level m2
Fabrication Yard m2
11 L/C for Housekeeping
Misc- Wheel wash, office, m2
Entry 03, 04,05 m2
CC BS m2
CC RS m2
CC Ground Level m2
12 L/C for repairing RM
13 L/C for Dewatering m2
14 L/C for welding works MT
15 L/C for giving direction to crane operator for lifting material(Rigger) No
16 L/C for scrap segregation/Rebar Shifting MT
17 L/C for loading & unloading of material MT
18 L/C for plaster work m2
19 Cleaning Of Spilled Concrete m2
20 L/C for dismantling Wooden Battens m2
21 Fixing of timber lagging m2
22 Dismantling of Brick Work m3
23 Compaction of soil for PCC m2
24 DWall cleaning m2
25 Hand Railing Fixing Rm
26 Toe Guard m3
Brickwork
27 Other m3
28 L/C For Manual Concreting Station, Entry m3
29
Total Qty Given Qty Balance Qty Nos L B H
104 48 56
104 48 56
104 61 43
104 31 73
104 70 34
2,086 1,124 963
2,086 1,890 196
5,318 1,204 4,114
5,318 3,157 2,161
5,318 1,100 4,218
62,592 31,861 30,731 1 50.0 6.50
1,490 - 1,490
3,477 38 3,439 1 10.7 5.50 0.65
3,477 2,520 957
20,864 14,320 6,544 85
200 164 36
- - 0
5,977 102 5,875 2 21.7 4.7 0.50
2,000 544 1,456
1,064 97 966
1,064 157 906
1,064 - 1,064
15,648 10,269 5,379
15,648 3,569 12,079 2 21.65 27
15,648 675 14,973
15,648 - 15,648
313 209 104
313 108 205
313 - 313
313 - 313
25,037 26,698 1,661 3 120 10.65
25,037 25,696 659 2 65.65 21.57
25,037 22,864 2,173
25,037 19,080 5,957
25,037 12,600 12,437
25,037 8,400 16,637
25,037 18,000 7,037
25,037 2,700 22,337
25,037 - 25,037
25,037 - 25,037
10,432 1,010 9,422
62,592 - 62,592
242 97 146
24,235 - 24,235
1,391 52 1,339 15
- 12 12 12
500 152 348
31,296 14,800 16,496
- - 0
- - 0
- - 0
4,000 4,000 0
- - 0
1,000 175 825 25
- - 0
- - 0
Diff
Total Qty Given Qty Balance Qty Nos L B H
130 130 23
130 130 30
130 130 37
130 130 45
130 130
1,299 1,299 1 15.7 10.60
1,299 1,299
1,299 1,299
1,299 1,299
1,299 1,299
77,969 77,969
928 928
2,166 2,166
2,166 2,166
25,990 25,990
- 0
- 0
4,968 4,968 1 22.8 45 0.40
- 0
260 260
260 260 2 12.33 4.6 0.45
260 260 2 12.65 4.5 0.65
19,492 19,492 1 11.5 12.65
19,492 19,492
19,492 19,492
19,492 19,492
195 195
195 195
195 195
195 195
19,492 19,492
19,492 19,492 1 215 20.65
19,492 19,492 2 265 21.57
19,492 19,492 2 125 21.65
19,492 19,492 6 50 6.5
19,492 19,492 10 25 5.65
19,492 19,492 10 36.56 10.65
19,492 19,492
19,492 19,492
19,492 19,492
33,121 33,121
38,985 38,985
302 302
30,189 30,189 245
866 866 15
- 0
- 0
38,985 38,985 2 21.65 12.1397229
- 0
- 0
- 0
- 0
- 0 6 31.75 5.35
- 0
- 0 2 6.55 21.65 0.35
- 0
Diff
Total Qty Given Qty Balance Qty Nos L B H
104 104 0
104 109 5
104 195 91
104 91 13
104 98 6
2,086 2,618 532 1 16.9 5.65
2,086 1,048 1,039
2,086 1,806 280
2,086 2,082 5
2,086 - 2,086
62,592 55,188 7,404
1,490 1,035 455
3,477 592 2,886
3,477 671 2,806 1 5.2 3.00
20,864 12,440 8,424 520
- - 0
- - 0
5,977 542 5,434 7 7.8 6.6
2,000 202 1,798 1 10 5 1.00
15,648 16,457 809 6 20.7 12.65
15,648 13,088 2,560 1 15.65 5.65
15,648 3,055 12,593
15,648 10,080 5,568
- - 0
- - 0
- - 0
- - 0
18,778 13,481 5,296
18,778 18,227 551
18,778 16,932 1,845
18,778 37,830 19,052 3 200 20.65
18,778 24,142 5,364 3 105.6 20.65
18,778 17,670 1,108 12 11.5 10.65
18,778 26,250 7,472
18,778 18,775 3
18,778 18,775 3
18,778 15,550 3,228
- - 0
- - 0
242 93 149
24,235 10,325 13,910 225
1,391 641 750
100 61 40
- - 0
11,500 8,160 3,340
2,845 1,406 1,439
1,647 150 1,497
- - 0
- - 0
- - 0
- - 0
- - 0
- - 0
- - - 1 22.35 4.772 0.30
Diff
Total Qty Given Qty Balance Qty Nos L B H
130 130
130 130
130 130 10
130 130 10
130 130 10
1,299 1,299
1,299 1,299
1,299 1,299
1,299 1,299
1,299 1,299
77,969 77,969
928 928
2,166 2,166
2,166 2,166 1 10.0 6.50 1.5
12,995 12,995 350
- 0
- 0
4,968 4,968
- 0
- 0
- 0
- 0
- 0
- 0
- 0
- 0
- 0
11,695 11,695
11,695 11,695 5 120 21.57
11,695 11,695
11,695 11,695
11,695 11,695
11,695 11,695
11,695 11,695 5 44.5 5.5
11,695 11,695
11,695 11,695
11,695 11,695
33,121 33,121
- 0
- 0
15,094 15,094
- 0
- 0
- 0
38,985 38,985 3 22 20.65
1,772 1,772
1,026 1,026
- 0
- 0
- 0
- 0
- 0
- 0
Diff
Amba Construction
Qty Rate Amount USL SSL SKL
- 600 - MD 32752 0 12096
- 600 - OT 12167 0 8344
- 600 -
- 600 - 5% PROFIT
- 600 - GRAND TOTAL
- 30 -
- 30 -
- 30 -
- 30 -
- 30 -
325.00 5 1,625
- 70 -
38.07 70 2,665
- 70 -
85.00 15 1,275
- 180 -
- 170 -
101.76 100 10,176
- 100 -
- 250 -
- 250 -
- 250 -
- 5 -
1,169.10 5 5,846
- 5 -
- 5 -
- 250 -
- 250 -
- 250 -
- 250 -
3,834.00 5 19,170
2,832.14 5 14,161
- 5 -
- 5 -
- 5 -
- 5 -
- 5 -
- 5 -
- 5 -
- 5 -
- 30 -
- 5 -
- 2000 -
- 20 -
20.00 225 4,500
12.00 75 900
- 75 -
- 10 -
- 110 -
- 190 -
- 388 -
- 20 -
- 30 -
25.00 172 4,300
- 600 -
- 275 -
1,633 64,617
Kalayan Sah
Qty Rate Amount USL SSL SKL
23.00 600 13,800 MD 93104 32560 20160
30.00 600 18,000 OT 35673 14347 15736
37.00 600 22,200
45.00 600 27,000 5% PROFIT
- 600 - GRAND TOTAL
165.89 30 4,977
- 30 -
- 30 -
- 30 -
- 30 -
- 5 -
- 70 -
- 70 -
- 70 -
- 15 -
- 180 -
- 170 -
410.40 100 41,040
- 100 -
- 250 -
51.05 250 12,762
74.00 250 18,501
145.65 5 728
- 5 -
- 5 -
- 5 -
- 250 -
- 250 -
- 250 -
- 250 -
- 5 -
4,439.75 5 22,199
11,432.10 5 57,161
5,412.50 5 27,063
1,950.00 5 9,750
1,412.50 5 7,063
3,893.64 5 19,468
- 5 -
- 5 -
- 5 -
- 30 -
- 5 -
- 2000 -
245.00 20 4,900
15.00 225 3,375
- 75 -
- 75 -
525.65 10 5,257
- 110 -
- 190 -
- 388 -
- 20 -
1,019.18 30 30,575
- 172 -
97.85 600 58,708
- 275 -
197,176 404,525 116800
Varsha Enterprises
Qty Rate Amount USL SSL SKL
- 600 -
- 600 - MD 62192 37037 22400
- 600 - OT 24357 15593 14000
- 600 -
- 600 - 5% PROFIT
95.65 30 2,870 GRAND TOTAL
- 30 -
- 30 -
- 30 -
- 30 -
- 5 -
- 70 -
- 70 -
15.65 70 1,096
520.00 15 7,800
- 180 -
- 170 -
360.36 100 36,036
50.00 250 12,500
1,567.34 5 7,837
88.42 5 442
- 5 -
- 5 -
- 250 -
- 250 -
- 250 -
- 250 -
- 5 -
- 5 -
- 5 -
12,390.00 5 61,950
6,541.92 5 32,710
1,469.70 5 7,349
- 5 -
- 5 -
- 5 -
- 5 -
- 30 -
- 5 -
- 2000 -
225.00 20 4,500
44.00 225 9,900
36.50 75 2,738
- 75 -
- 10 -
- 110 -
- 190 -
- 388 -
- 20 -
- 30 -
- 172 -
- 600 -
- 275 -
32.00 600 19,198
28,896 206,923
Krishna Enterprises
Qty Rate Amount USL SSL SKL
- 600 - MD 74704 0 5376
- 600 - OT 31993 0 6552
10.00 600 6,000
10.00 600 6,000 5% PROFIT
10.00 600 6,000 GRAND TOTAL
30 30
- 30 -
- 30 -
- 30 -
- 30 -
- 5 -
- 70 -
- 70 -
97.50 70 6,825
350.00 15 5,250
- 180 -
- 170 -
- 100 -
- 100 -
- 5 -
- 5 -
- 5 -
- 5 -
- 250 -
- 250 -
- 250 -
- 250 -
- 5 -
12,942.00 5 64,710
- 5 -
- 5 -
- 5 -
- 5 -
1,223.75 5 6,119
- 5 -
- 5 -
- 5 -
- 30 -
- 5 -
- 2000 -
- 20 -
- 225 -
35.00 75 2,625
- 75 -
1,341.22 10 13,412
- 110 -
- 190 -
- 388 -
- 20 -
- 30 -
- 172 -
- 600 -
- 275 -
- 250 -
- -
3,205 116,971
Total
44848
20511
65359
3268
68627
Total
145824
65756
211580
10579
222159
Total
121629
53950
175579
8779
184358
Total
80080
38545
118625
5931
124556
AMBA Construction
Dear sir
Kindly release the bill payment for the above mentioned period.
Dear sir
Kindly release the bill payment for the above mentioned period.
Dear sir
Kindly release the bill payment for the above mentioned period.
Vendor code
Station
Dear sir
Kindly release the bill payment for the above mentioned period.
Pan card no
Contact no
Bifurcation
Kalyan Qty Qty act Harendra Harendra Qty Varsha Ent Varsha Qty
7,691.18 200 Paswan
4,614,710 7,691.18 4,614,710 7,691.18
- 200 - - - -
- 200 - - - -
- 200 - - - -
- 600 - - - -
153,824 2,086 4,614,710 153,824 4,614,710 153,824
- 2,086 - - - -
153,824 2,086 4,614,710 153,824 4,614,710 153,824
- 2,086 - - - -
- 2,086 - - - -
4,614,710 62,592 23,073,548 4,614,710 23,073,548 4,614,710
109,874 1,490 7,691,183 109,874 7,691,183 109,874
- 3,477 - - - -
- 3,477 - - - -
1,538,237 20,864 23,073,548 1,538,237 23,073,548 1,538,237
- 200 - - - -
- 200 - - - -
588,085 7,977 35,734,937 357,349 58,808,485 588,085
- - - - - -
61,529 835 - - 7,691,183 30,765
- 835 - - - -
- 835 - - - -
2,307,355 31,296 - - 5,768,387 1,153,677
- 31,296 - - - -
- 31,296 - - - -
- 31,296 - - - -
46,147 626 - - - -
- 626 - - - -
- 626 - - - -
- 626 - - - -
2,307,355 31,296 4,614,710 922,942 6,922,065 1,384,413
- 31,296 - - - -
- 31,296 - - - -
- 31,296 - - - -
- 31,296 - - - -
- 31,296 - - - -
- 31,296 - - - -
- 31,296 - - - -
- 31,296 - - - -
- 31,296 - - - -
3,076,473 41,728 23,073,548 769,118 - -
- 62,592 - - - -
17,867 242 - - 35,734,937 17,867
1,786,747 24,235 - - 35,734,937 1,786,747
102,549 1,391 - - 23,073,548 102,549
- 1,000 - - - -
- 2,500 - - - -
2,307,355 31,296 - - - -
- - - - 23,073,548 209,760
- - - - 23,073,548 121,440
- - - - - -
- - - - - -
769,118 10,432 - - - -
- - - - - -
- - - - - -
- 50 - - - -
131,105,604 287,563,048
3,045,000 5,442,500
Qty act Krishna Ent Krishna Qty Qty act
104 4,614,710 7,691.18 104
104 - - 104
104 - - 104
104 - - 104
104 - - 104
2,086 4,614,710 153,824 2,086
2,086 - - 2,086
2,086 4,614,710 153,824 2,086
2,086 - - 2,086
2,086 - - 2,086
62,592 23,073,548 4,614,710 62,592
1,490 7,691,183 109,874 1,490
3,477 - - 3,477
3,477 - - 3,477
20,864 23,073,548 1,538,237 20,864
- - - 200
- - - 200
5,977 58,808,485 588,085 5,977
2,000 - - 2,000
417 7,691,183 30,765 417
417 - - 417
417 - - 417
15,648 5,768,387 1,153,677 15,648
15,648 - - 15,648
15,648 - - 15,648
15,648 - - 15,648
- - - -
- - - -
- - - -
- - - -
18,778 4,614,710 922,942 -
18,778 - - -
18,778 - - -
18,778 - - 25,037
18,778 - - 12,518
18,778 - - 12,518
18,778 - - 12,518
18,778 - - 25,037
18,778 - - 25,037
18,778 - - 12,518
- 23,073,548 769,118 10,432
- - - -
242 - - 2
24,235 - - -
1,391 - - 200
100 - - 200
- - - 200
11,500 - - 2,000
2,845 23,073,548 209,760 2,845
1,647 23,073,548 121,440 1,647
- - - -
- - - -
- - - 500
- - - -
- - - -
- - - -
213,785,819
4,165,000
L&T- SUCG JV CC 27 DE
(A Joint Venture between Larsen & Toubro Limited and Shan
Balance work
Duration Sub- contractor
Required
Sno Description Rate Kalyan Sah
Till Month
SKL SSK USK
Wooden Lagging Shifting May-16 12 2
Wooden scrap shifting May-16 12 2
L/C for Internal
1 Doka Shifting 600 May-16 12 2
carting of material
TMT scrap & offcut shifting May-16 12 2
Misc May-16 12 2
Dressing/Base Entry /Exit May-16 12 1
2
Preparation Misc May-16 12 1
L/C for Surface RS 30 May-16 12 1
Preparation for
3 CS May-16 12 1
Screed/
Waterproofing BS May-16 12 1
L/C for road 12 2
4 5 May-16
washing
Waterproofing May-16 12 1
5 L/C for Backfilling CC SP & wall gap filling 70 May-16 12 1
Misc May-16 12 1
Cleaning 15 May-16 12 2
6 Barrication boards Shifting(100m) 180 May-16 12
Shifting(200-250m) 170 May-16 12
L/C for PCC/ Entry /Exit/Station May-16 12 1 1
7 100
Concreting Misc May-16 12
RS May-16 12 1
8 L/C for Screed CS 250 May-16 12 1
BS May-16 12 1
Entry /Exit/Station May-16 12 2
Labour charges for Ancillary Building May-16 12 2
9 5
curing Column May-16 12 2
Misc May-16 12 2
Entry /Exit May-16 12 1
CJ May-16 12 1
10 L/C for chipping 250
Column Hacking May-16 12 1
Undercroft Hacking May-16 12 1
RS May-16 12 5
CS May-16 12 5
BS May-16 12 5
Ground Level May-16 12 5
L/C for Fabrication Yard May-16 12 5
11 5
Housekeeping Misc- Wheel wash, office May-16 12 5
Entry 02,03, 04,05 May-16 12 5
CC BS May-16 12 5
CC RS May-16 12 5
CC Ground Level May-16 12 5
12 L/C for repairing 30 May-16 12 2 2
13 L/C for Dewatering 5 May-16 12 1
14 L/C for welding works 2000 May-16 12 2
15 L/C for giving direction to crane operator for lifting ma 20 May-16 12 2
16 L/C for scrap segregation/Rebar Shifting 225 May-16 12 1
17 L/C for loading & unloading of material 75 May-16 12
18 L/C for plaster work 75 May-16 12
19 Cleaning Of Spilled Concrete 10 May-16 12 2
20 L/C for dismantling Wooden Battens 110 May-16 12
21 Fixing of timber lagging 190 May-16 12
22 Dismantling of Brick Work 388 May-16 12
23 Compaction of soil for PCC 20 May-16 12
24 DWall cleaning 30 May-16 12 -
25 Hand Railing Fixing 172 May-16 12
26 Toe Guard 600 May-16 12
Brickwork
27 Other 275 May-16 12
C 27 DELHI
ted and Shanghai Urban Construction Group)
May-15
ontractor
Krishna Ent
Kalyan Sah Quantity Krishna Ent Quantity
SKL SSK USK
2 77,969 130 77,969 130
2 77,969 130 77,969 130
2 77,969 130 77,969 130
2 77,969 130 77,969 130
2 77,969 130 77,969 130
1 38,985 1,299 38,985 1,299
1 38,985 1,299 38,985 1,299
1 38,985 1,299 38,985 1,299
1 38,985 1,299 38,985 1,299
1 38,985 1,299 38,985 1,299
2 389,847 77,969 389,847 77,969
1 64,975 928 64,975 928
1 64,975 2,166 64,975 2,166
1 64,975 2,166 64,975 2,166
1 389,847 25,990 194,924 12,995
- - - -
- - - -
1 1 496,810 4,968 496,810 4,968
- - - -
1 64,975 260 64,975 260
1 64,975 260 64,975 260
1 64,975 260 64,975 260
97,462 19,492 - -
97,462 19,492 - -
97,462 19,492 - -
97,462 19,492 - -
48,731 194.92 - -
48,731 195 - -
48,731 195 - -
48,731 195 - -
3 97,462 19,492 58,477 11,695
3 97,462 19,492 58,477 11,695
3 97,462 19,492 58,477 11,695
3 97,462 19,492 58,477 11,695
3 97,462 19,492 58,477 11,695
3 97,462 19,492 58,477 11,695
3 97,462 19,492 58,477 11,695
3 97,462 19,492 58,477 11,695
3 97,462 19,492 58,477 11,695
3 97,462 19,492 58,477 11,695
2 2 993,620 33,121 993,620 33,121
194,924 38,985 - -
603,772 302 - -
1 603,772 30,189 301,886 15,094
194,924 866 - -
- - - -
- - - -
2 389,847 38,985 389,847 38,985
1 - - 194,924 1,772
1 - - 194,924 1,026
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
6,791,371 4,716,171
M/S Prabhakar Rai
Workmen
Date Length of
Length of
Day Shift Night Shift pipeline
pipeline done
done
26-May-16 3 4
27-May-16 3 3
28-May-16 4 3
29-May-16 3 3
30-May-16 4 3
31-May-16 4 3
1-Jun-16 - -
2-Jun-16 3 3
3-Jun-16 3 4
4-Jun-16 3 4
5-Jun-16 4 4
6-Jun-16 4 3
7-Jun-16 4 3
8-Jun-16 - -
9-Jun-16 4 4
10-Jun-16 3 4
11-Jun-16 - -
12-Jun-16 4 4
13-Jun-16 3 4
14-Jun-16 3 4
15-Jun-16 - -
16-Jun-16 4 3
17-Jun-16 4 4
18-Jun-16 3 4
19-Jun-16 3 4
20-Jun-16 3 4
21-Jun-16 3 4
22-Jun-16 - -
23-Jun-16 4 4
24-Jun-16 3 4
25-Jun-16 3 4
Act Mandays 89 95
Theo Mandays 104 104
Nos
Nos
ai
Remarks
No concrete program
No concrete program
No concrete program
No concrete program
No concrete program
184
208
0.88
0.88
M/S Prabhakar Rai
Workmen
Date Length of
Length of
Day Shift Night Shift pipeline
pipeline done
done
26-May-16 4 3
27-May-16 4 3
28-May-16 4 3
29-May-16 4 4
30-May-16 4 3
31-May-16 4 4
1-Jun-16 4 3
2-Jun-16 4 3
3-Jun-16 4 3
4-Jun-16 4 3
5-Jun-16 4 4
6-Jun-16 4 3
7-Jun-16 4 4
8-Jun-16 4 3
9-Jun-16 4 3
10-Jun-16 4 3
11-Jun-16 4 3
12-Jun-16 4 4
13-Jun-16 4 3
14-Jun-16 4 4
15-Jun-16 4 3
16-Jun-16 4 3
17-Jun-16 4 3
18-Jun-16 4 3
19-Jun-16 4 4
20-Jun-16 4 3
21-Jun-16 4 4
22-Jun-16 4 -
23-Jun-16 4 3
24-Jun-16 4 -
25-Jun-16 4 3
Act Mandays 124 95
Theo Mandays 124 124
Nos
Nos
ai
Remarks
No concrete program
No concrete program
No concrete program
No concrete program
No concrete program
219
248
0.8831
0.8831
PROJECT
CLIENT : DELHI ME
CONTRACTO
Sub-Contractor's De
Period Durati T
Sno. Sub- Contractors Section
From To on USK OT
ontractor's Details
Mandays Verification
Total Acc to Time Office Actual amt. from Time Office
SSK OT SKL OT RKP Site Begampur
- - 27 75 67,601 64,617
- - 12 59 122,629 116,971
- - - - 0 0
- - - - 0 0
88,306 88,306
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
343,834
595,200
126,204
373,463
60,185
121,480
1,867,500
27,160
55,097
83,375
2,943,475
53,136
7,000
90,084
725,773
16,410
16,747
12,653
Err:509
Err:509
116,368
Err:509
23,334
3-Oct-15
3-Oct-15
3-Oct-15
3-Oct-15
3-Oct-15
4-Nov-15
4-Nov-15
4-Nov-15
4-Nov-15
4-Nov-15
30-Dec-99
4-Nov-15
4-Nov-15
4-Nov-15
3-Oct-15
4-Nov-15
4-Nov-15
4-Nov-15
4-Nov-15
4-Nov-15
4-Nov-15
4-Nov-15
4-Nov-15
4-Nov-15
4-Nov-15
4-Nov-15
L&T-SUCG JV CC-27 DMRC Project Delh
Measurement Book
Sub-Contractor BamBam
Period 26-May-16 25-Jun-16
sqm
b Lintel,Mullion sqm 40.000 2.400 0.300
277.760
268.800
28.800
10.250 143.026
10.650 495.358
3.650 33.954
5.510 153.770
4.585 85.304
911.412 35 31,899
0.000 201 -
112.000 172 19,264
100
35.000 3,500
175,734
ect Delhi
6.360
6.360 65 413.4
0.000
242.880
48.000
Dear sir
Kindly release the bill payment for the above mentioned period.
Dear sir
Kindly release the bill payment for the above mentioned period.
Dear sir
Kindly release the bill payment for the above mentioned period.
Dear sir
Kindly release the bill payment for the above mentioned period.
Dear sir
Kindly release the bill payment for the above mentioned period.
Nabdip Mehty
RKP STATION
Dear sir
Kindly release the bill payment for the above mentioned period.
35 -
- 35 -
100 -
100 -
250 -
Err:509 30 Err:509
600 -
Err:509
h
Pancard no PCCGXPS9434H
Vendor code S9003405
230 68,365
297.24
240
Err:509
- 35 -
525.59 35 18,396
117.20 30 3,516
600 -
Err:509
Gupta
Pancard no BKUPG0635E
Vendor code S0053466
14.60 65 949
Err:509 230
30 -
35 -
151.80 35 5,313
100 -
100 -
250 -
600 -
116,368
Pancard no CRPP59756
Vendor code S0068305
275 -
- 230 -
30 -
35 -
497.91 35 17,427
100 -
250 -
600 -
Err:509
on
Pancard no
Vendor code
Err:509 230
30 -
35 -
172.28 35 6,030
100 -
100 -
250 -
600 -
23,334
y
Pancard no
Vendor code
- 172 -
- 230 -
Err:509 240
30 -
35 -
-
Err:509 35 Err:509
100 -
100 -
250 -
600 -
Err:509
L&T-SUCG JV CC-27 DMRC Project
Measurement Book
Sub-Contractor Manoj Kumar
Period 26-May-16 25-Jun-16
SNo. Description
Transportation of D-wall muck from station locations to dumping yard at Kalindikunj or any other designated location for lead upto 26 km.
done by L&T SUCG JV. Measurement shall be as per actual material filled in dump truck. The wheels shall be cleaned at wheel washing ba
1 Contractor before leaving the site.
Transportation of Debris from station locations to dumping yard at Burari or any other designated location for lead upto 30 km. Loading o
L&T SUCG JV. Measurement shall be as per actual material filled in dump truck. The wheels shall be cleaned at wheel washing bay facility
2 leaving the site.
L&T-SUCG JV CC-27 DMRC Project
Measurement Book
Sub-Contractor M/sRajKumar
Period 26-May-16 25-Jun-16
Dim
SNo. Description Unit
No L
L/C for Drilling of pile of nominal dia 800mm in all kinds of soil strata upto a
1 Rmt 25
depth of 16m from GL at Entrys at RKP USING ROTARY Piling Rig Machine.
L&T-SUCG JV CC-27 DMRC Project
Measurement Book
Sub-Contractor Saras Infra Build
Period 26-May-16 25-Jun-16
Dim
SNo. Description Unit
No L
All Charges for breaking of RCC upto concrete grade of M20. Breaking shall be done
1
with JCB with breaker arrangement.
guidewall at ES02 Cum 1.000 16.000
1.000 5.000
All Charges for breaking of RCC upto concrete grade of M40. Breaking shall be done
2
with JCB with breaker arrangement.
a D-Wall breaking at ES02 TVS Shaft Cum 1.000 9.000
1.000 3.550
1.000 3.000
L&T-SUCG JV CC-27 DMRC Project
Measurement Book
Sub-Contractor SAS Infratech
Period 26-May-16 25-Jun-16
Distributi
SNo. Description Unit Previous Qty
on
1 Preparation & suppy of structural drawings based on tender drawing & bill of LS 100% 100%
permanent works & other items as per scope.
2 LS 35% 35%
Completion of Thrust Bed & all necessary arrangement for starting Box Pushing
4 LS 15% 0%
Completion in all respects including House Keeping of structure and Demobalization.
Measurement Book
Sub-Contractor M/s Allure Interiors
Period 26-May-16 25-Jun-16
Providing and applying two coats of Heritage surface texture paint after
applying corresponding roller coat as primer on pre plaster surface as per
1 approved shade,The first coat to be applied by brush or wool as a base Sqm 240
coat,diluted with sufficient water final to be applied by trowel to maintain
with or without Grooves.
Measurement Book
Sub-Contractor Chanderlekha
Period 26-May-16 25-Jun-16
1 Fixing wooden lagging between 2 soldier piles at RK Puram cut & cover & box pushing
as directed by eic.
a Cut & cover sqm 5884.58
b Box Pushing 663.00
c ES04 635.68
d ES01 34.58
e ES02 937.43
f ES05 951.41
g ES03 576.89
2 Removal of wooden lagging between 2 soldier piles at RK Puram cut & cover & box
pushing as directed by eic.
a Cut & cover 5884.58
b Box Pushing/ES01 667.30
c ES02 989.14
d ES04 668.71
e ES05 Box 951.41
Measurement Book
Sub-Contractor Amba Construction
Period 26-May-16 25-Jun-16
1 Fixing of wooden lagging between 2 soldier piles at RK Puram cut & cover & box sqm
pushing as directed by eic.
a Box Pushing 0
b Cut & cover 0
Total
Measurement Book
Sub-Contractor Spar Geo Infra Pvt Ltd
Period 26-May-16 25-Jun-16
1.1
Extraction of soldier Pile
a Cut&Cover m 3,924.99
b ES01 m 886.55
c ES02 m 589.18
d ES03 m 5.00
e ES04 m 315.51
Measurement Book
Sub-Contractor Axiom
Period 26-May-16 25-Jun-16
Core cutting with diamond core cutting method od dia 200mm & depth of 800mm.
Concrete debris generated shall be stacked properly at a loction inside station area as
directed by eic.
Core cutting with diamond core cutting method od dia 200mm & depth of 800mm.
Concrete debris generated shall be stacked properly at a loction inside station area as
directed by eic.
1 Station Nos 11
Measurement Book
Sub-Contractor Concrete Solutions
Period 26-May-16 25-Jun-16
Station Nos 1
3 Cutting of tunnel eye in RKP Head Wall
a Wall cutting using wire saw cutting sqm 88
b Nos 79
Core cutting with diamond core cutting method od dia 100mm & depth of 800mm
Placing & fixing 12mm dia MS nozzle of 70 mm length at leakage point on the entire
3 retaining wall after concreting by drilling or making holes with suitable tools Nos 188
Placing & fixing 12mm dia MS nozzle of 70 mm length at leakage point on the entire
3 retaining wall after concreting by drilling or making holes with suitable tools Nos 188
Supply & application of shrinkage free low viscosity, moisture toletant, epoxyinjection
1 adhesive above column heads product- Sikadue-52. Rate included packer also of Kg 96
approved quantity.
Measurement Book
Sub-Contractor Deepak Allied
Period 26-May-16 25-Jun-16
Installation of HDPE Pipe made out of size 355mm PE-80, PN-4 conforming to IS-14333
suitable for welding joints including weldings as per Direction of Engineer-in-Charge
with all labour as a complete job including all tools and plants, machinery all
2
equipments like JCB Crane, Welding and Cutting plant including material. Physical
Mtr
verification of utilities by digging of holes, mobilization and demobilization of
equipments and manpower as required.
a 355mm dia
Supplying and fixing 355mm dia (Outer dia) HDPE PN-4 pipe conforming to DJB
3 Mtr
standard and IS Code 14333 and as directed by Engineer-In-charge.
Construction of manhole of size 1.52m internal dia at bottom and 0.56m dia at top of
4 nos
required depth as per DJB pattern.
Pumping out water caused by springs, tidal or river seepage, broken water mains or
5 KL
drains and likes.
Note: Hold 10% of total amount of the bill after submitting of Revised Drawing of diverted
L&T-SUCG JV CC-27 DMRC Project
Measurement Book
Sub-Contractor HCH Engineering
Period 26-May-16 25-Jun-16
1 Nos 183
2 Nos 732
3 Nos 732
Description
SNo. Unit Scope Given No L
10,139.95 9,047.55
Note:
1) The above mentione qty is of only application
2) For the payment purpose for material is total qty payble is :252sqm
L&T-SUCG JV CC-27 DMRC Project
Measurement Book
Sub-Contractor Rattiputra
Period 26-May-16 25-Jun-16
Dim
SNo. Description Unit
No L
L/c For backfilling of Soil ,it includes cost of soil,transportation &Unloading of soil as
1
per EIC
PCC for piling of ES05 Trip 7.00
-
7.00
2
2
a
L&T-SUCG JV CC-27 DMRC Project
Measurement Book
Sub-Contractor Ashish Engineering
Period 26-May-16 25-Jun-16
Supply & application of shrinkage free low viscosity, moisture toletant, epoxyinjection adhesive above
1 Kg
column heads product- Sikadue-52. Rate included packer also of approved quantity.
Application of cement grout with injection technology. Cement grout shall be provided by L&T SUCG JV
2 free of cost. Rates includes packer also of approved quality. Subcontractor shall bring injection machine per packer
of required capacity.
Placing & fixing 12mm dia MS nozzle of 70 mm length at leakage point on the entire retaining wall after
3 concreting by drilling or making holes with suitable tools Nos
Supply & application of " CICO polygrout reactive water barrier grouting system" by injection
4 grouting machine. Nos
Sealing the wet cracks through cement using " CICO Quick Set No.3 " to avoid wastage of " CICO
5 Polygrout -Reactive Water Barrier Grouting System". m
L&T-SUCG JV CC-27 DMRC Project
Measurement Book
Sub-Contractor Pooja Constructtion
Period 26-May-16 25-Jun-16
1 Charges for Cross Passage aas per approved drawings and direction of eic.
Debit Remarks
1 Downline door erection by M/S Sri Sai 1.264MT x RS 7400 9354
2 Upline ring girder shifting by supply labor.(12labors) 6000
Balance Work Remarks
1 Ring girder dismantling/shifting for downline 9.604MT x 2660Rs 25546.64
2 Sump excavation /shortcrete done by M/S Varsha 1.4 Lakh will not be provided
40900.24
1 Charges for Cross Passage aas per approved drawings and direction of eic.
Debit
Description
1 UL Ring erection & Dismantling by M/S Sri Sai
2 UL Door Frame erection by M/S Sri Sai
3 DL Ring Dismantling by M/S Sri Sai
4 DL Ring erection by M/S HCH
5 DL Door Frame erection by M/S HCH
L&T-SUCG JV CC-27 DMRC Project
Measurement Book
Sub-Contractor M/S Dipesh Enterprises
Period 26-May-16 25-Jun-16
Providing and laying integral based water proofing treatment including prepration of surface as required
for roof,balconies,terraces etc,consisting of following actvities:a)applying slurry coat of 2.75kg/sqm
admixed with water proofing compound &confirming to IS:2645&approved by EIC at adjoining wall
upto300mm including the height treatement of wall,b)laying brick bat with mortor using broken bricks
1
25mm to 115mm size with 50% of cement mortor 1:5 admixed with waterproofing compound c)after two
days of curing applying second coat of slurry using 2.75kg/sqm of water proofing compound mixed with
cement. d)finishing the surface with 20mm thick jointless cement mortor of 1:4 and other operation as
per EIC
a With Avg Thickness of 120mm and minimum thk at Khurra as 65mm Sqm 1,250.00
Providing and Fixing of 3MM Thk SS304 Grade sheet cladding on Aluminium Base Frame 25mm thk
2 complete/(For payment purpose only SS shall be measured Alluminium item shall be paid as extra item Kg 13,044.45
under NDSR)
Providing and fixing of Alluminium Mill Finish SUB Frame work with Extra Built up Standard tubular
3 Kg 625.65
section of appproved Make confirming to IS:733 and IS:1285 fixed with raw Plugs and SS Screw
Providing and Fixing of Panals of 3mm Pressed Plate of Grade 304 SS Matte Finish including SS frame of
4 30X30X3mm All accessories and Fixtures of Removable Access Panals in Block work All complete as per Kg 717.66
drawings
Details of work:
Circular column G9 1nos
Rectangular Full height G16A 1nos
1 Fabrication&Erection of MS Handrailing of 50MM&25mm dia 3.15mm thick with polyurethane paint Kg 499.28
Total
Unit Rate
Qty Amount
o 26 km. Loading of muck shall be
ashing bay facility by Sub-
cum 195 - -
Total -
Project Delhi
ok
Site RKP STATION
Shift Day/ Night
Dimension
Qty Rate Amount
B/ H
-
-
- 0
-
- 0
373,463
Project Delhi
ok
Site RKP STATION
Shift Day/ Night
Dimension
Qty Rate Amount
B/ H
0 -
0% -
0% 12450000 -
1,867,500
ok
Site RKP STATION
Shift Day/ Night
27,160
ok
Site RKP STATION
Shift Day/ Night
5884.58 -
663.00 -
635.68 -
34.58 -
937.43 -
951.41 -
383.33 193.560
190.00
193.56 36776.40
302.55
266.87
479.51 166.55
119.52 -
4.20 -
0 -
0 -
- 190 -
-
ok
Site RKP STATION
Shift Day/ Night
1 - 5100 0
88 - 11200 0
79 - 3000 0
188 - 200 -
188 - 200 -
96 - 500 -
83,375
ok
Site RKP STATION
Shift Day/ Night
2.00 65,000.00
- 64.00 -
2,943,475
verted line to DJB For Approval
Project Delhi
ok
Site RKP STATION
Shift Day/ Night
414,495
Project Delhi
ok
Site RKP STATION
Shift Day/ Night
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
221.40
Dimension
Qty Rate Amount
B/ H
-
-
7.000 1000 7000
7,000
Project Delhi
ok
Site RKP STATION
Shift Day/ Night
94 94 - 1000 -
12 12 - 175 -
90,084
Project Delhi
ok
Site RKP STATION
Shift Day/ Night
9250
Project Delhi
ok
Site RKP STATION
Shift Day/ Night
Comp Given Qty Current Qty Rate Amount
Project Delhi
ok
Site RKP STATION
Shift Day/ Night
Comp Given Qty Current Qty Rate Amount
Project Delhi
ok
Site RKP STATION
Shift Day/ Night
Comp Given Qty Current Qty Rate Amount
-
-
8,113
73,020
Equipments Rate Hrs Amt Diesel(L)
7.5 9375.00 45
TFC 1250 3 3750.00 18
2.25 2812.50 13.5
65 TON CRANE 1000 1.5 1500.00 10.5
PICK & CARRY CRANE 116 2.5 288.75 8.75
48 95.75 4596.00
22322.25
Debit M/s Allure Interiors
USL SSL SKL Total
MD 9200 2035 0 11235
OT 1150 254 0 1404
12639
5% PROFIT 632
GRAND TOTAL 13271
Wooden Lagging Recon
Billing Status
Palnivel
Month Unit
CC BP ES04 ES03 ES01 ES02
RA 1, Apr '14 sqm 512.00 400.00
RA 2, May '14 sqm 566.40 263.00
RA 3, Jun '14 sqm 575.00
sqm
RA 4, Jul '14 791.88
RA 5, Aug '14 sqm 1,036.95
RA 6, Sep '14 sqm 922.59
RA 7, Oct '14 sqm 767.10
RA 8, Nov '14 sqm 495.66 120.76
RA 9, Dec '15 sqm - 125.92
RA 10, Jan '15 sqm 217.00 389.00
RA 11, Mar '15 sqm 104.93
RA 12, Apr '15 sqm 34.58 327.68
RA 12, May '15 sqm 330.84
RA 13, Nov '15 sqm 114.09 45.45
RA 14, Dec '15 sqm 128.54
RA 15, Jan '16 sqm 74.9
RA 16, Feb '16 sqm 144.498
RA 17, Mar '16 sqm 49.841
RA 18, Apr '16 sqm 193.56
Actual Consumptio sqm 5885 663 636 577 35 937
Completion
Area Unit Scope
Theoritical Actual
Box Pushing sqm 667 667 663
Cut & Cover sqm 6468 6468 6467
ES4 sqm 668.7076 669 636
ES02 sqm 989 989 937
ES05 sqm 1002 1002 -
661.5
6m
52m HDPE Pipe
6m
9m 9m
0.685
1.5
m
m
L&T HCH
251 217 468
183
Scope
Location Unit No L B Area
G(24-26),(1-3) m2 2 17.00 24.57 835.38
G(23-24) m2
1 13.20 21.57 284.72
G(1-3) m2
2 17.00 0.30 10.20
G(2-3),G(24-25) m2
4 1.50 0.30 1.80
G(23-26) Jn m2
2 30.20 0.30 18.12
G(1,26) Jn m2
2 24.57 0.30 14.74
G(3-20) m2 1 190.40 21.57 4,106.93
G(3-20) Jn m2
2 190.40 0.30 114.24
G(1-7),(23-26) Pedest m2
72 2.75 0.60 118.80
RB5- G(7-10) m2
2 30.88 0.59 36.43
RB5- G(17-20) m2 2 31.15 0.59 36.76
RB5- G(11-16) m2 2 51.50 0.59 60.77
RB 6A- G(16-17),G(10 m2 4 18.00 0.59 42.48
RB 3 m2
2 13.05 0.70 18.27
m2
2 2.75 0.70 3.85
RB 8 m2
1 19.82 0.50 9.91
m2
1 19.82 0.50 9.91
RB1 m2
1 17.80 0.60 10.68
m2
1 1.50 0.60 0.90
RB2 m2
1 19.00 0.60 11.40
m2
1 0.25 0.60 0.15
RB4 m2
1 17.65 0.60 10.59
m2
2 0.25 0.60 0.30
m2 1 12.10 0.60 7.26
RB7 m2
1 18.03 0.60 10.82
m2 1 0.25 0.60 0.15
Air Shaft m2 1 20.70 0.30 6.21
RSS Shaft at grid 01 m 2
1 5.85 0.30 1.75
Pipe line Support Ped m 2
9 2.80 0.30 7.56
Temp Wall- G8, G10 m 2
2 28.00 0.30 16.80
5,524
m2
CC Beam Inner Lengt 2 49.5 1 99.00
CC Beam Outer Bread m 2
2 12.45 1 24.90
CC Beam Inner Bread m 2
2 10.25 1 20.50
Opening m 2
1 20 5 100.00
4,394.55
USL
SSK
SKL
Shree Shyam
ES05 CC CC
302
180
115.45
340.6257
333.088
115.707
46.538
Bal
Sno Sub-Contractor Fore OT Hel OT Sup OT Cap OT Wel OT Mas OT
1 Ruby Rai 0 0 0 0 0 0
Shutter
2 Jha Const/Siddeshwar. 196 601 18 49 186 605
3 Vikram 130 470 0 0 130 500
4 Yogendra 188 555 23 66.5 109 354.5
4 Bum bum Shankar 235 957.5 25 82.5 65 230.5
Rebar
235,666
45,946 0
11 25 69,273 0
0
0 0 0
22 89 120,448 0
0 88,306
-160,038
###
Description Wt of Rebar L(m)
ES03 Pit slab 3.438
ES05 Subway Roof 4.498
ES05 Wall on Thrust Bed 9.386
ES02 Roof Slab G(8-9) 3.050
ES02 TVS Vent shaft 10.010
RSS Shaft 0.902
TOM 0.853
Ancillary Building Column 1.850
Staircase Center wall 8.092
ES01 Grade Slab 3.231
ES01&ES02 Pit slab(Grade) 0.946
ES02 Lift wall 1.356
BS Col --1200
BS Col -1500x700
CS Col -1000x700
CS Col -1200x600
CS Col --1200
CS Col -1500x700
Total Scope 47.612
L&T-SUCG JV CC-27 DMRC Project Delhi
Measurement Book
Sub-Contractor Rajan Engg
Period 26-May-16 25-Jun-16
USL SSL
5% CONT PROFIT
GRAND TOTAL
Date USL SSL
10-Apr-14 25 2
28-Apr-14 5 1
30 3
L&T-SUCG JV CC-27 DMRC Project Delhi
Measurement Book
Sub-Contractor Zainath Enterprises
Period 26-May-16 25-Jun-16
According to Mandays for meas
USL SSL
MAN DAYS 0 0
OT 0 0
5% CONT PROFIT
GRAND TOTAL
L&T-SUCG JV CC-27 DMRC Project Delhi
Measurement Book
Sub-Contractor Zainath Enterprises
Period 26-May-16 25-Jun-16
According to Mandays
USL SSL
MAN DAYS 0 0
OT 0 0
5% CONT PROFIT
GRAND TOTAL
B(m) H(m)
181
5.85
Site : IIT GATE
Shift: Day/Night
measurement
SKL Total
Err:509 Err:509
Err:509
Err:509
Err:509
Err:509
SKL OT
9
4
13 0
16589
elhi
SKL Total
0 0
0 0
0
0
0
elhi
SKL Total
0 0
0 0
0
0
0
Sno Item Unit
Scope
1 Cutting, bending ES03 Pit slab MT 8.25
ES05 Subway Roof MT 4.50
ES05 Wall on Thrust Bed MT 9.39
ES02 Roof Slab G(8-9) MT 3.05
ES02 TVS Vent shaft MT 10.01
RSS Shaft MT
TOM MT 0.85
Ancillary Building Column MT 1.85
Staircase Center wall MT 8.09
ES01 Grade Slab MT 3.23
RSS Shaft MT 0.90
ES02 Lift wall MT 1.36
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
2 Fixing ES03 Pit slab MT 8.25
ES05 Subway Roof MT 4.50
ES05 Wall on Thrust Bed MT 9.39
ES02 Roof Slab G(8-9) MT 3.05
ES02 TVS Vent shaft MT 10.01
RSS Shaft MT 0.90
TOM MT 0.85
Ancillary Building Column MT 1.85
Staircase Center wall MT 8.09
ES01 Grade Slab MT 3.23
ES01&ES02 Pit slab(Grade) MT 0.95
ES02 Lift wall MT 1.36
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
3 Coupler Box6,7 No 150
Loosening RSS Shaft No
ES05 Wall on Thrust Bed No 267
ES02 Roof Slab G(8-9) No 100
Cooling Tower Foundation @AB No 300
RSS Shaft No 621
TOM No 750
ES02 Roof G(1-3) No 201
ES02 TVS Vent shaft No 236
ES05 Subway Roof No 819
box No 440
4 Coupler Fixing Box6,7 No 200
Cooling Tower Foundation @AB No 300
ES05 Wall on Thrust Bed No 267
ES02 Roof Slab G(8-9) No 100
RSS Shaft No 621
TOM No 750
ES02 TVS Vent shaft No 236
ES02 Roof G(1-3) No 201
ES05 Subway Roof No 819
Box No 440
5 Shifting steel MT
ES05 Subway Roof MT 9.0
ES05 Wall on Thrust Bed MT 18.77
ES02 Roof Slab G(8-9) MT 6.10
ES02 TVS Vent shaft MT 20.02
RSS Shaft MT 1.80
TOM MT 1.71
Ancillary Building Column MT 3.70
AB Sump Roof MT 16.18
Box1(ES05) MT 16.50
ES01&ES02 Pit slab(Grade) MT 1.89
ES02 Lift wall MT 2.71
ES01 Grade Slab MT 1.10
BS Col -1500x700 MT -
ES03 Pit slab MT 6.88
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
6 Loading/ ES03 Pit slab MT 6.88
Unloading ES05 Subway Roof MT 9.0
ES05 Wall on Thrust Bed MT 18.77
ES02 Roof Slab G(8-9) MT 6.10
ES02 TVS Vent shaft MT 20.02
RSS Shaft MT 1.80
TOM MT 1.71
Ancillary Building Column MT 3.70
Staircase Center wall MT 16.18
ES01 Grade Slab MT 1.10
ES01&ES02 Pit slab(Grade) MT 1.89
ES02 Lift wall MT 2.71
BS Col --1200 MT -
BS Col -1500x700 MT -
ES01 Grade Slab MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
7 Concreting cum
cum
cum
cum
cum
Prepared by 1 Prepared by 2
Zainath Enterprises
Sno. Activity Unit Qty
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Staircase Center wall MT -
1 Cutting, bending
ES01 Grade Slab MT -
RSS Shaft MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Staircase Center wall MT -
2 Fixing
ES01 Grade Slab MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
Box6,7 No -
RSS Shaft No -
ES05 Wall on Thrust Bed No -
Coupler
3 ES02 Roof Slab G(8-9) No -
Loosening
ES02 TVS Vent shaft No -
ES05 Subway Roof No -
box No -
Box6,7 No -
#REF! #REF! #REF!
ES05 Wall on Thrust Bed No -
4 Coupler Fixing ES02 Roof Slab G(8-9) No -
ES02 TVS Vent shaft No -
ES05 Subway Roof No -
Box -
- No -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
AB Sump Roof MT -
5 Shifting steel
Box1(ES05) MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
ES01 Grade Slab MT -
BS Col -1500x700 MT -
ES03 Pit slab MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Loading/ Staircase Center wall MT -
6
Unloading ES01 Grade Slab MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
ES01 Grade Slab MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
- cum -
- cum -
- cum -
7 Concreting
- cum -
- cum -
- - -
Rajan Engg
Sno. Activity Unit Qty
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT 2.950
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Staircase Center wall MT -
1 Cutting, bending
ES01 Grade Slab MT -
RSS Shaft MT 2.550
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT 2.950
RSS Shaft MT 2.550
TOM MT -
Ancillary Building Column MT -
Staircase Center wall MT -
2 Fixing
ES01 Grade Slab MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
Box6,7 No -
RSS Shaft No -
ES05 Wall on Thrust Bed No -
Coupler
3 ES02 Roof Slab G(8-9) No -
Loosening
ES02 TVS Vent shaft No -
ES05 Subway Roof No -
box No -
Box6,7 No -
#REF! #REF! #REF!
ES05 Wall on Thrust Bed No -
4 Coupler Fixing ES02 Roof Slab G(8-9) No -
ES02 TVS Vent shaft No -
ES05 Subway Roof No -
Box No -
- MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT 2.950
RSS Shaft MT 2.550
TOM MT -
Ancillary Building Column MT -
AB Sump Roof MT -
5 Shifting steel
Box1(ES05) MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
ES01 Grade Slab MT -
BS Col -1500x700 MT -
ES03 Pit slab MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT 2.950
RSS Shaft MT 2.550
TOM MT -
Ancillary Building Column MT -
Loading/ Staircase Center wall MT -
6
Unloading ES01 Grade Slab MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
ES01 Grade Slab MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
- cum -
- cum -
7 Concreting - cum -
- cum -
- cum -
Malik Enterprises
Sno. Activity Unit Qty
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT 0.950
ES02 Roof Slab G(8-9) MT 0.550
ES02 TVS Vent shaft MT 2.280
RSS Shaft MT 5.850
TOM MT -
Ancillary Building Column MT -
Staircase Center wall MT -
ES01 Grade Slab MT -
1 Cutting, bending
RSS Shaft MT -
ES02 Lift wall MT 6.320
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT 0.950
ES02 Roof Slab G(8-9) MT 0.550
ES02 TVS Vent shaft MT 2.280
RSS Shaft MT 5.850
TOM MT 6.320
Ancillary Building Column MT -
Staircase Center wall MT -
ES01 Grade Slab MT -
2 Fixing
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
Box6,7 No -
RSS Shaft No -
ES05 Wall on Thrust Bed No -
ES02 Roof Slab G(8-9) No 221.000
Coupler
3 ES02 TVS Vent shaft No -
Loosening
ES05 Subway Roof No -
box No -
Box6,7 No -
#REF! #REF! -
ES05 Wall on Thrust Bed No #REF!
ES02 Roof Slab G(8-9) No 221.000
4 Coupler Fixing ES02 TVS Vent shaft No -
ES05 Subway Roof No -
Box No -
- MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT 0.950
ES02 Roof Slab G(8-9) MT 0.550
ES02 TVS Vent shaft MT 2.280
RSS Shaft MT 5.850
TOM MT 6.320
Ancillary Building Column MT -
AB Sump Roof MT -
Box1(ES05) MT -
5 Shifting steel
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
ES01 Grade Slab MT -
BS Col -1500x700 MT -
ES03 Pit slab MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT 0.950
ES02 Roof Slab G(8-9) MT 0.550
ES02 TVS Vent shaft MT 2.280
RSS Shaft MT 5.850
TOM MT 6.320
Ancillary Building Column MT -
Staircase Center wall MT -
Loading/ ES01 Grade Slab MT -
6
Unloading ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
ES01 Grade Slab MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
- cum -
- cum -
- cum -
7 Concreting - cum -
- cum -
- - -
Bum bum Shankar
Sno. Activity Unit Qty
ES03 Pit slab MT 8.250
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT 19.560
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Staircase Center wall MT -
1 Cutting, bending
ES01 Grade Slab MT -
RSS Shaft MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
ES03 Pit slab MT 8.250
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT 19.560
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Staircase Center wall MT -
2 Fixing
ES01 Grade Slab MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 No -
CS Col -1500x700 No -
Box6,7 No -
RSS Shaft No -
ES05 Wall on Thrust Bed No -
Coupler
3 ES02 Roof Slab G(8-9) No -
Loosening
ES02 TVS Vent shaft No 265.000
ES05 Subway Roof No -
box #REF! -
Box6,7 No -
#REF! No #REF!
ES05 Wall on Thrust Bed No -
4 Coupler Fixing ES02 Roof Slab G(8-9) No -
ES02 TVS Vent shaft - 265.000
ES05 Subway Roof No -
Box MT -
- MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT 19.560
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
AB Sump Roof MT -
5 Shifting steel
Box1(ES05) MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
ES01 Grade Slab MT -
BS Col -1500x700 MT -
ES03 Pit slab MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
ES03 Pit slab MT 8.250
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT 19.560
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Loading/ Staircase Center wall MT -
6
Unloading ES01 Grade Slab MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
ES01 Grade Slab MT -
CS Col -1200x600 MT -
CS Col --1200 cum -
CS Col -1500x700 cum -
- cum -
- cum -
7 Concreting - cum -
- cum -
- cum -
Sia Ram Sharma
Sno. Activity Unit Qty
ES03 Pit slab MT -
ES05 Subway Roof - -
ES05 Wall on Thrust Bed Unit -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Staircase Center wall MT -
1 Cutting, bending
ES01 Grade Slab MT -
RSS Shaft MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Staircase Center wall MT -
2 Fixing
ES01 Grade Slab MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
Box6,7 MT -
RSS Shaft MT -
ES05 Wall on Thrust Bed MT -
Coupler
3 ES02 Roof Slab G(8-9) No -
Loosening
ES02 TVS Vent shaft No -
ES05 Subway Roof No -
box No -
Box6,7 No -
#REF! No #REF!
ES05 Wall on Thrust Bed No -
4 Coupler Fixing ES02 Roof Slab G(8-9) No -
ES02 TVS Vent shaft #REF! -
ES05 Subway Roof No -
Box No -
- No -
ES05 Subway Roof No -
ES05 Wall on Thrust Bed No -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
AB Sump Roof MT -
5 Shifting steel
Box1(ES05) MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
ES01 Grade Slab MT -
BS Col -1500x700 MT -
ES03 Pit slab MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Loading/ Staircase Center wall MT -
6
Unloading ES01 Grade Slab MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
ES01 Grade Slab MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
- cum -
- cum -
7 Concreting - cum -
- cum -
- cum -
VK Singh
Sno. Activity Unit Qty
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Staircase Center wall MT -
1 Cutting, bending
ES01 Grade Slab MT -
RSS Shaft MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Staircase Center wall MT -
2 Fixing
ES01 Grade Slab MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
Box6,7 No -
RSS Shaft No -
ES05 Wall on Thrust Bed No -
Coupler
3 ES02 Roof Slab G(8-9) No -
Loosening
ES02 TVS Vent shaft No -
ES05 Subway Roof No -
box No -
Box6,7 No -
#REF! #REF! #REF!
ES05 Wall on Thrust Bed No -
4 Coupler Fixing ES02 Roof Slab G(8-9) No -
ES02 TVS Vent shaft No -
ES05 Subway Roof No -
Box No -
- MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
AB Sump Roof MT -
5 Shifting steel
Box1(ES05) MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
ES01 Grade Slab MT -
BS Col -1500x700 MT -
ES03 Pit slab MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Loading/ Staircase Center wall MT -
6
Unloading ES01 Grade Slab MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
ES01 Grade Slab MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
CS Col -1500x700 MT -
- cum -
7 Concreting
- cum -
Lokeshwar
Sno.
1 Activity Unit Qty
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Staircase Center wall MT -
Cutting, bending
ES01 Grade Slab MT -
RSS Shaft MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
2 CS Col -1500x700 MT -
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Staircase Center wall MT -
Fixing
ES01 Grade Slab MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
CS Col -1000x700 MT -
CS Col -1200x600 MT -
CS Col --1200 No -
3 CS Col -1500x700 No -
Box6,7 No -
RSS Shaft No -
ES05 Wall on Thrust Bed No -
Coupler
ES02 Roof Slab G(8-9) No -
Loosening
ES02 TVS Vent shaft No -
ES05 Subway Roof No -
4 box #REF! -
Box6,7 No -
#REF! No #REF!
ES05 Wall on Thrust Bed No -
Coupler Fixing ES02 Roof Slab G(8-9) No -
ES02 TVS Vent shaft - -
ES05 Subway Roof No -
5 Box MT -
- MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
AB Sump Roof MT -
Shifting steel
Box1(ES05) MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
ES01 Grade Slab MT -
BS Col -1500x700 MT -
ES03 Pit slab MT -
CS Col -1200x600 MT -
CS Col --1200 MT -
6 CS Col -1500x700 MT -
ES03 Pit slab MT -
ES05 Subway Roof MT -
ES05 Wall on Thrust Bed MT -
ES02 Roof Slab G(8-9) MT -
ES02 TVS Vent shaft MT -
RSS Shaft MT -
TOM MT -
Ancillary Building Column MT -
Loading/ Staircase Center wall MT -
Unloading ES01 Grade Slab MT -
ES01&ES02 Pit slab(Grade) MT -
ES02 Lift wall MT -
BS Col --1200 MT -
BS Col -1500x700 MT -
ES01 Grade Slab MT -
CS Col -1200x600 MT -
CS Col --1200 cum -
7 CS Col -1500x700 cum -
- - -
Concreting
Quantity
Zainath EnterRajan Engg Malik EnterprBum bum ShSia Ram Sha Lokeshwar
8.250
0.950
0.550
2.280
2.950 5.850 19.560
2.550 6.32
- - - 8.250 - -
- - 0.950 - - -
- - 0.550 - - -
- - 2.280 - - -
- 2.950 5.850 19.560 - -
- 2.550 6.320 - - -
- - - - - -
- - - - - -
- - - - - -
- - - - -
- -
221
-
- 265
-
-
- - - - - -
- - 221 - - -
- - - - - -
- - -
- -
- - - 265 - -
-
- - - - - -
- - - - - -
- 0.950 -
- 0.5500 -
- - 2.280 - - -
- 2.950 5.850 19.560
2.550 6.320 -
-
- -
-
- -
-
- - 8.250
- 0.950 -
- - 0.550
- - 2.280 - -
- 2.950 5.850 19.560
2.550 6.320 -
-
- ### -
-
-
-
-
Checked by Approved by Approved by
Rate Amount
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
15 -
15 -
15 -
15 -
15 -
15 -
15 -
15 -
15 #REF!
15 -
15 -
15 -
15 -
15
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
100 -
100 -
100 -
100 -
100 -
101 -
#REF!
Rate Amount
1500 -
1700 -
1700 -
1700 -
1700 5,015
1700 -
1700 -
1700 -
1700 -
1700 -
1700 4,335
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
2200 -
2400 -
2400 -
2400 -
2400 7,080
2400 6,120
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
15 -
15 -
15 -
15 -
15 -
15 -
15 -
15 -
15 #REF!
15 -
15 -
15 -
15 -
15 -
100 -
100 -
100 -
100 -
100 295
100 255
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
75 -
75 -
75 -
75 -
75 221
75 191
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
100 -
100 -
100 -
100 -
100 -
#REF!
Rate Amount
1500 -
1700 1,615
1700 935
1700 3,876
1700 9,945
1700 -
1700 -
1700 -
1700 -
1700 -
1700 10,744
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
2400 -
2400 2,280
2400 1,320
2400 5,472
2400 14,040
2400 15,168
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
15 -
15 -
15 3,315
15 -
15 -
15 -
15 -
15 -
15 #REF!
15 3,315
15 -
15 -
15 -
15 -
100 -
100 95
100 55
100 228
100 585
100 632
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
75 -
75 71
75 41
75 171
75 439
75 474
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
100 -
100 -
100 -
100 -
100 -
#REF!
0
Rate Amount
1500 12,375
1700 -
1700 -
1700 -
1700 33,252
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
2200 18,150
2400 -
2400 -
2400 -
2400 46,944
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
15 -
15 -
15 -
15 -
15 3,975
15 -
15 -
15 -
15 #REF!
15 -
15 -
15 3,975
15 -
15 -
100 -
100 -
100 -
100 -
100 1,956
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
75 619
75 -
75 -
75 -
75 1,467
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
100 -
100 -
100 -
100 -
100 -
#REF!
Rate Amount
1500 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
2200 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
15 -
15 -
15 -
15 -
15 -
15 -
15 -
15 -
15 #REF!
15 -
15 -
15 -
15 -
15 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
100 -
100 -
100 -
100 -
100 -
#REF!
Rate Amount
1500 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
2200 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
15 -
15 -
15 -
15 -
15 -
15 -
15 -
15 -
15 #REF!
15 -
15 -
15 -
15 -
15 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
100 -
100 -
#REF!
Rate Amount
1500 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
1700 -
2200 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
2400 -
15 -
15 -
15 -
15 -
15 -
15 -
15 -
15 -
15 #REF!
15 -
15 -
15 -
15 -
15 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
100 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
75 -
100 -
25-Jun-16
Paid Diff
8.250 0.00
0.950 3.55
0.550 8.84
2.280 0.77
28.360 18.35
- 0.00
- 0.85
- 1.85
- 8.09
- 3.23
8.870 7.97
- 1.36
- 0.00
- 0.00
- 0.00
- 0.00
- 0.00
- 0.00
8.250 0.00
0.950 3.55
0.550 8.84
2.280 0.77
28.360 18.35
8.870 7.97
- 0.85
- 1.85
- 8.09
- 3.23
- 0.95
- 1.36
- 0.00
- 0.00
- 0.00
- 0.00
- 0.00
- 0.00
- 150
- 0
221 46
- 100
265 29
- 819
- 440
- 200
221 46
- 100
265 29
- 819
- 440
8.250 8.25
0.950 8.05
18.77
2.280 3.82
28.360 8.34
1.80
- 1.71
- 3.70
- 16.18
- 16.50
8.870 6.98
- 2.71
- 1.10
- 0.00
- 6.88
- 0.00
- 0.00
- 0.00
8.250 1.37
0.950 8.05
- 18.77
2.280 3.82
28.360 8.34
- 1.80
- 1.71
- 3.70
- 16.18
- 1.10
8.870 6.98
- 2.71
- 0.00
- 0.00
- 0.00
- 0.00
- 0.00
- 0.00
- 0.00
- 0.00
- 0.00
- 0.00
- 0.00
L&T-SUCG JV CC-27 DMRC Project Delh
Measurement Book
Sub-Contractor Alam Ali
Period 26-May-16 25-Jun-16
g Fixing ofofwater
Fixing bar, as required
scaffolding and dismantling / RM
shifting of scaffolding to the next slab
4
including fixing of walers, H-Beams and
Plywood.
TVF Wall ES02 Cum 12 1.525 ###
Lintel Mullion Cum 12 1.525 1.525
Damper wall at Platform G5 Cum 5 1.525 1.525
ES02 Side wall Cum 4 1.525 1.525
Groove making in Block Cum
ject Delhi
5.65 157.68
4.55 126.98 -
6.6 184.19
-
-
468.85 35 16,410
16,410
ject Delhi
4.65 151.40
3.65 93.37
4.55 105.82 -
5.5
127.91
-
478.50 35 16,747
16,747
ject Delhi
- 30 -
5.65 157.677
3.65 101.862
4.25 49.420
5.65 52.559
Alam Ali
RKP STATION Pancard no
Dear sir
Kindly release the bill payment for the above mentioned period.
Dear sir
Kindly release the bill payment for the above mentioned period.
8 Err:509
a Roof/ Base Slab cum
b Wall/Column cum
Dear sir
Kindly release the bill payment for the above mentioned period.
Kindly release the bill payment for the above mentioned period.
Dear sir
Kindly release the bill payment for the above mentioned period.
8 Err:509
a Roof/ Base Slab cum -
b Wall/Column cum -
Dear sir
Kindly release the bill payment for the above mentioned period.
8 Err:509
a Roof/ Base Slab cum -
b Wall/Column cum -
e S0056741
Rate Amount
5750
62,704
6350 26,524
75 1,060
225 3,181
93,469
e SLL00130
Rate Amount
4300 13,115
15 1,125
15 1,125
225 686
75 229
7100 8,982
100 -
250 -
172.00 -
240.00 -
250 -
275 -
30 -
25,262
e
Rate Amount
5750 65,320
15 2,400
15 2,400
75 848
225.00 2,545
172.00 -
240.00 -
35.00 12,653
86,166
VMTP54243K
e S0026667
Rate Amount
4300 34,125
4700 44,114
15 8,625
15 8,625
75 1,783
225 5,350
7100 25,596
5750 16,388
100 -
150 -
172.00 -
240.00 -
250 -
275 -
30 -
144,605
DRVPS1217N
e S0051712
Rate Amount
1700 -
2400 -
15 -
15 -
100 -
75 -
35 -
100 -
250 -
172.00 -
240.00 -
275.00 -
250 -
275 -
30 -
0
e
Rate Amount
1700 -
2400 -
15 -
15 -
100 -
75 -
35 -
100 -
250 -
172.00 -
240.00 -
250 -
275 -
30 -
0
Summary for Rebar & Shuttering
Sno Item Unit Rate Alam Ali Rajan Engg Malik Err:509 Sia Ram Mujeeb
Planning Engg
25-Jun-16
Siddshwar Jha
0 Yogendra Sah 0
Prashad Gupta Construction
297.24 Err:509 -
- - - - -
- 117.20 - - -
- Err:509 - - -
- Err:509 - - -
- - - - -
Station Manager
L&T-SUCG JV CC-27 DMRC Project Delhi
Measurement Book
Sub-Contractor Sri Sai Engineering
Period 26-May-16 25-Jun-16
Glousing & cleaning the old / used structural steel including cutting of extra small bits of
1.4
steel from the main section, grinding & general cleaning.
Dismantling, lifting and stacking of structural steel members at ground level including
1
struts, walers etc as per requirement and instructions of Engineer-in-Charge.
Charges for splicing of soldier piles of section UB 610x229x125.1 as per drawing &
1
stacking of fabricated material as directed by eic.
a Bottom up D-wall Nos
b Cut & Cover Nos
Glousing & cleaning the old / used structural steel including cutting of extra small bits of
2
steel from the main section, grinding & general cleaning.
a Box Pushing MT
b Cut & Cover MT
Cumulative MT
L&T-SUCG JV CC-27 DMRC Project Delhi
Measurement Book
Sub-Contractor Hindustan Construction
Period 26-May-16 25-Jun-16
Glousing & cleaning the old / used structural steel including cutting of extra small bits of
3
steel from the main section, grinding & general cleaning.
Loading the fabrication steel on trailer, unloading at the station & erection & fixing of
structural steel fabricated by sub-contractor under item 3 above as per approved drawings,
8 as required. The rate shall include necessary welding at joints,connecting of joints with
bolts, nuts & anchor, fastner as per approved drawings.
99 98 - 1,920 -
41 ### - 6,000 -
111 110 - 6,000 -
7 7 - 6,000 -
1 - 122,500 -
304.609 304.609 -
42.974 42.974 -
18.876 18.876 -
88.738 51.404 37.334
455.197 417.863 37.334 3,650 136,269
Total 343,834
27 DMRC Project Delhi
rement Book
Site : RKP
Shift: Day/Night
2 2 - 6000 0.00
13 13 - 6000 0.00
35.840 35.840 -
109.001 109.001 -
12.720 ### -
157.561 157.561 - 5850 0.00
44.801 ### -
12.993 12.993 -
57.794 57.794 - 3650 0.00
Total -
27 DMRC Project Delhi
rement Book
Site : RKP
Shift: Day/Night
30.226 30.226 -
427.192 427.192 -
15.058 15.058 -
127.043 123.191 3.852
11.997 ### -
- -
2.088 2.088 - 3650 -
611.516 607.664 3.852 3650 14,060
Total 180,705
27 DMRC Project Delhi
rement Book
Site : RKP
Shift: Day/Night
31 ### - 1,920 0
42 42 - 1,920 0
31 31 - 6000 0
42 42 - 6000 0
Total 0
No of piles
Month Sri Sai Shree Shyam HCH
Remark
BP CC ES5 CC Water Supp CC
Jan '14 10 31 13 20
Feb '14 30 12 18
Mar '14 7
Apr '14 1 1 Extra Joint 2 11
May '14 9 7 Extra Joints 10
Jun '14 20 25
Jul '14 19 4EJ - 1 SP Hold 21
Aug '14 1
Sep '14
Oct '14
Nov '14
Dec '14 7
Oct '15
Total 40 99 7 13 2 106
57.135
53.063
50.863 25.323
220.546
570.230 285.247
285.247 285.247
59.485 6.291
50.066 7.069
53.063
50.863
213.477 13.36
35.46
-
3.85
8.41
3.85
25-Jun-16
HCH SBC
Remark Remark
ES3 ES05 CC ES4 ES2
2 Extra Joints
3 Extra Joints
17
(2KP)7 E 12 2 Extra Joints
1 Extra Joint-Ho 34 ES4-Only 23 Joints
19
15
33 10 ES05 not paid
53 10 29 53 0
PR Lenka
Approved by
373.99
L&T-SUCG JV CC-27 DMRC Project Delhi
Measurement Book
Sub-Contractor Raj Kumar
Period 26-May-16 25-Jun-16
Total Qty
SNo. Description Unit Qty Given
Comp
Drilling of pile of nominal diameter 750mm in all kinds of soil strata upto a depth
1 of 16m from ground level for Box Pushing at RK Puram Station using TMR Piling Rig m 656.00 656.00
Machine having higher torque & requisite associated tools as per direction of eic.
Drilling of pile of nominal diameter 750mm in all kinds of soil strata upto a depth
of 21m from ground level for Cut & cover at RK Puram Station using TMR Pilling
2 Rig Machine having higher torque & requisite associated tools as per direction of m 1,793.00 1,793.00
eic.
12.85
9.728
L&T-SUCG JV CC-27 DMRC Project Delhi
Measurement Book
Sub-Contractor SB Construction
Period 26-May-16 25-Jun-16
Total Qty
SNo. Description Unit Qty Given
Comp
Drilling of pile of nominal diameter 750mm for Cut & cover at RK Puram Station
1 using TMR Rig Machine as per direction of eic.
Depth -21m m 2,751.00 2,751.00
Depth -22m m 198.00 198.00
Drilling of pile of nominal diameter 750mm for Cut & cover at RK Puram Station
2 using Rotatry Piling Rig Machine as per direction of eic.
Depth -21m,0nos m 378.00 378.00
Depth -22m,0nos m 198.00 198.00
Drilling of pile of nominal diameter 750mm for ES4 at RK Puram Station using
3 Rotatry Piling Rig Machine as per direction of eic.
Depth -Variable,17nos m 155.85 155.85
Depth -13.6m,20nos m 272.00 272.00
Depth -14m,6nos m 84.00 84.00
Depth -14.5m,4nos m 58.00 58.00
Depth -15m,6nos m 90.00 90.00
Drilling of pile of nominal diameter 750mm for ES2 at RK Puram Station using
4 Rotatry Piling Rig Machine as per direction of eic.
Depth -Variable,7nos m 59.50 59.50
Depth -13.5m,40nos m 540.00 540.00
Depth -15.5m,9nos m 139.50 139.50
Drilling of pile of nominal diameter 750mm for ES3 at RK Puram Station using
5 Rotatry Piling Rig Machine as per direction of eic.
Depth -Variable,11nos m 94.17 94.17
Depth -11.645m,29nos m 337.71 337.71
Depth -13.145m,8nos m 105.16 105.16
Drilling of pile of nominal diameter 750mm for ES5 at RK Puram Station using
6 Rotatry Piling Rig Machine as per direction of eic.
Depth -11.1m,1nos m 11.10 11.10
Depth -12.1m,1nos m 12.10 12.10
Depth -12.5m,42nos m 525.00 525.00
Depth -13.1m,1nos m 13.10 13.10
Depth -14m,7nos m 98.00 98.00
Depth -16m,3nos m 48.00 48.00
Total 6,168.18 6,168.18
Site RKP STATION
Shift Day/ Night
Total Total
Qty for this
month Rate Amount
- 1,150 -
- 800 -
al -
Site RKP STATION
Shift Day/ Night
- 800 -
- 800 -
- 1,235 -
- 1,235 -
- 1,235 -
- 1,235 -
- 1,235 -
- 1,235 -
- 1,235 -
- 1,235 -
- 1,235 -
- 1,235 -
- 1,235 -
- 1,235 -
- 1,235 -
- 1,235 -
- 1,236 -
- 1,235 -
- 1,235 -
- 1,236 -
- 1,237 -
- 0
Boring Summery R0
SC Area Jan '14 Feb '14 Mar '14 Apr '14 May '14 Jun '14 Jul '14 Aug '14
BP 21 8 11
Raj Kumar
CC 25 8 2 2 24
CC 42 13 5 18 34 31
SBC
Mahalakshmi CC
ES1 21 8 11
Raj Kumar CC 25 8 2 2 24 18
HW 2
CC 44 13 5 18 38 31 17
ES4 34
SBC ES2
ES3
ES5
Mahalakshmi CC
Location No of piles
Cut & Cover 245 5390
Head Wall 2 44
ES1 48 672
ES4 53
ES2 56 784
ES3 48 672
ES5 55 770
507 8,332
Breakdown Period
To From No of Days
14-Oct-14 18-Oct-14 5
9-Nov-14 1
12-Nov-14 17-Nov-14 6
12
Ipsita Tikader Rohit Goggar PR Lenka
Prepared by Checked by Approved by
Total
40
61
143
25-Jun-16
Sep'14 Oct'14 Nov '14 Dec '14 May'15 Total
8 48
79
2
166
19 53
43 11 2 56
48 48
55 55
-
507
L&T-SUCG JV CC-27 DMRC Proje
Final Measurment
Sub-Contractor Starcon Infra
Period : 26-May-16 25-Jun-16
1 All charges for excavation in station, shaft & cut & cover portion by appropriate
means using the appropriate machinery.
Roof Shaft {Grid(24-26),(1-3)} cum
Roof Station(Upto Grid 3-4) cum
Beam RB1, RB2, RB4 cum
Deduction cum
a Roof Cumulative cum
Concourse Shaft {Grid(24-26),(1-3)} cum
Concourse Station (Grid(9-10) cum
Plunge Column Pile Concrete Deduction cum
b Concourse Cumulative cum
Base Shaft- Till Track Bed(24-26) cum
Base Shaft- Undercroft(24-26) cum
Base Station-Till Track Bed(3-24) cum
Base Station- Undercroft(3-24) cum
Base Station-Earthmat (18-22),(10-15),(5-8) cum
Base Station-Sump @ Grid 20,10,7 cum
Base Shaft-(1-3) cum
Base PCC cum
Plunge Column Pile Concrete Deduction cum
c Base Cumulative cum
Cut & Cover Upto Strut 1- From Head wall to KP 18 cum
Cut & Cover Upto Strut 2- From Head wall to KP 18 cum
Cut & Cover Upto Base,Haunch -Till 15.8m, (Sec 3) cum
Cut & Cover Upto Base,Undercroft -Till 15.8m, (Sec3) cum
Cut & Cover Upto Base,Corners -Till 15.8m, (Sec 3) cum
Cut & Cover Upto - From Head wall to KP 7, KP13-KP17 (Sec 1),excluding haunch cum
Cut & Cover Upto - From Head wall to KP 7, KP13-KP17 (Sec 1), Only Haunch cum
Cut & Cover Upto - From Head wall to KP 13 (Sec 2),excluding haunch cum
Cut & Cover Upto - From Head wall to KP 13 (Sec 2),Beam cum
Sno Description
Charges for lifting the excavated material below the roof slab using crane & bucket system/long boom/any other suitable e
1
same on ground level. The charges include equipment , manpower,consumables,fuel,etc. & work shall be executed as per
a Nov '14
L&T-SUCG JV CC-27 DMRC Project Delhi
Measurement Book
Sub-Contractor Starcon Infra
Period : 16-May-16 25-Jun-16
Description
Sno Unit
Charges for lifting the excavated material below from Entry/ Exit(Box Pushing) using
crane & bucket system/long boom/any other suitable equipment & dumping the same on
1
ground level. The charges include equipment , manpower,consumables,fuel,etc. & work
shall be executed as per direction eic.
All charges for excavation in station, shaft & cut & cover portion by appropriate
1
means using the appropriate machinery.
ES05 Subway Excavation(GL to Strut1) G2-5 cum
Total cum
2
Loading & disposal of excavated materials at dumping yard for all lifts within (50-
500)m as directed by eic.
ES05 Subway Excavation(GL to Strut1) G2-5 cum
Total cum
Transportation of Debris from station locations to dumping yard at Burari or any other
3
designated location for lead upto 30 km or internal shifting.
Debris for tunnel eye- SUCG-(4Trips) cum
Internal sisposal: Debris for tunnel eye- SUCG-(17Trips) cum
Total cum
Charging for backfilling with selected soil over RS. Rate includes cost of soil, loading,
4 transportation, unloading at RKP with min volume of 12cum.
July-15 Trip
Total cum
CG JV CC-27 DMRC Project Delhi
Final Measurment
Site RKP STATION
Shift Day/ Night
Total Qty Previously Dimension Current
Total Socpe Rate Amount
Comp Given L/No B/ H Qty
cum 0 55 0
0
Site RKP STATION
Shift Day/ Night
Total Qty Previously Dimension Current
Total Socpe Rate Amount
Comp Given L/Area B/ H Qty
0
0
6 Block Fixing(<1.5m) m 3
1 49.70 0.20 1.50 14.91 1,700 25,347
7 Block Fixing(1.5m-3.5m) m3 1 49.70 0.20 0.85 8.45 1,825 15,419
8 Block Fixing(>3.5m) m3 1 69.80 0.20 1.50 20.94 1,950 40,833
9 Drilling Dowels(Soffit of Top Slab) Nos 120 120 110 13,200
10 Drilling Dowels(Bottom of Slab) Nos 78 78 95 7,410
11 Lintel Beam- Rebar, Shutt, Conc m3 1 102.9 0.30 0.20 6.17 3,900 24,079
12 Column- Rebar, Shutt, Conc m 3
23 2.3 0.3 0.2 3.17 3,900 12,379
13 Scupper Drain m 19.7 19.70 495 9,752
166,227
1 D Wall Cleaning m2 25.00 5.00 125.0 30 3,750
2 Block Lowering & shifting Nos - -
3 Sand Shifting m3 -
4 Doka Tower Erection m3
- 35 -
5 Housekeeping m2
5
6 Block Fixing(<1.5m) m3 1 73.25 0.20 1.50 21.98 1,700 37,358
Oct'14
7 Block Fixing(1.5m-3.5m) m3
1 74.33 0.20 0.85 12.64 1,825 23,061
8 Block Fixing(>3.5m) m3
1 19.72 0.20 1.80 7.10 1,950 13,843
9 Drilling Dowels(Soffit of Top Slab) Nos - 110 -
10 Drilling Dowels(Bottom of Slab) Nos 60 60 95 5,700
11 Lintel Beam- Rebar, Shutt, Conc m3
45.5 0.30 0.20 - 3,900 -
12 Column- Rebar, Shutt, Conc m3
12 2.3 0.3 0.2 1.66 3,900 6,458
13 Scupper Drain m 25 25.00 495 12,375
102,545
DurgaConstruction Shree Shyam
No L B H CS-RS Rate Amt No L B H CS-RS Rate Amt
- 30 - 105.0 5.00 525.0 30 15,750
- - - -
- -
- 35 - - 35 -
- 5 - - 5 -
- 1,700 - 1 104.5 0.20 1.10 22.99 1,700 39,083
- 1,825 - 1 104.5 0.20 0.85 17.77 1,825 32,421
- 1,950 - - 1,950 -
- 110 - - 110 -
- 95 - 168 168 95 15,960
- 3,900 - 1 75.00 0.30 0.20 4.50 3,900 17,550
- 3,900 - 20 2.35 0.30 0.20 2.82 3,900 10,998
- 495 - 133.0 133.0 495 65,835
- 197,597
24.00 5.00 120.00 30 3,600 - 30 -
- - - -
- -
- 35 - - 35 -
- 5 - - 5 -
1 69.53 0.20 1.50 20.86 1,700 35,460 1 7.85 0.20 1.50 2.36 1,700 4,004
1 37.07 0.20 1.20 8.897 1,825 16,237 1 102.6 0.20 1.15 23.59 1,825 43,045
1 - 1,950 - 1 102.6 0.20 1.25 25.64 1,950 49,993
- 110 - 168 168 110 18,480
60 60 95 5,700 9 9 95 855
- 3,900 - 11 2.35 0.20 0.30 1.55 3,900 6,049
5 2.30 0.30 0.20 0.69 3,900 2,691 46.60 0.20 0.30 - 3,900 -
44.07 44.07 495 21,815 8.75 8.75 495 4,331
85,503 126,757
18.10 5.00 90.50 30 2,715 - 30 -
1,300 1,300 - - -
- -
1 40.00 1.58 3.00 189.0 35 6,615 - 35 -
100 12 1,200 5 6,000 - 5 -
1 74.75 0.20 1.50 22.43 1,700 38,123 - 1,700 -
1 63.75 0.20 0.85 10.84 1,825 19,778 - 1,825 -
1 - 1,950 - - 1,950 -
- 110 - - 110 -
78 78 95 7,410 - 95 -
31.50 0.20 0.30 - 3,900 - - 3,900 -
7 2.30 0.20 0.30 0.97 3,900 3,767 - 3,900 -
36.75 36.75 495 18,191 - 495 -
102,600 -
L&T-SUCG JV CC-27 DMRC Project Delhi
Measurement Book
Sub-Contractor Narayani Site RKP STATION
Period : 26-May-16 25-Jun-16
Debit Note Shift Day/ Night
Days
Sno Description Unit No Qty Rate
From To Duration
1 Cuplock standard L-1.5m Nos 500 0 0.00 0.35
2 Cuplock ledger L-1.5m Nos 1500 0 0.00 0.35
3 Adjustable Base Jack Nos 484 0 0.00 0.23
4 Adjustable U Jack Nos 450 0 0.00 0.23
5 Adjustable Base Jack Nos 16 0 0.00 0.23
6 Adjustable U Jack Nos 50 0 0.00 0.23
KP STATION
Day/ Night
Amount
-
-
-
-
-
-
0
L&T-SUCG JV CC-27 DMRC Project Delhi
Measurement Book
Sub-Contractor Durga Construction
Period ### 25-Jun-16
Total Qty
SNo. Description Unit Qty Given
Comp
1 L/C for block laying at all levels
a Upto 1.5m height cum -
b Between (1.5-3.5)m height cum -
c Above 3.5m height cum -
2 L/C for construction of RCC stiffener column / wind post 200mm x 200mm cum -
3 L/C for construction of RCC runner beam / tie beam cum -
4 L/C for construction of scupper drain 400mm wide & 300mm cum -
Total
L&T-SUCG JV CC-27 DMRC Project Delhi
Measurement Book
Sub-Contractor Shree Shyam
Period ### 25-Jun-16
Total Qty
SNo. Description Unit Qty Given
Comp
1 L/C for block laying at all levels
a Upto 1.5m height cum -
b Between (1.5-3.5)m height cum -
c Above 3.5m height cum -
2 L/C for construction of RCC stiffener column / wind post 200mm x 200mm cum -
3 L/C for construction of RCC runner beam / tie beam cum -
4 L/C for construction of scupper drain 400mm wide & 300mm cum -
Total
L&T-SUCG JV CC-27 DMRC Project Delhi
Measurement Book
Sub-Contractor United Associates
Period ### 25-Jun-16
Total Qty
SNo. Description Unit Qty Given
Comp
1 L/C for block laying at all levels
a Upto 1.5m height cum -
b Between (1.5-3.5)m height cum -
c Above 3.5m height cum -
2 L/C for construction of RCC stiffener column / wind post 200mm x 200mm cum -
3 L/C for construction of RCC runner beam / tie beam cum -
4 L/C for construction of scupper drain 400mm wide & 300mm cum -
Total
Site RKP STATION
Shift Day/ Night
Qty for
current Rate Amount
month
-
-
-
-
-
-
-
Site RKP STATION
Shift Day/ Night
Qty for
current Rate Amount
month
-
-
-
-
-
-
-
Site RKP STATION
Shift Day/ Night
Qty for
current Rate Amount
month
-
-
-
-
-
-
-
Balance Work Scope Amba Construction Kalayan Sah Harendra Paswan
Amount Qty
10584 60
1832 628
10043 3443
74504 51088
54656 468
6300 1440
3024 58
802 46
8803 377
13741 9423
58444 802
58444 802
1073442 736075
27825 1908
22050 15120
23100 7
10080 1728
2100 12
1260 29
1402589
a Enterprises Shivlal Kushwaha Krishna Enterprises MK Dubey
18 10584 ###
13 802 ###
1402589
Sno. Sub Contractors Aug'14 Sep'14 Oct'14 Avg Extended LOI
3,205,918 16.01%
6,011,097 32.08%
1,402,589 6.07%
4,808,877 20.53%
601,110 1.50%
2,805,178 14.60%
801,480 4.21%
1,402,589 5.02%
21,038,839
Balance Work Scope L B H Total Qty
11 20 5 16 2 9 3
11 20 5 16 2 9 3
10 18 4 14 2 8 2
10 18 4 14 2 8 2
5
5
4
4
139
44
400
400
204
14901
80
15
42
420
17
11
2
30
40
40
973
1176
599
13
6
11
204
48015
48015
48015
53424
5880
1890
9450
557
4410
14
504
4
8
L&T- SUCG JV CC 27 DELHI
(A Joint Venture between Larsen & Toubro Limited and Shanghai Urban Construction Gro
Balance work Feb-15
Quantity
SNo. Description
Amba Const. Kalyan Sah Harendra
Wooden Lagging Shifting 45,915 45,915 Paswan 22,958
Wooden scrap shifting 45,915 45,915 22,958
L/C for Internal
1 Doka Shifting 45,915 45,915 22,958
carting of material
TMT scrap & offcut shifting 45,915 45,915 22,958
Misc 45,915 45,915 22,958
Dressing/Base Entry /Exit 81,471 58,513 58,513
2
Preparation Misc 81,471 58,513 58,513
L/C for Surface RS 81,471 58,513 58,513
Preparation for
3 CS 81,471 58,513 58,513
Screed/
Waterproofing BS 81,471 58,513 58,513
L/C for road
4 114,788 114,788 114,788
washing
Waterproofing 38,263 38,263 38,263
5 L/C for BackfillingCC SP & wall gap filling 38,263 38,263 38,263
Misc 38,263 38,263 38,263
Cleaning 229,577 344,365 114,788
6 Barrication boards Shifting(100m) - - -
Shifting(200-250m) - - -
L/C for Entry /Exit/Station 407,354 407,354 177,777
7
PCC/Concreting Misc - - -
RS 135,785 174,048 -
8 L/C for Screed CS 135,785 174,048 -
BS 135,785 174,048 -
Entry /Exit/Station 57,394 57,394 -
Labour charges for Ancillary Building 57,394 57,394 -
9
curing Column 57,394 57,394 -
Labour charges for
9
curing
Misc 57,394 57,394 -
Entry /Exit 101,839 101,839 -
CJ 101,839 101,839 -
10 L/C for chipping
Column Hacking 101,839 101,839 -
Undercroft Hacking 101,839 101,839 -
RS 86,651 109,608 40,735
CS 86,651 109,608 40,735
BS 86,651 109,608 40,735
Ground Level 86,651 109,608 40,735
L/C for Fabrication Yard 86,651 109,608 40,735
11
Housekeeping Misc- Wheel wash, office 86,651 109,608 40,735
Entry 02,03, 04,05 86,651 109,608 40,735
CC BS 86,651 109,608 40,735
CC RS 86,651 109,608 40,735
CC Ground Level 86,651 109,608 40,735
12 L/C for repairing 177,777 814,708 241,678
13 L/C for Dewatering 114,788 114,788 -
14 L/C for welding works 177,777 177,777 -
15 L/C for giving direction to crane operator for lifting ma 177,777 177,777 -
16 L/C for scrap segregation/Rebar Shifting 114,788 114,788 -
17 L/C for loading & unloading of material - - -
18 L/C for plaster work - - -
19 Cleaning Of Spilled Concrete 114,788 459,154 -
20 L/C for dismantling Wooden Battens - - -
21 Fixing of timber lagging - - -
22 Dismantling of Brick Work - - -
23 Compaction of soil for PCC - - -
24 DWall cleaning - 114,788 -
25 Hand Railing Fixing - - -
26 Toe Guard - - -
Brickwork
27 Other - - -
4,291,929 5,732,379 1,578,529
tion Group)
eb-15
114,788 114,788
38,263 38,263
38,263 38,263
38,263 38,263
229,577 229,577
- -
- -
292,566 292,566
- -
97,522 80,559
97,522 80,559
97,522 80,559
28,697 28,697
28,697 28,697
28,697 28,697
28,697 28,697
- -
- -
- -
- -
52,214 40,735
52,214 40,735
52,214 40,735
52,214 40,735
52,214 40,735
52,214 40,735
52,214 40,735
52,214 40,735
52,214 40,735
52,214 40,735
- 114,788
- -
355,555 -
177,777 -
114,788 -
- -
- -
- -
229,577 229,577
229,577 229,577
- -
- -
- -
- -
- -
- -
3,310,633 2,496,836
L&T- SUCG JV CC 27 DELHI
(A Joint Venture between Larsen & Toubro Limited and Shanghai Urban Construction Gro
Balance work
Description Rate Required Duration
SNo.
Month Amba Const.
Wooden Lagging Shifting Sep-16 19 1
Wooden scrap shifting Sep-16 19 1
L/C for Internal
1 Doka Shifting 600 Sep-16 19 1
carting of material
TMT scrap & offcut shifting Sep-16 19 1
Misc Sep-16 19 1
Dressing/Base Entry /Exit Sep-16 19 1
2
Preparation Misc Sep-16 19 1
L/C for Surface RS 30 Sep-16 19 1 1
Preparation for
3 CS Sep-16 19 1 1
Screed/
Waterproofing BS Sep-16 19 1 1
L/C for road 19 1
4 5 Sep-16
washing
Waterproofing Sep-16 19 1
5 L/C for Backfilling CC SP & wall gap filling 70 Sep-16 19 1
Misc Sep-16 19 1
Cleaning 15 Sep-16 19 1
6 Barrication boards Shifting(100m) 180 Sep-16 19
Shifting(200-250m) 170 Sep-16 19
L/C for PCC/ Entry /Exit/Station Sep-16 19 1 1
7 100
Concreting Misc Sep-16 19
RS Sep-16 19 1 1
8 L/C for Screed CS 250 Sep-16 19 1 1
BS Sep-16 19 1 1
Entry /Exit/Station Sep-16 19 1
Labour charges for Ancillary Building Sep-16 19 1
9 5
curing Column Sep-16 19 1
Misc Sep-16 19 1
Entry /Exit Sep-16 19 1
Manpower
Kalyan Sah Harendra Paswan Varsha Ent Krishna Ent Amount
1 1 1 1 62,592
1 1 1 1 62,592
1 1 1 1 62,592
1 1 1 1 62,592
1 1 1 1 62,592
1 1 1 1 62,592
1 1 1 1 62,592
1 1 1 1 159,531
1 1 1 1 159,531
1 1 1 1 159,531
1 1 1 1 312,961
1 1 1 1 104,320
1 1 1 1 104,320
1 1 1 1 104,320
1 1 1 1 312,961
-
-
1 1 1 1 1 1 1 797,656
-
2 1 1 265,885
2 1 1 265,885
2 1 1 265,885
2 1 1 78,240
2 1 1 78,240
2 1 1 78,240
2 1 1 78,240
2 78,240
2 78,240
2 78,240
2 78,240
5 2 3 2 125,184
5 2 3 2 125,184
5 2 3 2 125,184
5 2 3 2 125,184
5 2 3 2 125,184
5 2 3 2 125,184
5 2 3 2 125,184
5 2 3 2 125,184
5 2 3 2 125,184
5 2 3 2 125,184
4 1 1 312,961
1 312,961
1 1 484,695
1 1 484,695
1 1 312,961
-
-
1 312,961
1 1 -
1 1 -
-
-
1 -
-
-
-
3 - 96 1 - 36 3 - 56 1 - 46 7,549,930
99 37 59 47
322
AY 6,790,000
Feb-15
Bifurcation
Quantity Kalyan Sah Quantity Harendra Quantity Varsha Ent
104 62,592 104 Paswan 62,592 104 62,592
104 62,592 104 62,592 104 62,592
104 62,592 104 62,592 104 62,592
104 62,592 104 62,592 104 62,592
104 62,592 104 62,592 104 62,592
2,086 62,592 2,086 62,592 2,086 62,592
2,086 62,592 2,086 62,592 2,086 62,592
5,318 62,592 2,086 62,592 2,086 62,592
5,318 62,592 2,086 62,592 2,086 62,592
5,318 62,592 2,086 62,592 2,086 62,592
62,592 312,961 62,592 312,961 62,592 312,961
1,490 104,320 1,490 104,320 1,490 104,320
3,477 104,320 3,477 104,320 3,477 104,320
3,477 104,320 3,477 104,320 3,477 104,320
20,864 312,961 20,864 312,961 20,864 312,961
- - - - - -
- - - - - -
7,977 797,656 7,977 484,695 4,847 797,656
- - - - - -
1,064 208,641 835 - - 104,320
1,064 208,641 835 - - 104,320
1,064 208,641 835 - - 104,320
15,648 156,480 31,296 - - 78,240
15,648 156,480 31,296 - - 78,240
15,648 156,480 31,296 - - 78,240
15,648 156,480 31,296 - - 78,240
313 156,480 626 - - -
313 156,480 626 - - -
313 156,480 626 - - -
313 156,480 626 - - -
25,037 156,480 31,296 62,592 12,518 93,888
25,037 156,480 31,296 62,592 12,518 93,888
25,037 156,480 31,296 62,592 12,518 93,888
25,037 156,480 31,296 62,592 12,518 93,888
25,037 156,480 31,296 62,592 12,518 93,888
25,037 156,480 31,296 62,592 12,518 93,888
25,037 156,480 31,296 62,592 12,518 93,888
25,037 156,480 31,296 62,592 12,518 93,888
25,037 156,480 31,296 62,592 12,518 93,888
25,037 156,480 31,296 62,592 12,518 93,888
10,432 1,251,843 41,728 312,961 10,432 -
62,592 312,961 62,592 - - -
242 484,695 242 - - 484,695
24,235 484,695 24,235 - - 484,695
1,391 312,961 1,391 - - 312,961
- - - - - -
- - - - - -
31,296 312,961 31,296 - - -
- - - - - 312,961
- - - - - 312,961
- - - - - -
- - - - - -
- 312,961 10,432 - - -
- - - - - -
- - - - - -
- - - - - -
9,278,105 2,988,381 5,835,536
4,165,000
SNo. Description Unit No L B H Qty
1,689.78
Scope
Location Unit No L B Area
G(24-26),(1-3) m2 2 17.00 24.57 835.38
G(23-24) m 2
1 13.20 21.57 284.72
G(23-26) Jn m 2
2 30.20 0.30 18.12
G(1,26) Jn m 2
2 24.57 0.30 14.74
G(3-20) m 2
1 190.60 21.57 4,111.24
G(3-20) Jn m 2
2 190.60 0.30 114.36
G(1-7),(23-26) Pedestral m2 72 2.75 0.60 118.80
G(1-20) Beam m 2
2 152.48 0.60 182.97
m 2
4 35.30 0.60 84.72
RB1 m 2
1 17.80 0.60 10.68
m 2
1 14.36 0.80 11.49
m 2
1 2.50 2.30 5.75
RB2 m 2
1 19.00 0.60 11.40
m 2
1 19.00 1.05 19.95
RB4 m 2
1 20.20 0.60 12.12
m 2
1 20.20 1.10 22.22
m 2
1 20.23 0.60 12.14
m 2
1 20.23 1.10 22.25
RB7 m 2
1 20.20 0.60 12.12
m 2
1 20.20 1.05 21.21
Air Shaft m 2
1 8.10 3.10 25.11
Temp Cutout m 2
3 8.50 5.50 140.25
m 2
1 10.00 8.50 85.00
Plumb Shaft m 3
2 1.40 0.30 0.84
Fresh Air Shaft m3 2 1.00 0.30 0.60
4,839
Date 25-Jun-16
Note- This is the credit note in reference to Debit note serial no 167.
Planning
Site RKP STATION
Shift Day/ Night
Net
Rate Amount
Reading
Station Manager
L&T-SUCG JV
Debit Note
Date 25-Jun-16
Total
Diesel
Sub-
SNo. Equipment per day Unit
Contractor Equipment
(L) Diesel
requisition
Planning
Bill Receiving
Si no Vendor Name MB No
1 Md Muzeeb 15432.15433.15434
lokeshwar 15147
2 Sia ram sharma 15148.15149
3 malik 15431
5 zenith 15145.15146
6 vikram singh 15428.1543
7 siddeshawar gupta 15425.15426.15427
8 yogender saw 15422.15423.15424
9 jha const 15421
10 ruby rai 15420,
11 amba(supply) 15133.15134
12 krishan(supply) 15137.15138
13 kalyan(supply) 15135.15136.
14 varhsa(supply) 15139.15140.
15 sas 15437
16 ashish 15438
17 prabhakar rai 15440
18 geo spar ltd 15436
19 hch 15131.15132
20 sri sai 15128.15129.15130
22 malik(block) 15260
23 krishna(block) 0
24 vimla(block) 0
25 mehti(block) 15261
26 rajan(block) 15262
1.06 76.50 - - -
0.13 10.50 - - -
0.21 8.75 - - -
1.50 - ### - 1.50 108.00 1.50
Rate
Amount
Equipment Manpower
Diesel
requisition (Rigger)
12,500 60 554.00 -
10,000 60 554.00 -
1,155 60 554.00 -
12,500 60 554.00 26,061
99,199
Station Manager
L&T-SUCG JV CC-27 DMRC Project Delhi
2 LS
Total
Site RKP STATION
Shift Day/ Night
LS 1.00
LS 1.000
L&T-SUCG JV CC-27 DMRC Project De
Measurement Book
Sub-Contractor Starcon Infra
Period : 26-May-16 25-Jun-16
1 All charges for excavationin station, shaft & cut & cover portion by
appropriate means using the appropriate machinery.
Roof Shaft {Grid(24-26),(1-3)} cum 3,195 3,195
Roof Station(Upto Grid 3-4) cum 19,059 19,059
Beam RB1, RB2, RB4 cum 427 427
a Roof Cumulative cum 22,681 22,681
Concourse Shaft {Grid(24-26),(1-3)} cum 4,845 4,845
Concourse Station (Grid(9-10) cum 28,899 28,899
b Concourse Cumulative cum 33,745 33,745
Base Shaft- Till Track Bed(24-26) cum 3,308 3,308
Base Shaft- Undercroft(24-26) cum 106 106
Base Station-Till Track Bed(11-16a) cum 38,615 23,927
Base Station- Undercroft(11-16a) cum 2,992 1,854
Base Station-Earthmat (18-22)-SL:5632 cum 413 413
Base Station-Sump @ Grid 20 cum 75 75
Base Shaft-(1-3) cum 4,151 3,483
c Base Cumulative cum 49,659 33,165
Cut & Cover Upto Strut 1- From Head wall to KP 12 cum 8,820 6,022
Cut & Cover Upto Strut 2- From Head wall to KP 11 cum 24,268 15,267
Cut & Cover Upto Base,Haunch -Till 15.8m, (Sec 3) cum 1,208 1,208
Cut & Cover Upto Base,Undercroft -Till 15.8m, (Sec3) cum 1,690 1,690
Cut & Cover Upto Base,Corners -Till 15.8m, (Sec 3) cum 1,131 1,131
Cut & Cover Upto - From Head wall to KP 7 (Sec 1),excluding haunch cum 21,076 11,520
Cut & Cover Upto - From Head wall to KP 7 (Sec 1), Only Haunch cum 147 80
Cut & Cover Upto - From Head wall to KP 10 (Sec 2),excluding haunch cum 12,652 6,491
d Cut & Cover Cumulative cum 70,992 43,409
e Box Pushing (Ground level to Strut 1) cum 432
Total cum 177,077 133,432
Loading & disposal of excavated materials at dumping yard for all lifts
2
within 20 km as directed by eic.
Roof Shaft {Grid(24-26),(1-3)} cum 3,195 3,195
Roof Station(Upto Grid 3-4) cum 19,059 19,059
Beam RB1, RB2, RB4 cum 427 427
a Roof Cumulative cum 22,681 22,681
Concourse Shaft {Grid(24-26),(1-3)} cum 4,845 4,845
Concourse Station (Grid(9-10) cum 28,899 28,899
b Concourse Cumulative cum 33,745 33,745
Base Shaft- Till Track Bed(24-26) cum 3,308 3,308
Base Shaft- Undercroft(24-26) cum 106 106
Base Station-Till Track Bed(11-16a) cum 38,615 23,927
Base Station- Undercroft(11-16a) cum 2,992 1,854
Base Station-Earthmat (18-22) cum 413 413
Base Station-Sump @ Grid 20 cum 75 75
Base Shaft-(1-3) cum 4,151 3,483
c Base Cumulative cum 49,659 33,165
Cut & Cover Upto Strut 1- From Head wall to KP 12 cum 8,820 6,022
Cut & Cover Upto Strut 2- From Head wall to KP 11 cum 24,268 15,267
Cut & Cover Upto Base,Haunch -Till 15.8m, (Sec 3) cum 1,208 1,208
Cut & Cover Upto Base,Undercroft -Till 15.8m, (Sec3) cum 1,690 1,690
Cut & Cover Upto Base,Corners -Till 15.8m, (Sec 3) cum 1,131 1,131
Cut & Cover Upto - From Head wall to KP 7 (Sec 1),excluding haunch cum 21,076 11,520
Cut & Cover Upto - From Head wall to KP 7 (Sec 1), Only Haunch cum 147 80
Cut & Cover Upto - From Head wall to KP 10 (Sec 2),excluding haunch cum 12,652 6,491
d Cut & Cover Cumulative cum 70,992 43,409
e Box Pushing (Ground level to Strut 1) cum 432
Total cum 177,077 133,432
Sno Description
1 Charges for lifting the excavated material below the roof slab using crane & bucket system/long boom/any other suitable equipment & dumpi
ground level. The charges include equipment , manpower,consumables,fuel,etc. & work shall be executed as per direction eic.
*Debit Note attached
ject Delhi
ject Delhi
300,000.00
Bill Receiving
Si no Vendor Name MB No
1 Md Muzeeb 15432.15433.15434
lokeshwar 15147
2 Sia ram sharma 15148.15149
3 malik 15431
5 zenith 15145.15146
6 vikram singh 15428.1543
7 siddeshawar gupta 15425.15426.15427
8 yogender saw 15422.15423.15424
9 jha const 15421
10 ruby rai 15420,
11 amba(supply) 15133.15134
12 krishan(supply) 15137.15138
13 kalyan(supply) 15135.15136.
14 varhsa(supply) 15139.15140.
15 sas 15437
16 ashish 15438
17 prabhakar rai 15440
18 geo spar ltd 15436
19 hch 15131.15132
20 sri sai 15128.15129.15130
22 malik(block) 15260
23 krishna(block) 0
24 vimla(block) 0
25 mehti(block) 15261
26 rajan(block) 15262
C
22
22
21.5
21.9
21.9
2-Nov 21.9
u
21.8
22
22
21.6
21.3
21.6
t
3-Nov
22
22
22
22.05
22
6/11/2015
&
22
22
22.7
21.4
18.95
7/11/2015 21.85
C
21.6
22.2
7/11/2015
9/11/2015
21.1
20.5
22
C
o
22.4
21.8
21.6
22.4
10/11/2015 21.9
22.6
v
21.2
22
22
14/11/2015
22
22
15
e
15
15
15
15
15
16/11/2015
r
15
15
15
15
15
15
22
17/11/2015 22
19.07
22
22
18/11/2015
S
22
20.7
21.8
19/11/2015 21.5
22
22
P
18.35
22
20/11/2015
22
21.3
22.3
22
23/11/2015 22
22
20.3
21.1
24/11/2015
20.8
24/11/2015
21.8
22
21.8
26/11/2015
20.4
21.8
21
27/11/2015
22.3
22
22
22
28/11/2015
22
22
22
2197.17
Chandralekha
date sqm type
30/10/2015 19.2 F 274.99
31/10/2015 13 F
2/11/2015 11.55 F
3/11/2015 7.41 F
17/11/2015 49.34 F
16/11/2015 19.48 F
5/11/2015 30.49 F
19/11/2015 19.27 F
6/11/2015 29.18 F
23/11/2015 29.6 F
7/11/2015 17.53 F
21/11/2015 18.54 F
25/11/2015 10.4 F
19/10/2015 43.1025 R BP
20/10 80.175 R BP
26/10 44.49 R ES02
28/10 66.45 R CNC 302.055
29/10 47.475 R CNC 123.2775
30/10 81.39 R CNC 107.895
38.635 R ES02
3-Nov 24.77 R ES02
18/11/2015 106.74 R CNC
808.2175
WBC CONCRETE QTY
towards iit hostel to before pit area 10.363 9.4 2 sqm 194.8244
ES04
pit area 7.65 10.9 1 sqm 83.385
pit area to GL(Stair) 10.791 3.8 2 sqm 82.0116
Towards road side 17.587 9.4 1 sqm 165.3178
Total qty 668.7076 636
G1-8 69 9.8 1 sqm 676.2
End wall at G8 6.5 9.8 1 sqm 63.7
ES05
Thrust bed area 24.98 10.5 1 sqm 262.29
Total qty 1002.19 951 0.000
HW Towards JNU 12.502 9.4 1 sqm 117.5188
HW Towards Bikaji 2.25 11.4 1 sqm 25.65
Flat area 10.363 9.4 2 sqm 194.8244
ES03 pit area 7.65 10.9 1 sqm 83.385
ES03
pit area to GL(Stair) 10.791 3.8 2 sqm 82.0116
Towards road side 17.587 9.4 1 sqm 165.3178
Total qty 668.7076 383.33 193.56
Total qty done 193.560
Fixing Removal
Krishna Varsha Shri shyam chandralekha
Current bill Current bill till now Till now current bill Remarks
482
479.51 166.550
120 0.000
-
Fixing 166.55 Removal
Shuettering & Reinforcement Details Of RKP
Total Distribution to each subcontractor at Site
Description Balance
UOM Rate Vikram Singh
Project
Sl.No Scope Qty Amount Till Nw Paid qty Current Bill Amount
4 REINFORCED CEMENT CONCRETE
Laying reinforcement cement concrete of specified grade as per
approved construction drawings using suitable equipment's,
vibrating/compacting, finishing smooth and as directed by Engineer-in-
charge and as per approved Construction drawings and specifications.
(Concrete of specified grade shall be supplied by Contractor free of cost
at ground level only in truck mixers). Concrete shall be laid with
stationary concrete pump including pipes/Boom Placer including diesel
supplied by Contractor. Payment shall be made by calculating the
cubical content based on the approved construction drawings. Including
for hacking/chipping the existing concrete surface to make it rough
before laying fresh concrete. Including cleaning of spilled pour, shifting
of vibrators, with all required quality procedures such as casting of test
cubes and curing for 14 days.
a Roof Slab cum 100 1450 104.167
b Concourse Slab/Intermediate slabs cum 125 69.7125
c Base Slab cum 100 1655.45
d Walls external cum 150 942.54 65.754
e Column cum 250 10.54
f UPE Wall, Platform slab and Platform walls. cum 250 75.45
5 SHUTTERING
Making shuttering panels (wooden and /or steel) and packing properly
using jute, cotton and thermocole. All materials including nails shall be
provided by Contractor in the station area.
For wall panels of Station box (in case of Bottom up method) and walls
a sqm 172 9616 1201.33 206,629.33 571.91 330.74 56,887.28
of Entry / Exits
b For all other members at all levels sqm 65 1450 95.8333 6,229.17
(For Top down and Bottom up) Base slab, Concourse Slab and Roof Slab
a sqm 140 432
of Station Box.
c Walls for station box (in case of Bottom-up Method) sqm 230 845.45 140.908 32,408.92 138.00 - -
Roof Slab and Concourse Slab for Station Box (in case of bottom up
d method) walls for Entry/exit, Entry / Exit roof Slab, Vent Shaft Wall, sqm 240 6711.75 839 Err:509
Plenum wall, UPE wall, Platform Slab, Station Cut-out Slab.
7 SCAFFOLDING
a All floor slab (except raft) including beams, staircases etc. Cum 35 30559.3 5093.21 178,262.29 1,353.76 497.91 17,426.94
Description
UOM Rate
Sl.No
Placing plywood 3mm/4mm on PCC and fixing with nails and sealing the joints
1 with tape. All the materials (plywood, nails and tape) shall be supplied by sqm 30
Contractor free of cost within station area.
3 REINFORCEMENT
Reinforcement Bars of all sizes for Slab of Station Box at Roof Level,
a MT 3,700
Concourse level, Base Slab. (Top Down Construction)
Reinforcement Bars of all sizes for Slab of Station Box at Roof Level,
b MT 4,100
Concourse level, Base Slab. (Bottom up Construction) including Cut and Cover
Reinforcement Bars of all sizes for Columns, Platform slab, Entry Exit, UPE
c MT 4,100
Wall and other misc structures. (Both Top Down and Bottom Up Construction)
Making shuttering panels (wooden and /or steel) and packing properly using
jute, cotton and thermocole. All materials including nails shall be provided by
Contractor in the station area.
For wall panels of Station box (in case of Bottom up method) and walls of
a sqm 172
Entry / Exits
Shifting the shuttering material from location of making (or from location of
First fixing to the next one) and fixing, using thermocole/plywood in position
shuttering (wooden and / or steel) and packing properly using jute, cotton and
thermocole. All materials including nails shall be provided by Contractor in the
6
station area. The rate shall include the fixing of fixtures if any, required for
works, making of cut-out boxes, if any, and removal and stacking of all
shuttering after completion of casting of concrete. Inclued for cleaning and
applying oil to shuttering material (oil supplied by Contractor).
(For Top down and Bottom up) Base slab, Concourse Slab and Roof Slab of
a sqm 140
Station Box.
c Walls for station box (in case of Bottom-up Method) sqm 230
Roof Slab and Concourse Slab for Station Box (in case of bottom up method)
d walls for Entry/exit, Entry / Exit roof Slab, Vent Shaft Wall, Plenum wall, UPE sqm 240
wall, Platform Slab, Station Cut-out Slab.
Fixing of couplers in cut-out locations in slabs and walls with proper packing
i Nos 15
using shuttering tape and thermocole to power level and alignment.
7 SCAFFOLDING
a All floor slab (except raft) including beams, staircases etc. Cum 35
28.54
422
845.45
20.4
1125.45
743
30559.25
3 REINFORCEMENT w
o
r
a L/C For C,B,F of Staircase, Subway Grade Slab MT 6,350 16.5 4.95 31,433 4.177 26,524
k
b L/C For C,B,F of (wall+Binder) of internal wall at Paltform,concourse at station level MT 5,750 43.55 8.71 50,083 10.905 62,704
L/C For C,B,F of Subway ,entry walls MT 4,700 194.65 38.93 182,971
L/C For C,B,F of Column Reinforcement upto 12dia bar MT 7,100 20.896 4.1792 29,672
L/C For C,B,F of column reinforcement above 12dia MT 6,800 9.65 1.93 13,124
5 SHUTTERING
Making shuttering panels (wooden and /or steel) and packing properly using jute, cotton and thermocole. All materials including nails shall be provided by
Contractor in the station area.
a For wall panels of Station box (in case of Bottom up method) and walls of Entry / Exits sqm 172 10,500.00 110 18,920
b For all other members at all levels sqm 65 1,550.00 0 -
Shifting the shuttering material from location of making (or from location of First fixing to the next one) and fixing, using thermocole/plywood in position
shuttering (wooden and / or steel) and packing properly using jute, cotton and thermocole. All materials including nails shall be provided by Contractor in the
6
station area. The rate shall include the fixing of fixtures if any, required for works, making of cut-out boxes, if any, and removal and stacking of all shuttering
after completion of casting of concrete. Inclued for cleaning and applying oil to shuttering material (oil supplied by Contractor).
a (For Top down and Bottom up) Base slab, Concourse Slab and Roof Slab of Station Box. sqm 140 0
b Base slab of Entry / Exit sqm 140 635.65 -
c Walls for station box (in case of Bottom-up Method) sqm 230 145
Roof Slab and Concourse Slab for Station Box (in case of bottom up method) walls for Entry/exit, Entry / Exit roof Slab, Vent Shaft Wall, Plenum wall, UPE wall,
d sqm 240 10,500.00
Platform Slab, Station Cut-out Slab.
e Columns (0 to 6 mtr) heights sqm 250 235
f Stair case and any other miscellaneous item. sqm 275 465.65
g Fixing of water bar, as required RM 30 825
h Loosening of couplers fixed on walls including aligning with the rebar of Roof/Concourse/Base Slab and fixing of threaded bars to couplers. Nos 15 12000 650 9,750 -
i Fixing of couplers in cut-out locations in slabs and walls with proper packing using shuttering tape and thermocole to power level and alignment. Nos 15 10000 650 9,750 -
7 SCAFFOLDING
Fixing of scaffolding and dismantling / shifting of scaffolding to the next slab including fixing of walers, H-Beams and Plywood. All materials will be given by L&T
SUCG JV. Include for shifting from store in the station for 1st fixing.
a All floor slab (except raft) including beams, staircases etc. Cum 35 35600
Erection and dismantlilng / shifting of working staging as per safety regulation, safe to work to the satisfaction of Engineer-in-Charge. All materials will be
provided by L&T SUCG JV.
b At all Levels. Cum 35 56765 14500 507,500 469 16,410
8 Labour charges for shifting of steel from lead of more than 50m to 500 m. MT 225 444.196 97 14.136 3,181
9 Labour charges for loading and unloading of steel MT 75 444.196 97 14.136 1,060
Labour charge for internal carting of material with four person with company provided vehicle including loading&unloading-Additional Description :Activity
12 MT 100 2150 -
includes shifting of construction materials from site to site,And within site etc.
Total 1,021,461.32 109,878.11
ECS1,2
Beams
9.791667 2.4 1.2 28.2
13 13
Balance Shutter Scope at RKP
Si no
b
c
a
b
c
e
f
g
7
b
8
9
10
Balance Shutter Scope at RKP
Description
SHUTTERING
Making shuttering panels (wooden and /or steel) and packing properly using jute, cotton and therm
All materials including nails shall be provided by Contractor in the station area.
For all other members at all levels
Labour charges for all type of board remaking excluding cost of wire nails.
Shifting the shuttering material from location of making (or from location of First fixing to the nex
and fixing, using thermocole/plywood in position shuttering (wooden and / or steel) and packing pr
using jute, cotton and thermocole. All materials including nails shall be provided by Contractor in
station area. The rate shall include the fixing of fixtures if any, required for works, making of cut
boxes, if any, and removal and stacking of all shuttering after completion of casting of concrete. In
for cleaning and applying oil to shuttering material (oil supplied by Contractor).
(For Top down and Bottom up) Base slab, Concourse Slab and Roof Slab of Station Box.
Base slab of Entry / Exit
Walls for station box (in case of Bottom-up Method)
Roof Slab and Concourse Slab for Station Box (in case of bottom up method) walls for Entry/exit, E
Exit roof Slab, Vent Shaft Wall, Plenum wall, UPE wall, Platform Slab, Station Cut-out Slab.
sqm 65 1550
sqm 35 5610
sqm 140 0
sqm 140 635.65
sqm 230 145
Cum 35 35600
Cum 35 56765
RMTR 172 18520
RMTR 201 2200
MT 100 2150
Description
UOM
Sr No.
1 REINFORCEMENT
a Column With couplers-top down MT
b Staircase MT
f Subway walls MT
Total
(Prepared By)
Planning Engineer
Station
HK
IIT
RKP
MNK
VV+SV
Total
(MT)
Total (Crs)
12
10
0
Proposal for Revis
6,800
9.650 2.41 0.00
0.09
As Per Actual Site Condition
Balance Qty
till Date
Total (Crs)
12
10
6
Column D
4 Column E
0
Proposal for Revised Rates of Reinforcement work from 01.01.2016
RK Puram
BamBam Alam Ali(Rebar)
Qty Amount
4.95
8.71
39.13
38.93
0.00
4.18
1.93
m 01.01.2016
RK Puram
Alam Ali(Rebar) Malik enterprises
Qty Amount
0.00
3.30 0.00
10.89 0.01
0.00
39.13 0.02
38.93 0.02
5.28 0.00
7.31 0.01
3.38 0.00
0.05
Malik enterprises Rajan Engg
Qty Amount
0.00
3.30 0.00
10.89 0.01
0.00
39.13 0.02
38.93 0.02
5.28 0.00
4.18 0.00
1.93 0.00
0.05