STYLE HM114

Country of buyer
Type of Buyer: Store/catalogue/importer/other* MEXX
Garment description: Men's L/S shirt
Fabric details - Knits/wovens/solid dyed/yarn dyed/print* woven/yarn dyed stripes
Fabric description: pin tuck stripes
Order quantity/original delivery date: 6990 15-Jun
Date
Activity Description On/From To Remarks
Date buyer meeting (sampling request+specifications received) 26-Feb
Date FIT samples were sent to the buyer 4/14/2007
Date comment (approval/rejection) received from the buyer 4/18/2007
Duration of FIT 1st iteration (steps 2 - 3)
Duration of FIT 2nd iteration(steps 2 - 3)
Date Order Confirmation (Col+Qty+Delv+Price) 4/9/2007
Date size set were sent to buyer 5/2/2007
Date comment on size set from buyer 5/4/2007
Duration of size set: 1st iteration (steps 5 - 6)
Duration of size set 2nd iteration (steps 5 - 6)
garment test at SGS 6/8/2007
Date lab dip were sent to the buyer 3/24/2007
Date comment (approval/rejection) on lab dip from buyer 3/28/2007
Duration of lab dip 1st iteration(steps 7 - 8)
Duration of lab dip 2nd iteration(steps 7 - 8)
Date first lot finished fabric received in store 4/25/2007
Date bulk fabric (from first lot) sent to buyer for colour approval 4/27/2007
Date bulk fabric colour (approval/rejection) received from buyer 4/30/2007
Duration of fabric colour approval 1st iteration (steps 10 - 11)
Duration of fabric colour approval 2nd iteration (steps 10 - 11)
Date processed fabric (first approved lot) sent for lab test 5/1/2007
Date lab test comment (approval/rejection) received 5/3/2007
Duration of lab test 1st iteration (steps 12 - 13)
Duration of lab test 2nd iteration (steps 12 - 13)
Date bulk trims received by the store 5/10/2007
received from lab after testing 5/12/2007
Duration embroidery thread approval 1st iteration (steps 14 - 15)
Duration embroidery thread approval 2nd iteration (steps 14 - 15)
pilot run actual+comments 5/14/2007
Duration cutting 5/12/2007 16-May
Duration Sewing 5/15/2007 10-Jun
Duration washing (if applicable) NA NA
Date production piece sent to buyer 6/8/2007
Date goods out of factory (in exporting country) 15-Jun

Note:
Activities starting with "date" please fill only first column
Activities starting with "duration" please fill two columns, i.e. start and finish date
Activities marked with light green colour is mandatory
Activities marked with light yellow is applicable for iterations i.e. in case of rejection
Only actual date to be filled up
For orders with multiple fabric colours: fill up for any one colour as approval may happen at different dates
Please do not fill up for repeat orders (where lot of above activities are not required)