CONTENTS
1. PURPOSE
2. SCOPE
3. APPLICABLE CODE AND SPECIFICATION
4. WORK ORGANIZATION
5. MANPOWER, MATERIAL AND ORGANIZATION
6. WORK METHOD
7. INSPECTION AND DOCUMENTATION
ATTACHMENT
A. REPORT FORM
PT. SUTINDO P. I. RAPP GAS SUPPLY PROJECT Job No.:
1. PURPOSE
The purpose of this procedure is to establish method and control to ensure field
joint coating application is in accordance with recognized practices, code and
specification.
2. SCOPE
This procedure is used to detect all defect of line pipe field joint coating i.e.
dimples, scratches, punctures, bum holes, holidays or foreign matter trapped
under, the applied field joint coating of welding joint for water Disposal line,
Butane Gas Line and Butane Crude line in Betara Complex Development
Project.
4. WORK ORGANIZATION
Holiday detection would be carried out by trained & experienced personnel and
one helper. QC Inspector checks the equipment and result of the coating
application before report to QC Coordinator.
6 WORK METHOD.
1. Check Holiday test equipment before using, Ampere range, Voltage range
calibration, brush condition, etc.
2. Voltage should be refer to Manufacturer recommendation. Ensure that cable
of the equipment is properly functioning (earth all time during testing)
3. Holiday tester shall be calibrated
4. The detector electrodes would be sized and operated such to be in direct
contact with the coated surface at all times and moved back and forth on the
surface being tested.
PT. SUTINDO P. I. RAPP GAS SUPPLY PROJECT Job No.:
ATTACHMENT
A