Contract No: CW2099527

Report No: PC-OP-BPO-DR-0007


Prepared By: Gandorj.M
Date: 2017.04.19
Section: 1 Manhours worked and number of manpowers

Days
Mon Tue Wed Thu Fri
1 Manhours worked 66 66 66
2 Number of workers 6 6 6
3 PCDP LLC 66 66 66
4
Section: 2 HSE Trainings

Mon Tue Wed Thu Fri


Number of trained personnel 1 1 1
Section: 3 Health and safety incident and personal damage

1 Total no of personal damage occurences 0


2 Total no of non injury incidents occurences 0
3 Number of Lost Time Injury 0
4 Number of Medical Threatment Injury 0
5 Number of Minor injuries 0
Section: 4 Hazard observation and actions

Observed Hazard Control


1 - 0
2
Section: 4 Other

Weather forecast Windy, +15


Number of visitors 0
HSE and permitting documents
Placing edgepoint of excavation limit of batchplant building -Permit to work, GHA, CCC
Sat Sun

Sat Sun

0
0
0
0
0

Control
0

Windy, +15
0

rk, GHA, CCC


Contract No: CW2099527
Report No: PC-OP-BPO-DR-0008
Prepared By: Gandorj.M
Date: 2017.04.20
Work name Work performed

1 Safety training Working at heights for supervisor

2 - Non worked

Photo report
k performed

eights for supervisor

on worked