Measurement of tendon Item - April'11

Labour Contractor - Tepi Biku Location P/House

Qnty. Description
Sl. No. Item Description UOM Total Qnty. Remarks
Nos. mt. Kg

Tendon DTH Drilling - 125mm dia.


1 Hole Rmt. 3 35 - 115 El.122-6,122-7,122-8

2 Tendon Water Pressure Test Rmt. 5 35 - 175 El.122-1,122-2,122-6,122-7,122-8


Loading, Unloading & Homing of
3 Tendon Rmt. 4 35 - 140 El.122-5,122-6,122-7,122-8

4 Tendon Grouting Kg - 7500 7500

5 Tendon Fabrication Rmt. 35 - 0

El.122-1,122-2,122-3,122-4,122-5,
6 Tendon Stressing Rmt. 8 35 - 280
122-6,122-7,122-8
Measurement of tendon Item - Dec' 09

POWER HOUSE

Qnty. Description B takar B tepi B Topuk TSB T Mortem


Sl. Total unit Remarks
Item Description UOM Rate
No. Qnty. rate
Nos. mt. Kg Qnty. Amnt. Qnty. Amnt. Qnty. Amnt. Qnty. Amnt. Qnty. Amnt.
Tendon
DTH
Tendon DTH Drilling - 125mm dia. Drilling -
1 Hole Rmt. 51.0 35 1785 20 700 0.0 0.0 0 0.0 0.0 0.0 0 125mm
dia. Hole
35m

2 WPT Rmt. 46 35 1610 5 175 0.0 0.0 0 0.0 0.0 0.0 0 WPT

Loading,
Unloadin
Loading, Unloading & Homing of g&
3 Tendon Rmt. 53 35 1855 7 245 0.0 0.0 0 0.0 0.0 0.0 0 Homing
of
Tendon
Tendon
4 Tendon Grouting Kg 32500 32500 0.5 0.5 0.0 0.0 0 0.0 0.0 0.0 0 Grouting

Tendon
5 Tendon Fabrication Rmt. 34 35 1190 40 1400 0.0 0.0 0 0.0 0.0 0.0 0 Fabricati
on 35 m

Tendon
7 Tendon Stressing Rmt. 45 35 1575 9 315 0.0 0.0 0 0.0 0.0 0.0 0 Stressin
g

0.0 0.0 0.0 0.0 0.0 0