STATE OF KUWAIT TENDER NO.

KUWAIT UNIVERSITY KU/KUCP/C0251/10-11

ELECTRICAL
METHOD STATEMENT Page 1 of 6

METHOD STATEMENT FOR INSTALLATION


OF LANDSCAPE AND STREET LIGHT FITTINGS

0 Issued for Review & Comments


Eng. A.H
Prepared by Checked by Approved by
Rev. Date Description
STATE OF KUWAIT TENDER NO.
KUWAIT UNIVERSITY KU/KUCP/C0251/10-11

ELECTRICAL
METHOD STATEMENT Page 2 of 6

REVISION CONTROL SHEET

REV. NO. DATE PAGE NO. DESCRIPTION

0 ALL FIRST ISSUE


STATE OF KUWAIT TENDER NO.
KUWAIT UNIVERSITY KU/KUCP/C0251/10-11

ELECTRICAL
METHOD STATEMENT Page 3 of 6

TABLE OF CONTENTS

1 Purpose.. 4
2 Scope of Work.. 4
3 Responsible Personnel on Site.. 4
4 Storage.. 4
5 Pre-Installation 4
6 Installation 5
7 Reference Documents. 6
8 Safety 6
STATE OF KUWAIT TENDER NO.
KUWAIT UNIVERSITY KU/KUCP/C0251/10-11

ELECTRICAL
METHOD STATEMENT Page 4 of 6

1. Purpose

This method of statement covers the on-site installation of landscape and street Light
Fittings as defined in the General Specification.

2. Scope of Work

This procedure will define the method to be used to ensure that the landscape and
street light fittings are installed correctly and acceptable and shall conform to the
Contract Documents and Specification.

3. Responsible Personnel on Site

3.1. Construction Manager


3.2. Electrical Field Engineers
3.3. Safety Officer
3.4. QA/QC Engineer
3.5. Electrical Supervisors

4. Storage

4.1 landscape and street Light Fittings shall be stored on clean, dry and ventilated location.

4.2 landscape and street Light Fittings accessories such as lamp shall be properly stacked
and keep on a clean, dry and ventilated location.

4.3 Make sure that every type of light fitting and lamp shall be stacked on one location.

5. Pre-Installation

5.1 All materials and documentation relevant to this particular section of works shall be
checked and verified ensuring that these are correct and approved type.

5.2 All building wiring related works shall be complete, tested and sign-off by the
Consultant.

5.3 Areas where in to start permanent works shall be checked ensuring that they are ready
for the said installation.

5.4 Make sure that hand holes, cable underground ducts are completed.

5.5 Make sure that the concrete bases are completed and their dimensions are suitable to
each light fitting type.
STATE OF KUWAIT TENDER NO.
KUWAIT UNIVERSITY KU/KUCP/C0251/10-11

ELECTRICAL
METHOD STATEMENT Page 5 of 6

6. Installation

6.1 Street Lighting poles

6.2 It has been presumed that all works and finishes related to Street Lighting poles
Installation are completed and ready for installation of permanent works.

6.2.1 Raise the street lighting poles by crane and put it on its concrete base and make
the rods in the concrete base entering the holes in the poles base.

6.2.2 Ensure that poles are fixed squarely and properly aligned. Make sure that
manufacturers recommendation for street lighting poles installation shall be
adhered.

6.2.3 Terminate power cables to the isolator/circuit breaker inside the pole hole. Ensure
that they are terminated properly. Street lighting pole shall be earthed.

6.2.4 Fix lamps housing on the poles. Check the type and colors of the lamps and make
sure that they are correct and approved type.

6.2.5 Fix the light fixture reflectors and diffusers. Ensure that they are aligned and
properly fixed.

6.2.6 Temporary power connection shall be made to check the proper operation of light
fittings.

6.2.7 Raise Request for Inspection of light fittings installation.

6.3 Flood Light Fittings

It has been assumed that all works related to flood light installation ahs been completed.
Building wires has been tested and signed-off by the Consultant.

6.4.1 Fix flood light mounting brackets. Ensure that they are fixed rigidly and properly.

6.4.2 Fix the flood light on the brackets. Connect power cables on the fittings and ensure
that the body of the flood lights is properly earthed.

6.4.3 Fix lamps on the fixtures. Ensure that the lamps are correct and approved type.

6.4.4 Connect temporary power supply to check the proper operation of the flood lights.

6.4.5 Raise Request for Inspection of light fittings installation.

6.4 Indirect Light Fittings


STATE OF KUWAIT TENDER NO.
KUWAIT UNIVERSITY KU/KUCP/C0251/10-11

ELECTRICAL
METHOD STATEMENT Page 6 of 6

It has been presumed that all finishes related to the installation of indirect lightings were
completed and all wiring installation and testing has been completed.

6.5.1 Install mounting holder / bracket of indirect lights to their designated location. Make
sure that it is fixed rigidly.

6.5.2 Install indirect light fittings on the bracket / holder.

6.5.3 Connect power cables to the light fittings. Ensure that all connections are correct
and the fittings shall be earthed.

6.5.4 Fix lamps on the light fittings. Make sure that the type and color of the lamp are
correct and approved type.

6.5.5 Connect temporary power supply to the light fittings to check for proper operation.

6.5.6 Raise Request for Inspection of indirect light installation.

7. Reference Documents

7.1 Approved Electrical Shop Drawings


7.2 Approved Material Submittals for Light Fittings
7.3 Approved Insulation Resistance Test for Building Wires
7.4 Approved Coordinated Ceiling Drawings
7.5 Approved Material Inspection Report
7.6 Approved Safety Plan
7.7 Approved QA/QC Inspection and Test Plan
7.8 Installation Guide For Light Fittings

8. Safety

8.1 All safety precautions shall be followed as per approved safety plan & procedure.
Ensure all involved persons are aware of the same.

8.2 Safety Officer shall ensure that all elevated flat forms to be used are safe and in
good conditions.

8.3 Ensure that tradesman will keep their working places clean, tidy and free from
rubbish.

------------------------ Procedure End----------------------