Professional Documents
Culture Documents
Revision
Date Purpose and Summary of Amendments Reviewed by Approved by
(in numbers)
19/09/2014 1 Initial Draft
*Note that all printed paper/hard copies of this document and related procedures are uncontrolled. The controlled copy of this document is
found either in Project Web, within the Project Management Plan section, or other project specific database/server approved by the Regional
EHS Manager.
CONSERVATION & HABITAT MANAGEMENT PLAN
This Conservation & Habitat Management Plan details protection and/or prevention measures to ensure that flora and fauna is managed appropriately during the construction phase. It
Scope: defines mitigation measures to be implemented during relevant construction activities, a monitoring program that enables assessment of the impacts of construction activities on
potentially affected areas, and contingency measures that may be implemented if required.
To minimise any potential for impacts to the environment and/or natural habitats.
To conserve existing vegetation communities and native species present on site.
Objective:
To protect any native fauna which may be identified on and/or adjacent to the site
To minimise the impact of any introduced fauna (i.e. vermin), or noxious flora (i.e. Weeds) or disease during construction.
Native Vegetation
The project is situated at the Williamtown RAAF base, with components extending across a number of habitats.
The project footprint covers approximately 209 hectares, 81 hectares of which is largely cleared and modified grassland with minimal ecological value. The remaining naturally
vegetated areas comprise an open forest / woodland and low woodland complex that are considered relatively high quality remnant natural bushland, both in terms of structure and
the diversity of plant species. These areas provide food resources for a rich assemblage of nectivorous and insectivorous fauna including birds, mammals, reptiles and frogs. They
also provide habitat (e.g. tree hollows) for a range of threatened fauna species known to occur in the area.
The project spans a number of native vegetation communities
forest/woodland
forest/woodland
Stringybark low
Drooping Red
Bloodwood/+-
Regenerating
Scribbly Gum
Scribbly Gum
Broad-leaved
coastal dune
open forest/
open forest
Paperbark/
Mahogany
Apple/Red
woodland
woodland
Gum low
complex
Swamp
Swamp
White
forest
open
land
Risks:
North-south access road (Zone A)
Dwarf Kerrawang (Rulingia prostrata) has the potential to occur in the study
area despite not being located during the field surveys.
Previous field surveys recorded a number of individuals within the OLA footprint
on land rehabilitated after sand mining.
The Scribbly Gum, Drooping Red Gum and Swamp Mahogany are preferred
habitat of Koalas. Field surveys within the confines of the Base identified
evidence of one Koala individual, further studies will be required to assess koala
numbers in the EO and NW runway sections of the project.
The freshwater swamp habitat located to the north-west of the NACC Facilities
and adjacent to the proposed access road support a large population of the
threatened Wallum froglet (Crinia tinnula), as well as, a diversity of ground and
tree-frogs. Freshwater swamp habitat occurs throughout lower lying areas of
Low Woodland and Wet Shrubland Complex, with the size of the swamps
varying from several square metres to several hectares. Water levels in the
swamps are expected to fluctuate seasonally depending on rainfall.
The Wallum froglet has also been recorded in flooded areas in the vicinity of the
NACC Precinct during wet conditions.
Phytophthora cinnamomi (Pc) a soil borne fungus that can cause dieback of native vegetation has been identified at the Base. The Northwest ORP, elements of the proposed
access road and EO area and NW runway take-off and landing clearance are located in high risk Pc areas
Myrtle Rust, although not detected on the Base had been detected on the Central Coast and across eastern NSW. Myrtle Rust is an exotic fungus from South America which infects
the leaves of plants from the Myrtaceae family (e.g. Gum trees (Eucalypts), Bottle Brush, Tea Tree etc.) leading to the loss of leaves and death of plant.
The key aspects of the Project that could result in adverse impacts on flora and fauna include:
clearing activities;
establishment of ancillary facilities such as stockpile sites, compounds and sediment basins;
construction of waterway crossings;
construction of drainage structures;
chemical usage near waterways and sensitive vegetation;
inadequate or absent erosion and sediment control devices;
exposure of disturbed areas;
delivery and movement of plant and equipment; and
changes in hydrology and drainage regimes.
The potential flora and fauna impacts that may occur during construction include:
loss of habitat value and biodiversity;
reduction in plant numbers and diversity;
barrier to normal fauna movement/migration;
direct mortality and injury to fauna;
damage or death of individual plants due to physical impact;
fragmentation of habitat and decrease in connectivity and fauna passage as a result of vegetation clearing;
disease and weed infestation;
aircraft bird / macropod strike,
increases in pest / vermin such as rabbits, rats and foxes
decline in aquatic habitat quality through changes in water course, decline in light penetration and inadequate erosion and sediment control.
Commonwealth:
Environmental Protection and Biodiversity Conservation Act 1999
Environmental investigations have concluded that the project is not likely to have significant adverse impacts on flora and fauna or indigenous and non-indigenous heritage;
Key Legislation /
however a general permit under Section 201 of the EPBC Act is required for activities that may kill or injure a listed threatened species or ecological community.
Standards /
Guidance State:
While state legislation does not apply to Defence activities, Defence aims to be good environmental stewards and comply with State government legislation and policies to the extent that
these do not conflict with Commonwealth legislative obligations or compromise operational objectives or capability.
The relevant State environmental legislation and planning instruments are described below.
Protection or the Environment Operations Act 1997 (POEO Act)
Regulates air, noise and water pollution and transport and disposal of waste in NSW
Work requiring removal of branches, roots etc. At all times Arborist to inspect trees and SM/ Sub-contractor Pre-clearing Permit Tree pruning / lopping
will be undertaken by or at the direction of a perform work where required performed in accordance with
qualified arborist. AS 4373-2007 Pruning of A, B,C,D,E & G
Removal of branches, or pruning by excavator Amenity Trees
bucket or similar is not permitted
Materials or spoil are not to be stored or At all times Stockpile and storage areas SM/ Sub-contractor Approved ESCP. Stockpile and storage only in
stockpiled in retained vegetation areas or to be identified in the Erosion Weekly Environmental approved areas, and outside
Vegetation Protection Zones and Sediment Control Plans. Inspections. retained vegetation areas or
All
Stockpile and storage only Vegetation Protection Zones.
Environmental Audits
allowed in these approved
areas
Driving or parking of plant and vehicles is not At all times Access tracks and parking SM/ Sub-contractor Approved ESCP. Access tracks and parking
All
permitted within in retained vegetation areas or areas to be identified in the only in approved areas, and
CONSERVATION & HABITAT MANAGEMENT PLAN Page 10 of 41
LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104
Control Measures Timing Methodology Responsibility Monitoring and Performance Measure
Relevant Zones
Reporting
Vegetation Protection Zones Erosion and Sediment Control Weekly Environmental outside retained vegetation
Plans. Inspections. areas or Vegetation
Protection Zones.
Environmental Audits
Limit disturbance of vegetated areas. At all times Schedule works to retain SM/ Sub-contractor Approved Environmental Vegetation disturbance limits
vegetation cover for as long Control Plan. enforced as per the
as possible, minimise Weekly Environmental Environmental Control Plan.
All
disturbance of vegetation Inspections.
outside the construction
Environmental Audits
footprint where ever possible
Minimise risk of bush fire as a result of At all times Check fire danger rating and SM/ Sub-contractor Hot works permit Hot works or plant do not
construction activities in vegetated areas fire activity rating prior to Weekly Environmental cause fire in vegetated areas
mobilising plant. Restrict Inspections.
spark generating activities
and plant with exposed hot All
parts (eg exhausts) in
vegetated areas prone to
easy ignition during periods of
fire danger.
During construction - Fauna
Ensure gates or fences are not left open such At all times Supervise open gates or SM/ Sub-contractor Weekly Environmental Animals, particularly
that animals, particularly kangaroos or openings in perimeter fences Inspections. kangaroos or wallabies, are
wallabies, are let onto the airfield or RAAF to prevent animal incursion. not let onto the airfield or
Base Close perimeter gates and RAAF Base due to
fence openings as soon as construction activities
possible and when ever specifically through breaks in All
unattended. Install some form the perimeter fence or open
of barrier underneath gates.
temporary perimeter fences
and gates to prevent animals
digging under the fence.
Encountered wildlife is to be protected and At all times Work in the immediate area to SM/ Sub-contractor Fauna Recovery Fauna is protected and
relocated by appropriately qualified and stop, the animal is to be Procedure relocated by appropriately
experienced handlers protected, and the Managing qualified and experienced
Contractor notified wildlife handlers All
Follow Fauna Recovery
Procedure
CONSERVATION & HABITAT MANAGEMENT PLAN Page 11 of 41
LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104
Control Measures Timing Methodology Responsibility Monitoring and Performance Measure
Relevant Zones
Reporting
Project Ecologist to be
available during vegetation
clearing.
Construct and manage trenches to limit At all times Where possible cover SM/ Sub-contractor Fauna Recovery Limit accidental trapping of
accidental overnight trapping of fauna, and trenches left open overnight. Procedure fauna
enable trapped fauna to escape. Trenches and excavations not Trapped fauna reported to Trapped fauna not harmed
covered overnight to be the Managing Contractor and reported to the Managing
inspected each morning for to arrange relocation Contractor
captured fauna. All
Where trenches are to be left
overnight, if possible
construct with shallow sloping
ends to allow natural escape
of trapped fauna
Construction Areas to be kept clean and tidy, to At all times All waste is placed in SM/ Sub-contractor Site Inspections Work areas clean and tidy,
limit attraction of fauna to the site. appropriate bins (as per fauna not attracted to waste
Waste Management Sub- or food scraps on the site
Plan).
Lids kept closed on bins All
containing food waste.
Work areas to be cleared of
waste at the end of each
day/shift
Pre-Clearing
Habitat trees to identified and marked in areas Pre - clearing Areas to be cleared to be SM/ Sub-contractor Ecologist Reports Habitat Trees identified and
to be cleared inspected by a qualified Pre-Clearing Permit managed as per Clearing and
ecologist to identify, mark and Grubbing eWMS
record potential habitat trees A,B,C,D & G
(hollow bearing) as per
Clearing and Grubbing eWMS
(appendix A)
Sensitive areas and protected vegetation to be Pre-clearing Sensitive areas and protected SM/ Sub-contractor Pre-Clearing Permit All sensitive areas identified
identified and protected vegetation described in the Environmental and protected.
SAP to be located and fenced A,B,C,D & G
Inspections
/ signposted
No harm to sensitive areas.
CONSERVATION & HABITAT MANAGEMENT PLAN Page 12 of 41
LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104
Control Measures Timing Methodology Responsibility Monitoring and Performance Measure
Relevant Zones
Reporting
Vegetation to be cleared to be identified and Pre - clearing Surveyor to mark out SM/ Sub-contractor Survey records / Clearing Clearing only of approved
clearly delineated. approved clearing limits as Drawing vegetation.
per the Environmental Pre-Clearing Permit No harm to vegetation outside
Clearance Certificate, as per approved clearing limits
Environmental
Clearing and Grubbing eWMS
Inspections A,B,C,D & G
(appendix C)
Delineation will be durable,
highly visible and signposted
where sensitive areas are to
be protected
All vegetation clearing and lopping / pruning Pre - clearing Pre-clearing inspections and SM/ Sub-contractor Pre-Clearing Permit No unapproved clearing of
must be approved prior to starting. signoff as per Pre-Clearing Clearing Drawing vegetation
Permit (See Appendix B) to
be completed before clearing A,B,C,D & G
starts
Approval by the Managing
Contractor
Proposed erosion and sediment controls to be Pre-clearing A progressive Erosion and SM/ Sub-contractor Approved ESCP Appropriate erosion and
identified prior to clearing Sediment Control Plan for the sediment controls identified
area to be cleared to be and resources allocated A,B,C,D & G
submitted for approval prior to
the clearing activity
Identify and rescue fauna in the clearing area Pre-clearing No more than 24hrs prior to SM/ Sub-contractor Ecologists report Records of inspection and
clearing the project ecologist Pre-Clearing Permit fauna relocation
is to survey the clearing area
to identify and if possible A,B,C,D & G
capture and relocate fauna as
per the Clearing and
Grubbing eWMS.
Capture and relocate frogs and other fauna Qualified ecologist captures SM/ Sub-contractor Ecologists report Work areas cleared of
from potential Wallum Froglet habitat (i.e. and relocates frogs and other Site inspections Wallum Froglet prior to
inundated or wetland) fauna to adjacent suitable construction
habitat. A,B,C& G
Progressively fill or drain the
inundated areas to encourage
any remaining fauna to move
Weed management
A survey of weeds will be conducted prior to Prior to clearing Qualified Ecologist to inspect CM / SM Ecologists weed Weed infested areas
construction to identify weed infested areas. the site to identify and record infestation report identified
weed infested areas. Herbicide use register
Noxious weeds will be
sprayed prior to clearing to
All
prevent spread of weed
propagules with mulched
vegetation
Weed spraying to only use
glyphosate herbicide
The construction areas will be managed to Ongoing Weed spraying to only use CM/ SM weekly inspections Noxious weeds are identified
control noxious weeds. glyphosate herbicide Herbicide use register and controlled to prevent
spread of weeds to the rest of All
the base or adjacent National
Park land
Seed Management
If required by Defence, seed will be collected Prior to and If required by Defence, Seed SM/ Sub-contractor Ecologists Report Records of seed collection.
from a selection of native trees prior to clearing, during clearing collection and propagation will (weight, species, viability test
in order to preserve the local genetic diversity. be carried out by experienced results)
seed collectors
Seed will be cleaned and
sorted and offered to Defence
for subsequent revegetation
A,B,C,D & G
works.
Collected seed will be
labelled and stored under
appropriate conditions,
reflective of the nature of the
seed collected, until
propagation or seed
CONSERVATION & HABITAT MANAGEMENT PLAN Page 19 of 41
LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104
Control Measures Timing Methodology Responsibility Monitoring and Performance Measure
Relevant Zones
Reporting
distribution is to be initiated.
Post Clearing If required by Defence, SM/ Sub-contractor Monthly Report Propagated trees of local
collected seed will be provenance
propagated to provide native
NA
trees of local provenance for
revegetation / rehabilitation
works.
Rehabilitation
After Includes removal of waste SM/ Sub-contractor
On completion of construction, areas to Environmental All construction areas
construction is spoil, earth bunds and any
returned to original or better condition to the Inspections / audits rehabilitated to satisfaction of All
completed in an other soil / rehabilitation
satisfaction of Defence. Defence prior to handover
area requirements
Disturbed areas will be SM/ Sub-contractor
stabilised either by the
permanent landscape Approved Seed Mix Disturbed areas stabilised in
As soon as
Stabilise disturbed areas as soon as possible planting, or using a cover Landscape plans a timely manner to minimise All
possible
crop / turf seed mix approved ESCP erosion potential
by the Base Senior
Environmental Manager
All landscape or stabilisation (i.e. cover crop / At all times Landscape and stabilisation SM/ Sub-contractor Landscape and Good growth and long-term
turf) planting will be maintained and watered to plans / contracts to include stabilisation plans / survival of landscaping and
ensure promote good growth and ongoing maintenance and watering contracts revegetation stabilisation All
survival requirements ESCP works.
Site Inspections
Where possible and consistent with the After If required by Defence and SM/ Sub-contractor Landscape plans Native flora used for
approved Landscaping plan, use native flora construction is the approved Landscape revegetation / rehabilitation All
species for re-vegetation as a natural control to completed in an plan, native flora will be used works where required
BACKGROUND
1.0 SUMMARY/PURPOSE OF ACTIVITY:
Clearing and grubbing involves the clearing of vegetation and the removal (grubbing) of roots and stumps. Timbers suitable for reuse are salvaged for milling, reused as construction materials or mulched
for use in landscaping activities. Clearing and grubbing activities involves the use of an excavator, dozer, chainsaw, chipper, tub-grinder, backhoe and trucks. A two stage clearing process will be carried out
on this project.
2.0 OBJECTIVES OF THIS WMS:
The objective of this eWMS is to provide specific control measures so that the minimum possible area of land is cleared, to minimise impacts on endangered ecological communities and threatened
species, and minimise the risk of spread of Phytophthora cinnamomi infection. Also the area cleared must be within the limits specified.
3.0 AREA/LOCATION OF ACTIVITY/SITE:
Within the boundaries of the NACC-Williamtown project and as per approvals.
4.0 APPROVALS REQUIRED
Environmental Clearance Certificate (ECC) issued by Senior Environmental Manager - RAAF Williamtown
5.0 CONSULTATION REQUIREMENTS:
Clearing on Defence land - Senior Environmental Manager - RAAF Williamtown
Clearing in State Conservation Area for Access Road construction National Parks and Wildlife Service
Consultation with external stakeholders, such community groups, Representative Aboriginal Parties (RAPs), Hunter Water Corporation and NSW Office of Water will be carried out by the Stakeholder
Manager as required
6.0 INCIDENT RESPONSE:
In the event of an incident such as clearing beyond the approved clearing limits or damage to protected vegetation or heritage item/area the Foreman or Environmental Officer will give directions to stop
work and contact the Environmental Manager immediately. If the Environmental Manager is not available then the Project Director shall be contacted.
Moderate (9 -14) Identified Control Measures must be capable of reducing the risk by eliminating or minimising to an acceptable level. Monitoring of key control measures allocated to specific responsibilities.
Low (3-8) -The work is relatively safe and can be managed by routine Control Measures outlined in Means & Methods, routine procedures, guidelines, pre-starts/restarts, Builder's Brief and Project EHS Rules.
No further action is required, unless additional impacts or hazards arise during the work.
Negligible (1-2) - No further control measures are required Monitor to ensure risk does not escalate
Moderate ECC to be consistent with the Habitat and Conservation Management Plan and this eWMS.
1 ECC Approval Approval not granted Environmental Officer
(C3) Produce Clearing drawing and Erosion and Sediment Control Plan (ESCP)
Project Engineer
Stakeholders and Notification Stakeholder Manager detailing works required. At least 5 days notice is required prior to Foreman/Site Engineer
Stakeholder / Community are exposed Low the commencement of construction. Stakeholder Manager
2
Community Notification to impacts without prior (D3) Notify relevant Stakeholders at least 5 working days prior to the commencement of clearing.
notice
Pre-Clearing Permit
Project: Date Inspected:
1. Are all sensitive areas noted on the attached to the Survey Drawings
3. Are the locations of sensitive areas included in the CEMP and site
induction?
5. Have all sensitive areas been clearly identified with signage and protected
with exclusion fencing?
7. Has the Area clearly marked out by the Survey team and clearly
understood by Abigroup / Clearing Sub-contractor Foreman
8. Have the signatories to this permit walked the area concerned and
confirmed the sensitive areas are clearly demarcated?
9. Has a survey for any known threatened species been carried out prior to
clearing?
11. Has the project ecologist been notified to attend the site every morning for
the duration of this clearing permit?
12. Has a clearing Work method statement (WMS) been prepared and
toolboxed?
13. Have all personnel involved been instructed / toolboxed on the sensitive
area locations and signed an acknowledgement toolbox sheet? This is to
include the clearing subSub-contractor.
14. Have all personnel involved been given a description of the threatened
species to be alert for?
15. Have all personnel been instructed / toolboxed on the process to follow if
it is necessary to enter a no-go area?
Permit signatories:
Name Company Position Signature Date
Foreman
Foreman
Surveyor
Project Engineer
Environmental Coordinator
Project Ecologists
Attached:
Drawings (SAPs) (Drainage)
1. BACKGROUND:
Phytophthora cinnamomi (Pc) has been detected in areas of the RAAF Williamtown. Phytophthora (pronounced fy-TOFF-thora) is a water mould that survives in water, soil and plant roots and
kills plants by attacking and rotting their roots.
Phytophthora is spread naturally in water and via infected roots, and faster and further by humans moving contaminated soil or plant material. It can remain dormant for long periods during dry
weather and is virtually impossible to remove from infected areas. Phytophthora Dieback attacks many native plants and can also impact on native animals, including marsupials, birds, reptiles
and insects, by reducing or eliminating vegetation they rely on for survival.
Even plants that are not highly susceptible will succumb during long periods of dry weather. The loss of root mass limits the amount of water and nutrients a plant can absorb, leaving it
susceptible to insect attack, plant diseases and drought stress. Early symptoms of dieback in plants include wilting, yellowing and drying out of leaves
The spores of Phytophthora can persist indefinitely in an area protected in the roots of plants, even those that are not susceptible to Phytophthora Dieback. Disease depends on three essential
components: plant host, environment and the pathogen. Phytophthora is most active when the soil is moist and warm. It can also survive for long periods in plant tissue and soil during dry soil
conditions. The only effective way to limit its spread by managing water and soil movement. Typically infection is restricted to the roots and bottom 1 2m of the trunk.
High Risk Activities for Pc introduction and spread include:
earthworks
situations where more than one access point into any given work area is required
heavy vehicles and machines involved - increased risk of contamination spread and complexity and cost of clean down
vegetation clearing
2. Pc MANAGEMENT STRATEGY
Management Strategies to prevent introduction of Pc infected material to uncontaminated areas of the Base, or spread of Pc infected material between areas of the Base or to off site areas will
include:
PROTOCOL
Sequence of Work
Responsibility
Activities Potential Hazards Safeguards/controls
(Who will direct works to ensure
(How will work be (What harm can occur?) (How can the risk be minimised?)
compliance?)
done?)
Prior to commencement of works in Pc Control Areas
Package work activities that are a significant risk for Pc spread or introduction (based on Pc risk map
and activity type) within an area to minimise movement of plant, equipment and personnel between
areas during that activity.
Work not planned to Conduct planning meetings with personnel and sub-Sub-contractors to communicate Pc risks and
Plan works in Pc Control minimise risk of cross develop management measures consistent with this plan. Project Manager
Areas contamination between Include Pc control measures on the location / activity specific ESCP Supervisor
areas Plan to include limit to access points to Pc Control Area and provide appropriate hygiene controls.
Planning may include a program of testing designed by a competent party to demonstrate absence of Pc
in an area. In the absence of this testing, as discussed above, all Medium and High Pc Risk areas will be
considered as Pc contaminated and designated Pc Control Areas.
Consider Pc risk in ECC application Project Manager
ECC Approval Works not approved
Include proposed mitigations and location / activity specific ESCP showing proposed controls Environmental Coordinator
Provide training to
Non compliance with the
personnel and sub-Sub-
eWMS
Toolbox personnel and sub-Sub-contractors on the Pc Risks and the requirements of this eWMS.
contractors involved
Risk of introduction or
Install all required Pc Install Pc controls as shown on the approved ESCP.
spread of Pc before
controls Where controls are to be introduced progressively this should be recorded on the ESCP
controls are established
Bringing Plant, Equipment and Vehicles to site
All vehicles and plant should be as free of soil, mud and vegetation before arriving at the base to be
Ensure all plant, confirmed at Plant prestart inspection.
equipment, materials and Introducing Pc to previously Where plant is not free of soil, mud and vegetation it should be removed from site and cleaned, or if Project Manager
footwear is free of dirt and unaffected areas available, cleaned at the nearest wash bay (see wash-down procedure) Supervisor
vegetation Footwear needs to be free of mud or soil.
All materials such as pipes etc. need to be free of mud and soil.
Sequence of Work
Responsibility
Activities Potential Hazards Safeguards/controls
(Who will direct works to ensure
(How will work be (What harm can occur?) (How can the risk be minimised?)
compliance?)
done?)
Moving into or out of Pc Control Areas Risk areas
All vehicles and plant should be cleaned of dirt and vegetation at the washdown bay before entering or
Ensure all plant, leaving a Pc Control Area. (See wash-down procedure)
equipment, materials and Introducing Pc to previously Tracks, Tires and any part of the machine that comes into contact with soil should be disinfected a per Project Manager
footwear is free of dirt and unaffected areas the disinfection procedure. Supervisor
vegetation Footwear needs to be free of mud or soil and disinfected before entering or leaving the Pc Control Area
All materials such as pipes etc. need to be free of mud and soil.
Sequence of Work
Responsibility
Activities Potential Hazards Safeguards/controls
(Who will direct works to ensure
(How will work be (What harm can occur?) (How can the risk be minimised?)
compliance?)
done?)
Working in Pc Control areas
Ensure equipment is clean
Ensure raw materials are Pc Free.
Where ever possible
o Avoid leaving formed areas.
o Avoid working in wet weather.
o Avoid sites prone to flooding or ponding.
o Work downhill of vegetation. Pc moves rapidly downhill on surface water runoff, while uphill
Whilst working in Pc movement occurs much more slowly
Spreading Pc to further Project Manager
Control areas General
areas.
Stay within cleared areas, avoid disturbing native vegetation. Supervisor
conditions Any water used needs to be drawn from a source that is Pc f r e e mains water is best
Do not drive vehicles through drainage lines, creek lines or puddles.
Do not drive over vegetation to turn vehicles.
Do not enter vegetation without disinfecting footwear Pc can be carried on a very small amount of
soil.
Always disinfect tools prior to beginning works and when moving from one area to another.
Wash down vehicles when moving between work sites, or leaving the Pc Control Area
Always work in areas where there is no infection before moving to infected areas
Plan erosion and sediment controls to prevent runoff from worksite into surrounding vegetation.
Apply adequate dust suppression to minimise dust generation, however avoid excess water application
Spreading Pc to further generating runoff to surrounding vegetation.
During Earthworks
areas. Only mains water, or standing water from within the Pc Control Area should be used for dust
suppression, surface or groundwater collected from outside the Pc Control Area must not be used.
All activities must be carried out to minimise soil movements and transport of soil and water.
Import of Pc contaminated
Fill Materials
materials
Sources of fill should be certified Pc free before use.
Working in drains / culverts Keep tyres / tracks on roadways /hardstand at all times and do not drive over vegetation or into drains.
and wet areas Drains and culverts should only be cleared in dry conditions.
Spoil should be reused within the Pc Control Area it came from.
Where reuse within the Pc Control Area is not possible the material must be tested and confirmed Pc
Spreading Pc to further
Excess Spoil and stockpiles
areas.
free before reuse in other areas, or disposed of to an appropriately licenced waste facility.
Stockpiled material should not be placed near native vegetation and should be contained by a silt fence
to minimise erosion by run on water and sediment transport into vegetation.
Never in vegetated road verges (including slashed road verges) or within vegetation.
Parking and laydown
Where possible down slope of vegetated areas and on constructed hard stand areas.
Sequence of Work
Responsibility
Activities Potential Hazards Safeguards/controls
(Who will direct works to ensure
(How will work be (What harm can occur?) (How can the risk be minimised?)
compliance?)
done?)
Clearing, Grubbing and Mulch
Trees should be stump cut, leaving 1 to 1.5m of the trunk upstanding.
The felled section of trunk and crown should be kept as soil free as possible and mulched as soon as
possible.
The mulch should be stockpiled on hardstand if available to minimise soil contamination and should be
protected with a sediment fence. If managed this way this mulch is considered low risk for Pc transfer
and can be used for ERSED control or landscaping within the Pc Control Area it originated from or in the
low Pc infection risk areas (see Risk Map)
The remaining stumps, root-balls and grubbed up ground cover should by collected up, placed in a
covered skip bin or truck and taken to a suitably licenced waste facility for disposal (NOTE the waste
Clearing within Pc Control Spreading Pc to further Project Manager
Areas areas.
facility must be aware of the potential for Pc contamination and must not mulch this material). Supervisor
Alternatively where the stumps, root-balls and grubbed up ground cover can be mulched in a separate
area within the Pc Control Area, away from native vegetation and managed by appropriate sediment
controls, and a suitable number of lab tests are negative for Pc infection, this material may be reused
within the Pc Control Area from which it originated.
Alternative disposal options, such as firewood, may be considered where the risk of Pc infection transfer
can be demonstrated to be low.
Where it is not practical to stump cut trees, and a dozer or other mechanical means are proposed to
push the trees over, the resulting vegetation must be either tested to demonstrate absence of Pc or
disposed of to a suitably licenced waste facility.
Wet Weather
Whenever possible avoid work earthwork or work involving contact with the soil during wet weather, or
when soils are still wet/damp after rain.
If rains begin when working, then works should stop and you should contact the Managing
Contractor for advice.
During Wet Weather If you are not working in an area where you are likely to move mud or soil around on vehicles or boots
Spreading Pc to further Project Manager
While working in Pc Control
areas.
then it is likely that work can continue. Supervisor
areas Grading of roads can occur if the surface is damp, but not wet.
Do not, under any circumstances, enter vegetation when it is raining, or just after rains, or if soils
are damp even if you have cleaned your boots / tools.
No revegetation or rehabilitation activities should be undertaken in wet weather.
Sequence of Work
Responsibility
Activities Potential Hazards Safeguards/controls
(Who will direct works to ensure
(How will work be (What harm can occur?) (How can the risk be minimised?)
compliance?)
done?)
Washdown / cleaning Procedures
Safely park vehicle or plant in the wash-down area. Ensure engine is off and vehicle is immobilised.
Look over vehicle to locate any soil. Pay attention to underside, tracks, tyres (inc. the spare) axles and
bumper bars etc.
Knock off large clods of soil - use crow bar if required, sweep out cabin and other areas.
Use broom or air hose to remove as much soil as possible. Brush off any remaining dry soil.
Start with underside of vehicle, wheel arches, wheels (including spare). Next do sides, radiator, tray,
bumper bars etc., finishing with upper body. Tracked machinery may need to be moved during wash
Plant / vehicles prior to
entering or leaving Pc
Spreading Pc to previously down. Project Manager
unaffected areas Clean any associated implements, tools, footwear and equipment. Check there is no loose soil Supervisor
Control areas
remaining.
Spray with quaternary ammonia solution e.g.: Phytoclean
Wash away effluent. Do not drive through effluent.
Note:
Wash-down water is to be captured and disposed of to an appropriately licenced waste facility.
Collected soil can be reused as fill within the Pc Control Area, or disposed of to an appropriately licenced
waste facility, it is not to be reused outside the PC Control Area it came from.
Sequence of Work
Responsibility
Activities Potential Hazards Safeguards/controls
(Who will direct works to ensure
(How will work be (What harm can occur?) (How can the risk be minimised?)
compliance?)
done?)
Some personnel will require a personal Pc hygiene kit to work on the base. Keeping footwear clean is vital
in minimizing the risk of spreading Pc. Footwear should be cleaned prior to entering and upon leaving a
works area and immediately before and after going off tracks or entering vegetation (even slashed road
verges), although this should be avoided wherever possible.
Ensure you disinfect your boots where they will not pick up soil again once you put them down.
Personal Pc hygiene kits should contain:
Hard brush to clean footwear.
Spray bottle containing Phytoclean* The spray bottle should be adequate in removing the soil from
your footwear.
Cleaning Procedure:
Footwear prior to entering Spreading Pc to previously 1. Select a hard well-drained site (or sitting in your vehicle);
or leaving Pc Control areas unaffected areas 2. Remove all plant and soil from one boot with the brush (if necessary);
3. Do not put that boot on the ground or onto surfaces where there is soil;
4. Disinfect the entire sole with the disinfectant (and any other areas of the shoe with soil). The nozzle
of the spray bottle should be on direct so that as much soil as possible is physically removed by the
spray;
5. Allow the sole of the shoe to dry for Phytoclean 30 seconds is enough;
6. Step forward to avoid recontamination (do not step onto areas where you will recollect soil);
7. Repeat steps 2 to 6 with other boot;
8. Disinfect the brush.
Alternatively a cleaning station may be provided including boot scrappers and footbath for personnel to pass
through when entering and leaving the work area.
Tools should be treated in the same manner as footwear
Tools and equipment prior once works have finished in an area, remain in that area,
Spreading Pc to previously
to entering or leaving Pc use the brush to remove any large amounts of soil from each tool,
unaffected areas
Control areas disinfect with Phytoclean, allow to dry for 30 seconds.
Repeat this measure if tools come into contact with soil after disinfecting, or in vehicles.
*Phytoclean is a hard surface application treatment which is classified a non- hazardous product. Phytoclean is high in detergency and washability ensuring there is no residue when used in washdown situations
and is effective in as little as 30 seconds. Phytoclean is a quaternary ammonium solution.
Identified local fauna rescue agencies and contacts as at November 2014 include:
Organisation Phone Number
Native Animal Trust Fund Wildlife Rescue Service 0418 628 483
2. Fauna Release
If the animal is not injured, it may be released nearby in an area that is not to be disturbed by the road construction in accordance with the following
guidelines:
Prior to any clearing works, several sites within or near the project site would be identified as suitable release points by the Project
Ecologist or Wildlife Handler.
The Project Ecologist or Wildlife Handler would be primarily responsible for undertaking any release, or advising site personnel on release
processes if not present on site.
If the species is nocturnal, release would be carried out at dusk.
No release would take place during periods of heavy rainfall, unless the Project Ecologist or Wildlife Handler determines that the animal is
too stressed to be held any longer.
Any fauna which cannot be released immediately or by the evening of the day clearing occurred will be handed to wildlife rescue
personnel.