PROJEK MENAIKTARAF JALAN FT092 DARI BANDAR PENAWAR (SENAI DESARU EXPRESSWAY) KE SG.

RENGIT (SEK 0-28) DARI 2 LORONG KEPADA 4 LORONG, KOTA TINGGI, JOHOR DARUL TAKZIM - PAKEJ A
BRIDGE OVER SG. LEBAM AT CH 2000
BILL NO. 7 - BRIDGEWORKS (25m+25m+25m)

ITEM RATE AMOUNT


DESCRIPTION UNIT QTY
NO (RM) (RM)

7.1 GENERAL ITEMS

7.1.1 Provide all labour, plants, materials etc., for the


excavation of existing ground to platform level,
transport and disposal of excavated
material to approved site.

7.1.2 Allow for Provisional Sum for temporary bridge and 1,500,000.00
protection work L.S.

7.2 EARTHWORKS:
Supply all labour, plants, materials, transports,
etc. for the proposed work in accordance with the
Specifications and Drawings.

7.2.1 Provide planking, shuttering and dewatering for the L.S. 150,000.00
construction of abutment and piers

7.2.2 Provide 100mm diameter Class 2 PVC


drainage pipe with fittings. m 175 20.00 3,500.00

7.3 TEMPORARY WORKS


Allow for provision of all labours, plants, materials etc for the
construction of sheetpiles cofferdams including excavation,
handling, disposal of excavated spoils and debris,
dewatering, shoring, levelling, driving, allowing for access
way platform, stagg and all other necessary works for the
purposes of construction of abutments and/or piers and
removal of all temporary works upon bridge completion.

7.3.1 Supply FSP IVA or equivalent Grade 43A steel sheet piles L.S 80,000.00 80,000.00

7.3.2 Handle, transport, pitch and drive Grade 43A steel sheet L.S 50,000.00 50,000.00
piles

BQ No. 7 (1 of 7)
PROJEK MENAIKTARAF JALAN FT092 DARI BANDAR PENAWAR (SENAI DESARU EXPRESSWAY) KE SG.
RENGIT (SEK 0-28) DARI 2 LORONG KEPADA 4 LORONG, KOTA TINGGI, JOHOR DARUL TAKZIM - PAKEJ A
BRIDGE OVER SG. LEBAM AT CH 2000
BILL NO. 7 - BRIDGEWORKS (25m+25m+25m)

ITEM RATE AMOUNT


DESCRIPTION UNIT QTY
NO (RM) (RM)

SUB-TOTAL CARRIED TO COLLECTION 1,783,500.00

7.4 700MM DIAMETER PRESTRESSED SPUN


CONCRETE PILES
Supply drive and install in accordance with the
Specifications and Drawings

7.4.1 Allow for mobilisation of all labour, plants, piling


equipment etc. on site for the proposed piling works. L.S. 150,000.00

7.4.2 Supply 700mm diameter initial prestressed spun


concrete piles of 12.0m lengths. Include all
reinforcements, prestressing, etc as in detail. nos. 156 1,950.00 304,200.00

7.4.3 -ditto- extension prestressed spun pile of 12.0m


length -ditto- nos. 156 1,700.00 265,200.00

7.4.4 Fillet weld vertical and raked extension pile joints


to detail. nos. 156 50.00 7,800.00

7.4.5 Provide cast iron shoes to initial piles. nos. 156 250.00 39,000.00

7.4.6 Handle, sling and pitch initial and extension


piles not exceeding 12m long. nos. 312 60.00 18,720.00

7.4.7 -ditto- - raked 1:4 piles - ditto nos.

7.4.8 Drive piles to the required depth. m 3744 25.00 93,600.00

7.4.9 -ditto- - raked 1:4 piles - ditto nos.

7.4.10 Cut off piles to the required level and roughen


inner surface of pile to detail. nos. 156 80.00 12,480.00

7.4.11 Supply and install high yield steel reinforcement


in pile head to detail.
i) 12mm diameter m/ton 2.00 4,800.00 9,600.00
ii) 20mm diameter m/ton 3 4,800.00 14,400.00

7.4.12 Supply and weld 6mm thick m.s. plate to detail nos. 156 50.00 7,800.00

7.4.13 Supply, place and compact 30/20 concrete to detail. m3 20 480.00 9,600.00

7.4.14 Provide all labour, plants, temporary staging, kentledge


testing equipment etc. and load 700mm diameter
test pile to 3000 KN nos. 1 10,000.00 10,000.00

7.4.15 -ditto- a successive test pile at location directed

BQ No. 7 (2 of 7)
PROJEK MENAIKTARAF JALAN FT092 DARI BANDAR PENAWAR (SENAI DESARU EXPRESSWAY) KE SG.
RENGIT (SEK 0-28) DARI 2 LORONG KEPADA 4 LORONG, KOTA TINGGI, JOHOR DARUL TAKZIM - PAKEJ A
BRIDGE OVER SG. LEBAM AT CH 2000
BILL NO. 7 - BRIDGEWORKS (25m+25m+25m)

ITEM RATE AMOUNT


DESCRIPTION UNIT QTY
NO (RM) (RM)
by the S.O. nos. 1 15,000.00 15,000.00

SUB-TOTAL CARRIED TO COLLECTION 957,400.00

7.5 ABUTMENTS

7.5.1 Earthwork
7.5.1.1 Excavate, load, haul and stockpile for reuse any material
except rock at abutments and embankment. m3 1500 20.00 30,000.00

7.5.1.2 - ditto - for rock NA

7.5.1.3 Fill, spread, grade and compact sutable material from


common excavation m3 700 20.00 14,000.00

7.5.1.4 Supply, spread, level and compact in layers, granular


backfill behind abutments and wingwalls as specified.
i) mining / river sand * m3 500 34.00 17,000.00

7.5.1.5 100 mm diameter perforated seepage pipe inclusive of


non-woven geofabric wrapping. m 50 80.00 4,000.00

7.5.1.6 Imported 20 - 40mm single size gravel fill as


drainage layer behind m2 50 60.00 3,000.00

7.5.1.7 50 mm thick Grade 15/20 lean concrete. m2 250 35.00 8,750.00

7.5.1.8 Two layers of bituminous coating on buried surface of


abutment and wingwalls. m2 250 15.00 3,750.00

7.5.2 In- situ Reinforced Concrete

7.5.2.1 50 mm thick Grade 15/20 lean concrete. m2 250 35.00 8,750.00

7.5.2.2 Concrete Grade 40/20 m3 190 480.00 91,200.00

7.5.2.3 Formwork
i) Class F1 for buried surfaces. m2 150 55.00 8,250.00
ii) Class F2 for exposed surfaces. m2 50 60.00 3,000.00

7.5.2.4 High Yield Steel Reinforcement


i) Up to 12mm diameter. t 1 4,800.00 5,760.00
ii) 16mm diameter. t 11 4,800.00 52,800.00
iii) 20mm diameter. t 3 4,800.00 14,400.00
iv) 25mm diameter. t 5 4,800.00 24,000.00

BQ No. 7 (3 of 7)
PROJEK MENAIKTARAF JALAN FT092 DARI BANDAR PENAWAR (SENAI DESARU EXPRESSWAY) KE SG.
RENGIT (SEK 0-28) DARI 2 LORONG KEPADA 4 LORONG, KOTA TINGGI, JOHOR DARUL TAKZIM - PAKEJ A
BRIDGE OVER SG. LEBAM AT CH 2000
BILL NO. 7 - BRIDGEWORKS (25m+25m+25m)

ITEM RATE AMOUNT


DESCRIPTION UNIT QTY
NO (RM) (RM)

SUB-TOTAL CARRIED TO COLLECTION 288,660.00

7.6 SUPERSTRUCTURE

7.6.1 STEEL BEAM NA

7.6.2 POST-TENSIONED PRESTRESSED BEAMS NA

7.6.3 PRE-TENSIONED PRESTRESSED BEAMS

7.6.3.1 25 m long Pre-tensioned Prestressed Tee-beams


including strands, prestressing, launching, grouting and
anchorage all in accordance with the Specification and as
shown in the Drawing. 42 38,000.00 1,596,000.00

7.6.3.2 Cast in-situ concrete

7.6.3.2.1 Concrete Grade 40/20 for deck slab and diaphragm. m3 425 480.00 204,000.00

7.6.3.2.2 High Yield Steel Reinforcement for deck slab and diaphragm.
i) Up to 12mm diameter. t 2.0 4,800.00 9,600.00
ii) 16mm diameter. t 90.0 4,800.00 432,000.00
iii) 20mm diameter. t 4.0 4,800.00 19,200.00
iv) 25mm diameter. t 26 4,800.00 124,800.00

7.6.3.2.3 Formwork Class F2 for deck slab and diaphragm. m2 375 55.00 20,625.00

7.6.3.2.4 12 mm thick cement board permanent formwork at bottom


of deck slab. m2 50 60.00 3,000.00

7.6.3.2.8 Laminated Elastomeric Bearings


i) 400 mm x 510 mm x 82.5 mm thick Laminated Elastomeric
bearings on 25 mm thick grout bedding. nr 84 1,500.00 126,000.00
ii) Test 400 mm x 510 mm x 82.5mm thick Laminated
Elastomeric bearings at Rubber Research Institute Of
Malaysia all in accordance with BS5400 part 9:1983. nr 2 3,000.00 6,000.00

7.3.2.3 BRIDGE PARAPET

7.3.2.3.1 Precast concrete parapets with concrete grade 40/20


including reinforcement, anchorage, hooks etc. with ribbed.
finish as per Drawing

BQ No. 7 (4 of 7)
PROJEK MENAIKTARAF JALAN FT092 DARI BANDAR PENAWAR (SENAI DESARU EXPRESSWAY) KE SG.
RENGIT (SEK 0-28) DARI 2 LORONG KEPADA 4 LORONG, KOTA TINGGI, JOHOR DARUL TAKZIM - PAKEJ A
BRIDGE OVER SG. LEBAM AT CH 2000
BILL NO. 7 - BRIDGEWORKS (25m+25m+25m)

ITEM RATE AMOUNT


DESCRIPTION UNIT QTY
NO (RM) (RM)
i) Type 1 nr 175 1,250.00 218,750.00
ii) Type 2 nr 6 1,500.00 9,000.00

7.3.2.3.2 G.I. post and handrails at parapets as shown in the m 175 250.00 43,750.00
Drawing.

SUB-TOTAL CARRIED TO COLLECTION 2,812,725.00

7.7 MISCELLANEOUS WORKS


Supply all materials, ancillaries, transport etc.
and execute the proposed works in accordance with
the Specification and Drawings.

7.7.1 Form expansion joints at;


a) Deck Slab and Parapets N.A
b) Approach Slabs N.A

7.7.2 Install and fix brass plaque at bridge as per


specification and drawing nos. 2 300.00 600.00

7.7.3 Transflek SR@ or equivalent including all connection to m 50 1,250.00 62,500.00


the deck slab as shown in the drawing

7.7.4 Galvanised high yield steel dowel bars not exceeding nr 28 100 2,800.00
1000mm long at joint between abutment and
approach slab.

7.7.5 Form resin bonded cork filler expansion joints all round the m 20 800 16,000.00
parapet wall and transition/approach slab.

7.8 RIVER BANK TRAINING/PROTECTION

7.8.1 Supply and lay1.0m x 1.0m x 1.0m gabion nos 350 160 56,000.00
-
7.8.2 Supply and lay stone pitching shape m2 500 80 40,000.00

7.9 Deck Drain

7.9.1 Supply and install deck drainage including pipe,


ms strap, flexible rubber hose, down pipe as per drawing m 175 750.00 131,250.00

7.10 SERVICE DUCTS

Supply and install 2 ways x 100mm diameter Class C

BQ No. 7 (5 of 7)
PROJEK MENAIKTARAF JALAN FT092 DARI BANDAR PENAWAR (SENAI DESARU EXPRESSWAY) KE SG.
RENGIT (SEK 0-28) DARI 2 LORONG KEPADA 4 LORONG, KOTA TINGGI, JOHOR DARUL TAKZIM - PAKEJ A
BRIDGE OVER SG. LEBAM AT CH 2000
BILL NO. 7 - BRIDGEWORKS (25m+25m+25m)

ITEM RATE AMOUNT


DESCRIPTION UNIT QTY
NO (RM) (RM)
uPVC Pipe as per drawing m 175 100.00 17,500.00

SUB-TOTAL CARRIED TO COLLECTION 326,650.00

COLLECTION

BQ 1/6

BQ 2/6

BQ 3/6

BQ 4/6

BQ 5/6

BQ No. 7 (6 of 7)
PROJEK MENAIKTARAF JALAN FT092 DARI BANDAR PENAWAR (SENAI DESARU EXPRESSWAY) KE SG.
RENGIT (SEK 0-28) DARI 2 LORONG KEPADA 4 LORONG, KOTA TINGGI, JOHOR DARUL TAKZIM - PAKEJ A
BRIDGE OVER SG. LEBAM AT CH 2000
BILL NO. 7 - BRIDGEWORKS (25m+25m+25m)

ITEM RATE AMOUNT


DESCRIPTION UNIT QTY
NO (RM) (RM)

TOTAL CARRIED TO SUMMARY OF BILLS OF QUANTITIES 6,168,935.00

BQ No. 7 (7 of 7)