Model letters for use by the Contractor

Letter to the Engineer


ML 4.24b

Claim No. *
Sub-Clause 4.24 Fossils
Discovery of (description) on Site

On (date) (description) was found on site at (location). We received your


instructions (reference, date) requiring us to suspend work pending further
instructions.

In accordance with the provisions of Sub-Clause 4.24, we hereby notify you that
we consider ourselves entitled to an extension of time together with
reimbursement of our costs.

We are maintaining records of our activities and request your cooperation in


agreeing these records.

Yours etc.