Professional Documents
Culture Documents
1.1 Drawing title, Dwg. No, Sht. No, Dwg. size, Rev. No. Correct.
1.2 Project No, Project name, Client name, Contractor & Client logo
3 DRAWING REPRESENTATION
Are all lines shown with line no.s. (lines shall include size, fluid spec, line seq. nos.,
4.1
pipe spec and insulation requirement as per project philosophy)
4.3 Are pipe class used consistent with Piping Material Specification
4.4 Are fluid code breaks shown, where required (for design pressure changes)
4.5 Are symmetrical piping requirements, where applicable, indicated on the P&ID
Are slope requirements identified for the lines (e.g. Major Process lines such as
4.6 KOD inlet, Gas outlet, RV inlet line, RV outlet line, BD inlet line, BD outlet line, Drain
lines, Flare lines, Compressor suction lines etc.)
Are two phase lines identified in Line List and a note mentioned for providing
4.7
adequate support
Are line insulation/tracing identification shown correctly on the P&ID (as well as on
4.8
the continuation drawing).
4.11 Are vent and drain lines isolation placed as per project philosophy.
Is minimum straight length requirement indicated for lines on the P&ID (e.g..
4.12
Separator inlet, KOD inlet, etc.)
Do line numbers differ with differing design pressures (with same pipe class), e.g.
4.13
drain lines
Are no pocket requirement for 2-Phase lines, sour gas condensing lines, air cooler
4.14
(2 phase) outlet lines etc. shown on the P&ID
4.15 Is free draining requirement shown on the P&ID (e.g. For condensing HC lines)
Is DBB isolation requirement as per project philosophy (e.g. DBB for 900# and
4.16
above or sour service is recommended)
4.17 Are break flanges provided for chemical injection lines near injection quill
Page 1 of 3
CHECK LIST FOR PROCESS & INSTRUMENTATION DRAWING (P&ID)
Is the note: HBGV (hot gas bypass valve) to be at a minimum distance from
4.18
compressor discharge" identified.
Is the note: "Anti-surge valve in the compressor loop to be at high point in the
4.19
discharge header" identified.
5 EQUIPMENT
5.1 Vessels
5.1.7 Are equipment inlet/outlet nozzle sizes consistent with the datasheet
5.1.10 Are all process vent and drain connections indicated on the P&ID
Is pressure relief system indication as per project philosophy and is the location of
5.1.11
nozzle (i.e. upstream of demister pad) checked on the P&ID
6 VALVES
Page 2 of 3
CHECK LIST FOR PROCESS & INSTRUMENTATION DRAWING (P&ID)
Is relief valve representation (i.e. relief case, size, set pressure, tag no.) consistent
6.4.1
with project philosophy (Estimated size to be provided and kept under hold)
6.4.3 Are PSV set points consistent with equipment design pressure
6.4.4 Is PSV discharge designation correctly identified (e.g. ATM, HP/LP flares )
Is relief valve isolation and bypass as per project philosophy, including interlocking
6.4.5
system, if applicable
7 INSTRUMENTATION
7.1 Is control representation of Local, control, PLC or DCS as per project philosophy
Are all field instruments (local reading instruments) identified, including notes for
7.6
preferential location
7.7 Are tag numbers for all the instruments consistent with project philosophy
8 PACKAGES
Initial
Sign
Date
Notes:
1 "Originitator" will check all checkpoints mentioned in the checklist for all documents attached with this checklist.
2 "Checker" will check 10% of the checkpoints mentioned in the checklist for all documents attached with this checklist.
3 "Lead Engineer" will spot check the checkpoints mentioned in the checklist for all documents attached with this checklist.
Page 3 of 3