ID Task Task Name Duration Start Finish Apr 9, '17 May 7, '17 Jun 4, '17 Jul 2, '17

Mode W S T M F T S W S
0 Residential 152 days Mon Tue
Construction 5/8/17 12/5/17
1 General Conditions 21 days Mon 5/8/17 Mon 6/5/17
2 Finalize plans 20 days Mon 5/8/17 Fri 6/2/17 General contractor[50%],Architec
and develop
estimate with
owner, architect
3 Sign contract 1 day Mon 6/5/17 Mon 6/5/17 General contractor,Architect,O
and notice to
proceed
4 Apply for 0 days Mon 6/5/17 Mon 6/5/17 6/5
Permits
5 Secure 0 days Mon 6/5/17 Mon 6/5/17 6/5
foundation
permit
6 Secure 0 days Mon 6/5/17 Mon 6/5/17 6/5
framing
permit
7 Secure 0 days Mon 6/5/17 Mon 6/5/17 6/5
electrical
permit
8 Secure 0 days Mon 6/5/17 Mon 6/5/17 6/5
plumbing
permit
9 Secure HVAC 0 days Mon 6/5/17 Mon 6/5/17 6/5
permit

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Apr 9, '17 May 7, '17 Jun 4, '17 Jul 2, '17
Mode W S T M F T S W S
10 Secure 0 days Mon 6/5/17 Mon 6/5/17 6/5
miscellaneous
permits
11 Site Work 3 days Tue 6/6/17 Thu 6/8/17
12 Clear and grub 1 day Tue 6/6/17 Tue 6/6/17 Site excavation contractor
lot
13 Install 1 day Wed 6/7/17 Wed 6/7/17 Electric company
temporary
power service
14 Install 1 day Thu 6/8/17 Thu 6/8/17 Electric contractor,Plumbing
underground
utilities
15 Foundation 42 days Fri 6/9/17 Mon 8/7/17
16 Excavate for 3 days Fri 6/9/17 Tue 6/13/17 Site excavation contracto
foundations
17 Form basement 13 days Wed Fri 6/30/17 Concrete con
walls 6/14/17
18 Place concrete 12 days Mon 7/3/17 Tue 7/18/17
for foundations
& basement
19 walls basement 7 days
Cure Wed Thu 7/27/17
walls for 7 days 7/19/17
20 Strip basement 2 days Fri 7/28/17 Mon
wall forms 7/31/17
21 Waterproof/insulate
2 days Tue 8/1/17 Wed 8/2/17
basement walls

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start Finish Apr 9, '17 May 7, '17 Jun 4, '17 Jul 2, '17
Mode W S T M F T S W S
22 Perform 1 day Thu 8/3/17 Thu 8/3/17
foundation
inspection
23 Backfill 2 days Fri 8/4/17 Mon 8/7/17
foundation
24 Framing 22 days Tue 8/8/17 Wed 9/6/17
25 Install 1st floor 2 days Tue 8/8/17 Wed 8/9/17
joists
26 Lay 1st floor 2 days Thu 8/10/17 Fri 8/11/17
decking
27 Frame 1st floor 4 days Mon Thu 8/17/17
walls 8/14/17
28 Frame 1st floor 1 day Fri 8/18/17 Fri 8/18/17
corners
29 Install 2nd floor 2 days Mon Tue 8/22/17
joists 8/21/17
30 Frame 2nd floor 2 days Wed Thu 8/24/17
decking 8/23/17
31 Frame 2nd floor 3 days Fri 8/25/17 Tue 8/29/17
walls
32 Frame 2nd floor 2 days Wed Thu 8/31/17
corners 8/30/17
33 Complete roof 3 days Fri 9/1/17 Tue 9/5/17
framing
34 Conduct framing 1 day Wed 9/6/17 Wed 9/6/17
inspection

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task Task Name Duration Start Finish Apr 9, '17 May 7, '17 Jun 4, '17 Jul 2, '17
Mode W S T M F T S W S
35 Dry In 22 days Wed 9/6/17 Thu 10/5/17
36 Install 1st floor 3 days Thu 9/7/17 Mon
sheathing 9/11/17
37 Install 2nd floor 3 days Tue 9/12/17 Thu 9/14/17
sheathing
38 Install roof 3 days Wed 9/6/17 Fri 9/8/17
decking
39 Install felt, 3 days Fri 9/22/17 Tue 9/26/17
flashing and
shingles
40 Hang 1st floor 1 day Wed Wed
exterior doors 9/27/17 9/27/17
41 Install 1st floor 3 days Thu 9/28/17 Mon
windows 10/2/17
42 Install 2nd floor 3 days Tue 10/3/17 Thu 10/5/17
windows
43 Exterior Finishes 19 days Fri 10/6/17 Wed 11/1/17
44 Complete 16 days Fri 10/6/17 Fri 10/27/17
exterior brick
45 Complete 3 days Mon Wed
exterior siding 10/30/17 11/1/17
46 Utility 21 days Mon Mon
Rough-B97Ins and 9/11/17 10/9/17
Complete
47 Concrete
Rough-in 5 days Fri 9/15/17 Thu 9/21/17
plumbing

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
ID Task Task Name Duration Start Finish Apr 9, '17 May 7, '17 Jun 4, '17 Jul 2, '17
Mode W S T M F T S W S
48 Conduct 1 day Fri 9/22/17 Fri 9/22/17
rough-in
plumbing
inspection
49 Place concrete 11 days Mon Mon
for basement 9/25/17 10/9/17
floor
50 Rough-in 5 days Fri 9/15/17 Thu 9/21/17
electrical
51 Conduct 1 day Fri 9/22/17 Fri 9/22/17
rough-in
electrical
inspection
52 Rough-in HVAC 3 days Mon 9/25/17Wed 9/27/17
53 Conduct 1 day Thu 9/28/17 Thu 9/28/17
rough-in HVAC
inspection
54 Rough-in 2 days Mon Tue 9/12/17
communication 9/11/17
- phone, cable,
computer, alarm
55 Interior Finishes 30 days Fri 10/6/17 Thu 11/16/17
56 Insulation 11 days Fri 10/6/17 Fri 10/20/17
57 Place wall 1 day Fri 10/6/17 Fri 10/6/17
insulation -
1st floor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
ID Task Task Name Duration Start Finish Apr 9, '17 May 7, '17 Jun 4, '17 Jul 2, '17
Mode W S T M F T S W S
58 Place wall 1 day Mon Mon
insulation - 10/9/17 10/9/17
2nd floor
59 Place ceiling 1 day Thu Thu
insulation - 10/19/17 10/19/17
2nd floor
60 Conduct 1 day Fri 10/20/17 Fri 10/20/17
insulation
inspection
61 Drywall 9 days Mon 10/9/17Thu 10/19/17
62 Install drywall 2 days Mon Tue
- 1st floor 10/9/17 10/10/17
walls
63 Install drywall 2 days Wed Thu
- 1st floor 10/11/17 10/12/17
overhead
64 Install drywall 2 days Fri 10/13/17 Mon
2nd floor 10/16/17
walls
65 Install drywall 2 days Tue Wed
2nd floor 10/17/17 10/18/17
overhead
66 Tape and float 1 day Fri 10/13/17 Fri 10/13/17
1st floor
drywall

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
ID Task Task Name Duration Start Finish Apr 9, '17 May 7, '17 Jun 4, '17 Jul 2, '17
Mode W S T M F T S W S
67 Tape and float 1 day Thu Thu
2nd floor 10/19/17 10/19/17
drywall
68 Paint and 17 days Mon Tue 11/7/17
Wallpaper 10/16/17
69 Texture all 1 day Mon Mon
except entry 10/16/17 10/16/17
and kitchen -
1st floor
70 Paint all 1 day Tue Tue
except entry 10/17/17 10/17/17
and kitchen -
1st floor
71 Hang 1 day Wed Wed
wallpaper 10/18/17 10/18/17
entry and
kitchen - 1st
floor
72 Texture all - 1 day Tue Tue
2nd floor 10/17/17 10/17/17
73 Paint all - 2nd 1 day Wed Wed
floor 10/18/17 10/18/17
74 Paint exterior 4 days Thu 11/2/17 Tue 11/7/17
siding & trim
work
75 Cabinets 6 days Thu 10/19/17Thu 10/26/17

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
ID Task Task Name Duration Start Finish Apr 9, '17 May 7, '17 Jun 4, '17 Jul 2, '17
Mode W S T M F T S W S
76 Install 1st 2 days Thu Fri 10/20/17
floor - kitchen 10/19/17
cabinets
77 Install 1st 1 day Mon Mon
floor - master 10/23/17 10/23/17
bath and
guest cabinets

78 Install 2nd 1 day Tue Tue


floor - hall 10/24/17 10/24/17
bath and
private bath
cabinets
79 Install chair 2 days Wed Thu
rails, crown 10/25/17 10/26/17
moldings,
trim
80 Finish Plumbing 6 days Mon 10/23/17
Mon 10/30/17
81 Complete 1st 1 day Mon Mon
floor - kitchen 10/23/17 10/23/17
plumbing
82 Complete 1st 2 days Tue Wed
floor - master 10/24/17 10/25/17
bath and
guest
plumbing

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
ID Task Task Name Duration Start Finish Apr 9, '17 May 7, '17 Jun 4, '17 Jul 2, '17
Mode W S T M F T S W S
83 Complete 2nd 2 days Thu Fri 10/27/17
floor - hall 10/26/17
bath and
private bath
plumbing
84 Conduct finish 1 day Mon Mon
plumbing 10/30/17 10/30/17
inspection

85 Finish Electrical 3 days Mon 10/30/17


Wed 11/1/17
86 Complete 1st 1 day Mon Mon
floor circuits 10/30/17 10/30/17
to service
panel
87 Complete 2nd 1 day Tue Tue
floor circuits 10/31/17 10/31/17
to service
panel
88 Conduct finish 1 day Wed Wed
electrical 11/1/17 11/1/17
inspection

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9
ID Task Task Name Duration Start Finish Apr 9, '17 May 7, '17 Jun 4, '17 Jul 2, '17
Mode W S T M F T S W S
89 Complete 2 days Tue Wed
communications 10/31/17 11/1/17
wiring -
phone, cable,
computer,
90 alarm
Finish HVAC 3 days Thu 11/2/17 Mon 11/6/17
91 Complete 1st 1 day Thu 11/2/17 Thu 11/2/17
floor - zone 1
HVAC
92 Complete 2nd 1 day Fri 11/3/17 Fri 11/3/17
floor - zone 2
HVAC
93 Conduct 1 day Mon Mon
HVAC 11/6/17 11/6/17
inspection
94 Carpet, Tile and 8 days Tue 11/7/17 Thu
Appliances 11/16/17
95 Tile entry, 3 days Tue 11/7/17 Thu 11/9/17
kitchen and
baths
96 Carpet 1st 2 days Fri 11/10/17 Mon
floor 11/13/17
97 Carpet 2nd 2 days Tue Wed
floor 11/14/17 11/15/17
98 Install 1 day Thu Thu
appliances 11/16/17 11/16/17

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10
ID Task Task Name Duration Start Finish Apr 9, '17 May 7, '17 Jun 4, '17 Jul 2, '17
Mode W S T M F T S W S
99 Landscaping and 12 days Wed Thu
Grounds Work 11/8/17 11/23/17
100 Pour concrete 2 days Wed Thu 11/9/17
driveway and 11/8/17
sidewalks
101 Install backyard 2 days Fri 11/17/17 Mon
fence 11/20/17
102 Sod and 2 days Tue Wed
complete 11/21/17 11/22/17
plantings - front
yard
103 Sod and 1 day Thu Thu
complete 11/23/17 11/23/17
plantings -
backyard
104 Final Acceptance 8 days Fri 11/24/17 Tue 12/5/17
105 Complete final 1 day Fri 11/24/17 Fri 11/24/17
inspection for
certificate of
occupancy
106 Cleanup for 1 day Mon Mon
occupancy 11/27/17 11/27/17
107 Perform final 1 day Tue Tue
walk-through 11/28/17 11/28/17
inspection

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11
ID Task Task Name Duration Start Finish Apr 9, '17 May 7, '17 Jun 4, '17 Jul 2, '17
Mode W S T M F T S W S
108 Complete punch 5 days Wed Tue 12/5/17
list items 11/29/17

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12
Jul 30, '17 Aug 27, '17 Sep 24, '17 Oct 22, '17 Nov 19, '17 Dec 17, '17 Jan 14, '18 Feb 11
T M F T S W S T M F T S W S T M F T S W

rchitect[50%],Owner[12%],Mortgage lender[12%]

tect,Owner,Mortgage lender

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 13
Jul 30, '17 Aug 27, '17 Sep 24, '17 Oct 22, '17 Nov 19, '17 Dec 17, '17 Jan 14, '18 Feb 11
T M F T S W S T M F T S W S T M F T S W

or

mbing contractor

ntractor

te contractor

Concrete contractor

Concrete contractor

Concrete contractor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 14
Jul 30, '17 Aug 27, '17 Sep 24, '17 Oct 22, '17 Nov 19, '17 Dec 17, '17 Jan 14, '18 Feb 11
T M F T S W S T M F T S W S T M F T S W
Inspector

Site excavation contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Inspector

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 15
Jul 30, '17 Aug 27, '17 Sep 24, '17 Oct 22, '17 Nov 19, '17 Dec 17, '17 Jan 14, '18 Feb 11
T M F T S W S T M F T S W S T M F T S W

Framing contractor

Framing contractor

Framing contractor

Roofing contractor

Framing contractor

Framing contractor

Framing contractor

Masonry contractor

Framing contractor

Plumbing contractor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 16
Jul 30, '17 Aug 27, '17 Sep 24, '17 Oct 22, '17 Nov 19, '17 Dec 17, '17 Jan 14, '18 Feb 11
T M F T S W S T M F T S W S T M F T S W
Inspector

Concrete contractor

Electric contractor

Inspector

Heating and AC contractor


Inspector

Electric contractor

Insulation contractor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 17
Jul 30, '17 Aug 27, '17 Sep 24, '17 Oct 22, '17 Nov 19, '17 Dec 17, '17 Jan 14, '18 Feb 11
T M F T S W S T M F T S W S T M F T S W
Insulation contractor

Insulation contractor

Inspector

Drywall contractor

Drywall contractor

Drywall contractor

Drywall contractor

Drywall contractor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 18
Jul 30, '17 Aug 27, '17 Sep 24, '17 Oct 22, '17 Nov 19, '17 Dec 17, '17 Jan 14, '18 Feb 11
T M F T S W S T M F T S W S T M F T S W
Drywall contractor

Painting contractor

Painting contractor

Painting contractor

Painting contractor

Painting contractor

Painting contractor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 19
Jul 30, '17 Aug 27, '17 Sep 24, '17 Oct 22, '17 Nov 19, '17 Dec 17, '17 Jan 14, '18 Feb 11
T M F T S W S T M F T S W S T M F T S W
Finish carpentry contractor

Finish carpentry contractor

Finish carpentry contractor

Finish carpentry contractor

Plumbing contractor

Plumbing contractor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 20
Jul 30, '17 Aug 27, '17 Sep 24, '17 Oct 22, '17 Nov 19, '17 Dec 17, '17 Jan 14, '18 Feb 11
T M F T S W S T M F T S W S T M F T S W
Plumbing contractor

Inspector

Electric contractor

Electric contractor

Inspector

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 21
Jul 30, '17 Aug 27, '17 Sep 24, '17 Oct 22, '17 Nov 19, '17 Dec 17, '17 Jan 14, '18 Feb 11
T M F T S W S T M F T S W S T M F T S W
Electric contractor

Heating and AC contractor

Heating and AC contractor

Inspector

Flooring contractor

Flooring contractor

Flooring contractor

Appliance contractor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 22
Jul 30, '17 Aug 27, '17 Sep 24, '17 Oct 22, '17 Nov 19, '17 Dec 17, '17 Jan 14, '18 Feb 11
T M F T S W S T M F T S W S T M F T S W

Concrete contractor

Fencing contractor

Landscape contractor

Landscape contractor

Inspector

Maid service

Owner

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 23
Jul 30, '17 Aug 27, '17 Sep 24, '17 Oct 22, '17 Nov 19, '17 Dec 17, '17 Jan 14, '18 Feb 11
T M F T S W S T M F T S W S T M F T S W
General contractor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 24