Professional Documents
Culture Documents
26 April 2017
Detailed Observations
There was no log maintained for the changes made to the BOM for the period April 2016 December 2016, instead the previous BOM was updated.
It was noted during the period April 2016 to December 2016 , 615 BOMs were updated and no versions of the same were maintained in SAP.
Plant 1000 2000 3000 3100
Number of BOM's Updated 69 4 458 80
It is important to note that the above changes does not include following type of amendments which were difficult to identify in absence of Log of changes / version management:
1. Instances where material ratio ( quantity , yield) was changed without changing the material type.
2. Instances where existing materials were replaced with different materials.
The above instances could not be verified for the defined SOP compliance for BOM amendments.
For details of BOMs which were updated for more than 3 times refer, Annexure 1
Root Cause
System was not configured to maintain BOM versions. Person responsible: Amit Sharma, Abhay Karhade
Timeline:
Annexure 1
There was no process defined to bifurcate between controllable and un-controllable reasons, for downtime also there was no formal action plan and root cause documented for reduction in downtime.
Machine downtime was entered in Z - delay report after each shift at all plants and reasons were noted. On review of delay report for all plants following inconsistencies were noted.
Incorrect MIS reporting for production loss reasons. We have initiated the process to maintain reasons for delay in Z-delay Report
Root Cause
Person responsible: S.K Banerjee, Ravi Rana, Anand Garg
There was no review of Z delay report. Timeline:
Absence of defined process for review and monitoring of SOP.
Down time
5% Trend showing department wise downtime
Repair reasons.
Labour
30%
30%
Maintenance as per
schedule
Power fail
7%
28% Others
Annexure 2
On analysis it was observed that there was no tracker maintained to record reasons for decrease in efficiency of machines for plant 1000, 2000 (Old looms) and 3000.
It was noted that efficiency percentage of machines was entered in SAP, but reasons for lower efficiency was not maintained by department.
On discussion with spinning head it was informed that major reasons for decrease in efficiency was speed loss and idle machine time. However root cause for speed loss was not documented. Refer Annexure 3 for trending of
efficiency percentage.
Root Cause
Person responsible: S.K. Banerjee.
SAP was not configured to record the reasons for inefficiency. Timeline:
Absence of tracking of reasons for speed loss.
On analysis of BOMs master and Input wiz a wiz output ratio following inconsistencies were observed:
Plant 1000:
It was observed that in case of 31 production orders input output ratio was not matched, i.e., the base quantity was not equal to consumption quantity as per BOM.
Plant 2000:
2000:
On analysis of standard v/s actual weft yarn requirement, it was observed that 80,000 Kgs of yarn was consumed lower than actually required as per BOM, variance % was ranging from 35% to 121%. ( BOM v/s
Actuals)
On analysis of standard v/s actual yield for loom, it was observed that for sort 1106, actual yield was also shown as standard yield however the difference was adjusted ( 87000 meters) against 4 production orders
out of total 35 production orders made for 78 Lac meters.
It was also observed that standard yield percentages ( Input v/s Output meters ) were varying for same sorts for Looms and the variation was ranging between 90.76% to 166.79% which ideally should be 91.74%
Plant 3000:
It was observed that in case of 3 materials ( Mercerization stage ) yield defined as per BOM is 100%, on comparison with actual yield percentages it was observed that actual yield was ranging between 93% to
108%.
Refer Annexure 4 for details
Standard output cannot be determined for each process . Plant 1000: Pending
Plant 2000: We are working on sort master, BOM for consumption viz a viz variation will be updated.
Plant 3000: The BOM master has been updated
Root Cause
Person responsible: Aashish Sonwalkar, S K Banerjee
BOM master was not reviewed on a periodic basis. Timeline:
Annexure 4
Root Cause
Person responsible: S K Banerjee and Aashish Sonwalkar
Reusable packing material was not used. Timeline:
Feasibility analysis of packing material was not performed.
Plastic cone
Internal Consumption 20% Paper cone used Cost of each cone Excess cost
7,51,490 1,50,298 2 2,70,536
Number of Number of
Qty used per Total Actual Number of Total Cost Savings (in one
Material Cost per Piece times can be Cost per Use Alternate Material times it can be Cost per piece Cost per Use Initial Investment
month cost per month pieces required Reduction per use year)
used used
Wooden Pallet 36 440 10 15,840 44 Plastic Pallet 50 150 3200 32 1,60,000 -12 90,000
corrugated sheet 720 34 5 24,422 7 Plastic sheet 700 150 130 1.3 91,000 -6 6,30,000
Polythene film 720 186 1 1,33,920 186 Bag/ HDPE Bag 50 30 399 15.96 19,950 -170 2,55,000
Paper Tube 500 19 4 9,250 5 GI Pipe 50 150 130 1.3 6,500 -3 22,500
Packing material
Recommended material
currently used
It was observed that, cost sheet of each packing material was not prepared during the period April 2016 to December 2016, there was no feasibility study conducted to reduce the cost of packing material.
It was observed that there was no reconciliation performed for the packing material used.
Quality testing machines used for packing materials are calibrated outside on a yearly basis, there was no check performed between the year to check if the machine is calibrated. ( Machines for checking CS, ECT are old
machines and needs to be replaced) .
Root Cause
Person responsible: Amrish Pundir
Cost sheet was not prepared for all packing material. Timeline:
Quality test machines were not procured not timely basis.
On review of boiler layout it was observed that, the coal feeding process can be automated resulting into reduction in man power cost.
Steam used by each department was not tracked since meters were not installed to check the consumption, the steam consumption was charged on plant wise basis the steam recorded on each plant meter.
Actual steam utilized Vs standard steam required was not tracked.
Root Cause
Person responsible: R K Gupta
Trolley was not used to feed coal in the boiler Timeline:
Semi finished material lying at production floor may lose its value. Plant 2000 & 3000 - Old material shall be consumed.
Plant 1000 - Pending
Root Cause
Person responsible: S K Banerjee Aashish Sonwalkar
Review of ageing of material was not performed. Timeline: 30 June 2017
0 - 15 days 15-
15-30 days 30-
30-90 days 90-
90-180 days 180 - 1yr > 1 year Total
Plant Production Supervisor
1000 Auto Corner 70,08,592 1,59,504 2,75,299 3,28,821 2,31,815 5,053 80,09,085
1000 Blow room 9,70,601 5,74,617 - 68 272 1,864 15,47,423
1000 Carding 14,47,240 6,79,295 - 108 85,878 - 22,12,521
1000 Comber 12,02,836 2,00,516 11,393 - - - 14,14,746
1000 Doubling 3,37,613 14,094 2,69,395 42,720 79,151 - 7,42,972
1000 Draw-frame 1,36,95,225 2,80,158 15,32,682 49,944 3,93,470 1,12,290 1,60,63,768
1000 Lap 18,91,885 7,49,510 - - - - 26,41,395
1000 Mercerise 9,55,642 4,61,281 2,51,319 27,011 3,623 - 16,98,876
1000 Mixing 1,28,06,736 13 67,65,916 18,642 11,631 1,596 1,96,04,534
1000 Open end 23,46,433 59,441 1,29,316 15,404 - - 25,50,595
1000 Reeling 38,12,465 2,53,737 1,55,547 49,151 12,854 389 42,84,145
1000 Ring Frame 43,31,168 1,04,632 76,208 1,01,716 73,128 35,874 47,22,726
1000 Speed Frame 1,06,20,540 66,367 20,50,700 21,779 27,794 99,132 1,28,86,311
1000 TFO 19,31,234 129 84,404 1,59,436 1,00,293 29,124 23,04,619
1000 Warehouse 61 15,512 4,27,907 48,060 2,185 142 4,93,867
1000 Winding 20,62,695 89,128 9,87,066 5,34,312 99,196 39,370 38,11,768
Preventive maintenance schedule is defined in SAP for the equipment's which determines the periodicity of maintenance ( Monthly, Quarterly, yearly).
On review of preventive maintenance during the period April 2016 to December 2016 following discrepancies were noted:
1. On review of 6784 preventive maintenance orders , noted in 730 orders there was delay in maintenance, ageing of such delay ranged from 14 days to 175 days. For further details refer Annexure 9
2. On review of 7938 maintenance orders, noted 478 orders there was delay in technically completing the orders in SAP, resulting into incorrect ot delayed scheduling of next preventive maintenance. For further details refer
Annexure 9a.
9a.
3. Segregation of Duty : It was observed that same person was responsible to raise and close the maintenance order in the system.
4. On review of equipment's included in preventive maintenance plan it was observed that CARD077 was not included in the schedule, further maintenance was not performed for 318 equipment's for the period April 2016 to
December 2016. For details refer Annexure 9b.
5. 9c..
On review of maintenance report it was noted that in case of 470 machines, deviations were found in the time for which machine was under maintenance as per production report. For details refer Annexure 9c
6. Breakdown Maintenance: On review of breakdown report it was observed that breakdown notifications were not updated in SAP at all times, resulting to incorrect recording of breakdown time and reasons for the same.
7. On analysis of spares issued for maintenance it was observed that material was issued to a cost center but was not updated in SAP against which machine the spare was used. For details refer Annexure 9d.
Root Cause
Annexure 9
Production can be booked against old open production orders to reduce cost of current order. Point 1: Technically completion of Production orders has been initiated on monthly basis.
Production order wise efficiency cannot be tracked. Point 2: Initiated booking in SAP Zdyelotw.
Material will be lying at a particular stage if confirmed in machine and not delivered against each order. Point 7: Chemical consumption is posted as per tolerance level maintained in BOM.
Pending for remaining points
Annexure 10
1. It was observed waste was not recorded against each production order, it was recorded shift wise or day wise against any production order.
2. Plant 1000: ItI was observed that there was variation in waste percentages defined in BOMs for the same processes, Refer Annexure 11.
3. On analysis of actual waste yield wiz a wiz standard waste yield defined in BOM for each process it was noted that actual waste yield was higher than defined in BOM. Refer Annexure 11 for further details
4. On analysis of waste percentages it was also noted that there was no waste recorded at OPEN END.
Root Cause
Review of standard and actual waste on timely basis. Person responsible: S K Banerjee
Timeline:
Waste %
Production Stage
Min BOM % Max BOM % Average Actual %
Root Cause
Person responsible: Anand Garg, N P Pachauri
Users were not trained regarding all the features in SAP. Timeline: