SCHEDULE "B"
ATTACHMENT II
1. Milestone Dates
MANDATORY
BASE PROPOSAL ALTERNATE
PROPOSAL
Critical Milestone Events
No. of Calendar Days No. of Calendar Days
After the Effective After the Effective Date
Date of the Contract of the Contract
Design/ Procurement
1.1 Project Commencement Date 0 0
Submit Tank Package Work
1.2
Schedule
30 30
Submission of Project Execution
1.3
Plan (PEP)
30 30
B-II-1
MP-LSTK / MP-IK-LSTK / MP-IK-LSPB 04/13
Revised 09/13
SCHEDULE B, ATTACHMENT II CONTRACT NO. 66000XXXXXX
B-II-2
MP-IK-LSTK / 04/13
Revised 09/13
SCHEDULE B, ATTACHMENT II CONTRACT NO. 66000XXXXXX
CONTRACTOR shall complete all required activities for the milestones, including
the following:
CONTRACTOR shall submit the Project Execution Plan per Section 5.3 of
Schedule B after incorporating SAUDI ARAMCOs final review
comments.
B-II-3
MP-IK-LSTK / 04/13
Revised 09/13
SCHEDULE B, ATTACHMENT II CONTRACT NO. 66000XXXXXX
The POs for Plates and any long lead materials (with a lead time of more
than eight (8) months) shall be placed with the Vendors by the Milestone
Date.
Submit technical studies, technical data sheets, master equipment list and
first takeoff of materials issued. Any other engineering documents and
drawings deemed necessary to illustrate the degree of completion and
accuracy commensurate with the progress at 60% are complete, and
obtain SAUDI ARAMCO acceptance. (Ref. SAEP-303)
CONTRACTOR has placed all Purchase Orders (PO) for all the Cathodic
Protection for the entire tank package.
CONTRACTOR has placed all Purchase Orders (PO) for all bulk materials
and equipment required to execute all tank construction works.
B-II-4
MP-IK-LSTK / 04/13
Revised 09/13
SCHEDULE B, ATTACHMENT II CONTRACT NO. 66000XXXXXX
CONTRACTOR shall have completed and issued the Tank Package Work
drawings which include but not limited to plot plans, sectional and
elevation details, soil improvement drawings, mechanical drawings and
data sheets, civil and structural drawings, electrical and instrumentation
drawings, Cathodic protection drawings, and any other drawings or
documents deemed required for the design package by SAUDI ARAMCO.
CONSTRUCTION:
Temporary Site offices for CONTRACTOR have been mobilized and ready
to be used, and the CONTRACTOR has mobilized all required equipment
and personnel resources to start construction work associated with
relevant approvals as per SAUDI ARAMCO requirements.
CONTRACTOR start all structural works for three DO, three DPK, one
DO/DPK and one Slop tank or as directed by SAUDI ARAMCO, that
includes fabrication, lifting, alignment, guide trestles, welding works and
any other necessary tasks /activity to be carried out with utmost care with
good workmanship and in accordance with SAUDI ARAMCO
specifications.
CONTRACTOR shall have completed all structural works for 50% storage
tanks corresponding to three DO, three DPK, one DO/DPK and one Slop
tank or as directed by SAUDI ARAMCO, that includes fabrication, lifting,
alignment, guide trestles, welding works and any other necessary tasks
/activity to be carried out with utmost care with good workmanship and in
accordance with SAUDI ARAMCO specifications.
CONTRACTOR starts the Hydrotest for three DO, three DPK, one
DO/DPK and one Slop tank or as directed by SAUDI ARAMCO.
Note: The CONTRACTOR shall submit its plan for selection of tank for each tank
batch. However, SAUDI ARAMCO reserves the right to select / prioritize
any tank or batch of tanks based on operational requirements and
CONTRACTOR shall adjust its plan accordingly without any impact to
schedule and cost. CONTRACTOR will ensure that tanks are sufficiently
protected between completion of each batch till final commissioning /
handover date