Professional Documents
Culture Documents
TABLE OF CONTENTS
1 PURPOSE
2 SCOPE OF WORKS
3 REFFERENCE
4 RESPONSIBILITIES
5 TOOLS AND EQUIPMENT
6 STEP OF WORKS
7 JOB SAFETY ANALYSIS
8 HEALTH AND SAFETY
1. PURPOSE
The purpose of this Work Method Statement for Floor and Wall Tiling Works is to outline and
describe in detail the procedure such as setting and lay-out plan on actual location, pre-laying of
tiles, mixing of tile grout, final laying of tiles and all other related activity..
2. SCOPE OF WORKS
Floor and wall ceramic tiles for Male & Female Toilet including Locker,
3. REFFERENCE
3.1 BS EN 13748-1; Terrazzo tiles. Terrazzo tiles for internal use
3.2 BS EN 14411: Ceramic tiles. Definitions, classification, characteristics, evaluation of
conformity and marking
3.3 General Technical specification
4. RESPONSIBILITY
a. SITE MANAGER
The site manager will provide inputs to the project execution plan to ensure that lifting
strategies & philosophy are addressed. And is responsible for the overall management of
the project construction team to ensure that safe and effective operations are conducted
and properly documented.
b. EQUIPMENT MANAGER/MECHANICAL
The equipment manager will be responsible for the transporting equipments availability
and good order.
c. SITE ENGINEER
Shall report to Site Manager, Shall be responsible for planning, execution and
implementation of all site activities related to this procedure.
e. QC ENGINEER
Shall report to site Engineer
Shall be responsible for attending all Inspection Stages as required by Inspection
test Plan.
Shall be responsible of performing all checks and shall prepare necessary Inspection
Reports.
f. HSE OFFICER
Shall report to Site Manager and shall be responsible for overall control and
inspection of HSE issues.
5. EQUIPMENT AND TOOLS
Bubble level
Carpenter's square (or speed square)
Chalk line
Tape measure
Long straightedge
Notched trowel
Narrow margin trowel
Mason's trowel
Tile wet saw
Tile scorer
Pencil and tile marker.
Tile crimpers (or nippers)
Rubber grout float
Large silicone sponge
Large bucket for water
Rubber hammer. Etc
6. STEP OF WORKS
6.6 Protection:
Do not permit any traffic at all on the flooring after completion.
Provide adequate protection if heavy loads are to be moved across the flooring.
6.7 Cleaning:
Brush off loose materials, wash with clean water and remove surplus water with cloth.
Treat with an appropriate acid cleaner in accordance with the Manufacturers instructions.
Before applying the cleaning agent, wet the floor and remove any surplus water; after
cleaning rinse it thoroughly with clean water