Introduction:

Condition/Problem

- The current problem in Salaya is the road is too rough.


- Too many holes in the alley.
- Alley cant prevent flooding problem.
- Dirt road in some alleys.
- Lots of building in process and safety isnt there.

What was done in the past to improve it?

- They fill up some of cement in the holes, but it could not be enough.
- Put the sign that there is a hole.

Objective: Plan to do? Why?

- Limit the weight of a car. To prevent rough road problem because a lot of time

that big car crash down the road.


- Fill up the holes with concrete inside the alley. To prevent accident that may

occurs in the future and formation of tiny pond.


- Improve drainage system. To prevent flooding inside the alley.
- Make the pathways fit in same level. (drainage system)
- Make sure to create the safety around the building in process. To prevent people

get an unexpected injury.

Method

1. The day that we going to start this project we need to contract with organization.

We will start the action at May and gather the action at April.
2. Buy equipment: cement, bucket, plaster equipment.
3. Check the location.
4. Start the process, working on the process and finish the process.
Time Table for fill up the holes

1 2 3 4 5 6
Contact Contract
with the with the
Organizati organizatio
on n

7 8 9 10 11 12 13
Gathering Gathering Check the Start the
the the location process
equipment equipment

14 15 16 17 18 19 20
Continue Continue Finish up
the The The process
process process

21 22 23 24 25 26 27

28 29 30 31

Clarify:

There are some method that will actually work such as limiting the car weight, make the

pathways fit in the same level, fill up the hole with concrete and make the safety around the

construction site. To make these method more efficient, for limiting the car weight, they will get

fined if they enter the alley. For the pathway, if it on the same level water will be drain out better.

It will drain out at the end of the alley and in the front of the alley. For fill up the hole with

concrete, this method will fix the problem temporarily but it would extend the time until there is a

better method.