You are on page 1of 14

DISMENTLING / RE-CONSTRUCTION OF 01 NO DANGEROUS CLASS ROOM WITH VER.

IN

ABSTRACT OF COST AND QUANTITIES

QTY.
2% Above on T.S. AMOUNT RS.
SR NO. DESCRIPTION OF ITEM UNIT AS per BOQ

1 2 3

Excavation in foundation of Building, bridges and other structures including dag-


1 belling, dressing, refilling around the structures with excavated earth, watering and %0 Cft 963 5,105.56 4,917
ramming lead upto one chain (30-m) and lift upto 5 feet (1.5-m) in ordinary soil.

Dry rammed brick blast 1 thick to 2" (40 mm to 50 mm) guage.


2 % Cft 353 3,231.36 11,407

3 Pacca B/Work in Foundation & Plinth in cement sand mortar 1:6. % Cft 910 16,402.93 149,267

Providing and Laying 1-1/2" thick D.P.C of C. Conc: 1:2:4 with one coat of bitumen
4 % Sft 208 4,257.28 8,855
and polythene sheet 500 guage.

Providing and Laying 1-1/2" thick Vertical D.P.C of Cement plaster (1:3) i/c bitumen
5 % Sft 94 2,765.22 2,599
coating and a layer of plolythene sheet.

6 Filling watering ramming earth under floors

i- form surplus earth %0 Cft 642 2,439.69 1,566

ii With new earth lead upto one mile. %0 Cft 1336 7,473.23 9,984

Page 1 of 14
DISMENTLING / RE-CONSTRUCTION OF 01 NO DANGEROUS CLASS ROOM WITH VER. IN

ABSTRACT OF COST AND QUANTITIES

QTY.
2% Above on T.S. AMOUNT RS.
SR NO. DESCRIPTION OF ITEM UNIT AS per BOQ

1 2 3

7 Pacca B/Work in (1:6) cement sand mortar in Ground floor. % Cft 1208 17,410.02 210,313

Recovery of Material

TOTAL Amount (Rs.) 188,595

Site Inspector
Contracor New Vision Engineer Consultant

Page 2 of 14
M WITH VER. IN GOVT. GIRLS PRIMARY SCHOOL AT CHAK # 93 / TDA (SR. # 89)

D QUANTITIES IPC # 1

THIS BILL PREVIOUS BILL TO DATE


WORK
QUANTITY AMOUNT RS. QUANTITY AMOUNT RS. QUANTITY AMOUNT RS. COMPLETED
%AGE
4=8-6 5=9-7 6 7=6x2 8 9=8x2

797.06 4,069 - ### 797.06 4,069 83%

298.90 9,658 - ### 298.90 9,658 85%

598.71 98,206 - ### 598.71 98,206 66%

208.97 8,896 - ### 208.97 8,896 100%

94.00 2,599 - ### 94.00 2,599 100%

531.38 1,296 - ### 531.38 1,296 83%

528.47 3,949 - ### 528.47 3,949 40%

Page 3 of 14
M WITH VER. IN GOVT. GIRLS PRIMARY SCHOOL AT CHAK # 93 / TDA (SR. # 89)

D QUANTITIES IPC # 1

THIS BILL PREVIOUS BILL TO DATE


WORK
QUANTITY AMOUNT RS. QUANTITY AMOUNT RS. QUANTITY AMOUNT RS. COMPLETED
%AGE
4=8-6 5=9-7 6 7=6x2 8 9=8x2

691.31 120,358 - ### 691.31 120,358 57%

- - - ### -

- - - ### -

- 249,033 - ### 249,033 132%

QUANTITY SURVEYOR Resident Engineer.


New Vision Engineer Consultant New Vision Engineer Consultant

Page 4 of 14
DISMENTLING / RE-CONSTRUCTION OF 01 NO DANGEROUS CLASS ROOM WITH VER. IN
(SR. # 89)

Contractor:- MR. RASHID RAFIQUE KH


Calculation Sheet

Sr. Request DETAIL OF


Date IPC # WORKS No
No. No.

Item No:-
Excavation in foundation of Building, bridges and other structures including dag-belling, dre
structures with excavated earth, watering and ramming lead upto one chain (30-m) and lift up
1 soil.

IPC # 1 L/W 2

IPC # 1 S/W 2

IPC # 1 P/W 1

Item No:-

2 Dry rammed brick blast 1 thick to 2" (40 mm to 50 mm) guage.

IPC # 1 L/W 2

IPC # 1 S/W 2

IPC # 1 P/W 1

Item No:-

Page 5 of 14
DISMENTLING / RE-CONSTRUCTION OF 01 NO DANGEROUS CLASS ROOM WITH VER. IN
(SR. # 89)

Contractor:- MR. RASHID RAFIQUE KH


Calculation Sheet

Sr. Request DETAIL OF


Date IPC # WORKS No
No. No.

3 Pacca B/Work in Foundation & Plinth in cement sand mortar 1:6.

IPC # 1 L/W I step 2

IPC # 1 " " II step 2

IPC # 1 " " III step 2

IPC # 1 " " IV step 2

IPC # 1 S/W I step 2

IPC # 1 " " II step 2

IPC # 1 " " III step 2

IPC # 1 " " IV step 2


IPC # 1 P/W I step 1
IPC # 1 " " II step 1
IPC # 1 " " III step 1
IPC # 1 " " IV step 1

Page 6 of 14
DISMENTLING / RE-CONSTRUCTION OF 01 NO DANGEROUS CLASS ROOM WITH VER. IN
(SR. # 89)

Contractor:- MR. RASHID RAFIQUE KH


Calculation Sheet

Sr. Request DETAIL OF


Date IPC # WORKS No
No. No.

Item No:-
Providing and Laying 1-1/2" thick D.P.C of C. Conc: 1:2:4 with one coat of bitumen and polythene shee
4

IPC # 1 Ist.D.P.C.L/W. 2
IPC # 1 " " S/W. 2

Item No:-
5 Pacca B/Work in Foundation & Plinth in cement sand mortar 1:6.
IPC # 1 P/W I step 2
IPC # 1 " " II step 2
IPC # 1 " " III step 1

Item No:-
Providing and Laying 1-1/2" thick D.P.C of C. Conc: 1:2:4 with one coat of bitumen and polythene shee
6

IPC # 1 P/W I step 2


IPC # 1 " " II step 2
IPC # 1 " " III step 1

D/d
IPC # 1 Door 1
IPC # 1 Ver. 3
IPC # 1 Sides. 2

Item No:-
Providing and Laying 1-1/2" thick Vertical D.P.C of Cement plaster (1:3) i/c bitumen co
7 plolythene sheet.
IPC # 1 L/W 2
Page 7 of 14
DISMENTLING / RE-CONSTRUCTION OF 01 NO DANGEROUS CLASS ROOM WITH VER. IN
(SR. # 89)

Contractor:- MR. RASHID RAFIQUE KH


Calculation Sheet

Sr. Request DETAIL OF


Date IPC # WORKS No
No. No.

IPC # 1 S/W 2
IPC # 1 P/W 2

Item No:-
8 Filling watering ramming earth under floors
form surplus earth
Take 2/3 Qty of item No.1 IPC # 1 1

ii With new earth lead upto one mile.


IPC # 1 1
IPC # 1 1

D/d ssurplus earth.

Item No:-
9 Pacca B/Work in (1:6) cement sand mortar in Ground floor.
IPC # 1 L/W 2
IPC # 1 S/W 2
IPC # 1 P/W 1
D/d
IPC # 1 Door 1
IPC # 1 Window 4
IPC # 1 Almirah 1
IPC # 1 Ver 2
IPC # 1 Ver 3

Contracor

Page 8 of 14
DISMENTLING / RE-CONSTRUCTION OF 01 NO DANGEROUS CLASS ROOM WITH VER. IN
(SR. # 89)

Contractor:- MR. RASHID RAFIQUE KH


Calculation Sheet

Sr. Request DETAIL OF


Date IPC # WORKS No
No. No.

QUANTITY SURVEYOR
New Vision Engineer Consultant

Page 9 of 14
OUS CLASS ROOM WITH VER. IN GOVT. GIRLS PRIMARY SCHOOL AT CHAK # 93 / TDA
(SR. # 89)

ctor:- MR. RASHID RAFIQUE KHAN


Calculation Sheet

IPC # 1
Length Width Depth
Quantity Remarks
(ft) (ft) (ft)
(Cft)

uctures including dag-belling, dressing, refilling around the


d upto one chain (30-m) and lift upto 5 feet (1.5-m) in ordinary

28 3/8 3 1/4 2 368.875

22 3 1/4 2 286.000

21 7/8 3 1/4 2 142.188

Total 797.063

Less Previouse -

This IPC 797.063

guage.

28 3/8 3 1/4 3/4 138.328

22 3 1/4 3/4 107.250

21 7/8 3 1/4 3/4 53.320

Total 298.898

Less Previouse -

This IPC 298.898

Page 10 of 14
OUS CLASS ROOM WITH VER. IN GOVT. GIRLS PRIMARY SCHOOL AT CHAK # 93 / TDA
(SR. # 89)

ctor:- MR. RASHID RAFIQUE KHAN


Calculation Sheet

IPC # 1
Length Width Depth
Quantity Remarks
(ft) (ft) (ft)
(Cft)

ar 1:6.

21-9/8 -9/4 -1/4 30.797

2-7/1 1-5/8 -1/4 25.313

21-3/8 -3/2 -1/4 19.969

10-5/4 -9/8 -2/1 118.125

2-3/1 -9/4 -1/4 25.875

18-7/8 1-5/8 -1/4 21.914

9-5/4 -3/2 -1/4 17.813

19-3/8 -9/8 -2/1 108.563


18-3/8 -9/4 -1/4 12.867
9-3/4 1-5/8 -1/4 10.898
18-9/8 -3/2 -1/4 8.859
2-4/1 -9/8 1-7/8 57.375

Total 458.367
Less Previouse -
This IPC 458.367

Page 11 of 14
OUS CLASS ROOM WITH VER. IN GOVT. GIRLS PRIMARY SCHOOL AT CHAK # 93 / TDA
(SR. # 89)

ctor:- MR. RASHID RAFIQUE KHAN


Calculation Sheet

IPC # 1
Length Width Depth
Quantity Remarks
(ft) (ft) (ft)
(Cft)

e coat of bitumen and polythene sheet 500 guage .

10-5/4 -9/8 59.063


19-3/8 -9/8 54.281

Total 113.344
Less Previouse -
This IPC 113.344

10-5/4 -9/8 1 59.063


19-3/8 -9/8 1 54.281
2-4/1 -9/8 1 27.000

Total 140.344
Less Previouse -
This IPC 140.344

e coat of bitumen and polythene sheet 500 guage .

10-5/4 -9/8 59.063


19-3/8 -9/8 54.281
2-4/1 -9/8 27.000

-4/1 -9/8 -4.500


2-9/4 -9/8 -24.469
-7/1 -9/8 -15.750

Total 95.625
Less Previouse -
This IPC 95.625

ment plaster (1:3) i/c bitumen coating and a layer of

2-4/1 1 48.000
Page 12 of 14
OUS CLASS ROOM WITH VER. IN GOVT. GIRLS PRIMARY SCHOOL AT CHAK # 93 / TDA
(SR. # 89)

ctor:- MR. RASHID RAFIQUE KHAN


Calculation Sheet

IPC # 1
Length Width Depth
Quantity Remarks
(ft) (ft) (ft)
(Cft)
1-6/1 1 32.000
-7/1 1 14.000

Total 94.000
Less Previouse -
This IPC 94.000

797.063 -2/3 531.375


Total 531.375
Less Previouse -
This IPC 531.375

24 16 1 8/9 737.280
24 7 1 8/9 322.560
Total 1,059.840
531.375
Less Previouse -
This IPC 528.465

10-5/4 -9/8 1-7/2 502.031


19-3/8 -9/8 1-7/2 461.391
2-4/1 -9/8 1-7/2 229.500

-4/1 -9/8 1-7/2 -38.250


-4/1 -9/8 -6/1 -108.000
-4/1 -3/4 -9/2 -13.500
-7/1 -9/8 1-7/2 -133.875
2-9/4 -9/8 1-7/2 -207.984
Total 691.313
Less Previouse -
This IPC 691.313

Site Inspector

Page 13 of 14
OUS CLASS ROOM WITH VER. IN GOVT. GIRLS PRIMARY SCHOOL AT CHAK # 93 / TDA
(SR. # 89)

ctor:- MR. RASHID RAFIQUE KHAN


Calculation Sheet

IPC # 1
Length Width Depth
Quantity Remarks
(ft) (ft) (ft)
(Cft)
New Vision Engineer Consultant

Resident Engineer.
New Vision Engineer Consultant

Page 14 of 14