REF: SB012/BLDK3D2/HYGC/WR06

CONSTRUCTION PROGRESS REPORT

PROJECT TITLE : CONSTRUCTION AND COMPLETION OF 1 UNIT OF WATCH TOWER AT K3D2, SIBU
CLIENT : BINTULU LUMBER DEVELOPMENT SDN BHD
CONTRACTOR : HY GENERAL CONTRACTOR
CONTRACT PERIOD : 16.02.2017 - 15.07.2017

WEEKLY REPORT
% Complete
NO SCOPE OF WORKS
Last Week 27/03-31/03/17
1 PILING 100% 100%
2 PILE CAP/FOOTING 100% 100%
3 GROUND BEAM 100% 100%
4 GROUND SLAB 100% 100%
5 FENCING + GATE 0% 0%
6 TRUSSES/BRACING 40% 65%
7 LADDER 0% 0%
8 ROOFING WORK 0% 0%
9 BOLT & NUT/PAINTING/WELDING WORK 15% 55%
10 LIGHTNING ARRESTER 0% 0%
OVERALL COMPLETION 45.5% 52.0%

PREPARED BY,

(WILLIAM TING)
PROJECT ENGINEER, KTS PD3 SIBU

Page 1 of 3
REF: SB012/BLDK3D2/HYGC/WR06

Site Photo

Trusses braced with bolt and nut. Trusses preparation.

Trusses braced with bolt and nut. Welding in progress.

Trusses braced with bolt and nut. Bolt and nut connection.

Page 2 of 3
REF: SB012/BLDK3D2/HYGC/WR06

Site Diary
1. Mr. Ling concerned about the welding issue whether the length for the welding is
sufficient for the load capacity.

2. The area of weld between the purlins is very little.

3. Some welding are rusting.

4. Neither lightning arrester nor the fencing can be seen on site.

5. Further discussion with contractor on the solution to fix the problems.