SimulatedExam#1|MP

Navigation

LessonPSM.SimulatedExam#1
Thereare80questionsinthisexamnormalmultiplechoicequestions,multipleanswerquestions,
andtrue/falseones.
Youhave60minutestocompleteyourexam,andthepassingscoreis85%.

Youcannavigatethroughthequestionswheneveryouwant.Theunansweredquestionsaremarked
inthenavigationsystem.Youcanclickonthereviewquestionbuttontoflagitforlaterreview.

Whenyouredoneansweringthequestions,clickontheQuizSummarybutton,thenonFinish
Quiz.Youwillseeyourscore,andyoucanclickontheViewQuestionsbuttontoreceivefeedback
forallquestions.

ImportantNote:Unfortunately,withthecurrentexamsystemwereusing,youlllosethefeedback
foreverifyoudontfollowtheaboveinstructions.So,pleasebeverycareful.

Ifyouhaveaproblemwithaquestion,youcanaskhelpfromnader@mplaza.pm.Questionsare
usuallyansweredin3days.MakesureyoumentionthefivedigitQuestionCodeinyouremailthe
codesareshownwhenyoufinishtheexamandreceivedthefeedback.

Goodluck!

Results
56of80questionsansweredcorrectly

Yourtime:00:42:13

Youhavereached56of80points,(70%)

Average 76.51%
score

Yourscore 70%

https://mplaza.pm/lesson/psmsimulatedexam1/ 1/37
5/10/2017 PSM.SimulatedExam#1|MP

Restartquiz Viewquestions

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51

52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68

69 70 71 72 73 74 75 76 77 78 79 80

Answered Review

1.Question

WhenshouldIncrementsbeshipped?

Whenitmakessense

AftereachSprint

WhentheIncrementisfreeofdefects

WhentheIncrementisshippable

Incorrect
QuestionCode:01048
AllIncrementsshouldbepotentiallyreleasable(shippable),butwedonthavetoreleaseallof
them.Itdependsontheprojectenvironmentandthecustomer,andtheProductOwneris
supposedtomakethedecision.

2.Question

WhichofthefollowingisthebestwayaScrumMastercanincreasetheteamproductivity?

OrderingtheProductBacklogitemsproperly

PreventingchangestotheSprintBacklogoncetheSprintbegins

Assigningtaskstodevelopersandfollowinguponthem

Facilitatingmeetingsandremovingimpediments

Correct
QuestionCode:01041

https://mplaza.pm/lesson/psmsimulatedexam1/ 2/37
5/10/2017 PSM.SimulatedExam#1|MP

Facilitation(asrequestedorneeded),removingimpedimentsandsolvingproblems,training,
coaching,consulting,andconvincingpeopletodotherightthingarethethingsweexpectfromthe
ScrumMaster.S/heisnotsupposedtoblocktheteamsselforganizationbygivingdevelopers
orders,ordecidingforthem,ands/heisnotsupposedtodootherpeoplesjobs(e.g.orderingthe
itemsinsteadoflettingtheProductOwnerdoso).

3.Question

Howshouldmultipleteamsbecomposedforasingleproject?

TheProductOwnerdecidesonhowtoformtheteams

Developersthemselveswilldecideonhowtoformtheteams

Managementwillformtheteams

Everyonetogetherwilldecideonhowtoformtheteams

Incorrect
QuestionCode:01050
Developersshouldbeselforganizedanditstheirresponsibilitytoformtheteams.

Besidestheinitialformation,thedevelopersmightalsodecidetoshiftamongteamsatthe
beginningofeachSprint.

Note:Scrum.orghasrecentlypublishedtheNexusGuide,whichisaframeworkforscaledScrum.
However,thequestionsintherealPSMIexamarenotadjustedyet,andsomeanswersmightnot
be100%compatiblewiththeNexusGuide.Fornow,youneedtoanswerthequestionsinyour
realexamthewaytheyareexplainedhere.

4.Question

TheSprintReviewis:

AnopportunityforimprovingtheScrumprocesses

Anopportunityforreviewingtheviabilityoftheproject

Anopportunityforinspectionandadaptation

Anopportunityforreceivingapprovalfortheworkdone

Correct
QuestionCode:01061
AllfoureventsinsidetheSprintareopportunitiesforinspectionandadaptation:SprintPlanning,
DailyScrums,SprintReview,SprintRetrospective.

https://mplaza.pm/lesson/psmsimulatedexam1/ 3/37
5/10/2017 PSM.SimulatedExam#1|MP

DuringtheSprintReview,theDevelopmentTeamdemonstratestheIncrementandtheProduct
Ownerpresentstheperformanceinformation.

5.Question

WhenshouldtheSprintRetrospectivebeheld?

Whenneeded,basedonlessonslearned

WhenaskedbytheScrumMaster

WhenaskedbytheProductOwner

EachSprint

Correct
QuestionCode:01054
AlleventsarenecessaryandareheldeverySprintincludingtheSprintRetrospective,whichis
thelasteventinsideeachSprint.

6.Question

WhichofthefollowingbestdescribesScrum?

Aframeworkforthedevelopmentofcomplexproducts

Apracticalprojectmanagementmethodology

Apracticalandmodernprojectmanagementstandard

Amethodologyforsoftwaredevelopment

Correct
QuestionCode:01019
Scrumisadaptiveinsteadofpredictive.Itsaframeworkratherthanamethodologyorbodyof
knowledge.Itsmainlyaboutprojectdeliveryratherthanprojectmanagement.Itsempirical(based
onexperience)ratherthantheoretical.Itssuitableforthedevelopmentofcomplexproductsin
complexenvironments.

7.Question

WhenshouldaSprintGoalbecreated?

InthepreviousSprintRetrospective

Inthebeginningoftheproject
https://mplaza.pm/lesson/psmsimulatedexam1/ 4/37
5/10/2017 PSM.SimulatedExam#1|MP

IntheSprintPlanningmeeting

AnytimeduringtheSprint

Itsnotmandatory

Correct
QuestionCode:01003
TheSprintGoaliscreatedduringtheSprintPlanningmeetingbythewholeScrumTeam.

8.Question

ItemsintheProductBacklogareusuallylargerthanitemsintheSprintBacklogs.

False

True

Correct
QuestionCode:01044
Thisishowitworks:

a.ItemsofdifferentsizesareaddedtotheProductBacklog.
b.Itemsaresortedbasedontheirbusinessvalue.
c.ThenwechecktheitemsonthetopoftheProductBacklog,andiftheyarelarge,wellbreak
themdownintosmalleritems.WeleavethelargeitemsonthebottomoftheProductBacklog
astheyarefornow.
d.Thebusinessvalueswillbeestimatedagain,andtheProductBacklogsortedbasedonthem.
Basedonthisexplanation,theitemsonthetopoftheProductBacklogwouldbe,statistically
speaking,smallerthantheaverage.SincetheitemsintheSprintBacklogcomefromthetopofthe
ProductBacklog,wecansaythattheitemsintheSprintBacklogareusuallysmallerthanthe
averageitemintheProductBacklog.

RememberthatwesorttheProductBacklogitemsbasedonlyontheirbusinessvalue.The
differenceinsizehappensnaturally,andisnotabasisforsorting.

9.Question

Scrumdoesnothavearolecalledprojectmanager.

True

False

Correct
https://mplaza.pm/lesson/psmsimulatedexam1/ 5/37
5/10/2017 PSM.SimulatedExam#1|MP

QuestionCode:01012
Scrumdoesnthaveaprojectmanagerrole.Theprojectmanagementactivitiesaredistributed
amongthethreeScrumroles.

10.Question

EachSprintBacklogitemisownedbyone,orapairofdevelopers.

False

True

Correct
QuestionCode:01039
TheDeveloperssharetheownershipoftheitemsandtasksintheSprintBacklog.
TasksareassignedtotheDevelopers(bythemselves),buttheyallstayaccountable(ownthe
task).
ItemsarenotassignedtoDevelopers,aseachitemconsistsofmultipletasksthatneedvarying
expertise.

Tosummarize:

1.Itemsarenotownedbyindividualsorpairs
2.Itemsarenotassignedtoindividualsorpairs
3.Tasksarenotownedbyindividualsorpairs
4.Tasksareindeedassignedtoindividualsorpairs

11.Question

WhichtwoofthefollowingaretrueabouttheScrumMasterrole?

Assignstaskstothedevelopers

HelpsthoseoutsidetheteaminteractwiththeScrumTeam

Itsamanagementposition

IdentifieswhathasbeendonepriortotheSprintReviewmeeting

Isresponsibleforupdatingtheburndownchart

Incorrect
QuestionCode:01074
TheScrumMasterdoesnotmanagepeople,but,managestheprocess.Thatswhyitsconsidered
amanagementrolebyScrum.org.
Therolecanbeparttime.
https://mplaza.pm/lesson/psmsimulatedexam1/ 6/37
5/10/2017 PSM.SimulatedExam#1|MP

TheDevelopmentTeamisselforganizeditstheresponsibilityofthedeveloperstohandlethe
assignmentsandmeasurestheperformanceoftheSprints.
ItistheProductOwnersresponsibilitytoidentifywhathasbeendonebeforetheSprintReview.

12.Question

WhichstatementbestdescribestheSprintBacklog?

ItstheDevelopmentTeamsplanfortheSprint

Eachofitsitemsisassignedtoateammember

Eachofitsitemshasbeenestimatedinhours

ItscomposedbytheProductOwner

Correct
QuestionCode:01029
TheSprintBacklogiscreatedduringtheSprintPlanning.Itincludestheitemsselectedfromthe
ProductBacklog(bytheDevelopmentTeam),andthetaskscreatedbydecomposingtheitems
(bytheDevelopmentTeam).TheDevelopmentTeamkeepsaddingtasksduringtheSprint,so,the
SprintBacklogupdates.ItstheDevelopmentTeamsplanforthecurrentSprint.Thisplanisnot
detailedupfront.
IftheDevelopmentTeamcannotdeliversomeoftheitems,theywillgobacktotheProduct
BacklogattheendoftheSprint,andtheywillbeorderedagaintheydonotgotothenextSprint
automatically.
Eachtaskisassignedtoonedeveloperorapairofdevelopers,buttheownershipisstillshared.
Itemsarenotassignedorownedbyspecificdevelopersallofthemshareaccountability.

13.Question

WhichofthefollowingbestdescribestheProductBacklog?

Itgrowsandchangeasmoreislearnedabouttheproject

Itprovidesinformationrequiredforthedesignphaseoftheproject

Itsabaselineforthechangemanagementprocess

Itcontainsallthetasksrequiredfortheproject

Incorrect
QuestionCode:01032
TheProductBacklogisatypeofplanning.However,wedontcreatepredictive,detailedupfront
plansinAgileenvironments:theProductBacklogisdynamicandnevercomplete.Itprovidesonly
enoughinformationforaselforganizedteamtofinditsownway.Itsalwayschangingtoenable
https://mplaza.pm/lesson/psmsimulatedexam1/ 7/37
5/10/2017 PSM.SimulatedExam#1|MP

adaptation.
TherearenotasksintheProductBacklogtheybelongtotheSprintBacklogs.

14.Question

WhichisNOTaDevelopmentTeamresponsibility?

OptimizingtheworkrequiredforSprintBacklogitems

Resolvinginternalteamconflicts

MeasuringtheperformanceoftheSprint

SelectingtheProductOwner

Correct
QuestionCode:01051
ItstheDevelopmentTeamsresponsibilitytomeasuretheirproductivityandperformanceduring
theSprint,findtheirway,plan,andoptimizetheworkrequiredforitemsandtheSprintGoal,andto
resolvetheirownconflicts.Rememberthattheyareselforganized.

15.Question

WhocanreplaceSprintBacklogitemsduringtheSprint?

Noone

TheProductOwner

TheDevelopmentTeam

TheScrumMaster

TheScrumTeam

TheProductOwnerandtheDevelopmentTeamtogether

Incorrect
QuestionCode:01068
RememberthattherearetwoelementsintheSprintBacklog:

1.ItemsselectedfromtheProductBacklog:wedontchangethemaftertheSprintPlanning.
2.Taskscreatedbybreakingdowntheitems:theyarealwayschanging.Tasksarereferredto
asworkinthePSMIexamandScrumGuide.

Thetasks(akaworkdefinedintheSprintBacklog)arechangingallthetime.However,theScrum
GuideisnotclearabouttheitemsintheSprintBacklog.JeffSutherlandbelievestheyshouldnt

https://mplaza.pm/lesson/psmsimulatedexam1/ 8/37
5/10/2017 PSM.SimulatedExam#1|MP

change,andoldwritingsfromKenSchwabersaythattheitemsarefrozenaftertheSprint
Planning.Theonlyexceptionisthatwhenyouredonewithallitems,youwillpickthenextitem
fromthetopoftheProductBacklog.

16.Question

WhatshouldtheProductOwnerdoduringtheSprintzero?

TheresnosuchthingasSprintzero

PreparetheProductBacklogforthenextfewSprints

PreparetheProductBacklogforthewholeproject

Communicatewiththecustomerandunderstandtherequirements

Correct
QuestionCode:01043
TheresnosuchthingasSprintzero.ThefirstSprintiscalledSprint1,anditsexactlythesameas
otherSprints:createsanIncrement.Theinfrastructureandtoolsandrequirementsareprepared
graduallythroughouttheproject.

17.Question

WhenisaSprintcanceled?

WhentheDevelopmentTeamfindsitnecessary

WhentheProductOwnerdeterminesitmakesnosensetofinishit

WhentheScrumMasterdecidesto

Whentheinfrastructureandtoolsarenotreadyforthewholeproject

Correct
QuestionCode:01063
OnlytheProductOwnerhastheauthoritytocancelaSprint.ItisdonewhentheSprintdoesnt
makesenseanymoreortheSprintGoalhasbecomeobsolete.

18.Question

WhathappensiftheDevelopmentTeamcannotcompleteitsworkbytheendoftheSprint?

Nothing

TheDevelopmentTeamwillcontinuetothenextSprintwithoutaSprintReview
https://mplaza.pm/lesson/psmsimulatedexam1/ 9/37
5/10/2017 PSM.SimulatedExam#1|MP

TheSprintwillbecanceled

TheSprintwillbeextended

Incorrect
QuestionCode:01024
Nothinghappens!TheDevelopmentTeamwilldeliveronlytheitemsthatare100%donebasedon
theDefinitionofDone.
TheonlythingstheDevelopmentTeammaydo,isinformtheProductOwner,sothats/hecan
revisetheorderofitemsifnecessaryandworkwithher/himtoreviewandadjustthework
(workherereferstothetasks,nottheitems).

19.Question

WhomustdoalltheworkrequiredforProductBacklogitems,tomakesuretheyarepotentially
releasable?

TheDevelopmentTeam

TheScrumMaster

TheScrumTeam

TheProductOwner

Incorrect
QuestionCode:01045
TheDevelopmentTeamiscrossfunctionalanddoestheAtoZofeachProductBacklogitem.
Theydontneedanyexternalhelp.
TheworkoftheProductOwnerandtheScrumMasteraredifferentandtheydonotdoanything
directlyontheitems.

20.Question

TheDefinitionofDoneisusedto(Choosetwoanswers).

Createasharedunderstandingofwhathastobedoneforeachitem

DescribethepurposeofeachSprint

Increasetransparency

DescribetheworkthatshouldbedoneduringtheSprint

Incorrect
QuestionCode:01057

https://mplaza.pm/lesson/psmsimulatedexam1/ 10/37
5/10/2017 PSM.SimulatedExam#1|MP

TheDefinitionofDoneexplainseverythingweshoulddoforallProductBacklogitems,so
everyonewillhavethesameunderstandingwhentheDevelopmentTeamsayssomethingisdone
(transparency).Italsohelpstheteambetterunderstandwhatisexpectedfromthemforeachitem,
andthereforeitiseasierforthemtoplantheSprint.
TheworkthatshouldbedoneuntiltheendoftheSprinttohaveallitemsdevelopeddependsboth
ontheDefinitionofDone,andthedefinitionofitemsthathavebeenselectedfromtheProduct
Backlog.
Thepurpose/objectiveofeachSprintisdescribedinitsSprintGoal.

21.Question

WhichofthefollowingcanbedeliveredastheoutputofaSprint?

AsetoftestsdesignedtobeusedinthenextSprint

Adocumentthatshowsthesolutiondesignandhelpstheteamdeveloptheproduct

AnIncrementofDonesoftware

Auserinterfacelayoutdesignedtobeusedforthesolution

Correct
QuestionCode:01033
AllSprintsaredonetocreateIncrements:apieceofworkingsoftwarewhichispotentially
shippableandDone,basedontheDefinitionofDone(includingallthetests).Allitemswedeliver
arenontechnicalandindependentofeachother.

22.Question

AllIncrementsshouldbepotentiallyreleasable.

False

True

Incorrect
QuestionCode:01052
AllIncrementsmustbecompletebasedontheDefinitionofDone,andbepotentially
releasable/shippable.However,wedonthavetoactuallyreleaseallofthem.ItsuptotheProduct
Ownertodecideonthereleasesbasedontheprojectenvironment.

23.Question

Whatsthemainresponsibilityoftesters?

https://mplaza.pm/lesson/psmsimulatedexam1/ 11/37
5/10/2017 PSM.SimulatedExam#1|MP

TheresnotesterroleinScrum

Theyproactivelyverifytheprogrammersoutput

Theyhelptheteamincorporatethetestdrivendevelopmentpractice

Theyverifytheprogrammersoutput

Theyfindbugs

Correct
QuestionCode:01055
ThereareonlythreerolesinScrum:ProductOwner,ScrumMaster,andDevelopmentTeam.Its
notallowedtodefinenewrolesandtheDevelopmentTeammembersshouldnothaveanytitles
theyarealljustdevelopers.Itisso,becausewewantallofthemtobeaccountablefor
everythingandtocollaboratewitheachother.
Eachpersonhashis/herownareaofexpertise,suchastesting,andthatpersonwillbemore
focusedontestingtasks,butitdoesntmeanthatwecancallthepersontestertheyarejust
developerswhoareexpertsintesting.

24.Question

WhichtwoofthefollowingarenotdoneduringthefirstSprint?

Prepareacompleteinfrastructureandsetoftoolsfortheproject

PlanasmallimprovementforthenextSprint

Deliverapieceofworkingsoftware

Developaplanforthewholeproject

Correct
QuestionCode:01037
TheresnodifferencebetweenthefirstSprintandtherestofthemwecreateanIncrementof
workingsoftware,getfeedbackfromthecustomer(SprintReview),andplanforimprovements
forthenextSprint(SprintRetrospective).

25.Question

WhatshouldbedonebetweenaSprintRetrospectiveandthenextSprintPlanning?

Nothingtheresnotimebetweenthetwo.

Refactorthedevelopeditems

ReleasetheIncrement

https://mplaza.pm/lesson/psmsimulatedexam1/ 12/37
5/10/2017 PSM.SimulatedExam#1|MP

PreparefortheSprintPlanning

Correct
QuestionCode:01009
TheresnotimebetweenoneSprintandthenext.
OrderingtheProductBacklogitemsandestimatingtheamountofworkofnewitemsneededfor
thenextSprintPlanningisdoneduringthepreviousone,inacontinuousprocesscalledProduct
Backlogrefinement(orProductBackloggrooming).

26.Question

WhatarethebenefitsofhavingtestsintheDefinitionofDone?(Choose3answers)

Incrementswillbemorecomplete

Reportingtotheprojectmanagerwillbeeasier

TherewillbeincreasedtransparencyoftheIncrements

Incrementswillbeclosertobeingpotentiallyshippable

Correct
QuestionCode:01008
ItemsarenotreallyDone,unlesswehavetestedthemso,testsshouldbeincludedinthe
DefinitionofDone.Inthiscase,theIncrementswillbeclosertowhatwecanpracticallycall
complete,done,potentiallyreleasable,orpotentiallyshippabletosomethingusableforthe
users.
Incrementsshouldbepotentiallyreleasableforstarters,becauseitmakesiteasierforthe
customertotryitandgiveususefulfeedback.Thefeedbackenablesadaptation,whichis
essentialtoAgile.
HavinganeffectiveDefinitionofDoneincreasestransparency,becauseeveryonewillknowwhat
wemeanwhenwesayanitemisDone.

Reportingtotheprojectmanager?WedonthaveaprojectmanagerinScrum.

27.Question

Whenmultipleteamsareworkingonthesameproject,howmanyDefinitionsofDoneshouldthey
use?

Therecanbemultipledefinitions,aslongastheyarecapableofcreatingapotentially
releasableIncrement

EachteamdefinesitsownDefinitionofDoneindependentlyofothers

https://mplaza.pm/lesson/psmsimulatedexam1/ 13/37
5/10/2017 PSM.SimulatedExam#1|MP

Therecanbemultipledefinitions,aslongastheyarewellcommunicatedandunderstood
amongteamsandwiththecustomer

ThereshouldbeonlyoneDefinitionofDoneforallteams

Incorrect
QuestionCode:01049
Theteamsmightbeworkingondifferentpartsoftheproduct(e.g.desktopapplication,mobile
application,webapplication)orsimplyhavedifferentstylesofwork,andthereforerequiredifferent
DefinitionsofDone.Thisisallright,aslongastheirdefinitionsarecompatibleandhavethe
capacitytocreateanintegratedpotentiallyreleasableIncrementsforthewholeproject.The
definitionsshouldalsocontainalltheminimumrequirementscomingfromtheorganization.
Note:whenmultipleteamsareworkingonthesameproject,alltheiroutputswillbecombinedinto
oneintegratedIncrement.TheyalsohaveonlyoneProductBacklogandoneProductOwner.

28.Question

WhoestimatestheworkduringtheSprint?

TheScrumMaster

TheDevelopmentTeam

TheProductOwner

TheDevelopmentTeamandtheProductOwnertogether

ThewholeScrumTeam

Correct
QuestionCode:01038
AllestimatesaredonebytheDevelopmentTeam,sincetheyaretheoneswhoknowhowtodo
thework.

29.Question

HowisaProductBacklogordered?

Basedonthevalueoftheitems

Basedonthesizeoftheitems

Basedonthecriticalityoftheitems

Basedondependenciesamongtheitems

Basedontheamountofriskrelatedtoeachitem

https://mplaza.pm/lesson/psmsimulatedexam1/ 14/37
5/10/2017 PSM.SimulatedExam#1|MP

Correct
QuestionCode:01034
TheProductBacklogisorderedbasedonthevalueoftheitemstothebusiness,anditisuptothe
ProductOwnertodeterminehowtocalculatethevalue.
Size,criticality,andriskallaffectthevalue,butarenotdirectlythebasisforordering.
Itemsshouldbeindependentofeachother,sothatwecanfreelyorderthembasedonthevalue.

30.Question

Whatstheverticalaxisinatypicalburndownchart?

Thetechnicaldebt

Theprogress

Theamountofremainingwork

Thecapacityoftheteam

Correct
QuestionCode:01065
Thehorizontalaxisistime,theverticalaxisistheremainingamountofwork,andthetrendline
showstheforecastfinishdateiftheProductBacklogandtheteamcapacitystaythesame.

31.Question

Which3ofthefollowingareScrumMasterresponsibilitiesduringtheSprint?

Solveproblems

EnsuretheDevelopmentTeamstaysselforganized

ApprovetheIncrement

Facilitatemeetingsasrequestedorneeded

Assigntaskstoteammembers

Correct
QuestionCode:01025
TheScrumMasterensuresthatScrumisunderstoodandenactedentirely,removesimpediments
(solvesproblems),andfacilitatesthemeetingsasrequestedorneeded.
AssignmentsaredonebytheDevelopersthemselves.
NooneofficiallyapprovestheIncrement.TheProductOwnerjustcheckstheitemstoknow
whatisDonebeforetheSprintReviewmeeting.

https://mplaza.pm/lesson/psmsimulatedexam1/ 15/37
5/10/2017 PSM.SimulatedExam#1|MP

32.Question

WhichofthefollowingisarightactionfromtheScrumMasterinresponsetoaProductOwnerwho
hasproblemsmanagingtheProductBacklog?

AsktheDevelopmentTeamtohelptheProductOwnerunderstandthedependenciesamong
itemstobeusedinorderingthem

HelptheProductOwnerordertheitems

AskthecustomertoordertheitemsinsteadoftheProductOwner

ExtendtheSprint,sothattheProductOwnerhasmoretimeorderingitems

Correct
QuestionCode:01036
TheScrumMasterissupposedtoknowthetoolsandtechniques,andtohelpeveryoneinthat
regard.However,itsonlyabouthelping,training,coaching,andconsulting,ratherthantakingover.
Rememberthatwerenotsupposedtohavedependencies(atleastnotmanydependencies)
amongitemsso,dependenciesarenotabasisfororderingthebacklog.Theonlybasisisthe
businessvalue.

33.Question

HowmuchoftheSprintBacklogshouldbedefinedduringtheSprintPlanningmeeting?

Justenoughtounderstandthedesignandarchitecture.

JustenoughfortheDevelopmentTeamtobeabletoforecastwhatitcando,andstart
thefirstseveraldaysoftheSprint.

JustenoughfortheScrumMastertobeabletoassigntaskstodevelopers

Allofthepotentialwork.

Incorrect
QuestionCode:01079
TherearetwoelementsintheSprintBacklog:

1.TheitemsselectedfromtheProductBacklog:wedontchangethemaftertheSprintPlanning
2.Thetaskscreatedbybreakingdowntheitems:onlyafewofthemarecreatedintheSprint
Planning,andtherestwillbecreatedduringtheSprint.Otherwise,itwouldbeaformof
upfrontplanning.TasksarereferredtoasworkorplaninthePSMIexam.

34.Question

ThecustomerhasthefinalsayontheorderofProductBacklogitems.
https://mplaza.pm/lesson/psmsimulatedexam1/ 16/37
5/10/2017 PSM.SimulatedExam#1|MP

True

False

Correct
QuestionCode:01027
Thedecisionontheorderofitemscanbeinfluencedbyacommittee,thecustomer,oranyother
stakeholder,butthefinalsaybelongstotheProductOwner.Thisdecisionshouldberespectedby
thewholeorganization.

35.Question

Which3ofthefollowingareresponsibilitiesofaselforganizingteam?

PullProductBacklogitemsfortheupcomingSprint

EstimatetheamountofworkofnewlycreatedProductBacklogitems

ReordertheProductBacklog

Reportprogresstostakeholders

CreatenewProductBacklogitems

CreatetasksforSprintBacklogitems

Correct
QuestionCode:01002
ItstheresponsibilityoftheDevelopmentTeamtoestimatetheamountofworkofProductBacklog
items,andtoselectanappropriatenumberofthemforeachSprint.Theyalsobreakdownthe
itemsintotasksduringtheSprint.
MeasuringtheprojectperformanceistheresponsibilityoftheProductOwner,whilemeasuringthe
SprintperformanceisdonebytheDevelopmentTeam.
CreatingnewProductBacklogitems,orderingthem(prioritization),andmakingsureeveryonehas
aclearunderstandingofthemistheresponsibilityoftheProductOwner.

36.Question

Whoshouldknowthemostabouttheprojectperformance?

TheDevelopmentTeam

TheScrumMaster

TheProductOwner

TheProjectManager
https://mplaza.pm/lesson/psmsimulatedexam1/ 17/37
5/10/2017 PSM.SimulatedExam#1|MP

TheScrumTeam

Correct
QuestionCode:01064
MeasuringthereleaseorprojectperformanceistheProductOwnersresponsibility.Measuringthe
SprintperformanceistheDevelopmentTeamsresponsibility.

37.Question

WhendoestheDevelopmentTeampreparethetoolsandinfrastructureforthedevelopment?

Throughouttheproject

IntheSprintzero

BeforethefirstSprint

Correct
QuestionCode:01031
Wedonotpreparetheinfrastructureandtoolsupfront,becauseitrequiresanunderstandingofthe
wholeproduct,whichisagainsttheadaptationconcept.Therequiredinfrastructureandtools
dependontheproductweregoingtocreate,whichinturnisdefinedthroughouttheproject.So,
theinfrastructureandtoolswillbepreparedgraduallythroughouttheproject.
TheresnoSprintzeroinScrum.AllSprintsarethesame,usedtocreateanIncrementofworking
software.

38.Question

ItsbettertohavelongerSprintswhentheprojectisriskier.

False

True

Correct
QuestionCode:01042
WhenSprintsareshorter,therearemoreopportunitiesfordemonstration,receivingfeedback,and
adaptation.So,whenrisksarehigher,itsbettertohaveshorterSprints(ifitspossible).
Generally,shorterSprintsarepreferred.

39.Question

WhenmustanewIncrementofworkingsoftwarebeavailable?

https://mplaza.pm/lesson/psmsimulatedexam1/ 18/37
5/10/2017 PSM.SimulatedExam#1|MP

Every3Sprints

AttheendofeachSprint

Whenevertheuseracceptancetestingisdone

WhentheProductOwnerasksforit

Beforeeachplannedrelease

Correct
QuestionCode:01076
AnIncrementofDoneworkingsoftware,whichispotentiallyreleasable,mustbeproducedatthe
endofeachSprint.
RememberthatallSprintsarethesame,andtherearenoSprintZeros,HardeningSprints,
IntegrationSprints,ReleaseSprints,etc.

40.Question

WhichofthefollowingiscommonwhentheScrumTeambecomesmatureenoughduringthe
project?

ThewontneedSprintReviewsanymore

TheywontneedaScrumMasteranymore

TheywillimprovetheDefinitionofDone

TheywontneedSprintRetrospectivesanymore

TheycanreleaseeveryIncrement

Correct
QuestionCode:01014
TheDefinitionofDoneincludesqualitymethodsandthatswhywekeepimprovingitwhenwe
mature.
AllScrumroles,events,andartifactsarenecessaryandshouldnotbeignoredforanyreason.

41.Question

TheProductOwnerdeterminesthenumberofitemsthatshouldbeselectedforeachSprint.

True

False

Correct
https://mplaza.pm/lesson/psmsimulatedexam1/ 19/37
5/10/2017 PSM.SimulatedExam#1|MP

QuestionCode:01066
itistotallyuptotheDevelopmentTeamtodecidehowmanyitemstheyaregoingtoselectforthe
Sprint.

42.Question

HowcansecurityconcernsbeaddressedinScrum?(Choose2answers)

TheycanbeaddedtotheProductBacklog

TheycanbeaddedtotheDefinitionofDone

TheycanbehandledinaseparateSprintdedicatedtosecurity

Theycanbeoutsourcedtoadepartmentresponsibleforsecurity

Correct
QuestionCode:01040
Manyofthesecurityconcernsarenonfunctionalfeatures,andthereforewillbeaddedtothe
DefinitionofDonetobeappliedtoallProductBacklogitems.

Somesecurityconcernsarespecific,andonlyaboutacertainpartoftheproducttheycanbe
itemsintheProductBacklog.

TheDevelopmentTeamiscrossfunctionalandshouldtakecareofeveryaspectoftheproduct,
includingsecurity.So,itwontbehandledbyexternalpeople.

EachSprintshouldbefocusedondevelopingitemswiththehighestvalue,anddeliveringDone
items.Wedontkeepthingssuchassecurity,tests,andintegrationforatimeinthefuture.

43.Question

WhencanaDevelopmentTeamcancelaSprint?

TheSprintdoesntmakesenseanymore

TheycantcancelSprints

Theresanunsolvedtechnicaldependency

Notenoughinformationisavailableforthedevelopment

Correct
QuestionCode:01001
OnlytheProductOwnerhastheauthoritytocancelaSprint.IthappenswhentheProductOwner
realizesthattheSprintdoesntmakesenseanymore,orinotherwords,theSprintGoalhas

https://mplaza.pm/lesson/psmsimulatedexam1/ 20/37
5/10/2017 PSM.SimulatedExam#1|MP

becomeobsolete.E.g.ifthecustomerdoesntneedmostoftheSprintBacklogitemsanymore.
Note:itsOKifweforecastthattheteamcannotdeliversomeoftheSprintBacklogitems(oreven
manyofthem)anditsnotareasonforcancelingaSprint.Wewilljustgoonanddeliverasmany
itemsaspossible.

44.Question

TheScrumMasterhasalotofunresolvedissues.Whichthreeofthefollowingactionscanbetaken
tofacilitateit?

Prioritizetheissuesandworkontheminorder

ConsulttheDevelopmentTeam

Escalatetheissuestotherightperson

Asktheseniormanagementforhelp

Informmanagementoftheimpedimentsandtheirimpact

Correct
QuestionCode:01017
Itsalwaysagoodideatoasktherestoftheteamforhelp(consultation),butweprefernottoget
helpfromoutsidetheteam,becauseitwillweakenourselforganization.

45.Question

WhichofthefollowingisthesubjectofSprintRetrospective?

ProductBacklogorder

Scrumprocess

Technicalapproach

Increment

Correct
QuestionCode:01071
SprintRetrospectivesareonlyabouttheScrumprocessandthewaytheteamworks.The
IncrementisthesubjectofSprintReview.Thetechnicalapproachiscompletelyuptothe
DevelopmentTeamandtheProductBacklogisuptotheProductOwner.

46.Question

https://mplaza.pm/lesson/psmsimulatedexam1/ 21/37
5/10/2017 PSM.SimulatedExam#1|MP

ScrumTeamsshouldnormalizetheirestimations,sothatmanagementcanmeasureandcompare
theirperformance.

False

True

Correct
QuestionCode:01080
Itsalmostimpossibletomaketheestimateunits(e.g.storypoints)comparable,andonlycreates
problemssuchaspadding.Besidesthat,themanagementisnotsupposedtomeasuretheir
performancetheyshouldbefocusedonthevaluesgeneratedbytheproject.

47.Question

Scrumisadetailedsoftwaredevelopmentmethodology.

False

True

Correct
QuestionCode:01056
Scrumisaframeworkratherthanamethodology,anditsnotdetailed.

48.Question

WhatsthetimeboxforacompleteSprintPlanningmeeting?

8hoursforaonemonthSprint

8hoursforatwoweekSprint

6hoursforaonemonthSprint

6hoursforatwoweekSprint

Correct
QuestionCode:01077
TheSprintPlanningistimeboxedfor8hourswhentheSprintisonemonthlong,andshorter
proportionally.

49.Question

WhichdoesaselforganizingDevelopmentTeamchoose?
https://mplaza.pm/lesson/psmsimulatedexam1/ 22/37
5/10/2017 PSM.SimulatedExam#1|MP

ProductBacklogordering

Whentorelease

Sprintlength

Howtobestaccomplishitswork

Correct
QuestionCode:01062
TheProductBacklogorderandcomposition,projectperformancemeasurement,andrelease
planningaretheProductOwnersresponsibilities.TheSprintlengthisdeterminedbythewhole
ScrumTeam.

50.Question

WhodetermineshowworkisperformedduringtheSprint?

Thebusinessanalyst

TheDevelopmentTeam

Thesolutionarchitect

TheProductOwner

TheScrumTeam

Correct
QuestionCode:01078
ItiscompletelyuptotheselforganizedDevelopmentTeamtodecideonthewaytheyworkandon
thetechnicalaspectsoftheproject.

51.Question

HowmanyhoursperdayshouldaDevelopmentTeammemberwork?

Atasustainablepace

AsmuchasneededforrealizingtheSprintBacklogitemsuntiltheendoftheSprint

Between6and16hours,dependingonthesituation

Atleast6idealmanhours

Correct
QuestionCode:01047

https://mplaza.pm/lesson/psmsimulatedexam1/ 23/37
5/10/2017 PSM.SimulatedExam#1|MP

WorkingatasustainablepaceisoneoftheAgileprinciples.Thishelpsincreaseproductivityand
quality.

52.Question

Which2ofthefollowingaretrueabouttheProductOwner?

IsaccountableforprioritizingtheProductBacklogitems

Canbeinfluencedbyacommittee

Therolecanbeplayedbyacommittee

Shouldbededicatedtooneproject

Incorrect
QuestionCode:01023
TheProductOwnercreatesandorderstheProductBacklogitemsandmakessurethateveryone
understandsthem.Estimatingtheitemsandbreakingthemdownintotasksaredonebythe
DevelopmentTeam.
Therecanbeacommitteefortheproductownership,butonlytheirrepresentativewillbecalledthe
ProductOwner.So,theresonlyoneProductOwner,evenwhentherearemultipleteams.This
personcanbefulltimeorparttime.OnepersoncanhavemorethanoneroleinScrum(e.g.both
theProductOwnerandtheScrumMaster).Whileitsnotforbidden,itsnotrecommendedeither.

53.Question

WhosrequiredtoattendtheDailyScrum?

TheDevelopmentTeammembersandtheProductOwner

TheDevelopmentTeammembersandtheScrumMaster

TheDevelopmentTeammembers

ThewholeScrumTeam

Correct
QuestionCode:01021
Anyonecanattendanymeeting,butnotethatthequestionsisaskingwhosrequiredtodoso.
DailyScrumisonlyfortheDevelopmentTeam,sonooneelseisrequiredtoattend,andifthey
do,theyarenotsupposedtoparticipatetheyjustlistenandwatch.

54.Question

https://mplaza.pm/lesson/psmsimulatedexam1/ 24/37
5/10/2017 PSM.SimulatedExam#1|MP

Adeveloperdoesnotworkproperlyandisblockingtheteamactivity.Whoshoulddecideon
removingthatperson?

TheProductOwner

TheDevelopmentTeam

Theresourcemanager

TheScrumMaster

Incorrect
QuestionCode:01035
ThisistheresponsibilityoftheDevelopmentTeam,becauseitsselforganized.Sinceitssome
kindofimpediment,theymayalsogethelpfromtheScrumMaster.

55.Question

ItemsatthebottomoftheProductBacklogareusuallylargerthanthoseonthetop.

True

False

Incorrect
QuestionCode:01075
Thisishowitworks:

a.ItemsareaddedtotheProductBacklog.Theyhavedifferentsizes.
b.Theyareorderedbasedontheirbusinessvalue.
c.IfalargeitemislocatedonthetopoftheProductBacklog,itisbrokendownintosmaller
ones.Wedontdoitwiththoseonthebottom.
Thatswhy,onaverage,weexpecttohavelargeritemsonthebottomoftheProductBacklog.

56.Question

ThereshouldbeahardeningSprinteveryfewSprints,toresolvedependenciesandfixopenbugs.

True

False

Correct
QuestionCode:01070

https://mplaza.pm/lesson/psmsimulatedexam1/ 25/37
5/10/2017 PSM.SimulatedExam#1|MP

TheresonlyonetypeofSprint,anditsgoalistocreateapotentiallyreleasableIncrementof
featuresthatbringvaluetothecustomer.TheresnoSprintzero,hardeningSprint,integration
Sprint,releaseSprint,etc.

57.Question

WhenisaSprintover?

WhenallSprintBacklogtasksaredone

Whenthetimeboxexpires

WhenallSprintBacklogitemsaredone

WhentheProductOwnerconsidersitdone,withanyappropriatereason

Correct
QuestionCode:01053
Sprintsaretimeboxedandtheyarenotextendable.Sometimeboxeshaveamaximumduration
andwillbefinishedearlierifeverythingisdone,butSprinttimeboxeshaveafixedduration,which
doesnotshrinkeither.IfeverythingisfinishedbeforetheendoftheSprint,theDevelopmentTeam
willpickthenextitemfromtheProductBacklogandstartsworkingonthat.

58.Question

WhiletheSprintPlanningisprogressing,theDevelopmentTeamhasrealizedthattheydonthave
enoughresourcestocompletealltheselectedSprintBacklogitems.Whichtwoofthefollowingis
usuallythebestaction?

RemovesomeoftheitemsfromtheSprintBacklog

Hiremoredevelopers

InformtheProductOwnerandstartthedevelopment

Workovertime

Correct
QuestionCode:01018
Wecanfreelyremovesomeoftheitems,becauseitsstillduringtheSprintPlanning(werenot
allowedtodosoaftertheSprintPlanning).
Ifwewantto,wecanjuststarttheSprintwiththehighnumberofitems,becausenothinghappens
ifwedonotdelivereverything,buttheProductOwnershouldknowthesituation.
Weworkataconstantpace(noovertimework).Wedonotliketochangethecompositionofthe
teamoften,becauseweknowthataddingmoredevelopersdoesnotalwaysincreaseproductivity,
andevenwhenitdoes,itwillnothappenintheshortterm.
https://mplaza.pm/lesson/psmsimulatedexam1/ 26/37
5/10/2017 PSM.SimulatedExam#1|MP

59.Question

WhencanthecompositionoftheDevelopmentTeamchange?

Aftereachrelease

Thecompositionoftheteamshouldnotchange

Wheneverneeded

NotduringtheSprints

Incorrect
QuestionCode:01073
Wedontexpectittochangeoften,butifrequired,itshouldntbeduringtheSprint,andweshould
keepinmindthatitcreatesashorttimereductionintheproductivity,becauseeveryonehasto
helpnewteammembersgettoknowtheproject.
Anotherimportantpointisthatincreasingthenumberofdevelopersdoesnotalwaysincrease
productivity.

60.Question

WhichtwoofthefollowingarethebestwaysaScrumMastercanteachteamstohelpthemself
organize?

Maintainandincreasevelocity

CreateareleasableIncrementattheendofeachSprint

Usepairprogramming

Timeboxeventstomanagerisk

Incorrect
QuestionCode:01060
BothtimeboxingandhavingthegoalofcreatingIncrementshelpdevelopersfocusonreal
problems,takeaccountability,andmakerightdecisionsforthedelivery.Bothofthemare
mandatoryinScrum.

Maintainingandincreasingvelocityisimportant,butdoesnthelpwithselforganization.

PairprogrammingisahelpfulAgilepractice,butitisnotmandatory,anditdoesntserveself
organization.

61.Question
https://mplaza.pm/lesson/psmsimulatedexam1/ 27/37
5/10/2017 PSM.SimulatedExam#1|MP

ThepurposeofALLSprintsistoreleaseapieceofworkingsoftware.

True

False

Incorrect
QuestionCode:01016
Didyounotethewordrelease?ThepurposeofallSprintsistocreateanIncrementthatis
done,apieceofworkingsoftwareusablefortheusers,potentiallyreleasable,andpotentially
shippable.However,wedonotnecessarilyreleaseorshipallIncrements.

62.Question

WhichofthefollowingshouldbedoneduringtheSprintReview?(Multipleanswers)

DemonstrationoftheIncrement

Communicationoftheprojectprogress

Revisionofthetechnicalpractices

DiscussionoftheScrumprocess,andhowitwasusedduringtheSprint

Incorrect
QuestionCode:01058
TherearetwomainthingsweshoulddointheSprintReviewmeeting:theDevelopmentTeam
demonstratestheIncrementtothecustomerandtheProductOwnerpresentstheperformance
information(especiallytheforecastofthecompletiondate)tothecustomer.

63.Question

Whichthreeofthefollowingarefeedbackloops?

DailyScrum

SprintRetrospective

SprintReview

ProductBacklogrefinement

Releaseplanning

Correct
QuestionCode:01067

https://mplaza.pm/lesson/psmsimulatedexam1/ 28/37
5/10/2017 PSM.SimulatedExam#1|MP

AllfoureventsinsidetheSprintarefeedbackloopsandopportunitiesforinspectionandadaptation
(butnottheSprintitself).So,anyofthefollowingarerightanswersforquestionslikethis:

1.SprintPlanning
2.DailyScrum
3.SprintReview
4.SprintRetrospective

RememberthatwhileScrum.orgconsidersreleaseplanningnecessary,andaresponsibilityof
theProductOwner,itsnotexplainedintheScrumGuide.

64.Question

Whosresponsibleforengagingthestakeholders?

TheProductOwner

Theprojectmanager

TheScrumMaster

TheDevelopmentTeam

Theteamleader

Correct
QuestionCode:01072
TheProductOwnerisresponsibleforengagingthem,understandingthem,communicatingwith
themandsoon.

65.Question

Acomprehensivebranchingandmergingmodelinsharedversioncontrolreducesthecoordination
problemswhenmultipleteamsareworkingonthesamecode.

False

True

Correct
QuestionCode:01010
Adevelopmentoptionistobranchapieceofcodefromthemainstream,makechanges,and
mergeitbackwhenitworksproperly.Otherscanbranchthesamecodewhileotherbranchesare
developed,anditmightcreateproblemswithmerging.Theremightbesomebenefitsinbranching
andmerging,butitdoesnthelpwithcoordinationandevenmakesitworse,becauseconflictswill
bediscoveredlater.
https://mplaza.pm/lesson/psmsimulatedexam1/ 29/37
5/10/2017 PSM.SimulatedExam#1|MP

Dontpanic!thereareonlyafewquestionslikethisintheexam!

66.Question

WhenisaSprintBacklogitemconsideredcomplete?

Whenallofitstasksarecomplete

WheneverythingisdonebasedontheDefinitionofDone

WhentheSprintisover

Whentheuseracceptancetestsaredone

Correct
QuestionCode:01028
WhentheitemiscompletebasedontheDefinitionofDone(whichmeansthattheenduserscan
useit),anditcreatesanIncrementofworkingsoftwarethatispotentiallyreleasable.
Note:ifallthetasksforanitemarecomplete,itdoesntnecessarilymeanthattheitemiscomplete,
becausewemighthaveforgottentoaddsomeofthetaskstobeginwith.

67.Question

WhichofthefollowingismostessentialtoScrum?

Adaptation

Prediction

Planning

Continuousimprovement

Incorrect
QuestionCode:01022
ScrumisanAgileframework,andAgilityismainlyaboutadaptation(insteadofprediction).

68.Question

ThecustomerwantstheDevelopmentTeamtoaddaveryimportantitemtothecurrentSprint.What
shouldtheydo?

Rejecttherequest

ReferthecustomertotheProductOwner

https://mplaza.pm/lesson/psmsimulatedexam1/ 30/37
5/10/2017 PSM.SimulatedExam#1|MP

AddtheitemtothecurrentSprintBacklog

ReplaceaniteminthecurrentSprintBacklogwiththenewone

AddtheitemtotheProductBacklog

Correct
QuestionCode:01013
OnlytheProductOwnercanaddnewitemstotheProductBacklog.Evens/hecannotaddanew
itemtotheSprintBacklogduringtheSprint.
WhensomeoneasksforachangeintheSprintBacklog,theyshouldbereferredtotheProduct
Owner,sothats/hecanworkwiththemtodefinetheitemandaddittotheProductBacklogforthe
nextSprints.
Infact,werejecttherequestforaddingtheitemtothecurrentSprintBacklog,butthisrejection
shouldbedonebytheProductOwner,ratherthantheDevelopmentTeam.

69.Question

HowisbudgetingdoneinScrum?

Usuallyeveryday

IdeallyrevisedeachSprinttoensurevalueisbeingdelivered

Scrumdoesntneedthetraditionalbudgetingsystem

Budgetingisverysimpleandlimitedtotheruncost(timeandmaterial)

Incorrect
QuestionCode:01020
BudgetingshouldbealignedwiththevaluedeliveredinthepreviousSprints,andthereforeupdated
frequently.Ifitsdoneproperly,wewillknowwhenitsbesttostoptheprojectandstartusingthe
productinoperationinsteadofspendingmoremoneydevelopinglessvaluableProductBacklog
items.

70.Question

WhichofthefollowingarecommonProductOwneractivitiesduringtheSprint?(Choose2answers)

AnswerquestionsfromtheDevelopmentTeamabouttheitemsintheSprintBacklog

Workwiththestakeholders

PrioritizetheDevelopmentTeamstasks

MeasuretheSprintprogress

https://mplaza.pm/lesson/psmsimulatedexam1/ 31/37
5/10/2017 PSM.SimulatedExam#1|MP

RuntheDailyScrums

Correct
QuestionCode:01069
TheProductOwnerkeepscommunicatingwiththestakeholders,createsnewitemsintheProduct
Backlog,revisestheorderofitems,answersquestionsandmakessureeveryonehastheright
understandingofitems,andchecksthecompleteditemswiththeDevelopmentTeamtoensure
theyarecompletebasedontheDefinitionofDone.
Creatingandprioritizingtasks,runningDailyScrums,andmeasuringtheSprintperformanceare
theDevelopmentTeamsresponsibility.

71.Question

WhatdoesitmeanforaDevelopmentTeamtobecrossfunctional?

Theteamshouldcollaboratewithallfunctionalunits

Theteamincludesnotonlyprogrammers,butalsotesters,architects,UIdesigners,etc.

AlltheDevelopmentTeammembersshouldbecrossfunctionalindividuals.

Thedevelopersshouldworkcloselywithbusinessanalysts,architects,andtestersexternalto
theteam.

Incorrect
QuestionCode:01046
Everythingneededtocreateapotentiallyreleasablepieceofsoftware,usablefortheendusers,
shouldbedoneinthecrossfunctionalteam.So,theyneedtohavealltheexpertise.
Eachdeveloperhasoneormoretypesofexpertise,suchasarchitecture,programming,testing,
andUIdesign.Thesumofallmemberscreateacrossfunctionalteamandtheindividualsdonot
needtobecrossfunctional.

72.Question

TheSprintBacklogonlycontainsitemsselectedfromtheProductBacklog.

False

True

Incorrect
QuestionCode:01005
TherearealsotasksintheSprintBacklog.

https://mplaza.pm/lesson/psmsimulatedexam1/ 32/37
5/10/2017 PSM.SimulatedExam#1|MP

TheitemsselectedfromtheProductBacklogarefrozenintheSprintBacklogwedontchange
them.However,wealsohavethetaskscreatedbybreakingdowntheitems,andthetasksare
alwayschanging.OnlytheDeveloperscanmakechangestotheSprintBacklog(thatis,changes
tothetasks,ratherthantheitems).

73.Question

TheScrumMastershouldcanceltheSprintPlanning,iftheSprintGoalisnotcomposedbeforehand.

True

False

Correct
QuestionCode:01015
TheSprintGoaliscomposedbythewholeScrumTeamduringtheSprintPlanning.Besides
that,wedontcanceltheSprintPlanninganyway!TheSprintcanbecanceledonlyinextreme
situations,bythedecisionoftheProductOwner.

74.Question

Nine(9)ScrumTeamsareworkingonasingleproduct.Whichofthefollowingisthebestwayof
planningSprints?

TheProductOwnermeetswithrepresentativesfromeachteamtocomposetheSprintGoal
andselectitemsfromtheProductBacklog.Theneachrepresentativeworkswithhis/herteamto
createtheirSprintBacklog.

EveryonemeetsinthesametimetochecktheProductBacklogandtoreceive
informationfromtheProductOwner.Thentheycoordinatedependencies,shiftteam
membersasneeded,andcreatetheirSprintBacklogs.

TheProductOwnerandallteammembersmeetandcreateoneSprintBacklogfortheproject.
AllteamswillsharethatSprintBacklogforthenextSprint.

Incorrect
QuestionCode:01030
SomepointsyouneedtorememberaboutscaledScrum:

1.TheresonlyoneProductBacklogandoneProductOwnerforaproject/product.Eachteam
needstohaveaseparateSprintBackloghowever.
2.TheDevelopmentTeamisresponsibleforselectingtheitemsfromtheProductBacklog,soit
cannotbedonewithoutthem.Theyshareownership,andthereforehavingoneperson
representingateamisnotagoodoption.

https://mplaza.pm/lesson/psmsimulatedexam1/ 33/37
5/10/2017 PSM.SimulatedExam#1|MP

3.ItsOKtoshiftteammembers(changethecompositionofteams)betweentwoSprints.
4.EventhoughProductBacklogitemsshouldbeindependentofeachother,thedependencies
betweenteamsisacommonprobleminscaledScrumsotheyshouldbecarefulaboutit.

Note:Scrum.orghasrecentlypublishedtheNexusGuide,whichisaframeworkforscaledScrum.
However,therearenodirectquestionsaboutitinthePSMIexamyet.

75.Question

WhichtwoofthefollowingaretrueaboutScrum?

Scrumisaframeworkfordevelopingandmaintainingcomplexproducts

Scrumisamethodologyformanagingcomplexprojects

Scrumisbasedonempiricalprocesscontroltheory

ScrumislikeatraditionalprocessbutwithSprintsandrelatedartifacts

Correct
QuestionCode:01026
Afewrelatedpointstoremember:

1.Scrumisaframework,notamethodologyorbodyofknowledge.
2.Scrumisempirical,ratherthantheoretical.
3.Scrumismoreaboutprojectdeliveryratherthanprojectmanagement.
4.Scrumisadaptive,ratherthanpredictive(itsmorethanjustusingSprintsandrelated
artifacts).
5.Scrumshouldbeusedentirely(wedonottailorit).

76.Question

TheSprintBacklogwouldnotchangeaftertheSprintPlanning.

True

False

Correct
QuestionCode:01011
TheSprintBacklogiscreatedintheSprintPlanningmeeting,andupdatedduringtheSprint.

TheitemsselectedfromtheProductBacklogarefrozenintheSprintBacklogwedontchange
them.However,wealsohavethetaskscreatedbybreakingdowntheitems,andthetasksare
alwayschanging.OnlytheDeveloperscanmakechangestotheSprintBacklog(thatis,changes
tothetasks,ratherthantheitems).
https://mplaza.pm/lesson/psmsimulatedexam1/ 34/37
5/10/2017 PSM.SimulatedExam#1|MP

77.Question

TheDevelopmentTeamhasrealizedthattheyhaveovercommittedthemselvesfortheSprint.Who
shouldbepresentwhentheyreviewandadjustthework?

OnlytheDevelopmentTeam

TheProductOwnerandtheDevelopmentTeam

ThewholeScrumTeam

OnlytheProductOwner

ThewholeScrumTeamandotherkeystakeholders

Correct
QuestionCode:01006
Whenwerealizethatwehaveovercommittedourselvesandwearenotabletodelivermanyof
theSpringBacklogitems,weshouldstillkeepworkingandwewontaddorremoveitems.
However,theorderoftheitemswillbemoreimportantnow,sincewewontbeabletodeliveritems
atthebottomoftheSprintBacklog.Forthisreason,theDevelopmentTeamwillcalltheProduct
Ownertocheckandseeifs/heneedstoadjusttheorderofSprintBacklogitems.Besidesthat,
therearedifferentwaysofdeliveringeachitem,whichisdefinedbythetasks,andtheProduct
OwnerandDeveloperscanrefineandadjustthosetasks(worktobedone).

78.Question

WhoaddsnewworktotheSprintBacklogduringtheSprint?

TheDevelopmentTeam

TheScrumMaster

TheProductOwner

ThewholeScrumTeamtogether

TheProductOwnerandtheDevelopmentTeamtogether

Correct
QuestionCode:01007
TheitemsselectedfromtheProductBacklogarefrozenintheSprintBacklogwedontchange
them.However,wealsohavethetaskscreatedbybreakingdowntheitems,andthetasksare
alwayschanging.OnlytheDeveloperscanmakechangestotheSprintBacklog(thatis,changes
tothetasks,ratherthantheitems).
OnlytasksrequiredforthefirstfewdaysoftheSprintarecreatedintheSprintPlanningmeeting
https://mplaza.pm/lesson/psmsimulatedexam1/ 35/37
5/10/2017 PSM.SimulatedExam#1|MP

therestwillbecreatedduringtheSprint,wheneverdevelopersidentifynewwork,orwhenitstime
toworkonanewitemandtheyneedtounderstanditsscope.

79.Question

Whataretwocommonbenefitsofselforganization?

Increasedcommitment

Increasedpredictability

Increasedselfaccountability

Increasedrulecompliance

Incorrect
QuestionCode:01004
Beingselforganizedmeansthattheteamfindsitsownway,insteadofreceivingorders.Whenitis
so,thereismorebuyin(commitment),accountability,andcreativityamongteammembers.

80.Question

WhentheScrumTeambecomesmatureenough,itdoesntneedaScrumMasteranymore.

False

True

Correct
QuestionCode:01059
EveryScrumTeamneedsaScrumMasterandaProductOwner,eveniftheyaremature.Both
rolescanbeparttime.
RememberthattheScrumMasterisalsoresponsibleforremovingimpediments.Anditdoesnt
matterhowmatureyouareintheprocessitsalwaysgreattohavesomeonetohelpyouwith
issues.

COMPLETELESSON

https://mplaza.pm/lesson/psmsimulatedexam1/ 36/37
5/10/2017 PSM.SimulatedExam#1|MP

Previous: PSM.AFewImportantNotes Next:PSM.SimulatedExam#2

Backto:PSMISimulatedExams

MaterialprovidedbyManagementPlaza(iPlazzaN.V).ShopisrunbyMPLAZAEOODPrivacyPolicyTermsand
Conditions
iPlazzaN.V.Barbarastraat13bus1,3120Tremelo,Belgium
MPLAZAEOOD,Bulgaria,Sofia1111,44NikolayKopernikStreet

ITIL,PRINCE2,PRINCE2Agile,MSP,M_o_R,P3O,MoPandMoVareregisteredtrademarksof
AXELOSLimited,usedunderpermissionofAXELOSLimited.Allrightsreserved.
TheSwirllogoisatrademarkofAXELOSLimited,usedunderpermissionofAXELOSLimited.Allrightsreserved.
PMI,PMP,PMBOKGuide,OPM3,andCAPMareeithermarksorregisteredmarksofProjectManagement
Institute,Inc.
DSDM,Atern,andAgilePMareRegisteredTradeMarksofDynamicSystemsDevelopmentMethodLimited.
PSM,ProfessionalScrumMaster,PSPO,andProfessionalScrumProductOwnerareregisteredtrademarksof
Scrum.org.